Report of an Investigation into the Spring Garden Road Poreporena Freeway Project (Part 1)
Mentions of people and company names in this document
It is not suggested or implied that simply because a person, company or other entity is mentioned in the documents in the database that they have broken the law or otherwise acted improperly. Read our full disclaimer
Document content
-
OMBUDSMAN COMMISSION
OF
PAPUA NEW GUINEA
REPORT OF AN
INVESTIGATION INTO
THE SPRING GARDEN ROAD
POREPORENA FREEWAY PROJECT
MEMBERS
OF THE
OMBUDSMAN COMMISION
Charles Maino Ango Wangatau Jim Ridges
Chief Ombudsman Acting Ombudsman Acting Ombudsman18 December 1992
-
Page 2 of 397
-
OMBUDSMAN COMMISSION
OF
PAPUA NEW GUINEA
REPORT OF AN INVESTIGATION
INTO THE SPRING GARDEN ROAD
POREPORENA FREEWAY PROJECTPART I: NATURE AND PURPOSE OF THE INVESTIGATION
1. INTRODUCTION 2
2. BACKGROUND OF THE FREEWAY PROPOSAL 9
3. STRUCTURE OF THE REPORT 14
PART H: RECORD OF EVENTS AND FINDINGS OF THE
OMBUDSMAN COMMISSION4. DECISION TO PUBLICLY INVITE 18
EXPRESSIONS OF INTEREST: MAY 19905. ADVERTISEMENT INVITING 23
EXPRESSIONS OF INTEREST: JUNE 19906. RESPONSES TO THE ADVERTISEMENT: JULY 1990 35
7. SIGNIFICANT INTERDEPARTMENTAL 49
MEETING: 31 JULY 19908. PROGRESS DURING SECOND 54
HALF OF 1990
9. PREPARATION OF SHORTLIST: 73
FEBRUARY 199110. TERMS OF REFERENCE FOR THE 94
PROJECT: EARLY 199111. THE MINISTERIAL COMMITTEE MEETING 103
OF 18 JULY 1991 -
Page 3 of 397
-
12. THE RELATIONSHIP BETWEEN THE CHINESE 120
CONSORTIUM AND THE MINISTER FOR TRANSPORT13. FURTHER CHANGE IN COMPOSITION OF
THE CHINESE CONSORTIUM: SEPTEMBER 1991 15514. MINISTER FOR TRANSPORT SIGNS CONTRACT 162
FOR CONSTRUCTION OF FREEWAY: OCTOBER 199115. ROLE OF THE WORLD BANK IN THE
SPRING GARDEN ROAD/POREPORENA 178
FREEWAY PROJECT16. FATE OF THE POLICY SUBMISSION FAVOURING 185
THE CHINESE CONSORTIUM: DECEMBER 199117. CONCERNS ABOUT CREDENTIALS OF TUNSON
ENGINEERING CO LTD: 196
DECEMBER 1991 – JANUARY 199218. MINISTER FOR TRANSPORT EXPEDITES
PREPARATION OF NEW POLICY 707
SUBMISSION: FEBRUARY 199219. HISTORY OF THE PROPOSAL BY 217
KINHILL KRAMER PTY LTD20. RESOURCE MANAGEMENT
COMMITTEE RECOMMENDS RE-TENDERING 238
OF PROJECT: 20 FEBRUARY 19922L THE MINISTER FOR TRANSPORTS 241
POLICY SUBMISSION OF FEBRUARY 199222. FAVOURABLE ASSESSMENT OF
THE KINHILL KRAMER PROPOSAL23. NATIONAL EXECUTIVE COUNCIL DECIDES TO
AWARD PROJECT TO KINHILL KRAMER 284
CONSORTIUM: 24 FEBRUARY 1992 -
Page 4 of 397
-
24. OVERVIEW OF EVENTS BETWEEN APPOINTMENT
OF KINHILL KRAMER CONSORTIUM AND 290
SIGNING OF CONTRACT: FEBRUARY – MAY 199225. CONCERNS RAISED BY DEPARTMENT OF WORKS
ABOUT DRAFT CONTRACT: 304
MARCH – APRIL 199226. DEPARTMENT OF TRANSPORT RECOMMENDS SIGNING
OF CONTRACT AGAINST ADVICE OF OTHER 321
DEPARTMENTS: 22 APRIL 199227. NATIONAL EXECUTIVE COUNCIL DECIDES THAT 332
CONTRACT MUST BE FINALISED: 23 APRIL 199228. ACTION TAKEN BY FOUR KEY DEPARTMENTS
PRIOR TO THE NATIONAL EXECUTIVE COUNCIL 334
MEETING ON 29 APRIL 199229. NATIONAL EXECUTIVE COUNCIL REJECTS ADVICE
OF DEPARTMENT OF ATTORNEY-GENERAL: 29 APRIL 1992 35530. ACTING STATE SOLICITOR GIVES LEGAL CLEARANCE 358
DESPITE DEFECTS IN CONTRACT: 6 MAY 199231. NATIONAL EXECUTIVE COUNCIL APPROVES 367
EXECUTION OF CONTRACT: 6 MAY 199232. EVENTS LEADING UP TO EXECUTION OF 375
THE CONTRACT: 6 – 27 MAY 199233. THE CONTRACT OF 27 MAY 1992 395
34. EVENTS AFTER 27 MAY TERMINATION
OF CONTRACT AND APPOINTMENT OF A 400
COMMISSION OF INQUIRYPART III: LAWS RELEVANT TO PUBLIC WORKS CONTRACTS
-
Page 5 of 397
-
35. THE PUBLIC TENDER REQUIREMENTS OF 406
THE PUBLIC FINANCES (MANAGEMENT) ACT36. THE PUBLIC WORKS COMMITTEE ACT AND THE
ROLE OF THE PARLIAMENT IN MONITORING 424
PUBLIC WORKS PROJECTS37. CONTROL OF OVERSEAS 39
BORROWING BY THE STATE38. LAWS GOVERNING FOREIGN INVESTMENT 446
39. LIMITS ON THE POWERS OF MINISTERS 451
40. FUNCTIONS OF THE DEPARTMENT OF 460
TRANSPORT AND THE DEPARTMENT OF WORKSPART IV; FINDINGS UNDER SECTION 219(1) OF THE
CONSTITUTION AND SECTION 22(1) OF THE
ORGANIC LAW ON THE OMBUDS • COMMISSION41. FINDINGS AS TO THE CONDUCT OF THE 468
FORMER MINISTER FOR TRANSPORT42. FINDINGS AS TO THE CONDUCT OF THE
DEPARTMENT OF TRANSPORT AND 480
THE SECRETARY FOR TRANSPORT43. FINDINGS AS TO THE CONDUCT OF THE
DEPARTMENT OF WORKS AND THE 497
SECRETARY FOR WORKS44. FINDINGS AS TO THE CONDUCT OF THE
DEPARTMENT OF ATTORNEY-GENERAL, THE 501
SECRETARY OF THE DEPARTMENT AND THE
ACTING STATE SOLICITOR45. FINDINGS AS TO THE CONDUCT OF THE
DEPARTMENT OF FINANCE AND PLANNING 506 -
Page 6 of 397
-
AND THE SECRETARY FOR FINANCE
46. FINDINGS AS TO THE CONDUCT OF THE 512
NATIONAL EXECUTIVE COUNCILPART V; RECOMMENDATIONS OF THE OMBUDSMAN COMMISSION
47. RECOMMENDATIONS CONCERNING LAWS RELEVANT 518
TO PUBLIC WORKS PROJECTS48. RECOMMENDATIONS AS TO THE EXERCISE 529
OF POWERS BY MINISTERS49. RECOMMENDATIONS CONCERNING THE POWERS 534
AND DUTIES OF DEPARTMENTAL HEADS50. RECOMMENDATIONS CONCERNING PROCEDURES 536
OF THE NATIONAL EXECUTIVE COUNCIL5L RECOMMENDATIONS TO THE DEPARTMENT 544
OF TRANSPORT52. RECOMMENDATIONS TO THE DEPARTMENT 548
OF ATTORNEY-GENERAL53. RECOMMENDATIONS TO THE DEPARTMENT 550
OF FINANCE AND PLANNING54. RECOMMENDATIONS TO THE MINISTER FOR
TRADE AND INDUSTRY AND THE INVESTMENT 554
PROMOTION AUTHORITY55. RECOMMENDED DISCIPLINARY PROCEEDINGS 557
56. RECOMMENDATIONS CONCERNING THE FUTURE OF THE 561
SPRING GARDEN ROAD/POREPORENA FREEWAY PROJECTPART VI SUMMING UP
57. SUMMING UP 566
-
Page 7 of 397
-
LIST OF EXHIBITS 571
i
PART I 1
NATURE AND PURPOSE OF THE INVESTIGATION2
1. INTRODUCTION
(1.1] THE OMBUDSMAN COMMISSION’S DECISION TO CONDUCT AN
INVESTIGATIONOn 27 May 1992 the Governor-General, Sir Wiwa Korowi, signed a
contract
on behalf of the Independent State of Papua New Guinea for the
design,
finance and construction of a freeway in the city of Port
Moresby. The
Governor-General was acting on the advice of the National
Executive
Council, which a few weeks earlier had given final approval
for the signing
of the contract. -
Page 8 of 397
-
The Ombudsman Commission received information from a number of
different sources suggesting that normal procedures had not
been
followed. It was also alleged there were irregularities in the
contract
negotiations and that the terms of the contract were heavily
weighted
against the interests of the State.After making preliminary inquiries, it appeared that the
project had neither
been put to tender nor considered by the Parliament. As it was
the
Commission’s understanding that public works projects of this
magnitude
(the contract committed the State to a minimum payment of US
$67 million
plus interest) were subject to these procedures, the
Commission decided
in May 1992 that it would conduct an investigation, on its own
initiative, into
the circumstances leading to and surrounding the decision of
the NationalChapter 1
3
Executive Council to advise the Governor-General to sign
the contract for
the design, finance and construction of the freeway.[1.2] JURISDICTION
The Commission conducted its investigation under the
Organic Law on the
Ombudsman Commission. Section 13 authorises it to
investigate, on its
own initiative, any “conduct” on the part of any
“governmental body” or any
of its officers. The Commission can thus investigate the
conduct of any
arm, department, agency or instrumentality of the National
Government,
including the National Executive Council (Schedule 1.2(1)
of the
Constitution).The Commission can investigate the policy of the National
-
Page 9 of 397
-
Government or
a Minister, to the extent that the policy is contrary to
law or to the National
Goals and Directive Principles, the Basic Rights or the
Basic Social
Obligations or any Act of the Parliament (Section 219(3) of
the
Constitution).The Ombudsman Commission is not authorised to conduct an
investigation
into the conduct of private citizens and companies.
Nevertheless, in the
course of reporting its findings and opinions on the
conduct of
governmental bodies, it is sometimes necessary to comment
on the
conduct of others who may not be within the jurisdiction of
the
Ombudsman Commission. That has happened in this report: we
have
occasionally made comments on the conduct of private
companies, as part
of the formation of an opinion on the conduct of various
governmental
bodies.Chapter 1
4
[1.3] THE PURPOSE OF THIS INVESTIGATION
The purpose of this investigation was not to report on whether
the city of
Port Moresby needs a freeway. That could have formed a part of
the
investigation, because Section 219(3) of the Constitution
allows the
Ombudsman Commission to inquire into National Government
policies
which are contrary to the National Goals and Directive
Principles.The second of our National Goals is for all our citizens to
have an equal
opportunity to participate in, and benefit from, the -
Page 10 of 397
-
development of our
country’. Directive Principles 2(3) and 2(4) require that
every effort be
made to achieve an equitable distribution of the benefits from
development
and an equalisation of services throughout the various parts
of the country.It is arguable whether these objectives were advanced by the
decision of
the National Executive Council to commit a large amount of
public money
to the building of a freeway in the nation’s capital;
especially as it is widely
recognised that the rural infrastructure of our country is
seriously under-
developed.Nevertheless, the Ombudsman Commission decided, in its
deliberate
judgment, not to make that policy decision of the National
Executive
Council the subject of this investigation. We were concerned,
instead, with
the decision-making process which attempted to implement that
policy.In accordance with Section 219(1) (a) of the Constitution the
purpose of the
investigation was:to determine whether any of the “conduct” under
investigation
was “wrong”; andChapter 1
5
to determine whether there were “defects in any law
oradministrative practice.
[1.4] WHAT IS ‘WRONG’ CONDUCT?
-
Page 11 of 397
-
Section 219(2) of the Constitution states that conduct is
“wrong” if, forexample, it is:
“(a) contary to law; or
(b) unreasonable, unjust/oppressive or improperly
discriminatory, whether
or not it is in accordance with law or practices or(c) based wholly or partly on improper motives,
irrelevant grounds or
irrelevant considerations; or(d) based wholly or partly on a mistake of law or of
fact or(e) conduct for which reasons should be given but were
not,whether or not the act was supposed to be done in the
exercise of deliberate
judgement within the meaning of Section 62 (decisions in
‘deliberate judgement’).”However, Section 219(2) of the Constitution also provides
that theOmbudsman Commission is not constrained in its determination
of whetherconduct is “wrong”, by the examples listed above. The
OmbudsmanCommission has a wide discretion to exercise in making this
determination.In exercising its discretion the Commission is guided, in
particular, by theNational Goals and Directive Principles and the Basic Rights
and the BasicSocial Obligations, as permitted by Sections 25 and 63 of
the Constitution. -
Page 12 of 397
-
Chapter 1
6
(1.51 RELEVANCE OF THE LEADERSHIP CODE
The Ombudsman Commission of Papua New Guinea is entrusted with
the
task of administering two Organic Laws:the Organic Law on the Ombudsman Commission; and
the Organic Law on the Duties and Responsibilities of
Leadership.The provisions of the Organic Law on the Duties and
Responsibilities of
Leadership, together with those in Division 111.2 of the
Constitution,
comprise the Leadership Code.We emphasise that this report has not been prepared for the
purpose of
recording alleged breaches of the Leaddership Code. The
procedure for
dealing with such matters is prescribed by the Organic Law on
the Duties
and Responsibilities of Leadership. This report has Int been
prepared
under that Organic Law.This is a report prepared in accordance with the Organic Law on
the
Qmbudsman Commission. Our primary function in this
investigation has
been to investigate and report on wrong conduct and defective
laws and
administrative practices and to make recommendations
accordingly.In discharging that function the Ombudsman Commission has not
formed
any judgment on whether any of the persons involved have -
Page 13 of 397
-
breached the
Leadership Code.Chapter 1
7
METHOD OF INQUIRY
The Commission obtained documents and other evidence from a number
of different sources and used its powers under Section 18 of the
Organic
Law on the Ombudsman Commission to summon persons to attend before
the Commission and give evidence under oath and produce documents
in their possession or control. Most persons summoned to attend were
co-
operative. However it was, on occasions, necessary to warn some
persons
of their obligation to comply fully with the terms of the summons
served
on them.We take this opportunity to point out that it is not sufficient for
a person
who has been required to produce all documents pertaining to a
certain
subject matter to attend the Commission and produce only some, or
even
most, of the documents required. Failure to comply fully with an
Ombudsman Commission summons is a serious criminal offence under
Section 30 of the Organic Law on the Ombudsman Commission, the
penalty for which is a K500.00 fine or three months imprisonment for
each
offence (see The State v Allan Ebu Marai, National Court decision,
O.P. 1
of 1991, 12.2.92).A number of the documents obtained by the Ombudsman Commission
under summons would in the ordinary course of events be regarded as
confidential in nature,e.g. those providing evidence of the
proceedings of
the National Executive Council. However, the effect of Section 19(1)
of the
Organic Law on the Ombudsman Commission is that the Ombudsman
Commission can only be denied access to such documents when the
Prime Minister, after consultation with the Chief Ombudsman,
certifies that
their production is likely to: -
Page 14 of 397
-
Chapter 1
“(a) prejudice the security, defence or international
relations of Papua New
Guinea (including Papua New Guinea’s relations with the
Government
of any other country or with any international
organization) or the
investigation or detection of offences; or(b) involve the disclosure of proceedings, deliberations or
decisions of the
National Executive Council which the “‘time Minister
certifies relate
to matters of a secret or confidential nature,
disclosure of which would
be contrary to the public interest.”In the present case, no certificate under Section 19(1) was issued
in
respect of any documents which the Commission sought access to and
so the Commission was able to require the production of those
documents.The investigation was conducted in private, as required by Section
17(2)
of the Organic Law on the Ombudsman Commission.* * * * * * * * * *
-
Page 15 of 397
-
Chapter 1
2. BACKGROUND OF THE FREEWAY PROPOSAL
[2.1] PORT MORESBY’S TRAFFIC PROBLEMS
It has been recognised for many years that the peculiar
geography of the
city of Port Moresby has given rise to a serious traffic
problem. Other than
following the long and winding “back road” through Baruni, or
the
inconvenient route along Scratchley Road through Kila Kila,
only the Sir
Hubert Murray Highway can carry traffic between downtown Port
Moresby
and the other major traffic-generating parts of the city at
Gerehu, Waigani,
Hohola, Boroko and Jacksons Airport.The Highway, however, is not a high quality road and it is
often congested.
Breakdowns and accidents on some sections, particularly Three
Mile Hill,
can cause huge traffic jams.2.2] THE UNCONNECTED SECTIONS OF THE SPRING GARDEN ROAD
NETWORKConstruction of an alternative route, between the suburbs of
Hohola and
Konedobu, has long been regarded as the solution to the
problem.
Various proposals have been put forward over the last thirty
years and -
Page 16 of 397
-
most have favoured a road passing through the saddle of Burns
Peak
linking two presently unconnected sections of “Spring Garden
Road”.
These two unconnected sections are shown on the map at the end
of this
chapter. They are:Chapter 2
10
from Champion Parade Konedobu to a point close to the
Department of Transport headquarters in Konedobu: see
map, points “B” to “C”; andfrom Burns Peak Road Hohola to Wards Road Hohola: see
map, points “D” to “E”.There are also other unconnected sections of the Spring Garden Road
network which have, at various times, been earmarked for
construction or
redevelopment. These are:from Wards Road Hohola to a point near the Hohola
Demonstration School: see map, points “E” to “F”; andfrom Hekakora Street Hohola to Boroko Drive: see map,
points “G” to “I”.More recently, it has been proposed that the Spring Garden Road
network
be extended at “both ends”, to form one arterial road linking the
seaport
at downtown Port Moresby with Jacksons Airport: see map, points “A”
to
‘. Under this proposal, the extended sections of the Spring Garden
Road
network would have been:from Stanley Parade in downtown Port Moresby, along
Champion Parade, to Spring Garden Road, Konedobu: see
map points “A” to “B”; andfrom the intersection of Spring Garden Road and Boroko
Drive, Gordons, via Geauta Road, across the Sir Hubert
Murray Highway at Erima to Jacksons Airport: see map,
points “in to “K’. via “J”.Chapter 2
11
-
Page 17 of 397
-
[2.3] DECISIONS OF THE NATIONAL EXECUTIVE COUNCIL DURING THE
1980sIn the 1980s, the Spring Garden Road issue was addressed by
the
National Executive Council on a number of occasions. In
dealing with
National Executive Council submissions and decisions in this
report, we
have paid special reference to the “Submissions Handbook for
National
Executive Council and National Parliament”. [EXHIBIT 1]In 1984, the National Executive Council directed the then
Department of
Transport and Civil Aviation to arrange a feasibility study on
the “Burns
Peak Road” and to ensure that funding was available under the
National
Road Improvement Programme for 1985-88. [EXHIBIT 2]In 1988, requests for assistance were made to the GoVernment
of Japan
for possible funding under grant aid and soft loan
arrangements for a
number of projects, including the Burns Peak tunnel. [EXHIBIT
3]Also in 1988, Barclay Bros (PNG) Pty Ltd put a proposal to the
National
Government which included an open-cut road through Burns Peak,
linking
the Konedobu and Hohola sections of Spring Garden Road, at an
estimated cost of K11 million. It was proposed that the
project take place
in conjunction with the redevelopment of Port Moresby’s port
facilities. The
Barclay Bros proposal was discussed by a committee which
recommended
that the project be tendered. This proposal also failed to
come to fruition.
[EXHIBITS 4 & 4A]In 1989, the Departments of Transport, Foreign Affairs and
Finance and
Planning were directed by NEC Decision No. 76/89 to approach
the
Government of Denmark for aid funding on this and other
transport
projects. [EXHIBIT 5]Chapter 2
-
Page 18 of 397
-
12
[2.4] THE NATIONAL EXECUTIVE COUNCIL DECISION OF 25 JANUARY
1990It was against this background that the National
Executive Council
reconsidered the matter at its meeting on 25 January
1990, following a
Policy Submission by the Minister for Transport, Mr
Anthony Temo.
[EXHIBIT 6]In Decision No.14/90, the National Executive Council:
directed the Department of Transport,
Department of Works and
Department of Finance and Planning to
formulate detail plans for the
construction of Burns Peak Road;2. directed that the plan should include the
re-evaluation of the Barclay
proposals and any other Turn-Key’
proposals available;3. approved the engaging of Ove Amp and
Partners (Pacific) Pty Ltd, to
undertake the Port Moresby Road Needs
Study (Arterial Roads);4. advised the Governor-General to enter into
agreement on behalf of the
State with Ove Amp and Partners (Pacific)
Pty Ltd” [EXHIBIT 6A]* * * * * * * * * *
-
Page 19 of 397
-
Chapter 2
MAP: THE SPRING GARDEN
ROAD NETWORK AND THE ROUTE OFTHE PROPOSED POREPORENA FREEWAY
Points marked:
A Stanley Parade/
Champion Parade
B Champion
Parade,Spring Garden Road
C End of Spring.
Garden Road Konedobu
D Spring Garden
Road/Burns Peak Road
E Spring Garden
Road/Wards Road
F Spring Garden Road
(Near Hohola Demonstration School)
G Spring Garden
Road/Hekakora Street
H Spring Garden
Road/Waigani Drive
I Spring Garden
Road/Boroko Drive/Geauta Road (Courts’ Roundabout)
Geauta Road/
Kookaburra Street/Sir Hubert Murray Highway
K Jackson
International Airport -
Page 20 of 397
-
• Burns Peak
Chapter 2
14
3. STRUCTURE OF THE REPORT
[3.1] FOCUS OF INVESTIGATION
On 6 May 1992 the National Executive Council decided to advise
the
Governor-General to enter into a contract with Kinhill Kramer
Pty Ltd and
Curtain Bros (Old) Pty Ltd for the design, finance and
construction of the
Poreporena Freeway. That decision was a crucial one. However,
in
conducting this investigation, the Ombudsman Commission was
not only
interested in the circumstances immediately surrounding that
particular
decision. Our wider concern was to determine whether the whole
decision-
making process which occurred after the National Executive
Council
decision of 25 January 1990 was carried out lawfully in
accordance with
sound administrative practices.The Ombudsman Commission therefore considered all the events
that
occurred after 25 January 1990, which culminated in the
signing of the
contract on 27 May 1992. After examining the evidence obtained
in the
course of the investigation, the Commission made a number of
findings.These are set out in Part II of the report, which contains a
chronological
account of the events which led to the signing of the
contract. Each of
Chapters 4 to 33 highlight a significant incident or decision
which formed
the chain of events up to 27 May 1992. -
Page 21 of 397
-
Chapter 3
15
2] ALL PERSONS ADVERSELY COMMENTED ON HAVE BEEN GIVEN A
RIGHT TO BE HEARD
During the course of documenting these findings, the
OmbudsmanCommission found it necessary to be critical of the conduct
of someindividuals and governmental bodies. All of these persons
and, in the caseof governmental bodies, their representatives, were given an
opportunityto be heard prior to the completion of this report, in
accordance with theduties imposed on the Ombudsman Commission under Section
17(4) ofthe Organic Law on the Ombudsman Commission.
Section 17(4) states:
“Nothing in this Law compels the Commission to hold any
hearing and no
person is entitled as of right to be heard by the
Commission except that –(a) where a report of the Commission may affect a State
Service, provincial
government body or statutory body, the Commission
shall provide -
Page 22 of 397
-
reasonable opportunity for the Permanent Head of
that service or the
statutory head of that body, as the case may be, to
comment on the
subject of the investigation; and(b) the Commission shall not make any comment in its
report that is adverse
to or derogatory of any person without –(i) providing him with reasonable opportunity of
being heard; and(ii) fairly setting out his defence in its report”
3.3] RELEVANT IAM
One of the main concerns of the Ombudsman Commission at the
commencement of the investigation was the allegation – which
came frommany sources – that proper financial and contractual
procedures had beenbypassed.
Chapter 3
16
Part II( of the report accordingly gives an account of
some of the important
laws regulating public works contracts in Papua New
Guinea.[3.4] PART IV SUMMARISES AND FORMALISES ADVERSE FINDINGS
-
Page 23 of 397
-
Part IV of the report summarises the adverse findings
made against
individuals and governmental bodies in Part II. These
findings are based
on Section 219 of the Constitution and Section 22 of
the Organic Law on
the Ombudsman Commission, which prescribe the type of
conduct which
is “wrong” or otherwise requires criticism by the
Ombudsman Commission.[3.5] RECOMMENDATIONS OF THE OMBUDSMAN COMMISSION
Part V of the report contains a number of important
recommendations
arising from our investigation. In particular, we make
suggestions as to the
manner in which public works projects such as the
Spring Garden Road
(also known as the Poreporena Freeway) project should
be handled in
future.[3.6] SUMMING UP
Part VI sums up the investigation and the findings of
the Ombudsman
Commission.* * * * * * * * * *
Chapter 3
17
PART II
RECORD OF EVENTS
AND FINDINGS OF THE OMBUDSMAN COMMISSION18
-
Page 24 of 397
-
4. DECISION TO PUBLICLY INVITE EXPRESSIONS OF INTEREST:
MAY 1990[4.1] THE INTERDEPARTMENTAL MEETING OF 22 MAY 1990
After the National Executive Council decided in January 1990
that detailed
plans ‘tor the construction of Burns Peak Road” be drawn up,
very little
happened until May 1990, when the Minister for Transport, Mr
Anthony
Temo, convened an interdepartmental meeting. The meeting was
held on
22 May 1990 and was chaired by Mr Temo. The subject was ‘the
Burns
Peak Road Development’. [EXHIBIT 8]Representatives from various departments and the Harbours
Board were
present, as well as a consultant employed by Ove Arup and
Partners, the
firm engaged to conduct the Port Moresby Road Needs Study.
This study
later concluded that construction of a link through Burns Peak
would have
a beneficial effect on the Port Moresby economy and that
traffic flow on
the Three Mile Hill section of the Sir Hubert Murray Highway
would
consequently be reduced by almost 50%.[42] ISSUES UNDER CONSIDERATION
During this meeting, two crucial issues were addressed:
Chapter 4
19
1. The method of construction of the Bums Peak link
Once it had been decided that the route for the new road
would pass through Burns Peak, the next thing to decide was
the best way of getting through. Should a tunnel be
constructed or would it be better to make a “cut” through the
mountain? -
Page 25 of 397
-
2. The method of financing the project
The other crucial issue discussed at the meeting was the
method of financing the project. One proposal, closely linked
with the tunnel option, was that part of Spring Garden Road
would become a tollway.This later became transformed into the Build-Operate-Transfer
(BOT) concept. Under this method of financing, it was
envisaged that the Government would engage a contractor
to build and operate the road as a tollway, holding the ‘title’
to it for, say, twenty years, until the contractor made a
reasonable return on its investment, and then returning the
road to the State. elThe Minister for Transport favoured this option, though he
was also willing to consider other options, provided they
involved no financial cost to the Government.Chapter 4
20
[4.3] NO FIRM POUCY DECISIONS MADE
No firm decisions were made on either the method of
construction or the
method of financing the project at the meeting of 22 May 1990.
The most
important outcome was that the Minister for Transport directed
the
Department of Transport to advertise the project so that
interested parties
could express their interest.The Minister also announced that he intended to direct the
Department of
Works to commence detailed design of the project immediately
and to
complete the design within six months. This was confirmed in
writing the
following day, 23 May 1990, in a letter to the Acting
Secretary of the
Department of Works, Mr G Morea. [EXHIBIT 9] -
Page 26 of 397
-
[4.4] MINISTER FOR TRANSPORT EXCEEDED HIS POWERS
It should be noted that the Minister for Transport had no
power to give this
direction to the Department of Works.Section 148 of the Constitution states that Ministers only
have such titles,
portfolios and responsibilities as are given to them, from
time to time, by
the Prime Minister. During 1990, Mr Temo had no responsibility
for the
Department of Works and therefore it was wrong of him to
direct the
Department to finish the design within six months. We are not
suggesting
there was anything improper about getting the design phase
underway;
but if the Minister for Transport wanted to expedite the
project, he should
have gone about it the right way, by liaising with the
Minister for Works,
Secretary for Works and Secretary for Transport.Chapter 4
21
When we made this finding in our preliminary report, Mr Temo
responded
as follows:‘The direction to Secretary for Works was a result of a
suppose to be ministerial
committee meeting. When the respective ministers did not
turn up their
respective secretaries or their nominees turned up.
The Department of Works representative suggested the
idea that it would take
up to 6 months to have the Geo-Technical report ready
and he wanted the
decision to be relayed officially as a result of this
meeting.
This letter was drafted by my staff relaying the
decision of the meeting.
I was also acting as Chairman of ministerial committee
on infrastructure_
[10331BIT 257, page 1] -
Page 27 of 397
-
Mr Temo’s response does not address the thrust of our
criticism. His
direction to the Department of Works was unlawful and wrong,
in that it
was contrary to Section 148 of the Constitution..5] MINISTERS DO NOT HAVE THE POWER TO DIRECT DEPARTMENTS IN 1
THEIR DAY-TO-DAY ACT1VMESThere is an important aspect of Sectior 148 of the
Constitution that muss
be emphasised here: though Section 148 gives Ministers
“political.
responsibility for particular Departments, it does not give
them any power
to direct or control a Department in its day-to-day
activities.A Minister is not the boss of a Department – the Head of the
Department
is the boss. The Ministers job – in conjunction with the
National Executive
Council – is to set the Department’s policy on important
issues. It is not his
job to give directions to the Departmental Head or to
Departmental officers
on day-to-day matters. The only exception is where a Minister
is specifically
empowered by an Act of Parliament to give directions or make
certain
decisions. 1Chapter 4
22
This important constitutional principle was explained
by the Supreme Court
in Supreme Court Reference No. 1 of 1982: Re Bouraga
[1982] PNGLR
178. We discuss it further in Chapter 39 of this
report.So, even if Mr Temo had had political responsibility
-
Page 28 of 397
-
for the Department of
Works, it still would have been wrong for him to direct
the Secretary for
Works to complete the design within six months. He
could only request
that that be done and ensure that there were sufficient
funds available for
that purpose.[4.6] IGNORANCE OF SECTION 148 OF THE CONSTITUTION: A MAJOR
PROBLEM
There is a lot of misunderstanding of Section 148 of
the Constitution in the
Public Service, and some Ministers appear to know
little about it.The Ombudsman Commission often finds that Ministers
believe that, simply
because they are Ministers, they have the right to give
directions to anyone
in “theirs Department, or even, as shown in the present
case, in a
Department for which they have no responsibility. This
is wrong. It is
unconstitutional and it leads to chaos.Unfortunately, there were many occasions during the
life of the Spring
Garden Road/Poreporena Freeway project when the
Minister for Transport
exceeded his powers as a Minister. This was the first
of them.* * * * * * * * * *
Chapter 4
23
5. ADVERTISEMENT INVITING EXPRESSIONS OF INTEREST:
JUNE 1990[5.1] ADVERTISEMENT PUBLISHED IN POST COURIER AND NATIONAL
GAZEnE
Advertisements inviting expressions of interests in the “Burns
Peak/Spring -
Page 29 of 397
-
Garden Road Link” were published in the Post Courier on 20 and
22 June
1990 and the National Gazette on 28 June 1990. [EXHIBITS 12 &
18]There are three points that should be noted about the
advertisement. They
concern:the scope of the project;
co-ordination of the project; and
financing of the project.
I. THE SCOPE OF THE PROJECT
[5.2] TERMS OF THE ADVERTISEMENT
The advertisement stated that the National Executive Council
had decided
that “the section of Spring Garden Road in the National
Capital District
between Waigani Drive and Kaevaga/Konedobu … is to be
constructed as
soon as possible”.Chapter 5
24
This statement was a little misleading.What precisely had the National Executive Council decided?
What the National Executive Council had, in fact, decided by
Decision No.
14/90 was that “plans for the construction of Burns Peak Road”
be
formulated.This was a very vague decision. The only road in Port Moresby
that is
called “Burns Peak Road” is the dirt track running from Spring
Garden
Road, near Walnut Place, Hohola to the top of Burns Peak where
the
telecommunications transmitters are located.Despite the vagueness of Decision No. 14/90 it was assumed by
everyone
concerned that the National Executive Council was actually
referring to -
Page 30 of 397
-
Spring Garden Road. However, this interpretation still caused
problems,
because the National Executive Council did not specify (and
has never at
any stage specified) the particular parts of Spring Garden
Road it wanted
constructed and/or upgraded.[5.3] WHAT WAS MEANT BY ‘THE BURNS PEAK ROAD” OR “SPRING GARDEN
ROAD”?This was not just a small side issue – it concerned the scope
of the whole
project. Did the National Executive Council want the upgraded
road to
begin at the junction of Stanley Esplanade and Cuthbertson
Street in
downtown Port Moresby or was the network to begin at the
junction of
Champion Parade and Spring Garden Road in Konedobu? Was the
road
to go through Burns Peak to Wards Road? Or one stage further,
to
Waigani Drive? Or to the end of Spring Garden Road at Boroko
Drive? Or
further still, to the Sir Hubert Murray Highway, at Erima? Or
was the road
required to go all the way to Jacksons Airport?Chapter 5
25
Any of these options could conceivably have been brought
within the
terms of the decision that “plans for the construction of the
Burns Peak
Road” be formulated.The Policy Submission which had generated the decision did not
shed any
light on this issue. It simply made reference to the scope of
the project in
general terms such as:The purpose of the Submission is to request the National
Executive Council
to direct Department of Works, Department of Transport and
Department of -
Page 31 of 397
-
Finance and Planning to adopt special procurement
procedures to undertake the construction of Burns Peak Road
(Spring Garden Road). The measures could
construction of Burns Peak Road (Spring Garden Road). The
measures could
include turnkey arrangements.-
Construction of the BUMS Peak will involve considerable
financial commitment’ [EXHIBIT 6, page 1]
[EXHIBIT 6, page 1]5.4] THE DEPARTMENT OF TRANSPORTS INTERPRETATION OF THE
5.4] THE DEPARTMENT OF TRANSPORTS INTERPRETATION OF THE
NATIONAL EXECUTIVE COUNCIL DECISIONThe Secretary for Transport, Mr B K Amini CBE, interpreted the
decision
as applying only to the section of Spring Garden Road between
Konedobu
and Waigani Drive. This is evident from a letter dated 7 June
1990 he
wrote to the Secretary for Works, Mr A Temu. Mr Amini
described the
scope of the project in the following terms:‘I wish to restate that the scope has not change except the
grade and the
elimination of the design of the tunnel option. Basically
the scope of works am-
am-8% grade
4 lanes (2 lanes in each direction)
80 km/ph
Establishment of a highway link between Rohola (Junction of
Waigani Drive
and Spring Garden Road East) and Konedobu (Junction of
Champion Parade
and Spring Garden Road West) by improving and extending
Spring Garden
Road over Burns Peak, Intersecting and crossing Wards
Road.’
[EXHIBIT 10, page 1]Chapter 5
-
Page 32 of 397
-
26
[5.5] CHANGE OF SCOPE WITHOUT EXPLANATION
The Secretary for Transport’s interpretation of the National
Executive
Council decision was reflected in the advertisements inviting
expressions
of interest. But that interpretation did not remain constant.Two years after the advertisement was published, the State had
entered
into a contract for construction of a freeway all the way from
downtown
Port Moresby to Jacksons Airport. This was a considerable
expansion in
the original scope of the project. [EXHIBITS 231 A, 231 B,
232][5.6] WHO MADE THE DECISION TO EXPAND THE SCOPE OF THE PROJECT?
In the course of this investigation, the Ombudsman Commission
was never
able to identify when the decision was made to alter the scope
of the
project. Nor can we say who made it. It seems to have “just
happened’
that way.Mr Amini’s explanation
When we raised this matter in our preliminary report, the
Secretary for
Transport, Mr Amini, responded in the following terms:For every major project undertaken by the Department of
Transport, there is
a feasiblity study that defines the scope in general terms.
The outcome of the
feasibility study is a three-part report – a summary
containing the main findings -
Page 33 of 397
-
and recommendations, – a main report containing the main
issues and – technical
appendices or working papers. These serve as working papers
on each project,
including this one and there is minimum of paperwork. After
these reports,
follows the detailed design that pins down the last
centimetre of the project’s
scope – where it starts and where it ends. It should be
noted that, for this
project, the detailed design had not been done as it was
part of the turn-key –
the consortium was going to do that as part of the
contract.Chapter 5
27
The project feasibility report prepared by the
consultants, Ove Arup of Australia
– entitled ‘Spring Garden Road Economic Assessment’ –
contained the detailed
scope of the project and it is a reference point and not a
file. The scope was
extended to connect the new DCA road from the airport
(note this is normal to
extend the scope – Department of Works almost invariably
extend every project
they implement). The end of the DCA project was known
because it had been
designed and that is where we were to end this project.
The DCA project was
two-lane and wisely we decided to widen it to four to
conform with the
Freeway. Both the start and the end of the project were
clearly known. The
Department followed its set procedures and this cannot be
construed as
defective administration.” [EXEUBIT 254, pages 2-3]Unsatisfactory explanation
-
Page 34 of 397
-
In our view, Mr Amini has not given a satisfactory explanation of
his
Department’s failure to make a careful and reasoned and properly
documented decision as to the scope of the Spring Garden
Road/Poreporena Freeway project.His reference to the ‘Spring Garden Road Economic Assessment’ report
by Arup Australia is, with respect, misleading. Mr Amini suggests
that the
scope of the project was determined in accordance with that report.
Even
if that were true, we would still expect to find evidence that at
some stage
the Department of Transport had made a formal decision to adopt the
recommendations of the report.However, the Arup report entitled ‘Spring Garden Road Economic
Assessment’ did not provide any basis for the decision to extend the
scope of the project to Jacksons Airport along the route envisaged
in the
contract with the Kinhill Kramer/Curtain Bros consortium.Despite Mr Amini’s claim that the start and end of the project were
clearly
known, the ‘Spring Garden Road Economic Assessment Report’ only
contemplated a four-lane road from downtown Port Moresby to the
intersection of Spring Garden Road and Waigani Drive (see Chapter 2Chapter 5
28
map, points “A” to “H”), plus other associated works. The Spring
Garden
Road project, according to that report, did not include the
upgrading of
Spring Garden Road from Waigani Drive to Boroko Drive (see map, “H”
to
“I”). The project also did not include a four-lane arterial road
from the
intersection of Spring Garden Road and Boroko Drive to Jacksons
Airport,
via Geauta Road, which was the route envisaged in the contract
entered
into with the Kinhill Kramer/Curtain Bros consortium (see map,
points “I”
to “K”). [EXHIBIT 9A, page 10, para 5.12; EXHIBIT 233, Part Z
Description of Concept]In Arup’s Study Report, which was separate from the Spring Garden
-
Page 35 of 397
-
Road
Economic Assessment Report, it was recommended that, in addition to
the
Spring Garden Road project, many other road construction and
improvement projects should be undertaken in the city of Port
Moresby.
These included widening the section of Spring Garden Road between
Waigani Drive and Boroko Drive to four lanes (see map, “H” to “I”).
However, the Study Report did not recommend the widening or
upgrading
of Geauta Road, from Boroko Drive to the Sir Hubert Murray Highway
(see
map, “I” to “J”). The Study Report, in fact, recommended that the
most
direct route between downtown Port Moresby and Jacksons Airport
should
be via Sir John Guise Drive, which was proposed to be extended as a
two-lane arterial road. [EXHIBIT 69A, para 7.0, table 1]Thus, neither the Spring Garden Road Economic Assessment Report nor
the Study Report recommended a four lane arterial road along the
route
contained in the contract executed with the Kinhill Kramer/Curtain
Bros
consortium.Mr Hitola’s explanation
When our criticism of the Department of Transport’s failure to
specify the
scope of the project was conveyed to the Secretary for Works, Mr
HitoloChapter 5
29
(who was responsible for this project for a considerable time in the
Department of Transport) he offered a different explanation.Mr Hitolo said that because the project was to be implemented using
Build-Operate-Transfer financing, it was up to the private sector to
determine the financial viability of the project before proposing
the scope
to the Government for approval. Mr Hitolo also said that a careful
and
reasoned and properly documented decision about the scope of the
project required a feasibility study costing between K200,000.00 and
K400,000.00, which had not been budgeted for.
[EXHIBIT 265, page 2]Explanation rejected
We find Mr Hitolo’s explanation unconvincing. Even if we accept
-
Page 36 of 397
-
that, in the
case of a Build-Operate-Transfer project, the scope is determined by
the
developer, the fact is that no Build-Operate-Transfer proposal was
ever
lodged for the Spring Garden Road/Poreporena Freeway project. All of
the
proposals involved turnkey financing.This meant that inevitably – at some stage – the Government would be
paying for the freeway. It was therefore necessary for the
Government to
know exactly where it wanted the freeway to go and how long the
freeway
would be.No proper comparison of competing proposals could be made unless
everyone concerned knew the beginning and end points of the freeway
and its route.It was the Department of Transport’s responsibility to make a
careful and
reasoned decision on this basic issue. However, it failed to do
this.Chapter 5
30
[5.71 CHANGE OF FUNDAMENTAL DESIGN ALSO WITHOUT EXPLANATION
We make a similar observation on the decision about the
tunnel/cut option.
Mr Amini’s letter to the Secretary for Works of 7 June 1990
makes mention
of the fact that the tunnel option had been eliminated.
[EXHIBIT 10, third
paragraph] But, at an interdepartmental meeting on 31 July
1990, it was
decided that a geotechnical investigation was required, before
a final
decision could be made (see Chapter 7).Throughout 1991, when negotiations were taking place with
likely
contractors, it was assumed the project would include a
tunnel. When the
National Executive Council made Decision No. 36/92 in favour
of IGnhill
Kramer Pty Ltd in February 1992, one of the key criteria (and
one on
which Knhill Kramer was rated “excellent”) was the “expected -
Page 37 of 397
-
quality of
tunnel”. But when the contract was signed, on 27 May 1992,
there was
no mention of a tunnel.MrAminarasmnrA
In our preliminary report, we were critical of the Department
of Transport
for the haphazard manner in which the tunnel/cut issue was
addressed.
The Secretary for Transport, Mr Amini, replied that the
geotechnical
investigation undertaken by Coffey Partners International (see
Chapter 8)
was meant to give a conclusive answer; but he said it turned
out to be
inconclusive. As to the eventual decision to opt for the cut,
rather than the
tunnel, Mr Amini said it was made by the Department of Works.
[EXHIBIT
254, page 3]Chapter 5
31
Mr Hitolo’s response
Mr Hitolo’s explanation of the confusion over the tunnel/cut issue
was that
it was an investment decision, to be made by the consortium selected
to
undertake the project. [EXHIBIT 254, page 2]Neither response was satisfactory
Having considered the responses of Messrs Amini and Hitolo, we
conclude
that neither offered a satisfactory explanation for the Department
of
Transport’s failure to make a careful, reasoned and properly
documented
decision on the tunnel/cut issue.Mr Hitolo’s claim that it was an “investment decision” could only
possibly
make sense if the project were based on Build-Operate-Transfer
financing. -
Page 38 of 397
-
But, as pointed out earlier, no such proposal was ever put to the
Department of Transport. The Government of Papua New Guinea was
always going to pay for this project and therefore it should have
decided
whether a tunnel or a cut through Burns Peak was preferable.We accept Mr Amini’s description of the geotechnical report as
inconclusive. But that report was made available in May 1991 – the
Department of Transport had ample time after that to make a
determination
on this basic technical issue. Though the Department of Works was
eventually consulted, this should have been done on a formal and
methodical basis – not by means of casual conversation between
officers
of the two Departments.We simply do not regard it as an acceptable administrative practice
for the
Department of Transport to have prepared a Policy Submission which
assumed the project would include a tunnel and then – without any
recordChapter 5
32
of consultation or any record of any different decision – to
allow a situation
to develop in which the project included a cut through Burns
Peak, rather
than the tunnel.[5.8] ADMINISTRATIVE INCOMPETENCE BY THE DEPARTMENT OF
TRANSPORTIt is stating the obvious to say that decisions concerning
Papua New
Guinea’s transport infrastructure should not be made as they
were in the
case of the Spring Garden Road/Poreporena Freeway project.Decisions such as the length of a freeway and its fundamental
design
should not be made haphazardly. These decisions involve the
expenditure
of large amounts of public money. They must be made carefully
and
methodically and they must be properly documented. If
Government
departments make important policy decisions haphazardly, it is
virtually
impossible to keep a check on the expenditure of public money.
And it -
Page 39 of 397
-
creates an environment ripe for corruption.
When an investigatory agency such as the Ombudsman Commission
does
a check on a decision-making process which led to the
commitment of
millions of kina of public money, it should be able to find
evidence of a
series of reasoned and methodical steps and the careful
evaluation of
alternatives. But the evidence we have gathered shows the
exact
opposite: it was as if decisions – like the route of the
freeway – were falling
out of the sky.The Ombudsman Commission has concluded that this situation
arose
because of the administrative incompetence of the Department
of
Transport.Chapter 5
33
IL CO-ORDINATION OF THE PROJECT
[5.9] EXPRESSIONS OF INTEREST CO-ORDINATED BY DEPARTMENT OF
WORKS
■Despite the Minister for Transport’s direction at the
meeting of 22 May
1990 that the project be advertised by the Department of
Transport, the
advertisements were actually organised by, and the
responses had to be
made to, the Department of Works.Apparently, this turnaround occurred because the First
Assistant Secretary
(Planning and Research) in the Department of Transport, Mr
Amoako, •
asked the Department of Works for assistance in drafting
the
advertisement. The Principal Engineer (Roads), Mr
Newberry, prepared a
draft which was forwarded to the Department of Transport -
Page 40 of 397
-
for review and
issue. However, Mr Amoako returned the document to Mr
Newberry,
advised him that it was satisfactory and requested that it
be published by
the Department of Works. [EXHIBIT 51, page 2 and EXHIBIT
52, page 2][5.10] A SIGNIFICANT LACK OF CO-ORDINATION
Though there was nothing improper in what was done by Mr
Amoako, this
incident is significant because it typified what was, and
continued to be,
a confusing state of affairs regarding the implementation
of the whole
project: there was a great deal of confusion as to the
respective roles of
the Department of Transport and the Department of Works,
which we
consider was ultimately detrimental to the overall
interests of the State.Chapter 5
34
III. FINANCING OF THE PROJECT
[5.11] TERMS OF THE ADVERTISEMENT
The advertisement of June 1990 alluded to the issue of
financing the
project, in the following terms:“The work may be financed by a combination of
any or all of the following:a toll on the new road link
commercial leases on reclaimed -
Page 41 of 397
-
land
grant funding by external agenciesOther means of funding will be considered but
it is not intended that the
Government will contribute to any major
extent.”[EXHIBITS 12 & 18]
The advertisement did not stipulate that the
successful contractor would
have to itself finance the project.This is significant, because, as the Commission was to
discover in the
course of the investigation, there were a number of
interested parties that
were later summarily rejected because of the
inadequacy of their financing
proposals.We consider this to have been quite unfair, because,
though the
advertisement stated that the Government would
probably not finance the
project, it did not stipulate that any company which
failed to submit a
“financial package” would be automatically excluded
from consideration.* * * * * * * * * *
Chapter 5
35
RESPONSES TO THE ADVERTISEMENT: JULY 1990
-
Page 42 of 397
-
6.1] RESPONSES SENT TO DIFFERENT PLACES
The Ombudsman Commission discovered that some of the
expressions of
interest were sent to the Department of Works, whereas others
went to the Department of Transport.
Department of Transport.[6.2] EXPRESSIONS OF INTEREST SENT TO THE DEPARTMENT OF WORKS
We have been able to confirm, by examining the files of the
Department
of Works, that ten expressions of interest were registered
with it, on or before 31 July 1990, as required by the
advertisement:
before 31 July 1990, as required by the advertisement:Coecon Pty Ltd [EXHIBITS 13, 21]
Barclay Bros (PNG) Pty Ltd [EXHIBIT 14]
Connell Wagner (Old) Pty Ltd [EXHIBIT 17]
Willing and Partners Pty Ltd [EXHIBIT 20]
Robert Laurie Company Pty Ltd [EXHIBIT 20AA]
Maunsell Consultants PNG/Hornibrook
Constructions Pty Ltd [EXHIBIT 22]Chapter 6
36
Curtain Bros (PNG) Pty Ltd [EXHIBIT 23]
LKN Construction Pte Ltd [EXHIBIT 25]
Cardno & Davies PNG Pty Ltd [EXHIBIT 26]
Juara Ltd [EXHIBIT 29]
(A number of documents we obtained referred to an expression
of interest
being received from Frame Harvey West (e.g. EXHIBITS 24, 38,
50, 148).
However, we could find no evidence of this. The consulting
firm of Frame
Harvey West & Maso later joined with Periquan International
Resources
and submitted a proposal to the Minister for Transport in July -
Page 43 of 397
-
1991, but
it appears not to have formally expressed any interest before
that.)[6.3] EXPRESSIONS OF INTEREST SENT TO THE DEPARTMENT OF
TRANSPORTDespite the clear statement in the advertisement that
expressions of
interest be registered with the Department of Works, five
groups wrote to
the Department of Transport. These were:Executive Decisions Inc Pty Ltd [EXHIBIT 1 OA]
Kumagai Gumi Co Ltd/Kinhill Kramer Pty Ltd
[EXHIBITS 15, 16]Pan Asia Management Consultants Center [EXHIBIT 27]
Chapter 6
37
Ove Arup & Partners (Pacific) Pty Ltd [EXHIBIT
21A]Sabina Ltd/Peter Chen & Partners Pty Ltd
[EXHIBIT 35][6.4] MOST EXPRESSIONS OF INTEREST HELD BY DEPARTMENT OF WORKS
The Department of Works was made aware of all but one of
these
expressions of interest (from the Singapore-based
Executive Decisions Inc
Pty Ltd) when the Department of Transport faxed copies to
them on 1 and
2 August 1990. [EXHIBITS 34, 35] MilIn light of the above, we are satisfied that as at 2
August 1990, the II
Department of Works had at least fourteen expressions of
interest in its
possession and that they were held by the Principal
Engineer (Roads), Mr IN
E Newberry, who was the Department of Works co-ordinator
of the project. -
Page 44 of 397
-
IR
[6.5] NO ACKNOWLEDGEMENT OF THE EXPRESSIONS OF INTERESTDuring the first week of August 1990, Mr Newberry
prepared a summary
of the expressions of interest and delivered it to the
Department of
Transport. No attempt was made at this stage to rank them
in any way.
We are not critical of this, because the advertisement
had not called for
firm proposals – all that was required were expressions
of interest.We consider, however, that the Department of Works should
have at least
sent an acknowledgment to each of the interested groups,
indicating when
a more detailed information package would be available,
which could be
used to formulate firm proposals for the project.Chapter 6
38
When we expressed this opinion in our preliminary report, the
Department
of Works advised that, in fact, several of the expressions of
interest were
acknowledged. We were referred to letters sent to Connell Wagner and
Ove Arup and Partners Pacific and to a telephone call made to the
Robert
Laurie Company. [EXHIBIT 261, page 1]We accept that acknowledgements were given to each of these
companies
in the manner described. [EXHIBITS 17A, 19A AND 20AA]However, acknowledgements were not given to the other twelve
interested
parties. In his response to the Ombudsman Commission, the Secretary
for Works, Mr Hitolo, gave an explanation for this:‘It seems that the major reason that E0Is were not acknowledged
was the rush
that things were done in. This meant that a proper terms of -
Page 45 of 397
-
reference (TOR)
was not sent out, so most EOI’s came in, not so much as
expressions of interest,
but as queries about the project. Concurrently, Mr Newberry was
singlehandedly writing a further TOR (which would have involved a
full team
of !specialists for a project of this scope and magnitude) and
handling all of
the other National Road Design Projects. For a period Mr Newberry
was (or
very nearly was) the only Road Engineer in the Roads & Bridges
Branch, where
the work load is more than 10 engineers ems could handle. He
probably ran out of
time to perform everything. This staff shortage still plagues the
branch…One further complication was that Department of Transport
contacted some of
the parties independently, asking for different information and
receiving their
expressions of interest. These were then passed on to Department
of Works two
weeks after the dosing of expressions of interest.These factors all contributed to the overlooking of the
acknowledgement of
most of the Expressions of Interest. There is no indication that
the failure to
acknowledge them was purposeful.’ [EXHIBIT 263, page 1]While we appreciate the difficulties faced by any Department
suffering
from shortages of staff or other resources, the Ombudsman Commission
remains critical of the Department of Works for not sending
acknowledgements to all the companies which had expressed interest
in
the project. It was a simple administrative task to perform. It was
wrong
of the Department of Works not to carry it out.Chapter 6
39
[6.6] BREAKDOWN IN COMMUNICATION BETWEEN DEPARTMENT OF WORKS
AND DEPARTMENT OF TRANSPORTWe noted earlier that despite the Minister for Transport’s
direction that the project be handled by his Department, the -
Page 46 of 397
-
advertisements calling for
project be handled by his Department, the advertisements
calling for
expressions of interest were actually organised by the
Department of
Works.This was very surprising because it is clear that the Minister
for Transport, Mr Temo, and the Secretary for Transport, Mr
Amini, both genuinely
Mr Temo, and the Secretary for Transport, Mr Amini, both
genuinely
believed that the project “belonged” to the Department of
Transport.The Ombudsman Commission formed this view after interviewing
both Mr
Temo and Mr Amini in the course of the investigation. It was
also apparent
from correspondence between the Minister and the Secretary for
Transport, that the project was regarded as belonging to the
Department
of Transport. We refer, for example, to a letter from Mr Amini
to Mr Temo
on 28 June 1990 in which, only a few days after publication of
the
advertisement, Mr Amini gave Mr Temo an update on the
expressions of
interest for his “advice and directive”. [EXHIBIT 1 9][6.7] DEPARTMENT OF TRANSPORT SUDDENLY INVITES DETAILED
PROPOSALSThe closing date given by the advertisements for registration
of
expressions of interest was 31 July 1990. The Ombudsman
Commission
was surprised to find that before that date, the Department of
Transport
decided – without consulting the Department of Works -to
contact a
selected group of companies and invite detailed proposals for
the project.Chapter 6
40
[6.8] ONLY A SELECT GROUP OF COMPANIES WERE INVITED TO SUBMIT
PROPOSALS IN JULY 1990 -
Page 47 of 397
-
This surprising turn of events occurred around the period
17-20 July 1990.
A pro-forma letter headed “HEARING FOR DEVELOPMENT OF THE
SPRING GARDEN ROAD” was drafted within the Department of
Transport
[EXHIBIT 20A]. It was apparently meant to be sent to all the
companies
which had lodged expressions of interest. We infer this from
the “List of
Interested Companies” attached to the pro-forma letter in the
Department
of Transport file. [EXHIBIT 20A, page 3]However, the Ombudsman Commission is not satisfied that the
letter was
in fact sent to all of those companies. There is no evidence
on file
verifying the postage or facsimile transmission of the letter
to all of the
companies that had lodged expressions of interest.Furthermore, the list in the Department of Transport file
excludes four
groups that had registered interest with the Department of
Works:Curtain Bros (PNG) Pty Ltd;
Cardno & Davies (PNG) Pty Ltd;
Maunsell Consultants/Hornibrook
Constructions Pty Ltd; andJuara Ltd.
Chapter 6
41
[6.9] WHY WERE SOME COMPANIES DROPPED FROM THE UST?
[6.9] WHY WERE SOME COMPANIES DROPPED FROM THE UST?Perhaps the reason for these companies not being on the
Department of
Transport’s list was that their expressions of interest were
received later
than the others (the four referred to above were received by
the
Department of Works during the period 27 July 1990 to 1 -
Page 48 of 397
-
August 1990).
But other than the expression of interest from Maunsell/
Hornibrook (which
was one day late) all were received within the period
specified in the
advertisement.There was therefore no justification for these companies
being dropped
from the list and deprived the opportunity to submit a formal
proposal.During the course of the Commission’s investigation,
representatives of
both Cardno & Davies and the Maunsell/Hornibrook consortium
were
questioned and they confirmed that they had never received
any formal
acknowledgement of their expressions of interest, or been
invited to submit
a formal proposal.It is surprising that these particular companies were omitted
from the short- list, even though they all have permanent
bases in Papua New Guinea and
list, even though they all have permanent bases in Papua New
Guinea and
their expressions of interest were among the most detailed of
those
received by the Department of Works.Indeed, it is ironic that the company which provided the
least amount of
information in its expression of interest – Curtain Bros
(PNG) Pty Ltd – was ultimately selected to be closely
involved in construction of the freeway.
ultimately selected to be closely involved in construction of
the freeway.
[EXHIBIT 23]Chapter 6
42
[6.1 0] RESPONSE BY THE SECRETARY FOR TRANSPORT
When we made these findings in our preliminary report, the
-
Page 49 of 397
-
Secretary for
Transport, Mr Amini, responded in the following terms:‘The Department did not receive any complaint from any
developer. I will urge
the Ombudsman Commission to be cautious in promoting any
particular
developer. If it was unreasonable, at least one or two of
the developers would
have made suggestions as they always do. No developer was
ever stopped or
prevented from submitting a proposal. They were actively
encouraged. In any
case, the submission date was extended twice to
accommodate late bids. This
is not defective administration.’ [EXHIBIT 254, page 31The Ombudsman Commission does not regard Mr Amini’s response
as
satisfactory. His assertion that no developer was ever
prevented from
submitting a proposal is not borne out by the facts.We are not suggesting the Department rejected or refused to
accept any
proposal. What the Department did wrong was to invite
proposals from
only a select group of companies, thus excluding a number of
companies
from consideration.[6.11] OTHER MATTERS OF CONCERN
The Ombudsman Commission is not only concerned about the
Department
of Transport letter being sent to only a select group of
companies. What
is also disconcerting is the timing of the letter and the
demands placed
upon the companies chosen to receive it.The Ombudsman Commission has been able to confirm that the
letter
inviting proposals was sent, during the second half of July
1990, to at least
five of the companies and consortiums referred to on the -
Page 50 of 397
-
Department of
Transport list:Chapter 6
43
Coecon Pty Ltd [EXHIBIT 20B]
Willing and Partners Pty Ltd [EXHIBIT 22A]
Ove Arup & Partners Pacific Pty Ltd [EXHIBIT 28]
Sabina Ltd/Peter Chen & Partners Pty Ltd [EXHIBIT 30]
Kumagai Gumi Co Ltd/Kinhill Kramer Pty Ltd. [EXHIBIT
31][6.12] THE DEPARTMENT’S REQUIREMENTS COULD NOT BE MET
Unreasonable and unrealistic demands were imposed by the
Department
of Transport. The letter stated:“Dear Sir
HEARING FOR DEVELOPMENT OF THE SPRING GARDEN ROAD
This is to inform you of the fact that the Steering
Committee administering
the above-mentioned project will be meeting to consider
your proposals and
you are advised to send the details to this Department
before the 25/7/90.The following planning information is required from you to
assist the
Government in selecting the developer. -
Page 51 of 397
-
I. Technical Feasibility Report
2. Preliminary Design or Plans.
3. Financial Viability for a Toll System.
4. Details of Financial Arrangements.5. Involvement of Landowners in the Development
Chapter 6
44
Since the Government is anxious to complete this project
by September next
year in preparation for the South Pacific Games, it is
important that you state
very clearly whether you can achieve this time frame.Yours faithfully
[Signed]
BRIAN K AMINI CBE
Secretary’. [EXHIBIT 20A]The Ombudsman Commission is at a loss to see how the
Department of
Transport could reasonably have expected these requirements
to be met
within one week. The only specifications available to the
companies were
those in the June 1990 advertisements. How could they be
expected to
submit meaningful technical feasibility reports, preliminary
designs and
financial arrangements, as well as give a proper assessment
of the financial
viability of a toll system and the involvement of landowners,
in the space
of a few days? -
Page 52 of 397
-
As one consultant explained to the Ombudsman Commission, a
detailed
feasibility study of the type being sought by the Department
of Transport
would cost thousands of kina and it would take considerably
longer to do
than the few days suggested in the letter.In sending this letter, the Department of Transport gave the
impression it
had no idea at all of what was involved in a project of this
magnitude.[6.13] MR HETOLO’S EXPLANATION
In his response to our preliminary report, the former head of
the Policy
Secretariat in the Department of Transport, Mr Hitolo, made
these
comments:Chapter 6
45
‘The unreasonable and unrealistic demands were placed on
the plight&
developers because the department was under pressure to
meet the September
1991 Games as mentioned in the letter. This letter was
sent to a selected few
which was a normal practice and usually is called
selective tendering. As long
as three or more proposals are tendered a selection can be
convened. The
whole purpose was for interested and so-called reputable
companies to propose
a plan of execution of the tasks mentioned in the letter
and propose an
alternative if they cannot meet the deadline of September
Games stated in the -
Page 53 of 397
-
letter. It was not mandatory to include all those that
showed interest because
some of the companies saw me personally or phoned to find
out whether
funding was available and when it was explained otherwise
they indicated
disinterest as most of them are not financiers. They only
offer their engineering expertise and were unable to
finance such a big project.•
expertise and were unable to finance such a big project.•
[EXHIBIT 265, page 3]Mr Hitolo’s explanation that representatives of some companies
had seen
him personally or telephoned to find out whether funding was
available is
not considered satisfactory. There were no file notes kept of
the occasions
on which these companies signalled their loss of interest in
the project. We
are also unimpressed by the suggestion that, provided at least
three
proposals were received, a proper selection could be made.The private and undocumented “selective tendering” evident in
the limited
dispatch of the letters of July 1990 is very, very dangerous,
because it can
easily lead to corruption. It is vitally important that the
public tendering
procedures in the Public Finances (Management) Act are
strictly adhered
to, especially in projects which involve millions of kina of
public money (see
Chapter 35).6.14] LETTERS WERE SENT LATE
The unreasonableness of the demands contained in the letters
of July 1990
was exacerbated by the fact that the letters were sent late. -
Page 54 of 397
-
Chapter 6
46
Of the five companies we verified as receiving the letter,
only one received
it before the deadline for submission of proposals. [See the
reference in
each of EXHIBITS 28, 30 and 31 to the letter having arrived
late and the
date-received stamp of 26 July 1990 on EXHIBIT 22k]An example of the confusion caused by the Department of
TransportCoecon Pty Ltd received its letter by facsimile transmission
at 9.32 am on
20 July 1990, but the company was obviously (and
understandably)
confused as to what was required of it. At 2.25 pm on the
same day, the
General Manager, Mr P J Neville, sent a facsimile message to
the Principal
Engineer (Roads), Mr Newberry, at the Department of Works:‘Please advise us of present stage of development for
Burns Peak. For instance:
any technical reports such as preliminary design plans
etc.’ [EXHIBIT 711There is a handwritten note at the foot of that document
(though it is not
clear who its author is, it was probably made by an officer
of the
Department of Works) that typifies the general state of
confusion:‘The information requested of Department of Works by
Coecon is what is
requested of Coecon by Department of Transport. We seem to
be going around
in circles? [EXHIBIT nj -
Page 55 of 397
-
[6.15] ADMINISTRATIVE INCOMPETENCE BY THE DEPARTMENT OF
TRANSPORTTo sum up, the Ombudsman Commission is of the view that the
conduct
of the Department of Transport in dispatching the pro-forma
letter dated
17 July 1990, advising companies that they had to send
details of their
proposals by 25 July 1990, was unfair, unrealistic and
incompetent
administratively for the following reasons:Chapter 6
47
(a) the letter was sent to only a select group of
companies and,
furthermore, excluded the two PNG-based companies
which
had submitted detailed expressions of interest;(b) the Department of Transport failed to advise the
Department
of Works (which was co-ordinating the expressions
of interest)
that it was sending the letter;(c) the letter placed unrealistic demands on the
companies,
which made it impractical for them to respond by
the
deadline;(d) the deadline for submission of proposals was on a
date It
before the closing date given in the
advertisements for
registration of expressions of interest; and(e) the letter was sent late, which resulted in most
of the
companies not receiving it until after the
deadline set for
submission of proposals. -
Page 56 of 397
-
[6.16] SOME COMPANIES WERE NEVER GIVEN ANOTHER OPPORTUNITY TO
SUBMIT PROPOSALSThe conduct of the Department of Transport during July 1990
cannot be
dismissed as a mere administrative hiccup. It would have
been possible
to *forgive” the Department for its unfairness and
incompetence if, at some
later time, a proper opportunity to submit detailed
proposals was given to
a companies which had expressed genuine interest in the
project. But this
never happened.f’hRpter 6
48
As we show later in the report, a number of companies
were never
considered or even contacted by the Department of
Transport again. This
was a disgraceful state of affairs.When this sort of thing goes on, how can honest and
responsible
companies have confidence in the Department of
Transport, or any other
Department for that matter? How can anybody have
confidence in the
integrity of government in Papua New Guinea? The
selective picking-
and-choosing of companies to submit proposals must be
avoided at all
costs, since it is unfair and not in the best interests
of the State and such
practices breed corruption.[6.17] LITTLE RESPONSE TO THE REQUEST FOR PROPOSALS
The Department of Transport’s attempt, in July 1990, to
get the “selected”
companies to submit proposals, was so badly
implemented, that hardly
any of those companies responded. This meant that in
1991, the -
Page 57 of 397
-
shortlisting process had to begin again.
But as we show in Chapter 9, the shortlisting process
in 1991 was also
carried out in an arbitrary, unfair and unsatisfactory
way.* * * * * * * * * *
Chapter 6
49
SIGNIFICANT INTERDEPARTMENTAL MEETING:
31 JULY 19907.1] ORIGINAL PURPOSE OF MEETING
An interdepartmental meeting, involving representatives of
the Departments
of Transport, Works, Finance and Planning and Attorney-
General, was held
on 31 July 1990. It was jointly chaired by the Secretary
for Transport, Mr
Amini, and the Secretary for Works, Mr Temu.It was originally intended that the meeting would consider
proposals invited
by the Department of Transport’s letters of 17-20 July
1990. [See the
minute from the Director of the Department of Transport’s
Policy
Secretariat, Mr Hitolo, to Mr Amini dated 27 July 1990 at
paragraph 2 and
the handwritten notes which refer to the “selection
criteria”: EXHIBIT 24.] -
Page 58 of 397
-
However, because the letters were sent late, the companies
could not
respond in time. Rather than being a forum for assessment
of proposals
the meeting therefore focused on other important issues
concerning the
project.2] ISSUES DISCUSSED AT THE MEETING OF 31 JULY 1990
The minutes of the meeting record discussion of the
following issues:Chapter 7
50
The name of the project – the Secretary for Transport
favoured the name “Spring Garden Road (Burns Peak) Link”.Funding of the project – Mr Hitolo advised that the World
Bank had been approached.The Port Moresby Roads Needs Study – the First Assistant
Secretary of the Department of Transport’s Planning and
Research Division, Mr Parakei, advised that the Burns Peak
project was part of the Study.Engineering details – the Department of Works’ Principal
Engineer (Roads), Mr Newberry, addressed the tunnel/cut
option, particularly the problems associated with disposal of
the cut.Landowner issues – Mr Hitolo advised that preliminary
discussions had been held with landowners, some of whom
were claiming lump sum payments prior to commencement
of the project.Scope of the project – some consideration was given to
upgrading other sections of the Spring Garden Road network,
particularly Wards Road to Waigani Drive. -
Page 59 of 397
-
Target date for completion – it was generally agreed the
project could not be completed by the original target of
September 1991, coinciding with the South Pacific Games.
[EXHIBIT 33]Chapter 7
51
[7.3] FUTURE ACTION
[7.3] FUTURE ACTIONAs to the next action to be taken, two things were decided:
1. The National Executive Council was to be informed that the
project
could not be completed for the South Pacific Games.2. Further geological investigations would have to be
undertaken, so
that a decision could be made on the tunnel/cut option.
[EXHIBIT
33, paragraph 5 and EXHIBIT 51, page 4, para 3][7.4] PROPOSALS WERE NOT CONSIDERED AT MEETING ON 31 JULY 1990
[7.4] PROPOSALS WERE NOT CONSIDERED AT MEETING ON 31 JULY 1990
MAIAITLOILEBIEIEIIING
We note there is a reference to this meeting of 31 July 1990
in the Policy Submission presented to the National Executive
Council in February 1992,
Submission presented to the National Executive Council in
February 1992,
which led to the decision to award the project to Kinhill
Kramer Pty Ltd
(see Chapter 21).It was suggested in the Policy Submission that the various
expressions of interest and proposals had been presented at
the meeting of 31 July 1990.
interest and proposals had been presented at the meeting of 31
July 1990.However, it is quite dear, from the minutes of the meeting and
other
documents considered by the Ombudsman Commission, that the
proposals were Dot presented at that meeting. There were no
proposals,
as at 31 July 1990, that could be considered. -
Page 60 of 397
-
Moreover there was never, in the life of the Spring Garden
Road/Poreporena Freeway project, any interdepartmental meeting
at which
all the proposals were considered. Neither was there a meeting
within theChapter 7
52
Department of Transport at which all the proposals were
considered. There
was not even a meeting at which all the expressions of
interest were
considered.The Department of Transport’s failure to methodically consider
all options
available to the Government was one of the worst aspects of
the decision-
making process that led to the National Executive Council
decision in
favour of IGnhill Kramer Pty Ltd in February 1992.It was very unfair of the Department of Transport to
arbitrarily reject
expressions of interest from other companies that had put
considerable
time and effort into responding to the June 1990
advertisement.[7.51 SECRETARY FOR TRANSPORT CLAIMS THAT ALL OPTIONS WERE
CONSIDEREDWhen we put these allegations to the Secretary for Transport,
he claimed
that all options were considered:“As I have said, all options were considered, including the
Barclay proposals.
Mr Lohia Hitolo with his immense breath of experience and
qualifications, did
the assessment. Although he did not use the preferred
approach, nevertheless,
the approach he used has been used quite often by the -
Page 61 of 397
-
Department of Works
Design Branch. In addition, an NEC sub-committee reviewed
his assessment
This is not defective administration.”[EXHIBIT 254, page 4][7.6] MR HITOLO CONCEDES THAT SOME COMPANIES WERE REJECTED ON
THE BASIS OF THEIR EXPRESSION OF INTERESTIn contrast to Mr Amini’s response, the former head of the
Department of
Transport Policy Secretariat, Mr Hitolo, conceded some
companies had ngt
been seriously considered. The reason, he said, was that their
expressionsChapter 7
53
of interest did not state that they were willing to
finance the project.
[EXHIBIT 265, page 3, para 5].7] FAILURE TO CONSIDER ALL OPTIONS
In our view, Mr Hitolo’s response is testimony to the
lack of effective
communication which pervaded the whole project.As we pointed out in Chapter 5, the June 1990
advertisement did rat state
that the successful contractor had to itself finance the
project. Nor had
such a requirement been imposed by the National Executive
Council.It was therefore unfair and wrong of the Department of
Transport to
summarily reject companies, simply because they had not
indicated an
ability to provide finance.In the opinion of the Ombudsman Commission, by failing to
convene a
meeting at which all expressions of interest could be
formally considered,
the Department of Transport failed to consider all of the -
Page 62 of 397
-
options available
to the Government. This was wrong and defective
administration.* * * * * * * * * *
Chapter 7
54
8. PROGRESS DURING SECOND HALF OF 1990
[8.1] A PERIOD OF INACTION 1
The period between the meeting of 31 July 1990 and the
beginning of
1991 was significant in three respects:1. There was little action taken to follow-up the
expressions of
interest.2. The geotechnical survey was initiated by the
Department of
Works, but not completed.3. A draft information paper was prepared for the
National
Executive Council, but not presented.LACK OF ACTION FOLLOWING INVITATION FOR EXPRESSIONS OF INTEREST
[8.2] DEPARTMENT OF WORKS GUILTY OF DEFECTIVE ADMINISTRATION
Other than the unsuccessful attempt by the Department of
Transport in
July 1990 to obtain firm proposals from some companies, no
further action -
Page 63 of 397
-
was taken by either the Department of Transport or the
Department of
Works during the second half of 1990 to follow-up the
expressions of
interest.Chapter 8
55
It is apparent that Mr Newberry, of the Department of Works,
drafted a
letter of acknowledgment around the end of October 1990, which
was
intended to be sent to all companies which had expressed
interest.
[EXHIBIT 50]. But this was not done. The letter was drafted
very late and
shows incompetence by the Department of Works. In a minute to
the
Secretary of the Department of Works, Mr Temu, on 11 January
1991, Mr
Newberry conceded “an acknowledgement should have been sent’,
and
added “… but I wished to advise them what was happening or
going to
happen. There was/is considerable confusion over the
acceptability of a
tunnel proposal.” [EXHIBIT 51, page 5, paragraph 3]In our view, this was not an acceptable reason for not sending
the
acknowledgments. A number of companies had invested time and
expense in formulating their expressions of interest and the
very least they deserved was an acknowledgment. Mr Newberry’s
draft letter of 31
deserved was an acknowledgment. Mr Newberry’s draft letter of
31
October 1990 correctly and succinctly stated the position as
at that date
and we can see no good reason for it not being dispatched,
although it
was very late.Since the Department of Works was at that time co-ordinating
the
expressions of interest, it should be held responsible for
this bad
administrative error.THE GEOTECHNICAL INVESTIGATION
THE GEOTECHNICAL INVESTIGATION -
Page 64 of 397
-
[8.3] PROS AND CONS OF TUNNEL AND CUT
[8.3] PROS AND CONS OF TUNNEL AND CUTThe most important outcome of the interdepartmental meeting of
31 July
1990 had been the decision to conduct a comprehensive
geotechnical
investigation of the Burns Peak Saddle.Chapter 8
56
The rationale for this decision was explained in a minute
from Mr Newberry
to the Secretary for Works on 11 January 1991:‘Confusion was increased by the letter/fax sent by DOT to
some of the
registrants on 20 July. The DOW/DOT meeting on 31 July did
clarify some of
the issues.
Since that time Works has proceeded on the basis that no
requests can be made
for detailed proposals until the additional geotechnical
investigation provides
data sufficient to allow a developer to make a reasoned
choice between a tunnel
and a cut.The concept of the project if a tunnel is chosen is
entirely different from that
if a cut is to be constructed. A tunnel provides very
little material for filling
or for use in other parts of the construction. If any
reclamation is to be carried
out it would have to be from imported materiaL The road
pavement and fill
materials would also have to be imported. The tunnel also
has a continuing
high operation and maintenance cost. The tunnel option
also carries a higher
risk of damage, closure or operational loss as a result of
an accident or
vandalism particularly with only a single two lane tunnel
for the initial period.
The presently proposed tunnel cross section may be
inadequate for safe use by -
Page 65 of 397
-
trucks carrying containers. Trucks with dangerous
materials would not be
allowed to use the tunnel but would have to use an
alternate route.It has been claimed that the tunnel would allow a grade of
only 3% for the
road connection. This is possible but would require a
tunnel of much greater
length and cost than that presently proposed. The present
proposal has grades
of over 8% on the western approach road.The cut provides considerable, possibly excessive,
material for use in the
construction of the project and connecting roads
embankments and pavements
and also for port and other reclamation. The cut would
provide an immediate
four lane road connection. The provision of four-lanes
reduces the risk of
accident, damage and operational loss. However the risk of
loss from collapse
of part of the cut wall still exists with the level of
risk increasing as the cut
slopes are steepened and the volume and cost of the cut
decrease. There is
however increased opportunity for early financial return
from port and harbour
reclamation works which may reduce the financial risks in
the project.The developer has a difficult choice to make between the
tunnel and cut options
and the government also has to make an assessment of the
risks it is prepared
to take and the charges (eg. toll) it is prepared to allow
the developer to make
for provision of facilities.’ (Emphasis added) [EXHIBIT
511[8.4] WHY WAS A FURTHER GEOTECHNICAL INVESTIGATION NECESSARY?
A preliminary study in 1977 by consultants Dames and Moore
had found
it was geologically feasible to build a tunnel, but the
Department of Works -
Page 66 of 397
-
Chapter 8
57
obviously felt that a more detailed investigation should be
carried out. This
point was explained in a press statement drafted by Mr
Newberry on 18
January 1991 (which apparently was not released):The last time a detailed investigation was made of the
underground conditions
along the Spring Garden Road Link from Hohola to Konedobu
was in 1977.
Then holes were drilled in the rock and samples of the
rock taken for
examination. These holes were generally along the line of
a proposed deep cut
It was then decided that the sides of the cut may fall
down unless flatter side slopes were used so a tunnel was
proposed. However tunnels are expensive as
slopes were used so a tunnel was proposed. However tunnels
are expensive as
the rock in the tunnel roof must be supported so that it
does not fall into the tunnel Ventilation also becomes
important as air can only enter and leave at
tunnel Ventilation also becomes important as air can only
enter and leave at
the ends of the tunnel and fans may be necessary.Since 1977 there have been other geological investigations
around Port Moresby
and it is now believed that the underground rock
conditions may be more
complicated than was thought in 1977. It is now considered
too risky to decide
on building either a tunnel or a rock cut without further
investigation of the
underground conditions. This is particularly important
since the estimated cost of the rock cut for a 4-lane mad
is about 1(20 million, 2-lane tunnel would cost about 1(20
million and a 4-lane tunnel would cost about IC40 million with about
another KS million for improvements to Champion Parade, Wards Road,
Waigani
of the rock cut for a 4-lane mad is about 1(20 million, 2-
lane tunnel would cost about 1(20 million and a 4-lane
tunnel would cost about IC40 million with about another KS
million for improvements to Champion Parade, Wards Road, Waigani
about 1(20 million and a 4-lane tunnel would cost about
IC40 million with about another KS million for
improvements to Champion Parade, Wards Road, Waigani
another KS million for improvements to Champion Parade, -
Page 67 of 397
-
Wards Road, Waigani
Drive and the existing sections of Spring Garden
Road.’ [EXHIBIT 52A][8.5] CO-ORDIANATION OF THE GEOTECHNICAL INVESTIGATION
[8.5] CO-ORDIANATION OF THE GEOTECHNICAL INVESTIGATIONThe geotechnical investigation was co-ordinated by Mr
Newberry and also
involved the Senior Engineering Geologist from the Geological
Survey of
PNG in the Department of Minerals and Energy. It was decided
the project
would be offered to a private consultant, so the first step
was to formulate
terms of reference for the project. This was done during
August 1990 by
Mr Newberry. [EXHIBIT 51, page 4][8.6] THE PROCEDURE USED TO SELECT THE CONTRACTOR
[8.6] THE PROCEDURE USED TO SELECT THE CONTRACTORTerms of Reference
The terms of reference was sent to the Department of
Transport for
ratification during August 1990. The Secretary for Transport
replied thatChapter 8
58
his Department agreed with the course of action proposed by the
Department of Works.
[EXHIBIT 42A]Invitations, accompanied by a document entitled “Sub Surface
Exploration
and Assessment for Spring Garden Road Link between Hohola and
Konedobu Via Burns Peak Saddle: Terms of Reference for Consultants
Brief’, were sent in September 1990 to the following companies: -
Page 68 of 397
-
Engineering Geology Ltd, of Lae.
Coffey Partners International Pty Ltd, of Australia.
Cardno & Davies Pty Ltd, of Port Moresby.
Kinhill Kramer Pty Ltd, of Port Moresby
Maunsell Consultants PNG Pty Ltd, of Port Moresby.
Ove Arup & Partners Pacific Pty Ltd, of Port Moresby.
Snowy Mountains Engineering Corporation, of Australia.
Hollingsworth, Dames & Moore (PNG) Pty Ltd, of Port
Moresby. [EXHIBITS 44A, 44B1Failure to publicly invite tenders
We note that there was no public advertisement inviting tenders for
the
geotechnical project. Nor was a “certificate of inexpediency” –
which could
have authorised the selective tendering procedure – issued under
SectionChapter 8
59
40(3)(b) of the Public Finances (Management) Act. This meant that,
though the matter was ultimately referred to a Supply and Tenders
Board,
there had been a breach of the Public Finances (Management) Act.Section 40(1) of the Act requires that tenders be publicly invited
for the
supply of works and services expected to cost more than the
prescribed
amount (which at the relevant time was K5,000.00). The public tender
procedures of the Public Finances (Management) Act are discussed in
detail in Chapter 35 of this report.We are satisfied that none of the exceptions to the general rule
imposed
by Section 40(1) applied in the case of the geotechnical project.The Department of Works therefore acted wrongly, by engaging in the
process of selective tendering without obtaining a certificate of
inexpediency in accordance with the Public Finances (Management)
Act.Evaluation of proposals
-
Page 69 of 397
-
The closing date for submission of proposals was 25 October 1990
and,
according to Mr Newberry’s minute to the Secretary for Works of
January
1991, this was when the task of evaluating the proposals began.
[EXHIBIT
51, page 4] However, because of ambiguity in the wording of the
terms
of reference, due to the incompetence of the Department of Works, it
was
necessary to obtain supplementary proposals from a number of
respondents. This delayed the selection process by at least a month.
[EXHIBITS 48A, 50A, 50B]Submission to Design Priorities Committee and Tender Board
On 5 December 1990, Mr Newberry presented a detailed submission to
the Design Priorities Committee and Tender Board, recommending theChapter 8
60
contract for the geotechnical investigation be awarded to
Coffey Partners
International of Sydney, Australia, at a cost of K184,000.00.
[EXHIBIT 500].
The recommendation was endorsed by the Board at its meeting on
11
December 1990. [EXHIBIT 50F] Coffey Partners International was
subsequently advised it had won the contract and arrangements
were
made to commence the seismic field work during January 1991
[EXHIBITS
50G, 51A][8-7] GEOTECHNICAL INVESTIGATION DURING JANUARY – MAY 1991
The investigation took approximately four months to complete.
A “Burns
Peak Geotechnical Steering Committee” was established to
monitor the
project and progress reports were provided during the course
of the
investigation [EXHIBITS 55A, 64A, 66A, 79A, 80A, 84A]. The
final report
was presented to the Department of Works at the end of May
1991.
[EXHIBITS 87A, 87B]It was recommended that “the deep open cut option through
Burns Peak
Saddle will involve greater financial uncertainty than the -
Page 70 of 397
-
tunnelling option”.
[EXHIBIT 87B, page 29, paragraph 8]The time it took to organise the geotechnical investigation
was a cause of
frustration to some people, including the Minister for
Transport, Mr Temo.
On the EM TV news bulletin of 8 January 1991 he was reported
to be
highly critical of the Department of Works and apparently
blamed the
Department for delaying the project. This prompted a detailed
response
from the Secretary for Works, Mr Temu, which was forwarded to
the
Secretary for Transport in a letter dated 11 January 1991
[EXHIBIT 52]Chapter 8
61
.8] THE GEOTECHNICAL INVESTIGATION CAUSED A DELAY OF NINE
MONTHSIn retrospect, it can be seen that the decision to undertake the
geotechnical investigation delayed the planned commencement of
the
project by about nine months. After the interdepartmental
meeting on 31
July 1990:It took five weeks for the terms of reference for the
consultancy brief to be finalised and invitations for
proposals
to be dispatched.The consultants were given six weeks to lodge their
proposals.Six weeks were spent on clarifying and evaluating the
proposals.The recommendation favouring Coffey Partners International
was before the Design Priorities Committee and Tenders
Board for about a week before a decision was made and
announced.It took Coffey Partners International about five weeks to
mobilise its equipment and personnel and commence the -
Page 71 of 397
-
seismic field work.
The actual investigation, including laboratory testing of
core
samples, took four months to complete (from late January
1991 to late May 1991).Chapter 8
11
62
[8.9] FINDINGS IN RELATION TO THE GEOTECHNICAL INVESTIGATION
1. The need for the investigation
We do not question the need for the investigation.
Irrespective of whether
a tunnel or a cut is built through Burns Peak, safety
considerations
obviously must be paramount.2. IMaltinSIII .cgAngthatthQinvgggigatcKLI8MINKMEM:Y.
investigation
However, we are critical of the Department of Works for the
delay in
making the decision that a geotechnical investigation was
necessary.The decision to go ahead with the Spring Garden Road project
was
conveyed to the Department of Works in late January 1990. The
Department of Works, amongst others, was directed to
“formulate detailed
plans for the construction of the Burns Peak Road”. [EXHIBIT
61■] We
have already noted the impreciseness of that decision and
criticised the
National Executive Council for not being more explicit in its
requirements.
However that does not excuse the Department of Works for its
failure to
expeditiously implement the decision.Nor is it an excuse to say that the Department of Works was
waiting for
an indication from the Department of Transport as to the route
of the road.
The geotechnical investigation was a matter that was clearly
within the
jurisdiction of the Department of Works. -
Page 72 of 397
-
When we raised these matters in our preliminary report, the
Secretary for
Works responded in the following terms:Chapter 8
63
‘What caused the delay in deciding to perform the Geotechnical
Investigation?
Initially it was not projected to perform a further Geotechnical
Investigation.
However, Department of Transport wanted to jump in and build the
project
without any significant planning, while Works was pushing for as
much
planning and advise from specialists as possible. Several times
Mr Newberry
(then Principal Engineer Roads) met with the Geological Survey
Section of
DME to discuss the project. Of specific concern was the “ICold
Fault’ which
was known to run right through the ‘saddle’. It appears that the
requirement
for further investigation was not seriously considered until
advised accordingly
by a Senior Engineering Geologist at an inter-departmental
working group on
19 July 1990 [see Exhibit 51]—This seems to be the conception of
the requirement
for further geotechnical investigation to give a degree of
confidence to any
decision regarding ‘Open Cut” or ‘Tunnel”‘ [OCKIBIT 263, page 1]Having considered this response, the Ombudsman Commission retains
the
view that the Department of Works should have, by itself, raised the
issue
of the need for a geotechnical investigation sooner than it did,
since it is
the appropriate Department responsible for such matters in the
interests
of the State.The excavation of the Burns Peak Saddle was clearly going to be a
complex engineering task. It was up to the Department of Works to -
Page 73 of 397
-
find
out whether any further geotechnical investigation was necessary as
soon
as possible and take follow-up action. The need for this should have
been
raised at least as early as the interdepartmental meeting on 22 May
1990
(see Chapter 4).
NThe Ombudsman Commission considers that the six month delay in
making the decision to undertake the geotechnical investigation was
unjustifiable. Furthermore, in the absence of a certificate of
inexpediency,
invitations to submit tenders for this work should have been
publicly
advertised – not selectively issued.Once the decision was made, on 31 July 1990, to undertake the
investigation, there were some further delays but – with the
exception of
the failure to publicly invite tenders – the Department of Works
handled the
matter well from then on.Chapter 8
64
We note that various proposals were carefully and
methodically evaluated.
The proposal made by Coffey Partners International was
detailed and well
presented [EXHIBIT 48A]. There was a sharp contrast between
the quality
of that document and some of the atrocious documents [eg
EXHIBIT 115]
that were later to be paraded as serious proposals for
construction of the
freeway.Indeed, the professional way in which the geotechnical
investigation
proposals were evaluated was in stark contrast to the events
which later
led to the execution of the contract for the design, finance
and
construction of the Poreporena Freeway. -
Page 74 of 397
-
THE MINISTER FOR TRANSPORTS DRAFT POLICY SUBMISSION OF AUGUST 1990
[8.10] DECISION TO ADVISE NATIONAL EXECUTIVE COUNCIL OF PROGRESS
Besides the decision to undertake the geotechnical
investigation, the other
important outcome of the interdepartmental meeting of 31 July
1990 was
the decision to advise the National Executive Council of
progress on the
project, in particular to clarify the fact that it would be
impossible to finish
the Burns Peak link in time for the South Pacific Games in
September
1991. To this end, a document headed “Policy Submission For
Members
of the National Executive Council” was drafted within the
Department of
Transport in August 1990. [EXHIBIT 36]Chapter 8
65
18.11] CONTENT OF THE DRAFT POLICY SUBMISSION
This document gave an update of the status of the project
as at August1990, and referred to the decision to undertake a further
geotechnicalinvestigation of the Burns Peak Saddle. The bulk of the
document,however, was devoted to explaining the need for public
participation in theplanning process and the preparation of an environmental
impact -
Page 75 of 397
-
statement.
The document concluded as follows:
It is recommended that the Spring Garden Road
project scope includes
the commencement point (Cuthbertson and
Stanley Esp. Junction) at the
Port Moresby main overseas wharf and
termination at the Jackson’s
AirPort-2. It is recommended that an Environmental
Impact Statement be made
of the whole route using the N.S.W. manuals
including soil erosion
guide for the assessment.3. It is recommended that the upgrading to the
Waigani Road and any
other spot improvements along the main
arterial network be done as
a matter of urgency in preparation for the
South Pacific Games in 1991.4. It is recommended that the savings be
immediately identified in the
current capital works and studies votes in
order to implement these
projects.5. It is recommended that the Council note that
advice of the experts for
delay in the opening of the Burns Peak link
and approve the new scope
to be implemented in three stages.6. It is recommended that this project be
developed through involvement
of the private sector and the landowners
using toll for financing.” -
Page 76 of 397
-
.12] WIDE CIRCULATION OF THE DRAFT POLICY SUBMISSION
This document was widely circulated and comments were
received froma number of Government departments. [EXHIBITS 39, 40, 41,
42, 43, 44,48]
Chapter 8
66
Some departments expressed serious reservations about its
recommendations. The Secretary for Finance, Mr Morea Vele,
for example,
was particularly concerned about the economic viability and
the security
risk of the tunnel/toll road proposal. [EXHIBIT 42]The Secretary of the Department of Environment and
Conservation, Mr
Barney Rongap, pointed out that Papua New Guinea had its own
environmental impact legislation – the Environmental Planning
Act (Chapter
No. 370) – and therefore it was inappropriate to rely on the
New South
Wales model for this purpose.The draft policy submission was also sharply criticised
within the
Department of Transport itself. [EXHIBITS 46, 47] The First
Assistant
Secretary (Land Transport Division), Mr M Ume, went so far as
to say:‘It is very difficult to follow what the Submission is
about and perhaps if it is
on Burns Peak then more discussion should be on Burns Peak
Road itself.* -
Page 77 of 397
-
[8.13] RE-DRAFTING OF THE JULY 1990 DOCUMENT
In January 1991, after receiving the views and comments from
various
departments, the Department of Transport redrafted the
National Executive
Council submission. This time, the document was entitled
“Information
Paper For Members of the NEC: Burns Peak Link of Spring
Garden Road”.
[EXHIBIT 54]This document also emphasised the need for an environmental
impact
statement. But it was different to the earlier document in a
significant
respect: whereas the July 1990 document contained very little
discussion
of the method of financing the project, the January 1991
document was
dogmatic in its assertion that “this project will be
constructed under Build,
Operate and Take-over (BOT) system”. [EXHIBIT 54, page 5,
para 2.12]Chapter 8
67
[8.14] POUCY SUBMISSION AND INFORMATION PAPER NOT PRESENTED TO
NATIONAL EXECUTIVE COUNCILThe Ombudsman Commission was surprised to discover that,
despite the
time and effort put into the drafting and redrafting of the
National Executive
Council submission and the wide circulation of the first
draft, neither the
first nor the second draft submission was actually filed with
the National
Executive Council.That is, despite the fact that draft submissions had been
circulated for
more than six months, the National Executive Council was not
fully
informed – as it should have been – of progress on the
project and the
reasons for delay in its commencement. -
Page 78 of 397
-
We note that the Department of Transport complied with the
normal
administrative requirement to give status reports to the
Secretary of the
Department of Prime Minister and National Executive Council.
[EXHIBITS 6C, 25A, 63A, 77A, 87C & 124A]However, the Ombudsman Commission considers that, because of
the
magnitude of the project, the Minister for Transport had an
administrative
obligation to ensure the National Executive Council was fully
and formally
advised of the important developments that were taking place.
In our view,
this duty was not discharged.[8.15] MINISTER FOR TRANSPORT FAILED TO PROPERLY ADVISE NATIONAL,
EXECUTIVE COUNCIL OF PROGRESSThere were some aspects of the August 1990 document which
should
have been brought to the attention of the National Executive
Council as aChapter 8
68
matter of priority, particularly the recommendation that the
scope of the
project be expanded. But this important policy matter was
very poorly
documented and was eventually put before the National
Executive Council,
in February 1992, without explanation or justification. The
scope of the
project, being essentially important, should have been
explained and
defined in detail for the benefit of the members of the
National Executive
Council.The August 1990 document was widely circulated for views and
comments.
The failure to present it reveals a lack of regard for proper
administrative
procedures by the Minister for Transport, Mr Temo. He did not
appreciate
the importance of keeping his colleagues, at the National
Executive Council
level, fully informed of progress of the project and
explaining significant -
Page 79 of 397
-
changes in policy.
[8.16] THE NEED TO KEEP THE NATIONAL EXECUT1VE_COUNCIL FULLY
INFORMEDThere is a lesson to be learned here by all departments and
ministries: if
delays are experienced in the implementation of Government
policies, the
National Executive Council must be advised of the delay and
the reasons
for it.Often there are justifiable reasons for projects not being
implemented as
soon as originally planned. But if the National Executive
Council is not
advised why there has been a delay, it will naturally be
assumed that there
are no good reasons for further delay. The National Executive
Council will
become frustrated and impatient and the environment will be
ripe for the
making of rash and ill-considered decisions in the end.Chapter 8
69
All of these things happened in the case of the Spring Garden
Road/Poreporena Freeway project.3.17] SCOPE OF THE PROJECT
The first recommendation of the August 1990 “Policy
Submission” was that
the scope of the project should be expanded, so as to create a
direct link,
via Spring Garden Road, between downtown Port Moresby and
Jacksons
Airport. [EXHIBIT 36, page 5, para 11.1]However, there was no discussion or analysis – in fact, hardly
a mention –
of this crucial policy decision in the text of the Submission.As we emphasised in Chapter 5, the Ombudsman Commission found
ft
extraordinary that in the course of this investigation we were
not able to -
Page 80 of 397
-
pinpoint when the decision was made to expand the scope of the
project,
from the original proposal to link the two unconnected
sections of Spring
Garden Road between Konedobu and Hohola.The way in which this recommendation was added to the document
–
giving the appearance that it was an afterthought – simply
adds to the
mystery surrounding that decision.18] THE BUILD-OPERATE-TRANSFER CONCEPT
Another feature of the January 1991 draft “Information Paper’
is that it is
the first Department of Transport document which referred to
the Build-
Operate-Transfer method of financing the project.Chapter 8
70
However, just as the August 1990 document failed to explain
or discuss
the pros and cons of expanding the scope of the project, the
January
1991 document failed to weigh the pros and cons of different
methods of
financing the project. [EXHIBIT 54, page 5, paragraphs 2.12 –
2.13]These failures clearly indicate lack of consultation
resulting in the poor
drafting of the documents for the National Executive Council.[8.19] DEFICIENT POUCY MAKING BY THE DEPARTMENT AND MINISTRY OF
TRANSPORTThe fact that both the August 1990 Policy Submission and the
1991
Information Paper documents were only in draft form and never
actually
filed with the National Executive Council means that the
Ombudsman
Commission cannot be overly critical of their contents.But, in the absence of evidence to the contrary, these
documents support -
Page 81 of 397
-
our conclusion that important policy decisions such as the
length of the
freeway and the method of financing were being made by the
Department
and Ministry of Transport without proper analysis or
documentation.SUMMARY OF DEVELOPMENTS DURING 1990
[8.20] PROGRESS DURING 1990
Progress on the project during 1990 can be summarised as
follows:Chapter 8
71
In late January 1990 the National Executive Council directed
the Department of Transport, the Department of Works and
the Department of Finance & Planning to formulate detailed
plans for the project.Nothing was done until 22 May 1990, when the Minister for
Transport chaired an interdepartmental meeting and directed
that design of the project be finalised within six months and
expressions of interest be publicly invited.An advertisement inviting expressions of interest was
published in June 1990 by the Department of Works.Around 17 – 20 July 1990, the Department of Transport invited
a select group of companies to lodge proposals for the
project, but this exercise was incompetently handled, hence
there was little response.On 31 July 1990, it was decided that the Department of
Works would arrange a further geotechnical investigation of
the Burns Peak Saddle.A draft policy submission, intended to provide an update on
progress, was circulated for comment during August and
September 1990. The submission was subsequently revised
but never presented to the National Executive Council.The first version of the submission proposed that the scope
of the project be considerably expanded, but there was no
documented discussion or analysis of this proposal. -
Page 82 of 397
-
Chapter 8
72
On 11 December 1990, the contract for the
geotechnical
investigation was awarded to Coffey
Partners International Pty
Ltd of Australia after invitations were
sent to selected
companies by the Department of Works.[8.21] STATUS OF THE SPRING GARDEN ROAD PROJECT AT THE END OF
1990By the end of 1990:
The National Executive Council had not
been fully and
formally advised of the delay in
commencement of the project
or the apparent proposal to expand its
scope.The geotechnical investigation had not
begun, so no decision
had been made on the tunnel/cut option.No decision had been made on the exact
route or length of
the road.No decision had been made on the method
of financing the
project.* * * * * * * * * *
Chapter 8
73
9. PREPARATION OF SHORTLIST: FEBRUARY 1991
-
Page 83 of 397
-
9. PREPARATION OF SHORTLIST: FEBRUARY 1991
[9.1] FIFTEEN GROUPS HAD EXPRESSED INTEREST
[9.1] FIFTEEN GROUPS HAD EXPRESSED INTERESTThe advertisements in June 1990 inviting expressions of
interest in the
“Burns Peak/Spring Garden Road Link” had attracted fifteen
interested
parties. In July 1990, the Department of Transport made an
abortive
attempt to get some of them to submit firm proposals.It was later decided that the Department of Works would
organise a
detailed geotechnical investigation of Burns Peak, so a firm
decision could
be made on the tunnel/cut option. This investigation began in
January
1991 and continued until May 1991. While that investigation
was still in
progress, a shortlist of prospective developers was prepared.In this chapter we record our findings as to the preparation
of the shortlist.
.MINISTER FOR TRANSPORT PREPARES SHORTLIST
MINISTER FOR TRANSPORT PREPARES SHORTLIST[9.2] WHEN WAS THE SHORTLIST PREPARED AND WHO PREPARED IT?
[9.2] WHEN WAS THE SHORTLIST PREPARED AND WHO PREPARED IT?The Ombudsman Commission has concluded that the shortlist was
prepared in February 1991 by the Minister for Transport, Mr
Anthony
Temo.Chapter 9
74
On 27 February 1991, Mr Temo wrote to the Secretary of the
Department
of Transport in the following terms: -
Page 84 of 397
-
“My Dear Secretary
A total of 15 (Fifteen) companies have shown or
registered expressions
of interest to design and construct the Burns Peak
Road..This is under Turnkey arrangement meaning financing
will be done
by them.The following Companies have been selected for short
list-1. Outlet Year Limited
2. Sietco
3. Barclay Bros and Maunsell Joint
4. Curtain Bros
5. L.K.N. Construction
6. Kumagai Gumi
7. Sabina Group Consortium
Please inform them respectively by way of fax and
organise a bid walk
in 3 weeks from 27/2/91.” [EXHIBIT 631[9.3] A LATE ADDITION TO THE SHORTLIST
On 28 March 1991, the Minister for Transport wrote another
letter to the
Secretary for Transport:‘My dear Secretary
I refer to my letter dated 27 February, 1991 in which I
short listed a number of
companies for the Burns Peak Project. -
Page 85 of 397
-
Chapter 9
75
I now wish to include the following on the short list-
Tasman Pacific International
Please inform the Company accordingly” [F3CIBB1T 69]
[9.4] THE MINISTER PREPARED THE SHORTLIST WITHOUT ADVICE OR
CONSULTATIONIn his response to our preliminary report Mr Temo
emphatically denied
that he had prepared the shortlist. He said the letter to the
Secretary for
Transport of 27 February 1991 was simply a list of companies
which had
sent written expressions of interest to his office. He said
his staff in the
Ministry did not understand the term “shortlist”:‘The various expressions of interest in the Burns Peak
Road project by different
companies was sent by way of letter or verbal to 3
different place:(a) Department of Works
(b) Department of Transport
(c) Chairman of Ministerial Committee and Minister for
Transport.Some companies about 15 contacted my office. About half of
them verbally and
the other half by way of letter or fax.It was the Department of Transport in consultation with
Department of Works
that prepared the short list not me or my office. -
Page 86 of 397
-
Department of Works and the Department of Transport did
their short list and
Chairman of the Ministerial Committee did their own short
list”
[EXHIBIT 257, page 1]With due respect to Mr Temo, the Ombudsman Commission cannot
accept
what he says about the preparation of the shortlist. The
terms of his letter
to the Secretary for Transport on 27 February 1991 were quite
clear: he
advised that seven companies “have been selected for
shortlist”. There is
no evidence the companies on the Minister’s list had written
directly to him,
rather than the Department of Transport.Chapter 9
76
The Ombudsman Commission is satisfied that neither the
Department of
Transport nor the Department of Works had any involvement in
the
preparation of the shortlist. The Minister prepared the
shortlist without
consulting either Department.[a5] MINISTERS SHOULD NOT BE INVOLVED IN IMPLEMENTATION MATTERS
The Minister for Transport’s preparation of the shortlist in
February 1991
was defective administration in a number of respects.First, there was no need for a shortlist to be prepared. The
interested
parties had only submitted expressions of interest in the
project and had
not been given the opportunity to submit firm proposals, so
preparation
of a shortlist was premature.Even if it had been an appropriate time to prepare a
shortlist, this job
should have been done by officers of the Department of -
Page 87 of 397
-
Transport and/or
the Department of Works. It is not the function of a Minister
to prepare a
shortlist for a public works project.Too often in Papua New Guinea, Ministers make unilateral
decisions without
calling on their qualified and experienced Departmental
officers for advice.
This is very bad. If Ministers cut themselves off from their
Departments –
by always giving directions, rather than asking for advice –
it is inevitable
they won’t always have the best information before them on
which to make
decisions.It was very naive of the Minister for Transport to believe he
had the
necessary technical knowledge to prepare a shortlist of
developers without
the advice of his Department.Chapter 9
77 O
Whenever a Minister makes an important decision in this way,
it inevitably
leads to suspicion about his motives. People start to ask
questions. Why
were some companies selected for the shortlist and others left
out? Did
some companies make the shortlist because the people running
them
were friends or wantoks of the Minister? Was anyone bribed? Et
cetera.The only way the People can have confidence in their
Government
departments and Ministers is if normal, established procedures
are
followed.The decision-making process must be above suspicion.
[9.6] SOME COMPANIES WERE SHORTLISTED WITHOUT JUSTIFICATION
The Ombudsman Commission makes the following findings in
relation to
the eight groups shortlisted by the Minister for Transport: -
Page 88 of 397
-
1. Outlet Year Ltd
This Hong Kong-based company had not lodged an expression of
interest.
It first became interested in the project in February 1991,
when the Minister
for Transport travelled to Taiwan and Hong Kong and was
entertained by
the company’s officers and its associates (see Chapter 12).As a result of the Minister’s visit, the company’s Managing
Director, Mr
Leung Keung, wrote a letter dated 12 February 1991 to Prime
Minister
Namaliu. Outlet Year Ltd offered to “design and build Southern
Highlands
Kikori Road and Burns Peak Road in Port Moresby’ and “invest
up to US
dollars 5 billion in Papua New Guinea.” [EXHIBIT 57]Chapter 9
78
On 13 February 1991, Outlet Year Ltd wrote similar letters addressed
to:
“Hon. Anthony Temo, Minister for Transport or Hon. Ted Diro, Deputy
Prime Minister, Acting Transport Minister”. [EXHIBITS 59 & 60]Soon after that, on 19 February 1992, Mr Diro wrote to the Secretary
for
Transport, advising that he had received advice from Mr Temo that
Outlet
Year Ltd be “included in the pre-qualification for all tenders in
Erave-Kikori
and Burns Peak roads in Port Moresby”. Mr Diro directed the
Secretary
to take “necessary actions” in relation to the “pre-qualification”
of Outlet
Year Ltd. [EXHIBIT 61]The Ombudsman Commission was to discover in the course of this
investigation that the Minister for Transport’s trip to Hong Kong,
where he
held discussions with Outlet Year Ltd, was paid for by associates of
that
company. This is wrong.The shortlisting of this particular company was therefore improper.
It should also be noted that the Deputy Prime Minister does not have
power to give directions to a Departmental Head, unless such a power -
Page 89 of 397
-
is
expressly given by an Act of the Parliament or some other law. The
office
of Deputy Prime Minister is created by Section 2 of the Prime
Minister Act
(Chapter No. 27 of the Revised Laws). However it does not carry with
it
any greater power of direction and control than those held by other
Ministers. The purpose of the office of Deputy Prime Minister is to
enable
a Minister to step into the shoes of the Prime Minister whenever the
Prime
Minister is unable to perform the duties of his office or any of the
other
situations in Section 143 of the Constitution exist.Chapter 9
79
That is, the person holding the office of Deputy Prime Minister
is not the
“second-in-charge” of the Ministry and does not have any powers
of
direction and control by virtue of holding that office. His
powers and
responsibilities are at all times constrained in accordance with
Section 148
of the Constitution (see Chapter 39).2. Sietco
The company known as Sietco (PNG) Pty Ltd is a PNG off-shoot of a
government agency in the People’s Republic of China, known as the
“China Sichuan Corporation for International Techno-Economic Co-
operation”. Neither of these groups had lodged an expression of
interest.Sietco is interested in road construction projects in the
Southern Highlands
Province and, during 1991, the company had a very close business
connection with the Minister for Transport, Mr Temo. In fact,
just a few
weeks before directing that Sietco be included on the shortlist,
the
Minister’s family company, Outskirts Construction Pty Ltd, had
entered into
a “partnership agreement” with Sietco, whereby the two companies
agreed
to jointly invest in Papua New Guinea and set up a “partnership
enterprise” -
Page 90 of 397
-
to undertake “construction and maintenance of roads and some
other civil
engineering projects as contractor or sub – contractor’. This
agreement
was signed by the Minister, on behalf of Outskirts Construction
Pty Ltd.
[EXHIBIT 55B]The closeness of the relationship between the Minister and Sietco
is further
demonstrated by the fact that only five days before including the
company
on the shortlist, the Minister had visited China and signed an
agreement
with Sietco’s Chinese parent company, which was intended to
clarify the
partnership contract signed just a couple of weeks before in
Papua New
Guinea. [EXHIBITS 62k 62B]Chapter 9
80
When the Minister was interviewed by the Ombudsman Commission, he
was asked whether he thought it improper a company he was so
closely
involved with, was asked by him to lodge a proposal for
construction of
the freeway. He did not deny his close relationship with Sietco
but stressed
that, as soon as the company had expressed an interest, he had
instructed
that it not be further considered because it might not look
right.But, if that is the case, why did the Minister put the company on
the
shortlist?The Ombudsman Commission cannot accept Mr Temo’s explanation and
is forced to conclude that his decision to shortlist this company
was
improper.3. Barclay Bros and Maunsell Joint
Both of these groups had lodged expressions of interest -but not
as joint
venturers. Maunsell Consultants were linked with Barclay Bros in
1988
(see Chapter 2), but had actually lodged a joint expression of
interest with -
Page 91 of 397
-
Baulderstone Hornibrook in response to the June 1990
advertisement.The Minister’s decision to link Maunsell with Barclay Brothers
therefore did
not make sense.4. Curtain Bros
This company – though it ultimately became closely involved with
the
consortium selected to undertake the project – had submitted the
expression of interest with the least amount of detail.Chapter 9
81 ■
While it is an established construction company, with experience
in Papua
New Guinea, we query its inclusion at the expense of other
companies
which had expressed their interest in the project in a more
active and
detailed manner.5. LKN Construction
This Singapore-based company, represented by LKN (PNG) Pty Ltd,
had
lodged a two page expression of interest in July 1990.6. Kumagai Gumi
This Japanese company had lodged a joint expression of interest
with
Kinhill Kramer Pty Ltd in 1990. The company had shown interest
in the
project for some time.7. Sabina Group Consortium
Peter Chen and Partners, of Brisbane Australia, had lodged an
expression
of interest on behalf of the Sabina Group Consortium, in July
1990. A
brochure, giving details of the consortium’s previous
activities, was
enclosed, but otherwise no details concerning the Spring Garden
Road
project were provided.8.. TagitaL.PagifiCalea
-
Page 92 of 397
-
This PNG company is essentially a K2.00 shelf company, which
operates
a small consultancy business in Port Moresby. It was added to
the
shortlist one month late. At the relevant time, its 100%
shareholder was
Mr Sam Pepena.The Ombudsman Commission also became aware that the Deputy Clerk
of the National Parliament, Mr Ano Pala, had a close association
with the
company.Chapter 9
82
Tasman Pacific International has few assets and no employees.
It has no
experience in road construction or design. It had not lodged
an
expression of interest.The company later joined with the Australian company Cooks
Mitchell
Peacock Stewart Pty Ltd to lodge a formal proposal for the
project.However, in March 1991, there was little justification for
Tasman Pacific
International being on the shortlist at the expense of other
established
PNG companies.[9-7] PREPARATION OF THE SHORTLIST WAS IRRESPONSIBLE AND
QUESTIONABLEThree of the groups on the shortlist had not submitted an
expression of
interest. Of these, the Ombudsman Commission discovered that
the
Minister for Transport, Mr Temo, had direct negotiations with
two of them
(Outlet Year and Sietco) outside Papua New Guinea, just a
couple of
weeks before he gave the shortlist to the Secretary for
Transport. The
other one – a Port Moresby shelf company with no experience in
road
construction or design, Tasman Pacific International – was
added to the -
Page 93 of 397
-
shortlist one month later.
Question-marks also surround the decision to put companies
such as
Curtain Bros and Sabina on the shortlist, because their
expressions of
interest were flimsy compared with the carefully documented
expressions
of interest submitted in July 1990 by established PNG
consulting firms
such as Cardno & Davies and Maunsell Consultants.Chapter 9
83
In the opinion of the Ombudsman Commission the most favourable
view
that can be taken of the Minister for Transport’s shortlist is
that it was
unfair and arbitrary. But unfortunately the way in which it was
prepared
leaves room for suspicion that the Minister for Transport was
compromised.
Whether this was, in fact, the case, the Ombudsman Commission
cannot
say, because we found no hard evidence of bribery.However, the evidence shows that, if the Minister was not
compromised,
he was at least naive and irresponsible in believing that he
alone – and not the officers of the Department of Transport or
the Department of Works –
the officers of the Department of Transport or the Department
of Works –
had the necessary technical expertise to decide which companies
were
to be shortlisted.VENTS AFTER PREPARATION OF SHORTLIST
).8] WHAT ACTION WAS TAKEN FOLLOWING PREPARATION OF THE
MINISTER’S SHORTLIST?Shortly after preparation of the shortlist, a standard letter
was drafted
within the Department of Transport, over the signature of the -
Page 94 of 397
-
Secretary for
Transport, Mr Amini.Copies of this letter – dated 8 March 1991 – were apparently
intended to
be dispatched to each of the shortlisted companies, explaining
the
information to be contained in their proposals.Chapter 9
84
The letter read, in part:
Your company has been short-listed for the above-
mentioned project and you
are hereby requested to send K40.00 … for cost of
reproducing the Terms of
Reference and preliminary “Economic’ and “Financial
Assessment’ reports plus
air mail to your address if you do not have an
Office here in Port Moresby —Your proposal should contain the following
information:-Financial Plan
1.1 Traffic Forecasts
Traffic throughout estimates and
anticipated growth of Pori
Moresby with your estimate of timing for
maximum capacity,1.2 Design, construction and other
associated costs for suggested
alternative schemes must be on a fixed
prize [sic] basis.These conceptual designs should
estimated Bills of Quantifies
for our guide only.
The estimate of total project cost must
include the engineering -
Page 95 of 397
-
elements of the work as well as costs
payable to Government,
including a land premium for area
occupied if and when needed,
An estimate cost of setting up the
project company for this
project and training the operatives
prior to opening _11
[EXHIBIT 64, page 1]The letter concluded by stating:
It must be pointed out very clearly that all
financing will be your
responsibility.” [EXHIBIT 64, page 3][9.9] MISSING DOCUMENTS
There are some perplexing things to note about the
standard letter drafted
by the Department of Transport. In particular, there are
no copies of it on
any Department of Transport files that the Ombudsman
Commission
inspected: there is simply no Departmental record that
these letters were
sent, or even that they were drafted.Chapter 9
85
We only became aware of their existence when the former Minister for
Transport, Mr Temo, was summoned to appear before the Commission
and produce relevant documents. Mr Temo had fourteen copies of the
letter in his possession, addressed to the following companies:1. Barclay Bros (PNG) Pty Ltd 1
2. Cardno & Davies PNG Pty Ltd
3. Coecon Pty Ltd -
Page 96 of 397
-
4. Connell Wagner (Old) Pty Ltd
5. Curtain Bros (PNG) Pty Ltd
6. Frame, Harvey and West
7. Juara Ltd
8. Kumagai Gumi/Kinhill Kramer
9. LKN (PNG) Pty Ltd – •
10. Maunsell Consultants PNG
11. Ove Arup & Partners Pacific Pty Ltd ■
12. Robert Laurie Pty Ltd
13. Sabina Group Consortium
14. Sietco (PNG) Pty Ltd
[EXHIBITS 64, 64B – 64N] •I
We also became aware that a copy of the same letter – dated 28 March
1991 – was sent to Tasman Pacific International, the company that
was a
late addition to the Minister’s shortlist. There was also no copy of
this
letter in the Department of Transport’s files. [EXHIBIT 68B]Chapter 9
86
[9.10] FURTHER MYSTERY SURROUNDING THE LETTERS OF MARCH 1991
Each of the letters dated 8 March 1991 began by stating:
“Your company
has been short-listed for the above-mentioned project” (but
the letters in
fact had no title). This was very strange. The Minister had
short-listed
seven companies for the project on 27 February 1991. Why were
fourteen
companies being advised by a letter dated 8 March 1991 that
they had
been short-listed? This simply did not make sense.Upon discovering the existence of the fourteen letters dated
8 March
1991, each of which bore the signature of the Secretary for
Transport, the
Ombudsman Commission conducted interviews with -
Page 97 of 397
-
representatives of
four Port Moresby-based companies, among the list of
fourteen:Barclay Bros (PNG) Pty Ltd
Maunsell Consultants PNG
Cardno & Davies (PNG) Pty Ltd
Frame Harvey and West.
Some companies did not receive the Secretary’s letter
Each of the persons interviewed had knowledge of the Spring
Garden
Road project and their company’s interest in it. They each
stated that they
had never seen the letter of 8 March 1991 before. Not only
that, they had
never received acknowledgment of their company’s expression
of interest
in the project, let alone been advised that their company had
been short-
listed.Chapter 9
87
9.11] OTHER COMPANIES DID RECEIVE THE LETTER
Some companies did receive a copy of the letter of 8 March
1991. A
representative of LKN Construction (PNG) Pty Ltd, for
example, was able
to confirm, by checking the company’s files, that the letter
had been
received. [EXHIBITS 66B, 70]It is also likely that Sabina Ltd, of Brisbane Australia,
received a copy of
the letter. [See the letter from Sabina to Mr Amini of 8
April 1991, which
refers to a letter dated 18 March 1991: EXHIBIT 71]9.12] THE SECRETARY FOR TRANSPORTS EXPLANATION
-
Page 98 of 397
-
Mr Amini’s explanation of the confusion over the letters of
March 1991 was
as follows:‘Normally for a common letter meant for more than one
addressee, the original
is signed and then photocopied for the different
addressees to be typed on. In
so doing, the clerks were missing out mating additional
copies for files. In the
end, only one copy was left for filing. This practice was
discovered and
corrected. As far as I am aware, all those short-listed
were sent an invitation.
Some were by facsimile. To suggest that such a simple
mistake could not occur
is just being unrealistic. This is not defective
administration.’ [EXHIBIT 254,
para 71(9.13] DEPARTMENT OF TRANSPORT GUILTY OF DEFECTIVE ADMINISTRATION
We accept Mr Amini’s point that simple mistakes can occur in
any
organisation. But we find it difficult to understand why the
Department of
Transport files contain no record at all of the existence of
these letters.
And why were fourteen letters drafted, when only seven
companies had
been shortlisted? Why did some companies not receive the
letter? Why is
there no record of the existence of the Tasman Pacific
International letter
in the Department’s files?Chapter 9
88
If no proper records are maintained, especially in projects
such as this,
how can the decision-making process be properly put in place
and
justified? -
Page 99 of 397
-
One of the themes of this report is that unequal treatment
was given to
companies which had expressed interest in the project. Some
were treated
very favourably, whereas others did not even have their
expressions of
interest acknowledged.There are too many unanswered questions surrounding the
letters of
March 1991 to dismiss the above matters as a minor
administrative bungle.
We are surprised that the Minister for Transport had copies
of the letters
and not the Department of Transport – though they were signed
by the
Secretary for Transport.We can only conclude that the Department of Transport’s
failure to retain
any record of these letters and the failure to ensure that
all the letters
were sent was a serious case of defective administration,
which had the
effect of denying a number of companies the opportunity of
making a bid
for the project.[9.14] THE STATE OF THE SHORTLIST IN MARCH 1991
In light of the above evidence, the situation with the
Minister’s shortlist, as
at March 1991, can be summarised as follows:In February 1991 the Minister short-listed seven
companies,
two of which had not lodged expressions of interest,
without
the advice of his Department.Chapter 9
89
One month later, the Minister added another company to
the
shortlist, even though it also had not lodged an
expression
of interest. This company had no experience in road
design -
Page 100 of 397
-
or construction. It was advised in writing it had been
shortlisted, but there is no copy of the letter in the
Department’s files.In the meantime, standard letters advising fourteen
companies they had been short-listed, were signed by
the
Secretary for Transport.However, there is no record of the existence of these
letters
in the Department’s files.At least four of the fourteen letters were not
received.At least one of the companies on the Minister’s
shortlist –
Barclay Bros (PNG) Pty Ltd – did not receive the
letter.This was all quite bizarre. However, even stranger things
were to
happen in the months ahead. •[9.15] THE FATE OF THE SHORTLISTED COMPANIES
As at the end of March 1991, the Minister had shortlisted
eight
consortiums for the project. However, when the Ministerial
Committee on
Spring Garden Road met on 18 July 1991, it had a shortlist of
five:Chapter 9
90
Topbay Investment Limited & China Ample
Development Ltd, the Second Surveying & Designing
Institute, Ministry of Railways, People’s Republic of
China, together with Moore’s Investment Group.Kumagai Gumi-Kinhill Kramer consortium.
Periquan’s International Resources Pty Ltd and Pty Ltd
Asia Management Consultants Centre.Tasman Pacific International and Crooks Mitchell
Peacock Stewart Pty Limited. -
Page 101 of 397
-
McConnell Dowell.
Only two of these were on the original shortlist of eight.
So, what
happened to the six groups that disappeared from the list?
And
where did the three new ones come from?[9.16] THE COMPANIES WHICH LEFT THE SHORTLIST
The Ombudsman Commission makes the following observations
in
relation to the six companies which disappeared from the
shortlist:1. Outlet Year Ltd – in June 1991 it was “substituted” by
Topbay
Investment Ltd, another Hong Kong-based company (see
Chapter 12).Chapter 9
91
III2. Sietco (PNG) Pty Ltd – there is no evidence that
this U
company was advised it was on the shortlist. In
fact, there
is no evidence on the Department of Transport
files of any
correspondence from or to this company.III
3. Barclay Bros (PNG) Pty Ltd/Maunsell Consultants
PNG Pty
Ltd – neither of these companies were advised
they had la
been shortlisted.FE
4. Curtain Bros – there is no evidence that either
Curtain Bros
(PNG) Pty Ltd or Curtain Bros (Old) Pty Ltd were
advised II
they had been shortlisted.
5. LKN Construction – on 8 April 1991 LKN (PNG) Pty
Ltd wrote II -
Page 102 of 397
-
to the Department of Transport and advised that
it was
withdrawing its expression of interest. [EXHIBIT
70]6. Sabina Group Consortium – this group was
definitely aware
it had been shortlisted, but was unable to meet
the deadline
for submission of proposals. [EXHIBITS 76, 82,
83][9.17] THE THREE NEW GROUPS “ADDED ” TO THE SHORTLIST
The Ombudsman Commission makes the following
observations in
relation to the three groups included in the July
1991 shortlist, but
not in the March 1991 shortlist:1. Topbay Investment Ltd – this company replaced
Outlet Year
Ltd, but essentially the same group of Asian
businessmen
was involved (see Chapter 12).Chapter 9
92
2. Periquan’s International Resources Pty Ltd – this
company
joined with the Port Moresby consulting firm, Frame
Harvey
West & Maso, and submitted a late proposal. But no
formal
expression of interest had been lodged before this.3. McConnell Dowell – this Brisbane-based company only
heard
about the project in April 1991. On the basis of a
half-page
fax to the Department of Transport and two telephone
conversations with the Director of the Policy
Secretariat, Mr
Hitolo, a letter was dispatched to the company,
advising it
had been shortlisted. [EXHIBITS 74, 75, 77] -
Page 103 of 397
-
SUMMARY OF PREPARATION OF SHORTLIST
[9.18] UNEQUAL TREATMENT WAS GIVEN TO COMPANIES WHICH HAD
EXPRESSED INTEREST IN THE PROJECTThere was a great disparity in the treatment given to the
various
companies that had expressed interest in the Spring Garden
Road project
since July 1990:Some companies were shortlisted, even though they had
not
lodged an expression of interest (e.g. Outlet Year Ltd,
Topbay Investment Ltd, Tasman Pacific International and
McConnell Dowell) whereas others which had lodged
detailed expressions of interest in July 1990 were
excluded
and never received acknowledgement of their interest
(e.g.
Cardno & Davies and Maunsell Consultants).Chapter 9
93
Some shortlisted companies were allowed extensions of
time
to submit proposals [see EXHIBITS 67, 72, 76, 78, 79,
81,
83, 93, 94] whereas others (e.g. Barclay Bros) were
not even
advised they had been shortlisted.The result of this arbitrary and unsatisfactory process was that, by
July
1991, a shortlist of five had been prepared for the consideration of
the
Ministerial Committee on Spring Garden Road.* * * * * * * * * *
-
Page 104 of 397
-
Chapter 9
94
10. TERMS OF REFERENCE FOR THE PROJECT: EARLY 1991
[10.1] PURPOSE OF THE TERMS OF REFERENCE
In early 1991, a document was drafted within the Department
of Transport,
entitled ‘Terms of Reference-Spring Garden Road”. The purpose
of this
document was to describe the requirements of the Department
of
Transport and assist potential developers in the formulation
of proposals.
[EXHIBIT 55]In the Ombudsman Commission’s view, the document was
seriously
flawed and very confusing. It failed to specify the scope of
the project
and its technical parameters. The timing of the document’s
release, its
limited circulation and. its stipulation concerning Build-
Operate-Transfer
financing are also matters for concern.[10.2] THE SCOPE OF THE PROJECT
We reported in Chapter 5 that, despite extensive
investigations, we were
never able to pinpoint who made the decision to extend the
scope of the
Spring Garden Road/Poreporena Freeway project from the
original plan to
link Konedobu, through Burns Peak, with Hohola. -
Page 105 of 397
-
Nor could we determine when the decision was made that a
freeway
should be built all the way from downtown Port Moresby to
Jacksons
Airport.Chapter 10
95
The problem of defining the scope of the project was
exacerbated by the
Terms of Reference document. Whereas the advertisements
published by
the Department of Works in June 1990 had specified
(arbitrarily) that the
new road would link Konedobu and Waigani Drive, the
Department of
Transport’s Terms of Reference simply spoke in vague terms
such as “the
Spring Garden Road Link near the Burns Peak”.[10.3] WHAT DOES THE “SPRING GARDEN ROAD UNK” MEAN?
This term can mean at least three things:
a link between Champion Parade Konedobu and Wards
Road Hohola; ora link between Champion Parade Konedobu and Waigani
Drive; ora link between Champion Parade Konedobu and Boroko
Drive. [See the map at the end of Chapter 2]All of the above alternatives would “link” various
unconnected sections of
Spring Garden Road, which runs from Champion Parade Konedobu
to
Boroko Drive, Gordons.The Terms of Reference document was seriously deficient in
its failure to
specify exactly what was required of prospective developers.
The
qualifying words which appear in the document – “near the
Bums Peak” –
suggest the scope of the project was intended only to be the
link between
Champion Parade and Wards Road. -
Page 106 of 397
-
Chapter 10
96
But if that was the case, why did the State eventually enter
into a contract
for the construction of a freeway going all the way from
downtown Port
Moresby to Jacksons Airport?[10.4] THE TERMS OF REFERENCE DEFIED COMMON SENSE
It seems common sense that when the Government commissions
the
building of a road, one of the first things to decide is
where the road is
going to go and how long it should be. How can a company
lodging a
proposal to build a road estimate the total project cost
(inclusive of design
and construction) when it doesn’t know where the road is
supposed to
go or how long it is supposed to be?In his response to our preliminary report, the Secretary for
Works, Mr
Hitolo, who was responsible for the project for a
considerable time in the
Department of Transport, stated that the scope of the project
was
deliberately not specified in the Terms of Reference
document, because
this was to be a Build-Operate-Transfer project:“Government’s role is purely to create the business
atmosphere conducive to
the private company to become interested in investing on a
scale and scope it
believes it can get a profitable return.” [EXHIBIT 265,
page 3]Mr Hitolo said it would have been premature to specify the
scope of the
project in the Terms of Reference. He also suggested that the
Ombudsman Commission did not understand the Build-Operate-
Transfer -
Page 107 of 397
-
concept.
By contrast, when the Secretary for Transport, Mr Amini,
responded to our
preliminary report, he maintained that the detailed scope of
the project
was contained in the Terms of Reference document. However,
when
asked to point to the section of the document which specified
the scope,
Mr Amini was unable to do so. [EXHIBIT 254, page 4]Chapter 10
97
Quite dearly, the Terms of Reference did nol specify the
scope of the
Spring Garden Road project. It did not state where the road
was
supposed to begin and end. We reject Mr Amini’s claim that it
did. We
also reject Mr Hitolo’s claim that it was unnecessary for the
scope of the
project to be specified.The Ombudsman Commission concludes that the Terms of
Reference
document was vague and confusing, especially because of its
failure to
specify what was required of prospective developers.The inadequacy of the document is borne out by the fact that,
despite its
insistence that proposals be based on Build-Operate-Transfer
financing,
no such proposal was ever lodged with the Department of
Transport.[10.5] THE TERMS OF REFERENCE ALSO FAILED TO SPECIFY THE
TECHNICAL PARAMETERS OF THE PROJECTAnother serious defect in the Terms of Reference document was
its failure
to specify the fundamental technical parameters of the -
Page 108 of 397
-
project. This point
was made by the World Bank Mission which visited Port Moresby
in
September 1991 to monitor the Spring Garden Road project:Mu technical parameters are left =claw as to whether Papua
New Guinea
was seeking a two or four lane road, one or two tube
tunnels, and whether the road surface would be of
compacted gravel or asphalt concrete, and whether an open
cut or tunnel was desired.’
road surface would be of compacted gravel or asphalt
concrete, and whether an open cut or tunnel was desired.’
open cut or tunnel was desired.’
[EXHIBIT 111, at page 1 and see generally Chapter 15J[10.6] TIMING OF THE RELEASE OF THE TERMS OF REFERENCE
The Terms of Reference document was first released in March
1991. This
was before the results of the geotechnical investigation
undertaken byChapter 10
98
Coffey Partners International was completed. However, the
interdepartmental meeting on 31 July 1990 had decided that
firm
proposals would not be called for, until after that
investigation was
complete (see Chapter 7).The Ombudsman Commission therefore seriously questions the
timing of
the release of the document0.7] LAVED CIRCULATION OF THE TERMS OF REFERENCE
An even more serious concern is the fact that the Terms of
Reference
document was only circulated to a limited number of
developers. It was
only those companies shortlisted by the Minister for
Transport, Mr Temo,
in February/March 1991, that were eligible to receive a -
Page 109 of 397
-
copy.
We have already commented on the unsatisfactory and
arbitrary way in
which that shortlist was prepared (see Chapter 9). It would
have been far
better to publicly advertise the availability of the Terms
of Reference,
rather than selectively offer it to only a few companies.Whenever investment opportunities are offered to companies
“selected” by
a Minister, there are bound to be suspicions of corruption.
The best way
to avoid this is to give all interested companies an equal
opportunity to
submit proposals through public advertisements..8] BUILD-OPERATE-TRANSFER FINANCING
A feature of the Terms of Reference document. is that it
dictated that the
project be undertaken using the Build-Operate-Transfer (BOT)
method of
financing.Chapter 10
99
The Ombudsman Commission has been unable to establish how or, even,
when this important policy decision was made, because the Terms of
Reference document is undated and the Department of Transport files
did
not disclose this information. It was certainly never the stated
policy of the
National Executive Council that the project be financed in this way.In the absence of such a policy directive, the Ombudsman Commission
expected to find some evidence that, before stipulating the project
would
be financed in this way, the Department of Transport had carefully
and
methodically considered all the policy options available and
formally made
a decision to invite proposals on the basis of Build-Operate-
Transfer
financing. However, our examination of their files revealed that
Build-
Operate-Transfer financing was addressed only in the following
documents: -
Page 110 of 397
-
the Information Paper that was supposed to be presented to
the National Executive Council, but which never was (see the
final part of Chapter 8); andthe Terms of Reference document. [Exhibits 36 & 55]
Neither document could satisfy us that the decision concerning
Build-
Operate-Transfer financing for the Spring Garden Road project had
been
made carefully or competently.In our preliminary report we suggested that the Department of
Transport
had failed to make a careful, reasoned and properly documented
decision
on financing the Spring Garden Road project. The Secretary for
Transport,
Mr Amini, responded by stating:Chapter 10
100
‘The concept of BOT was debated at length at our Executive
Meetings. It was
introduced by Mr Hitolo. I do not encourage new concepts which
are not fully
assessed for implications and impacts to be put before the NEC.’
[EXHIBIT 254, page 31However, when Mr Amini was pressed on this issue, the only evidence
he
could provide was the minutes of a Department of Transport Executive
Staff Meeting on 14 September 1990. The minutes stated:“Director (Policy Secretariat) said he will prepare a submission
to NEC for
discussion when considering plans for the project on the BOT
system. HOT
stands for Build, Operate and Takeover.The system simply means that the company awarded the contact will
build the
mad (project) and operate it in a bid to recover costs and -
Page 111 of 397
-
expenses. Then hands
the mad back to National Government.” [EXHIBIT 45A, page 4]Mr Amini also provided copies of two papers presented at a Transport
Sector Seminar held in Port Moresby in 1991, which addressed the
issue
of Build-Operate-Transfer financing. One of them was prepared by Mr
Hitolo, then Director of the Policy Secretariat in the Department of
Transport, entitled “Spring Garden Road BOT Concept’. Mr Hitolo
stated:‘The main reason to get Spring Garden Road to be proposed for
financing
through private sector was the fact that the Government’s
intention for this
project to attract aid was not successful despite its good
economic justifications.
Hence the Government, decided to get private funding by directing
the
Department of Transport to assess the turn-key concept as the
basis for
implementing the project. This simply meant that a particular
company be
selected on a competitive basis and get it to arrange a private
loan on behalf
of the Government. As the general policy and understanding was to
use the
private sector for the total financing, construction and
operation so that
efficiency in the private sector may be tapped in the provision
of infrastructure
services.In actual fact the BOT (Build, Operate and Transfer) or the
alternative BOO
(Build, Own and Operate) systems were implied in the above-
mentioned policy.
Hence the concept of BOT system came into consideration followed
by an
invitation for interests in this sort of scheme. Unfortunately,
the concept was
not very well known in this country and therefore the responses
were not
satisfactory.’ [EXHIBIT MA, page 303]Chapter 10
-
Page 112 of 397
-
101
The Ombudsman Commission does not dispute Mr Hitolo’s
expertise. Nor
do we take issue with the Build-Operate-Transfer concept, as
such. As an
innovative method of financing it deserved to be closely and
widely
considered.What we are critical of is the Department of Transport’s
failure to carefully consider all the financing options
available and its failure to formulate a
consider all the financing options available and its failure
to formulate a
policy and advise the Minister for Transport to table it
before the National
Executive Council so that a formal Cabinet policy decision
could be made
on this important issue.10.9] SUMMARY OF THE TERMS OF REFERENCE: INCOMPETENT
ADMINISTRATION BY THE DEPARTMENT OF TRANSPORTThere were many unsatisfactory aspects of the Terms of
Reference
document prepared by the Department of Transport in early
1991:As a document which was supposed to indicate to developers
what
was required in their proposals, it was very vague. It did
not
mention where the road would go, or how long it would be.It also failed to specify basic engineering aspects of the
project.It was prematurely released.
It dictated that the proposals incorporate Build-Operate-
Transfer
financing, however no formal decision in favour of this
method of
financing had been made by the Department of Transport, the
Minister for Transport or the National Executive CouncilChapter 10
102
-
Page 113 of 397
-
It was made available – unfairly – to only a selected group of
companies.
In the opinion of the Ombudsman Commission the preparation and
distribution of this important – but defective – document was
another
example of incompetent administration by the Department of
Transport.* * * * * * * * *
Chapter 10
11. THE MINISTERIAL COMMITTEE MEETING
OF 18 JULY 1991[11.1] PERSONS PRESENT AT THE MEETING
The Minister for Transport Mr Anthony Temo convened a meeting
of “the
Ministerial Committee on Spring Garden Road” in his
Parliamentary office
on 18 July 1991. Present at the meeting were:Mr Temo, MP;
the Minister for Lands and Physical Planning, Sir Hugo
Berghuser MP; -
Page 114 of 397
-
the Minister for Works, Lukas Waka OBE, MP;
the Parliamentary Secretary for Finance and Planning,
Thomas
Negints MP;the Head of the Policy Secretariat in the Department of
Transport, Lohia Hitolo; andthe First Assistant Secretary (Planning & Research) in
the
Department of Transport, Henry Paraket.Chapter 11
104
[11.2] WHAT WAS THE PURPOSE OF THE MINISTERIAL COMMITTEE
MEETING?The purpose of the meeting was to select a developer to
undertake the
Spring Garden Road project. As a result of the arbitrary and
unsatisfactory
shortlisting process between February and July 1991
(considered in
Chapter 9) five consortiums were to be considered.THE MINISTERIAL COMMITTEE ON SPRING GARDEN ROAD
[11.3] STATUS OF THE MINISTERIAL COMMITTEE
Before we address the deliberations of the Ministerial
Committee, there is
one important point to note: in the course of its
investigation the
Ombudsman Commission was unable to find any document showing
how
or when this Committee was established or who its members
were.The Secretary to the National Executive Council testified
there was no
record of the establishment of such a committee and the
Secretary for
Transport said his Department had also tried in vain to find
some record
of the Committee’s existence. -
Page 115 of 397
-
When we put the issue to Mr Temo, he was adamant that the
Committee
had been duly authorised by the National Executive Council to
report back
to it on the preferred method of implementing the project. He
could not,
however, provide any details of the Committee’s
establishment.Chapter 11
105
Mr Temo stated:
“My mind is quite clear that there was a NEC
decision which authorised the
Minister for Transport to be Chairman of the
Ministerial Committee on
infrastructure. Also the same Ministerial Committee
used NEC decision to
bypass normal tender procedures to construct Enga
Highway Stage 2 or 3. If
NEC did not make this decision), Porgera mine would
not have started
production on time because normal department tender
procedures normally
takes a very long time even the normal political
will does not work.One should understand that if there was no such
Ministerial Committee
established why was NEC recognising and expecting
Ministerial Committees
recommendations?Therefore obviously I acted with some lawful
authority even if we are unable
to get the records. See letter from NEC Secretary
dated 19 November 1992′
[EXHIBIT 257 para 2] -
Page 116 of 397
-
When we questioned Sir Hugo Berghuser on this point, he
stated that theCommittee had been established at his initiative. But Sir
Hugo, also, couldnot point to any formal record of its existence.
[11.4] THE MINISTERIAL COMMITTEE ACTED WITHOUT AUTHORITY
The Ombudsman Commission concludes that the “Ministerial
Committeeon Spring Garden Road” was never formally established by
the NationalExecutive Council and had no authority to make decisions
binding orpurporting to bind the National Executive Council.
At this juncture, we note that Section 149(4) of the
Constitution provides:‘Except where the contrary intention appears,
nothing in this
Constitution prevents the powers, functions, duties
or responsibilities
of ti e [National Executive Council] from being
exercised, as determined
by t, through a Minister.” -
Page 117 of 397
-
Thus, the Constitution does allow the powers of the
National ExecutiveCouncil to be delegated to Ministers.
Chapter 11
106
But this does not mean that any group of Ministers can
appoint
themselves to “committees” of the National Executive Council
and clothe
that “committee” with powers or status.A Ministerial Committee – even one which only intends to make
recommendations to the National Executive Council – must have
its powers
and responsibilities properly delegated and controlled by the
National
Executive Council under Section 149(4) of the Constitution
before it makes
any decisions or holds itself out as having any powers or
responsibilities.This did not occur in relation to “the Ministerial Committee
on Spring
Garden Road”. It therefore had no lawful status or power or
authority.[11.5] WHAT DOCUMENTS WERE CONSIDERED AT THE “MINISTERIAL
COMMITTEE” MEETING?The Head of the Policy Secretariat in the Department of
-
Page 118 of 397
-
Transport, Mr
Hitolo, brought the following documents to the meeting on 18
July 1991,
for the consideration of the Ministerial Committee:the proposals of the five shortlisted consortiums; and
a document dated 17 July 1991 entitled “Financing the
Construction of the Spring Garden Freeway”.Chapter 11
107
LOSS OF DOCUMENTS
[11.6] MOST OF THE FIVE PROPOSALS HAVE BEEN LOST
It has been very difficult for the Ombudsman Commission to
ascertain
exactly which proposals the Ministerial Committee had before
it. By the
time we conducted our investigation, most of the proposals
had been lost.The investigation was also hampered by the fact that the
meeting is poorly
documented in the files of the Department of Transport. In
fact, the only
evidence of the meeting taking place is a letter from the
Minister for
Transport to the Secretary for Transport asking him to attend
the meeting
and a one-page memorandum of the decisions made at the
meeting.
[EXHIBITS 97,102][11.7] HOW WERE THE PROPOSALS LOST?
Mr Hitolo testified that at the end of the meeting he had
left all five
proposals in the Minister for Transport’s office at the
request of Sir Hugo
Berghuser, who said that he wanted to study them further
before making
a decision. -
Page 119 of 397
-
When Sir Hugo was questioned on this point, he agreed the
proposals
had been left, at his request, in the office. But he said he
only asked that
copies be made for him. He was dissatisfied with the
proposals before
the Committee and he said as much to the other members of the
Ministerial Committee. ‘When I left the office, the proposals
were still there
and I have never seen them since’, Sir Hugo said.Chapter 11
108
Correspondence between Mr Hitolo (who became Secretary for
Works in
early 1992) and Mr Amini in March 1992 confirmed that this
incident took
place [EXHIBIT 160, final paragraph]. But the Ombudsman
Commission
has not been able to trace the whereabouts of the proposals
left in the
Minister’s office.The Ombudsman Commission concluded that the proposals were
lost by
the Minister for Transport, Mr Temo.When we made this allegation in our preliminary report, Mr
Temo claimed
that, in fact, the proposals had been lost by Sir Hugo
Berghuser.
However, even if this were, in fact, the case, Mr Temo was
the Minister of
the State entrusted with custody of these important and
confidential
documents. It was his responsibility to take adequate steps
to ensure the
documents were in safe hands.[11.8] THE DEPARTMENT OF TRANSPORT FAILED TO KEEP COPIES OF THE
PROPOSALSSurprisingly, the Department of Transport had not kept copies
of the
proposals, except the one made by the Chinese consortium –
which was
the group selected by the Ministerial Committee to undertake
the project. -
Page 120 of 397
-
This meant, therefore, that most of the proposals had been
lostTM.This particular administrative mistake was to have far-
reaching
consequences several months later, when pressure was put on
the
Department to expedite the project and the Department had
second-
thoughts about supporting the Chinese proposal (see Chapter
18).Chapter 11
109
It meant that when the Department was required to prepare a
National
Executive Council Policy Submission in February 1992,
recommending a
consortium to undertake the project, it only had one proposal
in its
possession.[11.9] DEPARTMENTAL RECORDS SHOULD NOT BE GIVEN TO MINISTERS
As a general rule the Ombudsman Commission believes that
official
Government records and files should not be left in the
possession of
Ministers. An official Government file is the property of the
State – it does
not belong to a Minister. A Minister has the right to be
fully and objectively
briefed by his or her Departmental Head. But he does not have
the right
to keep possession of official files.If this principle of sound public administration had been
followed in the
present case, the proposals probably would not have been
lost.EVALUATION OF PROPOSALS
[11.10]la
SPRING GARDEN FREEWAY -
Page 121 of 397
-
This document was the focus of discussion ac the Ministerial
Committee
meeting of 18 July 1991. It is dated 17 July 1991, i.e. one
day before the
Ministerial Committee meeting. were in fact two versions of
it:Chapter 11
110
One version was addressed to “the Members of the
Resource Management Committee”. It was drafted as a
submission by the Department of Transport and shows the
submitter as “B K Amini CBE Secretary”; however, it was
unsigned. [EXHIBIT 100]The other version of the document was drafted as a Policy
Submission to the National Executive Council by the Minister
for Transport; it was signed by Mr Temo. [IXHIBIT 99]Although there are some minor variations, both versions of the
document
are essentially the same:They outline the background of the Spring Garden Road
project.The scope of the project is described as being from
downtown Port Moresby to Jacksons Airport.The five short-listed proposals are evaluated, according to
ten criteria.The conclusion is reached that the Second Surveying and
Designing Institute of the Peoples’ Republic of China (which
lodged a proposal in conjunction with Topbay Investment
of Hong Kong) be “appointed” to commence negotiations
with the Department of Transport for the development of the
Spring Garden Road.Chapter 11
111
[11.11] THE METHOD USED TO EVALUATE THE SHORTLISTED PROPOSALS
-
Page 122 of 397
-
The “Financing the Construction of the Spring Garden
Freeway” document
evaluated the five proposals according to ten criteria:1. Interpretation of the Terms of Reference.
2. Logical Phasing of Tasks in the Methodology.
3. Environment Impact Statement.
4. Financier’s Credibility.
5. Main Contractor’s Relevant Experience.
6. Local Partner Participation.
7. Proposed Equity Distribution.
8. Personnel Proposed in General.
9. Team’s Experience in B.O.T. System.
10. Funding Proposal for the Project.The proposals were given a rating of “Excellent”, “Very
Good”, “Good”,
“Fair” or “Satisfactory” on each criteria.The proposals were then given an overall ranking, as
follows:1st: Topbay Investment Ltd/Second Surveying & Designing
Institute, People’s Republic of China.2nd: Periquan’s International Resources.
3rd: Kumagai Gumi/Kinhill Kramer.
4th: Tasman Pacific International.
5th: McConnell Dowell.
Chapter 11
112
In light of these rankings, the document concluded that the
project be
awarded to the Chinese consortium.(11.12] FURTHER UNSATISFACTORY ADMINISTRATION BY THE DEPARTMENT
OF TRANSPORTWe have noted elsewhere in this report that the standard of
documentation of important policy decisions by the
Department of
Transport was extremely poor. We made that finding in
relation to a
number of issues, e.g. the decision to extend the freeway to
Jacksons -
Page 123 of 397
-
Airport, the tunnel/cut issue and the Build-Operate-Transfer
method of
financing (see Chapters 5 & 10).We make a similar finding in relation to the evaluation of
the five proposals
shortlisted for consideration by the Ministerial Committee.
The
Ombudsman Commission considers that a much more detailed and
methodical comparison of the alternative proposals was
required than the
one page table attached as an appendix to the “Financing the
Construction of the Spring Garden Freeway” document.The subjective rankings on the basis of the ten selected
criteria were
vague and meaningless.This situation occurred because the Department of Transport
did not have
any established procedures for evaluating proposals for
construction of
roads or other transport infrastructure. The Department of
Transport, on
the instructions of the Minister for Transport, had wrongly
assumed
responsibility for a task that should have been carried out
by a Supply
and Tenders Board, in accordance with the Public Finances
(Management)
AMChapter 11
113
[11.13] OTHER DEPARTMENTS NOT INVOLVED IN THE RANKING OF
PROPOSALSA feature of the decision-making process which led to the
selection of the
consortium to build the Spring Garden Road/Poreporena
Freeway, is the
flagrant disregard of normal tender procedures (see Chapter
35).If the project had been properly put to public tender in the
first place, the
Ministerial Committee would not have had to deliberate on
the matter and
the Department of Transport would not have been required to
rank the
proposals shortlisted by the Minister. -
Page 124 of 397
-
Though these mistakes were made, the maladministration would
not have
been so serious, if the Minister for Transport and the
Department of
Transport had been willing to consult other Departments when
ranking
the shortlisted proposals. However, no consultation took
place.We are particularly concerned that the Department of Works
was not
consulted. This Department has far more experience in
selection of
contractors to undertake road projects than the Department
of Transport.It was also wrong for the Department of Transport not to
consult the
Department of Finance and Planning. There is no evidence
that any proper
checks were made by the Department of Transport on criteria
such as
“Financier’s Credibility” and “Funding Proposal for the
Project”. We note the
Chinese proposal was rated “excellent” on both these
criteria. Yet six
months later the Department of Transport found it necessary
to seriously
question the bona fides of the proponents (see Chapter 15).Chapter 11
114
[11.14] DID THE PROJECT “BELONG” TO THE DEPARTMENT OF TRANSPORT?
We have no doubt many mistakes were made because the
Minister for
Transport and the Secretary for Transport believed that the
Spring Garden
Road/Poreporena Freeway project was “a Department of
Transport project”
– not “a Department of Works project”.However, the terms of National Executive Council Decision
No. 14/90 were
that “the Department of Transport, the Department of Works
and the
Department of Finance and Planning formulate detail plans -
Page 125 of 397
-
for the
construction of Burns Peak Road”. [EXHIBIT 6A]We could therefore see no justification for the Minister for
Transport or the
Department of Transport shutting out these two other
departments from
the decision-making process.Though it was within the policy prerogative of the
Department of Transport
to determine where the freeway would go, whether there would
be a
tunnel or cut through Burns Peak and whether the project
would be
undertaken using Build-Operate-Transfer financing, it was
wrong for the
Minister for Transport and the Department of Transport to
exclude the
other key Departments from the decision on who was going to
design,
finance and build the freeway.[11.15] THE FORMAL RECORD OF THE MINISTERIAL COMMITTEE’S DECISION
In his oral testimony to the Ombudsman Commission, Sir Hugo
Berghuser
stated that the Ministerial Committee meeting lasted not
much longer than
30 minutes and that the discussion had been confined to the
contents
the “Financing the Construction of the Spring Garden
Freeway” document.Chapter 11
115
No minutes of the meeting were kept and the only record
of the
Committee’s decision is a document, under Ministry of
Transport
letterhead, that was signed by Mr Temo, Mr Waka and Mr
Negints. It
stated:‘On the 18th day of July 1991, the Ministerial
Committee On The Spring Garden -
Page 126 of 397
-
Road Development met at the Transport Minister’s
office in the National
Parliament House and authorized and approved the
following recommendation:That the Chairman of this Committee seek
National Executive Council
(NEC) endorsement for the appointment of
The Second Surveying and
Designing Institute, Ministry of Railways
of Peoples Republic China to
commence negotiation for the development
of the Spring Garden Road.2. That the Chairman of the Committee seek
National Executive Council
endorsement to authorize the Attorney-
General’s Department and the
Department of Finance and Planning to
negotiate and execute the
principle terms and conditions of the
contract emerging from their
proposals.3. That the Chairman of this Committee seek
National Executive Council
endorsement to negotiate and use B.O.T. or
turnkey as the basis of
funding the Spring Garden Road
Development.4. That the Chairman of the Ministerial
Committee seek National
Executive Council endorsement in order to
authorize Department of
Finance and Planning to negotiate and
execute the Franchise agreement
and any other necessary and desirable
documents relating thereto on
behalf of the State? [EXHIBIT 102]Sir Hugo testified that this document was not signed at
the meeting of 18
July 1991 and we accept that that was in fact the case.[11.16] WHAT HAPPENED AFTER THE MEETING?
-
Page 127 of 397
-
The document recording the decisions of the Ministerial
Committee
appears to have been signed a day or two after the
meeting took place.Chapter 11
116
Sir Hugo stated that, though he had seen this document, he
had
deliberately not signed it because he did not agree with its
contents. He
was very suspicious about the negotiations that had already
taken place
with the Chinese. In fact, Sir Hugo alleged that he had been
invited to a
Chinese restaurant in Port Moresby, and asked to sign the
document in
the presence of other members of the Ministerial Committee
and
representatives of the Chinese consortium. He said that he
refused to sign
the document and walked out of the restaurant.The Ombudsman Commission has been unable to obtain any
corroborating evidence of this particular incident. However,
we share Sir
Hugo’s concern about the propriety of the decision to favour
the Chinese
consortium.WAS THERE AN OBJECTIVE EVALUATION?
[11.17] HAD THERE BEEN A GENUINE ATTEMPT TO EVALUATE THE
ALTERNATIVES?On the face of it, the selection of the Chinese consortium
was yet another
example of the type of haphazard and careless decision -
Page 128 of 397
-
making that had
come to characterise the Ministry and Department of
Transport’s handling
of the Spring Garden Road/Poreporena Freeway project. But
our
investigations revealed that there was more to the selection
of the Chinese
than just slipshod administration.Chapter 11
117
[11.18] THE DECISION HAD ALREADY BEEN MADEIn the opinion of the Ombudsman Commission, the Ministerial
Committee
meeting of 18 July 1991 was really just a rubber-stamping
exercise for a
decision already made by the Minister for Transport, Mr
Temo, to award
the project to the Chinese consortium.Both versions of the “Financing the Construction of the
Spring Garden
Freeway” document actually referred to “the Ministerial
Committee’s
decision to appoint the SSDI to commence negotiations …for
the
development of the Spring Garden Road”. But the document was
dated
17 July 1991 – one day before the Ministerial Committee made
that
decision!The Ombudsman Commission discovered that, in fact, the
Minister for
Transport had formed a close association with members of the
Chinese
consortium well before the meeting. He had entertained a
delegation from
the consortium, in Port Moresby, only one week before the
Committee’s
decision to favour them (see Chapter 12). 1In light of that evidence, the Ombudsman Commission was
forced to
conclude that the deliberations of the Ministerial Committee
were not a
genuine attempt to objectively evaluate the five short-
listed proposals. -
Page 129 of 397
-
[11.19] MR TEMO’S RESPONSE
When we suggested in our preliminary report that Mr Temo had
improperly arranged the selection of the Chinese consortium,
he
responded in the following terms:Chapter 11
118
“Most of the companies that showed or expressed interest either did
not
understand the terms of reference of the project or did not bother
to re-check
with the Committee or Departments of Transport or Works.As you can see in NEC decision or purpose of the NEC submission No.
14/90
it was the wish of the NEC to speed up the project. That is why the
NEC
submission’s purpose was to bypass normal tender procedures in order
to speed
up the project to be completed in time for the SP Games. Also there
was a
criticism against me in NEC or Parliament every time there was a
traffic
problem along Sir Hubert Murray Highway even by public what are you
doing
Mr Chairman or Mr Minister for Transport.While I was being pressured by the public NEC and Parliament I had
to
negotiate with any of these companies that showed interest as a
Chairman of
Committees I was left to look like a fool if I did not report back
to NEC with
a positive report I would have failed my duty and I was scared I
could loose
my job.No companies complained because it was a new concept proposed by
Barclay
Bros. before my time. I had to carry on from that initiative. It has
been a very -
Page 130 of 397
-
tough job trying to get the best companies to do the job.
Some companies responded again when it was convenient to them. We
had to
follow them because PNG does not have the resources in monetary and
manpower.The companies that came up with fancy proposals and sort of got in
touch with
my office or the Secretary’s office kept getting our attention.At least I was given a responsibility to present to NEC. I did not
discriminate
other companies against that showed interest It was a mere who comes
first
with the best proposal for PNG.I have a feeling that the Chinese companies were not consortium but
they were
selling their information from one company to another.The Department was very uncooperative to me or NEC.
I, Mr Temo was not hiding any transactions from the Department. I
always
notified of the progress that is why I have them all information. I
therefore
regardless whether I had meeting or not prior to not really relevant
in the
situation of this new confused situation as there was no better
proposals and
interest shown other than that of the Chinese.All the time the Department was aware I did not organise any secret
de–11c an
my mine was dear all the time.” [EXHIBIT 257, page 2]Chapter 11
119
[11.20] CONCLUSION AS TO THE DELIBERATIONS OF THE MINISTERIAL
COMMITTEE -
Page 131 of 397
-
With due respect to Mr Temo, he has not satisfactorily
answered our
criticism of the way in which the Chinese consortium
was favoured by the
Ministerial Committee. We conclude that he convened the
meeting of the
Ministerial Committee for the purpose of facilitating
the Chinese consortium
selected by himself to undertake the project.The closeness of the relationship between Mr Temo and
the Chinese
consortium is explored further in the next chapter.* * * * * * * * * *
Chapter 11
120
12. THE RELATIONSHIP BETWEEN THE CHINESE
CONSORTIUM AND THE MINISTER FOR TRANSPORT -
Page 132 of 397
-
[12.1] A MATTER OF CONCERN
The manner in which the Chinese consortium was chosen by the
Ministerial Committee was a matter of concern to the
Ombudsman
Commission.We therefore wanted to find out who was actually behind the
proposal of
the “Second Surveying and Designing Institute, Ministry of
Railways,
People’s Republic of China”. We were also interested to know
whether the
Minister for Transport had any particular association with
those negotiating
on behalf of the Chinese.WHO WAS IN THE CHINESE CONSORTIUM?
[12.2] KEY PARTIES IN THE PROPOSAL INVOLVING THE SECOND SURVEYING
AND DESIGNING INSTITUTEMr Leo Moore of Taiwan
Our investigations revealed that a key person was Mr Leo
Moore, a citizen
of the Republic of China (Taiwan). Mr Moore is a businessman,
with
interests in the Taiwanese fishing industry, who had made a
number of
visits to Papua New Guinea during 1991 and 1992.Chapter 12
121
Mr Moore was called to give evidence under oath on several occasions
in
the course of this investigation. We formed the view that he was a
co-
operative and reliable witness. His evidence shed considerable light
on
the events leading to the selection of the Chinese consortium.Outlet Year Ltd and Mr Leung Keung of Hong Kong
Mr Moore stated that he had first become interested in Papua New
Guinea
in September 1990, after a meeting in Taiwan with another -
Page 133 of 397
-
businessman,
Mr Leung Keuno (hereafter referred to as Mr Leung).. Mr Leung is the
head of a Hong Kong-based company known as Outlet Year Ltd, which
was supposedly considering making large investments in Papua New
Guinea. The meeting between Mr Moore and Mr Leung was arranged by
Mr To Ken Chung (Mr Moore’s godfather and Mr Leung’s close friend)
and Mr Stephen Zohr (one of Mr Moore’s business advisers).At that meeting it was agreed that an invitation would be extended
to a
group of government officials from Papua New Guinea to come to
Taiwan
to discuss business opportunities in Papua New Guinea.Business relationship between Outlet Year Ltd and the SSDI
Mr Moore explained that Outlet Year Ltd had business connections
with
a number of government authorities in the Peoples’ Republic of China
(ie
mainland China); one of them being the Second Surveying and
Designing
Institute (SSDI).The SSDI is a civil engineering agency involved in design and
construction
of railways and highways. Mr Moore supplied the Ombudsman
Commission with a brochure describing its activities. [EXHIBIT 102A]Cnapter 12
122
Mr Moore explained that, as a result of overtures made by Mr
Leung, the
SSDI had contacted Mr Moore on 27 January 1991. In a one page
facsimile transmission, a representative of the SSDI
indicated that they
were a very strong and influential government company in
China and that
they were keen to go into business with Mr Leung and Mr Moore
for the
purpose of building a freeway in Port Moresby, which they had
been
informed about by Mr Leung. [EXHIBIT 53]OVERSEAS TRIP PAID FOR BY CHINESE CONSORTIUM
[12.3] VISIT TO TAIWAN AND HONG KONG BY PAPUA NEW GUINEA
-
Page 134 of 397
-
PARLIAMENTARIANS IN FEBRUARY 1991: A MATTER OF CONCERN
Mr Moore testified that on 6 February 1991 he purchased four
return
tickets from Port Moresby to Hong Kong, which were later
picked up at
the Cathay Pacific office in Port Moresby.After being invited to Taiwan and Hong Kong, a “delegation”
from Papua
New Guinea arrived in Taipei on 8 February 1991. The
delegation
comprised:the Minister for Transport, Mr Anthony Temo;
the Member for Gulf Province, Mr Aaron Noaio;
the Member for Sohe Open, Mr David Beu; and
Chapter 12
a member of the Official Personal Staff of the
Minister for
Fisheries & Marine Resources (who at that time was the
Deputy Prime Minister Mr Akoka Doi) Mr Chris Maravis.The Ombudsman Commission interviewed Mr David Beu in
connection
with this trip and the evidence he gave corroborated that
given by Mr
Moore.[12.4] STATUS OF THE PNG DELEGATION
Before we address the events that transpired during and after
the trip,
there is one important matter to emphasise: the Papua New
Guinea
“delegation” had no official status. Although the members of
the group
were, in a sense, representing the Government of Papua New
Guinea, the
delegation was privately sponsored. All the expenses,
including airfares,
accommodation and meals, were paid for either by Mr Leo Moore
or
Outlet Year Ltd. -
Page 135 of 397
-
[12.5] PRIVATELY SPONSORED OVERSEAS TRIPS CAN BE UNLAWFUL
It is important for all leaders of Papua New Guinea who
contemplate
privately sponsored trips to bear in mind that it is a
requirement of the
Leadership Code that permission from the Ombudsman Commission
be
obtained before accepting the benefits of such a trip.This is a principle of Papua New Guinea law that should also
be
considered by any person or company thinking about offering
such a trip
to a leader.Chapter 12
124
[12.6] THE MINISTER ALLOWED HIMSELF TO BE ENTERTAINED BY ONE OF
THE COMPANIES BIDDING FOR THE PROJECT AT THE SAME TIME HE
WAS PREPARING THE SHORTLISTThe Ombudsman Commission is concerned that the Minister for
Transport,
Mr Temo, made his trip to Taiwan and Hong Kong and involved
himself
in negotiations for the Spring Garden Road/Poreporena Freeway
project
at the same time be was preparing the shortlist of
prospective developers
(see Chapter 9).The Ombudsman Commission emphasised earlier in this report
that
Ministers should not be preparing shortlists for public works
projects. In
this case, the Minister for Transport was not only preparing
the shortlist,
he was, at the same time, allowing himself to be wined and
dined
overseas, at the expense of one of the companies interested
in getting the
contract for construction of the freeway.When this sort of thing happens, it is very difficult to
conclude that the
decision-making process was legitimate, fair and proper.It is also difficult to say there was no bribery or
corruption. -
Page 136 of 397
-
[127] THE MINISTER FOR TRANSPORTS DEFENCE
When we suggested in our preliminary report that it was wrong
of Mr
Temo to make an overseas trip, paid for by one of the
companies bidding
for the project, at the same time he was preparing a
shortlist of
prospective developers, he denied any impropriety. He said he
did not
realise it was a privately sponsored trip until after he
accepted the
invitation to go to Hong Kong:Chapter 12
125
“The trip to Taiwan and Hong Kong was organised by a Chris
Maravis in Mr
Akoka Dors office. Mr Doi was the Deputy Prime Minister so I took
it that
I was going on an official trip. later I realised that it was a
PAP fishing trip
paid by Mr Leo Moore and some fishing people.While in Taiwan and Hong Kong as I was not Minister for Fisheries
so I was
asked about Transport Projects and I said we have a 10 year plan
that need to
be completed. However, we did not have finance and manpower it
was paid
by Mr Leo Moore not short listed company.I did not prepare the final short list.
While in Hong Kong I told the company representative to let the
Prime
Minister, Minister for Finance and the other senior ministers
know of their
investment proposal in PNG.According to me I did not hide anything and I told them, if you
want to invest
for the trip and accommodation while in Taiwan and Hong Kong. I
did this
after learning that it was a PAP fishing trip. Therefore, I -
Page 137 of 397
-
notified the
Ombudsman in writing about who was paying for the trip and
accommodation
while in Taiwan and Hong Kong. I did this after learning it was a
PAP fishing
trip.” [F.XHIBIT 257, page 3]The Ombudsman Commission, with respect, does not consider Mr Temo’s
explanation to be satisfactory. We find it difficult to believe that
a Ministerof the State would legitimately travel overseas without knowing what
the
purpose of the trip was.As to the claim that he advised the Ombudsman Commission of the trip
and who was paying for it, we refer to a letter dated 28 March 1991
received by the Commission from Mr Temo:Mr Temo stated:
‘Thank you for your very helpful Leadership Manual received
today. I note
that I must declare to the Commission every time I leave for
overseas be it
official or unofficiaLI therefore wish to inform the Commission that from the 22
February, 1991 until
4 March, I was on an official visit paid for by M.T.L
Organisation. This trip
was approved by the National Government to lead a delegation to
Taiwan.’
[EXHIBIT 68B]Chapter 12
126
[12.8] POOR ADMINISTRATION BY THE MINISTER FOR TRANSPORTOne thing is certain: irrespective of whether Ministers and
other
Government officials breach the Leadership Code when they -
Page 138 of 397
-
accept
benefits such as free travel, free accommodation and gifts
from foreign
enterprises, it is a very bad administrative practice.It undermines the integrity of the decision-making processes
of
Government. It creates the impression that to get Government
approval for
a project in Papua New Guinea, it is necessary to be on
friendly terms
with the right Minister. It attracts the wrong sort of
foreign investors to
Papua New Guinea. It creates a bad image of Papua New Guinea.If this sort of administrative practice continues, instead of
honest and
genuine investors coming to our country, we will be overrun
by fly-by-
night operators, only too willing to bypass normal procedures
in the quest
for easy money for themselves and not for the People of Papua
New
Guinea. Papua New Guinea has had enough of them already.Since it is not in the best interests of the People of Papua
New Guinea
and our country, such practices must be stopped at all costs.[12.9] WHAT HAPPENED DURING THE TRIP TO TAIWAN AND HONG KONG?
Mr Moore testified that Messrs Temo, Noaio, Beu and Maravis
spent three
days in Taipei, followed by four days in Hong Kong.Three days in Taipei
In Taipei, the members of the PNG “delegation” were
entertained by Mr
Moore.Chapter 12
127
Mr Moore testified that during this visit there was a lot
of talk about road
projects, particularly “the 8.8 km road in Port Moresby”,
as well as other
investment opportunities in Papua New Guinea. The Papua
New Guinea
people described their country as a good place to invest –
particularly in -
Page 139 of 397
-
mining, oil, fishery and forestry projects – but they said
the road network
was not very good and that is why Papua New Guinea is a
poor country.Mr Moore told the Minister for Transport he would like to
come to Papua
New Guinea and see the country for himself.
Four days in Hong KongAfter spending three days in Taiwan the group from Papua
New Guinea
travelled to Hong Kong, leaving Mr Moore behind. Mr Moore
stated that
throughout their stay in Hong Kong, the group from Papua
New Guinea
was looked after by Mr Leung of Outlet Year Ltd. He said
that, as it was
Chinese New Year, much of the time was taken up in social
activities and
the group from Papua New Guinea was housed at the Sheraton
Hotel.It was during this visit to Hong Kong that Mr Temo, in his
capacity as
Minister for Transport, signed a quite extraordinary
document: a
“memorandum of agreement” for the construction of the
Southern
Highlands-Kikori Road. [EXHIBIT 58][12.10] THE MEMORANDUM OF AGREEMENT FOR THE CONSTRUCTION OF
THE SOUTHERN HIGHLANDS – GULF ROADThe Minister for Transport, Mr Temo, signed this agreement
in Hong Kong
on 12 February 1991, on behalf of “the Ministry of
Transport, National
Government of Papua New Guinea”. The other signatory was
Mr Leung
Keung, who entered into the agreement on behalf of Outlet
Year Ltd ofChapter 12
128
Hong Kong. The document was witnessed by Mr Aaron Noaio, the
Member for Gulf Province and Mr To Ken Chung (Mr Leo Moore’s
godfather). -
Page 140 of 397
-
Terms of the agreement for the construction of the Southern
Highlands
Gulf RoadThe terms of this agreement, which appeared under the letterhead of
Outlet Year Ltd, were as follows:‘MEMORANDUM OF AGREEMENT
‘KNOW ALL MEN BY THESE PRESENTS:
This Memorandum of Agreement is entered into and executed this
12th day of
February, 1991, by and between:Ministry of Transport, National Government of Papua New Guinea
with
principal offices of P.O. Box 457 Konedobu, National Capital
District, Papua
New Guinea represented by Hon. Anthony Temo, Minister for
Transport
(hereinafter referred to as NPG).and
Outlet Year Limited, a duly registered Hong Kong Corporation
with principal
offices at No. 20, HOK Yuen Street, Block FL 3/F Hunghom,
Kowloon, Hong
Kong, herein represented by Mr Leung Keung, Managing Director
(hereinafter
referred to as HK).1NITNESSETH:
WHEREAS, the National Government of Papua New Guinea has fully
authorized NPG to implement an Infrastructure Development PlanWHEREAS, NPG is willing to undertake this job per engineering
details and
specifications, contained in the NPG’s Cost Study (Gulf-Southern
Highlands
Province – ERAVE to KEREMA [sic]).WHEREAS, NPG has found the credentials of HICG to be financially
qualified
and technically capable to execute this project in a manner
consistent with the
technical standards set forth by engineering standards. -
Page 141 of 397
-
WHEREAS, HEW has offered to undertake construction of this
project.NOW, THEREFORE, for and in consideration of the above premises
and of the
mutual covenants heretofor set forth, the parties have agreed,
as they hereby
agree, on the following terms and conditions:Chapter 12
129
1. PROJECT
NAME Southern Highlands Kikori Road
LOCATION From ERAVE to KIKORI
SPECIFICATION AND INSPECTION
Per Cost Study (Gulf-Southern
Highlands Province – ERAVE to KEREMA)DURATIONFrom May 1st, 1991 to May 1st, 1993.
BONUS AND PENALTY.2. CONTRACT PRICE : HKG shall submit within 60 days after
signing of this Memorandum a price, to
be forwarded to and acceptable to PNG.3. PAYMENT Payment plan to be negotiated between
PNG and HKG on an equitable and
acceptable basis to both parties4. PERFORMANCE Upon signing of Contract by both parties
BOND MG shall provide to PNG a
Performance Bond in the form of cash,
bank guarantee or other form of
guarantee acceptable to PNG, for an
amount not less than 10% of the Contract
value, to warrant the performance of
EKG’s obligation under the Contract
(Gulf-Southern Highland Province –
ERAVE TO KEREMA). This -
Page 142 of 397
-
Performance Bond shall be returned
HKG without interest, when HKG shall
have fulfilled its obligations under the
Contract.5. FORCE MAJEURE HKG is not responsible for delay or non-
performance of its contractual obligation
to construct, caused by war, blockade,
revolution, insurrection, civil commotion,
riots, mobilization, strikes, Act of God,
plague, or other epidemic, fire, flood,
action or acts of government or public
enemy.Chapter 12
130
6_ CANCELLATION & : PNG may cancel the Contract, and
ALTERATION OF confiscate the Performance Bond,
if
CONTRACT IIKG is unable to deliver in
accordance
with the stipulated time schedule
or
breath of Contract.Postponement or alteration of the
Contract if required, should be
agreed
by both parties in writing.IN WITNESS WHEREOF, the parties hereto have hereunto
affixed their
signatures at Hong Kong this 12th day of February
1991.MINISTRY OF TRANSPORT
[signed]
-
Page 143 of 397
-
HON. ANTHONY TEMO
MINISTER FOR TRANSPORTWITNESS: MEMBER OF PARLIAMENT
[signed]
HON. AARON NOAIO
MP For Gulf ProvinceFor and on behalf of
OUTLET YEAR LIMITED
[signed]
Authorized Signature
LEUNG KEUNG
MANAGING DIRECTORWITNESS:
[signed]
TO KEN CHUNG” [EXHIBIT 58][12.11] THE AGREEMENT OF 12 FEBRUARY 1991 DID NOT MAKE SENSE
Any person with a basic knowledge of contracts and the
English language
would realise that this document is very poorly drafted. The
grammar is
atrocious and, in places, the document just does not make
sense. ForChapter 12
131
instanLe though the subject of the agreement is described
in Clause 1 as
“Southern Highlands Kikori Road from Erave to Kikori”,
there are three sai
other references in the document to the “Erave to Kerema”
Cost Study or
Contract. -
Page 144 of 397
-
1111
The Ombudsman Commission is left wondering whether the
parties to this
agreement actually knew what they were agreeing to. In
view of this, it is
very doubtful whether the agreement could have ever been
regarded as
valid or enforceable.But that does not, in our view, excuse the Minister for
Transport for his
actions in signing this agreement.[12.12] THE PROPRIETY OF THE MINISTER FOR TRANSPORTS ACTIONS
In the opinion of the Ombudsman Commission, it is very
embarrassing for
our country when persons holding official positions sign
documents as
amateurish as the agreement for the construction of the
Southern
Highlands-Kikori Road. It is terrible administration for
any office-holder,
particularly a Minister of the State, to unilaterally
decide to enter into such
agreements.The Ombudsman Commission believes that whenever any
Minister goes
overseas to engage in negotiations on behalf of Papua New
Guinea, he
should be accompanied by at least one senior Departmental
adviser. If
that had happened in this case, we have no doubt the
Minister for
Transport would have been advised not to sign the
agreement for the
construction of the Southern Highlands-Guff Road.Having said that, the Ombudsman Commission still finds it
remarkable
that, during the course of being entertained by foreign
businessmen, andChapter 12
132
while outside Papua New Guinea, the Minister for Transport
-
Page 145 of 397
-
would have
signed an agreement for the carrying out of an extremely
important
national road project without the advice or knowledge of the
Department
of Transport or the Government he was supposed to be
representing.This sort of thing simply should not happen. It raises
questions of legal
authority and breeds the atmosphere and environment ripe for
bribery
and corruption.[12.13j COULD THE MINISTER’S ACTIONS BE JUSTIFIED?
During the course of this investigation, the Ombudsman
Commission
questioned the former Minister for Transport on his actions.
He agreed hehad been to Hong Kong and signed the Memorandum of
Agreement. In
his view, however, he had done nothing improper. His
explanation wasthat it was not intended to be a binding document:
“While in Hong Kong I signed a couple of pages
documents as memorandum
of understanding. This a Chinese Government policy that
before they leave
to go out of R.O. China it is a mandatory that they
must have some form of
agreement of some sort so they be allowed to leave
their country. They had
no choice but to show their Government information why
they were leaving
for PNG. I was authorised by NEC to negotiate on Burns
Peak Road.Therefore, I had some authority to negotiate not make a
decision. The
Department was made known as usual.”
[EXHIBIT 257, pages 3-4] -
Page 146 of 397
-
In the opinion of the Ombudsman Commission, that is not a
satisfactory
explanation.A Minister should not sign any document which purports to
bind himself
or his Department or the Government of Papua New Guinea to
any course
of action unless he has been expressly and lawfully
authorised to do so.
LChapter 12
133
There is no evidence, as Mr Temo claims, that he was
authorised by theNational Executive Council to conduct any negotiations.
Nor is there anyevidence he advised the Department of Transport what he
was doing.The Secretary for Transport’s evidence was to the
contrary. 11The Minister for Transport had no authorisation to conduct
negotiations 11concerning the Southern Highlands-Gulf Road or the Spring
GardenRoad/Poreporena Freeway project. He had no right to sign
this -
Page 147 of 397
-
document He signed it without the advice or knowledge of
hisDepartment or the National Executive Council. tt was very
wrong of him tosign it.
[12.14] OTHER EVIDENCE OF OUTLET YEAR LTD’S INTEREST IN PAPUA NEW
GUINEA
a
Mr Leo Moore’s oral evidence of Outlet Year Ltd’s interest
in Papua NewGuinea is corroborated by three documents that the
Ombudsman111
Commission has obtained:a
(i) A letter from Outlet Year Ltd. dated 12 February
1991, to the thenPrime Minister. Mr Rabbie Namaliu. The letter states:
‘Your Excellency:
-
Page 148 of 397
-
A delegation from your Government headed by
Hon. Anthony Temo,
Minister for Transport, approached our Company
seeking funds and
technical assistance to develop – an
infrastructure Development Plan –
in your country Papua New Guinea. We are
interested to invest up to
US Dollars 5 billion in Papua N. G.As per our meetings, [with Mr Terns)] we wish
to design and build
Southern Highlands ICikori Road and Burns Peak
Road in Port Moresby.
We shall build these roads under a Turnkey
arrangement, which means
we shall supply manpower as well as financing.
111Should your Government endorse this idea,
please send me an
invitation so our delegation consisting of the
undersigned and Mr
Steven Zohr and Mr Leo Moore, could assist your
Country in the
nearest future.Chapter 12
1111
134
We are taking this as a matter of urgency and priority,
and hope to
meet you personally.Respectfully yours,
[signed]
LEUNG ICEUNG
MANAGING DIRECTOR” -
Page 149 of 397
-
This letter was marked:
“c.c. His Excl. Ted Biro [sic], Deputy Prime Minister
His Excl. Sir Michael T. Samare, [sic], Foreign Minister
His Excl. Hon. Paul Bora [sic], Finance Minister
His Excl. Hon Anthony Temo, Minister for Transport’.
[EXHIBIT 57](ii) A letter from Outlet Year Ltd dated 13 February 1991 to Mr
Temo
(also addressed to Deputy Prime Minister Mr Ted Diro, who was
described as the Acting Transport Minister).This letter was headed “Application for pre-qualification of
Southern
Highlands Kikori Road’ and states:“We wish to design and construct Southern Highlands/
Kikori Road in
Port Moresby [sic] under a Turnkey arrangements which
means we will
supply manpower and finance’. [EXHIBIT 59](iii) Another letter from Outlet Year Ltd dated 13 February 1991 to
Mr
Temo (also addressed to Mr Diro).This letter was headed “Application for Pre-qualification of
Bums
Peak Road” and states:‘We wish to design and construct Burns Peak Road in Port
Moresby
under a Turnkey arrangements which means we will supply
manpower
and finance”. [EXHIBIT 60]Chapter 12
-
Page