Report of an Investigation into the Spring Garden Road Poreporena Freeway Project (Part 1)
Mentions of people and company names in this document
It is not suggested or implied that simply because a person, company or other entity is mentioned in the documents in the database that they have broken the law or otherwise acted improperly. Read our full disclaimer
Document content
-
OMBUDSMAN COMMISSION
OF
PAPUA NEW GUINEA
REPORT OF AN
INVESTIGATION INTO
THE SPRING GARDEN ROAD
POREPORENA FREEWAY PROJECT
MEMBERS
OF THE
OMBUDSMAN COMMISION
Charles Maino Ango Wangatau Jim Ridges
Chief Ombudsman Acting Ombudsman Acting Ombudsman18 December 1992
-
Page 2 of 397
-
OMBUDSMAN COMMISSION
OF
PAPUA NEW GUINEA
REPORT OF AN INVESTIGATION
INTO THE SPRING GARDEN ROAD
POREPORENA FREEWAY PROJECTPART I: NATURE AND PURPOSE OF THE INVESTIGATION
1. INTRODUCTION 2
2. BACKGROUND OF THE FREEWAY PROPOSAL 9
3. STRUCTURE OF THE REPORT 14
PART H: RECORD OF EVENTS AND FINDINGS OF THE
OMBUDSMAN COMMISSION4. DECISION TO PUBLICLY INVITE 18
EXPRESSIONS OF INTEREST: MAY 19905. ADVERTISEMENT INVITING 23
EXPRESSIONS OF INTEREST: JUNE 19906. RESPONSES TO THE ADVERTISEMENT: JULY 1990 35
7. SIGNIFICANT INTERDEPARTMENTAL 49
MEETING: 31 JULY 19908. PROGRESS DURING SECOND 54
HALF OF 1990
9. PREPARATION OF SHORTLIST: 73
FEBRUARY 199110. TERMS OF REFERENCE FOR THE 94
PROJECT: EARLY 199111. THE MINISTERIAL COMMITTEE MEETING 103
OF 18 JULY 1991 -
Page 3 of 397
-
12. THE RELATIONSHIP BETWEEN THE CHINESE 120
CONSORTIUM AND THE MINISTER FOR TRANSPORT13. FURTHER CHANGE IN COMPOSITION OF
THE CHINESE CONSORTIUM: SEPTEMBER 1991 15514. MINISTER FOR TRANSPORT SIGNS CONTRACT 162
FOR CONSTRUCTION OF FREEWAY: OCTOBER 199115. ROLE OF THE WORLD BANK IN THE
SPRING GARDEN ROAD/POREPORENA 178
FREEWAY PROJECT16. FATE OF THE POLICY SUBMISSION FAVOURING 185
THE CHINESE CONSORTIUM: DECEMBER 199117. CONCERNS ABOUT CREDENTIALS OF TUNSON
ENGINEERING CO LTD: 196
DECEMBER 1991 – JANUARY 199218. MINISTER FOR TRANSPORT EXPEDITES
PREPARATION OF NEW POLICY 707
SUBMISSION: FEBRUARY 199219. HISTORY OF THE PROPOSAL BY 217
KINHILL KRAMER PTY LTD20. RESOURCE MANAGEMENT
COMMITTEE RECOMMENDS RE-TENDERING 238
OF PROJECT: 20 FEBRUARY 19922L THE MINISTER FOR TRANSPORTS 241
POLICY SUBMISSION OF FEBRUARY 199222. FAVOURABLE ASSESSMENT OF
THE KINHILL KRAMER PROPOSAL23. NATIONAL EXECUTIVE COUNCIL DECIDES TO
AWARD PROJECT TO KINHILL KRAMER 284
CONSORTIUM: 24 FEBRUARY 1992 -
Page 4 of 397
-
24. OVERVIEW OF EVENTS BETWEEN APPOINTMENT
OF KINHILL KRAMER CONSORTIUM AND 290
SIGNING OF CONTRACT: FEBRUARY – MAY 199225. CONCERNS RAISED BY DEPARTMENT OF WORKS
ABOUT DRAFT CONTRACT: 304
MARCH – APRIL 199226. DEPARTMENT OF TRANSPORT RECOMMENDS SIGNING
OF CONTRACT AGAINST ADVICE OF OTHER 321
DEPARTMENTS: 22 APRIL 199227. NATIONAL EXECUTIVE COUNCIL DECIDES THAT 332
CONTRACT MUST BE FINALISED: 23 APRIL 199228. ACTION TAKEN BY FOUR KEY DEPARTMENTS
PRIOR TO THE NATIONAL EXECUTIVE COUNCIL 334
MEETING ON 29 APRIL 199229. NATIONAL EXECUTIVE COUNCIL REJECTS ADVICE
OF DEPARTMENT OF ATTORNEY-GENERAL: 29 APRIL 1992 35530. ACTING STATE SOLICITOR GIVES LEGAL CLEARANCE 358
DESPITE DEFECTS IN CONTRACT: 6 MAY 199231. NATIONAL EXECUTIVE COUNCIL APPROVES 367
EXECUTION OF CONTRACT: 6 MAY 199232. EVENTS LEADING UP TO EXECUTION OF 375
THE CONTRACT: 6 – 27 MAY 199233. THE CONTRACT OF 27 MAY 1992 395
34. EVENTS AFTER 27 MAY TERMINATION
OF CONTRACT AND APPOINTMENT OF A 400
COMMISSION OF INQUIRYPART III: LAWS RELEVANT TO PUBLIC WORKS CONTRACTS
-
Page 5 of 397
-
35. THE PUBLIC TENDER REQUIREMENTS OF 406
THE PUBLIC FINANCES (MANAGEMENT) ACT36. THE PUBLIC WORKS COMMITTEE ACT AND THE
ROLE OF THE PARLIAMENT IN MONITORING 424
PUBLIC WORKS PROJECTS37. CONTROL OF OVERSEAS 39
BORROWING BY THE STATE38. LAWS GOVERNING FOREIGN INVESTMENT 446
39. LIMITS ON THE POWERS OF MINISTERS 451
40. FUNCTIONS OF THE DEPARTMENT OF 460
TRANSPORT AND THE DEPARTMENT OF WORKSPART IV; FINDINGS UNDER SECTION 219(1) OF THE
CONSTITUTION AND SECTION 22(1) OF THE
ORGANIC LAW ON THE OMBUDS • COMMISSION41. FINDINGS AS TO THE CONDUCT OF THE 468
FORMER MINISTER FOR TRANSPORT42. FINDINGS AS TO THE CONDUCT OF THE
DEPARTMENT OF TRANSPORT AND 480
THE SECRETARY FOR TRANSPORT43. FINDINGS AS TO THE CONDUCT OF THE
DEPARTMENT OF WORKS AND THE 497
SECRETARY FOR WORKS44. FINDINGS AS TO THE CONDUCT OF THE
DEPARTMENT OF ATTORNEY-GENERAL, THE 501
SECRETARY OF THE DEPARTMENT AND THE
ACTING STATE SOLICITOR45. FINDINGS AS TO THE CONDUCT OF THE
DEPARTMENT OF FINANCE AND PLANNING 506 -
Page 6 of 397
-
AND THE SECRETARY FOR FINANCE
46. FINDINGS AS TO THE CONDUCT OF THE 512
NATIONAL EXECUTIVE COUNCILPART V; RECOMMENDATIONS OF THE OMBUDSMAN COMMISSION
47. RECOMMENDATIONS CONCERNING LAWS RELEVANT 518
TO PUBLIC WORKS PROJECTS48. RECOMMENDATIONS AS TO THE EXERCISE 529
OF POWERS BY MINISTERS49. RECOMMENDATIONS CONCERNING THE POWERS 534
AND DUTIES OF DEPARTMENTAL HEADS50. RECOMMENDATIONS CONCERNING PROCEDURES 536
OF THE NATIONAL EXECUTIVE COUNCIL5L RECOMMENDATIONS TO THE DEPARTMENT 544
OF TRANSPORT52. RECOMMENDATIONS TO THE DEPARTMENT 548
OF ATTORNEY-GENERAL53. RECOMMENDATIONS TO THE DEPARTMENT 550
OF FINANCE AND PLANNING54. RECOMMENDATIONS TO THE MINISTER FOR
TRADE AND INDUSTRY AND THE INVESTMENT 554
PROMOTION AUTHORITY55. RECOMMENDED DISCIPLINARY PROCEEDINGS 557
56. RECOMMENDATIONS CONCERNING THE FUTURE OF THE 561
SPRING GARDEN ROAD/POREPORENA FREEWAY PROJECTPART VI SUMMING UP
57. SUMMING UP 566
-
Page 7 of 397
-
LIST OF EXHIBITS 571
i
PART I 1
NATURE AND PURPOSE OF THE INVESTIGATION2
1. INTRODUCTION
(1.1] THE OMBUDSMAN COMMISSION’S DECISION TO CONDUCT AN
INVESTIGATIONOn 27 May 1992 the Governor-General, Sir Wiwa Korowi, signed a
contract
on behalf of the Independent State of Papua New Guinea for the
design,
finance and construction of a freeway in the city of Port
Moresby. The
Governor-General was acting on the advice of the National
Executive
Council, which a few weeks earlier had given final approval
for the signing
of the contract. -
Page 8 of 397
-
The Ombudsman Commission received information from a number of
different sources suggesting that normal procedures had not
been
followed. It was also alleged there were irregularities in the
contract
negotiations and that the terms of the contract were heavily
weighted
against the interests of the State.After making preliminary inquiries, it appeared that the
project had neither
been put to tender nor considered by the Parliament. As it was
the
Commission’s understanding that public works projects of this
magnitude
(the contract committed the State to a minimum payment of US
$67 million
plus interest) were subject to these procedures, the
Commission decided
in May 1992 that it would conduct an investigation, on its own
initiative, into
the circumstances leading to and surrounding the decision of
the NationalChapter 1
3
Executive Council to advise the Governor-General to sign
the contract for
the design, finance and construction of the freeway.[1.2] JURISDICTION
The Commission conducted its investigation under the
Organic Law on the
Ombudsman Commission. Section 13 authorises it to
investigate, on its
own initiative, any “conduct” on the part of any
“governmental body” or any
of its officers. The Commission can thus investigate the
conduct of any
arm, department, agency or instrumentality of the National
Government,
including the National Executive Council (Schedule 1.2(1)
of the
Constitution).The Commission can investigate the policy of the National
-
Page 9 of 397
-
Government or
a Minister, to the extent that the policy is contrary to
law or to the National
Goals and Directive Principles, the Basic Rights or the
Basic Social
Obligations or any Act of the Parliament (Section 219(3) of
the
Constitution).The Ombudsman Commission is not authorised to conduct an
investigation
into the conduct of private citizens and companies.
Nevertheless, in the
course of reporting its findings and opinions on the
conduct of
governmental bodies, it is sometimes necessary to comment
on the
conduct of others who may not be within the jurisdiction of
the
Ombudsman Commission. That has happened in this report: we
have
occasionally made comments on the conduct of private
companies, as part
of the formation of an opinion on the conduct of various
governmental
bodies.Chapter 1
4
[1.3] THE PURPOSE OF THIS INVESTIGATION
The purpose of this investigation was not to report on whether
the city of
Port Moresby needs a freeway. That could have formed a part of
the
investigation, because Section 219(3) of the Constitution
allows the
Ombudsman Commission to inquire into National Government
policies
which are contrary to the National Goals and Directive
Principles.The second of our National Goals is for all our citizens to
have an equal
opportunity to participate in, and benefit from, the -
Page 10 of 397
-
development of our
country’. Directive Principles 2(3) and 2(4) require that
every effort be
made to achieve an equitable distribution of the benefits from
development
and an equalisation of services throughout the various parts
of the country.It is arguable whether these objectives were advanced by the
decision of
the National Executive Council to commit a large amount of
public money
to the building of a freeway in the nation’s capital;
especially as it is widely
recognised that the rural infrastructure of our country is
seriously under-
developed.Nevertheless, the Ombudsman Commission decided, in its
deliberate
judgment, not to make that policy decision of the National
Executive
Council the subject of this investigation. We were concerned,
instead, with
the decision-making process which attempted to implement that
policy.In accordance with Section 219(1) (a) of the Constitution the
purpose of the
investigation was:to determine whether any of the “conduct” under
investigation
was “wrong”; andChapter 1
5
to determine whether there were “defects in any law
oradministrative practice.
[1.4] WHAT IS ‘WRONG’ CONDUCT?
-
Page 11 of 397
-
Section 219(2) of the Constitution states that conduct is
“wrong” if, forexample, it is:
“(a) contary to law; or
(b) unreasonable, unjust/oppressive or improperly
discriminatory, whether
or not it is in accordance with law or practices or(c) based wholly or partly on improper motives,
irrelevant grounds or
irrelevant considerations; or(d) based wholly or partly on a mistake of law or of
fact or(e) conduct for which reasons should be given but were
not,whether or not the act was supposed to be done in the
exercise of deliberate
judgement within the meaning of Section 62 (decisions in
‘deliberate judgement’).”However, Section 219(2) of the Constitution also provides
that theOmbudsman Commission is not constrained in its determination
of whetherconduct is “wrong”, by the examples listed above. The
OmbudsmanCommission has a wide discretion to exercise in making this
determination.In exercising its discretion the Commission is guided, in
particular, by theNational Goals and Directive Principles and the Basic Rights
and the BasicSocial Obligations, as permitted by Sections 25 and 63 of
the Constitution. -
Page 12 of 397
-
Chapter 1
6
(1.51 RELEVANCE OF THE LEADERSHIP CODE
The Ombudsman Commission of Papua New Guinea is entrusted with
the
task of administering two Organic Laws:the Organic Law on the Ombudsman Commission; and
the Organic Law on the Duties and Responsibilities of
Leadership.The provisions of the Organic Law on the Duties and
Responsibilities of
Leadership, together with those in Division 111.2 of the
Constitution,
comprise the Leadership Code.We emphasise that this report has not been prepared for the
purpose of
recording alleged breaches of the Leaddership Code. The
procedure for
dealing with such matters is prescribed by the Organic Law on
the Duties
and Responsibilities of Leadership. This report has Int been
prepared
under that Organic Law.This is a report prepared in accordance with the Organic Law on
the
Qmbudsman Commission. Our primary function in this
investigation has
been to investigate and report on wrong conduct and defective
laws and
administrative practices and to make recommendations
accordingly.In discharging that function the Ombudsman Commission has not
formed
any judgment on whether any of the persons involved have -
Page 13 of 397
-
breached the
Leadership Code.Chapter 1
7
METHOD OF INQUIRY
The Commission obtained documents and other evidence from a number
of different sources and used its powers under Section 18 of the
Organic
Law on the Ombudsman Commission to summon persons to attend before
the Commission and give evidence under oath and produce documents
in their possession or control. Most persons summoned to attend were
co-
operative. However it was, on occasions, necessary to warn some
persons
of their obligation to comply fully with the terms of the summons
served
on them.We take this opportunity to point out that it is not sufficient for
a person
who has been required to produce all documents pertaining to a
certain
subject matter to attend the Commission and produce only some, or
even
most, of the documents required. Failure to comply fully with an
Ombudsman Commission summons is a serious criminal offence under
Section 30 of the Organic Law on the Ombudsman Commission, the
penalty for which is a K500.00 fine or three months imprisonment for
each
offence (see The State v Allan Ebu Marai, National Court decision,
O.P. 1
of 1991, 12.2.92).A number of the documents obtained by the Ombudsman Commission
under summons would in the ordinary course of events be regarded as
confidential in nature,e.g. those providing evidence of the
proceedings of
the National Executive Council. However, the effect of Section 19(1)
of the
Organic Law on the Ombudsman Commission is that the Ombudsman
Commission can only be denied access to such documents when the
Prime Minister, after consultation with the Chief Ombudsman,
certifies that
their production is likely to: -
Page 14 of 397
-
Chapter 1
“(a) prejudice the security, defence or international
relations of Papua New
Guinea (including Papua New Guinea’s relations with the
Government
of any other country or with any international
organization) or the
investigation or detection of offences; or(b) involve the disclosure of proceedings, deliberations or
decisions of the
National Executive Council which the “‘time Minister
certifies relate
to matters of a secret or confidential nature,
disclosure of which would
be contrary to the public interest.”In the present case, no certificate under Section 19(1) was issued
in
respect of any documents which the Commission sought access to and
so the Commission was able to require the production of those
documents.The investigation was conducted in private, as required by Section
17(2)
of the Organic Law on the Ombudsman Commission.* * * * * * * * * *
-
Page 15 of 397
-
Chapter 1
2. BACKGROUND OF THE FREEWAY PROPOSAL
[2.1] PORT MORESBY’S TRAFFIC PROBLEMS
It has been recognised for many years that the peculiar
geography of the
city of Port Moresby has given rise to a serious traffic
problem. Other than
following the long and winding “back road” through Baruni, or
the
inconvenient route along Scratchley Road through Kila Kila,
only the Sir
Hubert Murray Highway can carry traffic between downtown Port
Moresby
and the other major traffic-generating parts of the city at
Gerehu, Waigani,
Hohola, Boroko and Jacksons Airport.The Highway, however, is not a high quality road and it is
often congested.
Breakdowns and accidents on some sections, particularly Three
Mile Hill,
can cause huge traffic jams.2.2] THE UNCONNECTED SECTIONS OF THE SPRING GARDEN ROAD
NETWORKConstruction of an alternative route, between the suburbs of
Hohola and
Konedobu, has long been regarded as the solution to the
problem.
Various proposals have been put forward over the last thirty
years and -
Page 16 of 397
-
most have favoured a road passing through the saddle of Burns
Peak
linking two presently unconnected sections of “Spring Garden
Road”.
These two unconnected sections are shown on the map at the end
of this
chapter. They are:Chapter 2
10
from Champion Parade Konedobu to a point close to the
Department of Transport headquarters in Konedobu: see
map, points “B” to “C”; andfrom Burns Peak Road Hohola to Wards Road Hohola: see
map, points “D” to “E”.There are also other unconnected sections of the Spring Garden Road
network which have, at various times, been earmarked for
construction or
redevelopment. These are:from Wards Road Hohola to a point near the Hohola
Demonstration School: see map, points “E” to “F”; andfrom Hekakora Street Hohola to Boroko Drive: see map,
points “G” to “I”.More recently, it has been proposed that the Spring Garden Road
network
be extended at “both ends”, to form one arterial road linking the
seaport
at downtown Port Moresby with Jacksons Airport: see map, points “A”
to
‘. Under this proposal, the extended sections of the Spring Garden
Road
network would have been:from Stanley Parade in downtown Port Moresby, along
Champion Parade, to Spring Garden Road, Konedobu: see
map points “A” to “B”; andfrom the intersection of Spring Garden Road and Boroko
Drive, Gordons, via Geauta Road, across the Sir Hubert
Murray Highway at Erima to Jacksons Airport: see map,
points “in to “K’. via “J”.Chapter 2
11
-
Page 17 of 397
-
[2.3] DECISIONS OF THE NATIONAL EXECUTIVE COUNCIL DURING THE
1980sIn the 1980s, the Spring Garden Road issue was addressed by
the
National Executive Council on a number of occasions. In
dealing with
National Executive Council submissions and decisions in this
report, we
have paid special reference to the “Submissions Handbook for
National
Executive Council and National Parliament”. [EXHIBIT 1]In 1984, the National Executive Council directed the then
Department of
Transport and Civil Aviation to arrange a feasibility study on
the “Burns
Peak Road” and to ensure that funding was available under the
National
Road Improvement Programme for 1985-88. [EXHIBIT 2]In 1988, requests for assistance were made to the GoVernment
of Japan
for possible funding under grant aid and soft loan
arrangements for a
number of projects, including the Burns Peak tunnel. [EXHIBIT
3]Also in 1988, Barclay Bros (PNG) Pty Ltd put a proposal to the
National
Government which included an open-cut road through Burns Peak,
linking
the Konedobu and Hohola sections of Spring Garden Road, at an
estimated cost of K11 million. It was proposed that the
project take place
in conjunction with the redevelopment of Port Moresby’s port
facilities. The
Barclay Bros proposal was discussed by a committee which
recommended
that the project be tendered. This proposal also failed to
come to fruition.
[EXHIBITS 4 & 4A]In 1989, the Departments of Transport, Foreign Affairs and
Finance and
Planning were directed by NEC Decision No. 76/89 to approach
the
Government of Denmark for aid funding on this and other
transport
projects. [EXHIBIT 5]Chapter 2
-
Page 18 of 397
-
12
[2.4] THE NATIONAL EXECUTIVE COUNCIL DECISION OF 25 JANUARY
1990It was against this background that the National
Executive Council
reconsidered the matter at its meeting on 25 January
1990, following a
Policy Submission by the Minister for Transport, Mr
Anthony Temo.
[EXHIBIT 6]In Decision No.14/90, the National Executive Council:
directed the Department of Transport,
Department of Works and
Department of Finance and Planning to
formulate detail plans for the
construction of Burns Peak Road;2. directed that the plan should include the
re-evaluation of the Barclay
proposals and any other Turn-Key’
proposals available;3. approved the engaging of Ove Amp and
Partners (Pacific) Pty Ltd, to
undertake the Port Moresby Road Needs
Study (Arterial Roads);4. advised the Governor-General to enter into
agreement on behalf of the
State with Ove Amp and Partners (Pacific)
Pty Ltd” [EXHIBIT 6A]* * * * * * * * * *
-
Page 19 of 397
-
Chapter 2
MAP: THE SPRING GARDEN
ROAD NETWORK AND THE ROUTE OFTHE PROPOSED POREPORENA FREEWAY
Points marked:
A Stanley Parade/
Champion Parade
B Champion
Parade,Spring Garden Road
C End of Spring.
Garden Road Konedobu
D Spring Garden
Road/Burns Peak Road
E Spring Garden
Road/Wards Road
F Spring Garden Road
(Near Hohola Demonstration School)
G Spring Garden
Road/Hekakora Street
H Spring Garden
Road/Waigani Drive
I Spring Garden
Road/Boroko Drive/Geauta Road (Courts’ Roundabout)
Geauta Road/
Kookaburra Street/Sir Hubert Murray Highway
K Jackson
International Airport -
Page 20 of 397
-
• Burns Peak
Chapter 2
14
3. STRUCTURE OF THE REPORT
[3.1] FOCUS OF INVESTIGATION
On 6 May 1992 the National Executive Council decided to advise
the
Governor-General to enter into a contract with Kinhill Kramer
Pty Ltd and
Curtain Bros (Old) Pty Ltd for the design, finance and
construction of the
Poreporena Freeway. That decision was a crucial one. However,
in
conducting this investigation, the Ombudsman Commission was
not only
interested in the circumstances immediately surrounding that
particular
decision. Our wider concern was to determine whether the whole
decision-
making process which occurred after the National Executive
Council
decision of 25 January 1990 was carried out lawfully in
accordance with
sound administrative practices.The Ombudsman Commission therefore considered all the events
that
occurred after 25 January 1990, which culminated in the
signing of the
contract on 27 May 1992. After examining the evidence obtained
in the
course of the investigation, the Commission made a number of
findings.These are set out in Part II of the report, which contains a
chronological
account of the events which led to the signing of the
contract. Each of
Chapters 4 to 33 highlight a significant incident or decision
which formed
the chain of events up to 27 May 1992. -
Page 21 of 397
-
Chapter 3
15
2] ALL PERSONS ADVERSELY COMMENTED ON HAVE BEEN GIVEN A
RIGHT TO BE HEARD
During the course of documenting these findings, the
OmbudsmanCommission found it necessary to be critical of the conduct
of someindividuals and governmental bodies. All of these persons
and, in the caseof governmental bodies, their representatives, were given an
opportunityto be heard prior to the completion of this report, in
accordance with theduties imposed on the Ombudsman Commission under Section
17(4) ofthe Organic Law on the Ombudsman Commission.
Section 17(4) states:
“Nothing in this Law compels the Commission to hold any
hearing and no
person is entitled as of right to be heard by the
Commission except that –(a) where a report of the Commission may affect a State
Service, provincial
government body or statutory body, the Commission
shall provide -
Page 22 of 397
-
reasonable opportunity for the Permanent Head of
that service or the
statutory head of that body, as the case may be, to
comment on the
subject of the investigation; and(b) the Commission shall not make any comment in its
report that is adverse
to or derogatory of any person without –(i) providing him with reasonable opportunity of
being heard; and(ii) fairly setting out his defence in its report”
3.3] RELEVANT IAM
One of the main concerns of the Ombudsman Commission at the
commencement of the investigation was the allegation – which
came frommany sources – that proper financial and contractual
procedures had beenbypassed.
Chapter 3
16
Part II( of the report accordingly gives an account of
some of the important
laws regulating public works contracts in Papua New
Guinea.[3.4] PART IV SUMMARISES AND FORMALISES ADVERSE FINDINGS
-
Page 23 of 397
-
Part IV of the report summarises the adverse findings
made against
individuals and governmental bodies in Part II. These
findings are based
on Section 219 of the Constitution and Section 22 of
the Organic Law on
the Ombudsman Commission, which prescribe the type of
conduct which
is “wrong” or otherwise requires criticism by the
Ombudsman Commission.[3.5] RECOMMENDATIONS OF THE OMBUDSMAN COMMISSION
Part V of the report contains a number of important
recommendations
arising from our investigation. In particular, we make
suggestions as to the
manner in which public works projects such as the
Spring Garden Road
(also known as the Poreporena Freeway) project should
be handled in
future.[3.6] SUMMING UP
Part VI sums up the investigation and the findings of
the Ombudsman
Commission.* * * * * * * * * *
Chapter 3
17
PART II
RECORD OF EVENTS
AND FINDINGS OF THE OMBUDSMAN COMMISSION18
-
Page 24 of 397
-
4. DECISION TO PUBLICLY INVITE EXPRESSIONS OF INTEREST:
MAY 1990[4.1] THE INTERDEPARTMENTAL MEETING OF 22 MAY 1990
After the National Executive Council decided in January 1990
that detailed
plans ‘tor the construction of Burns Peak Road” be drawn up,
very little
happened until May 1990, when the Minister for Transport, Mr
Anthony
Temo, convened an interdepartmental meeting. The meeting was
held on
22 May 1990 and was chaired by Mr Temo. The subject was ‘the
Burns
Peak Road Development’. [EXHIBIT 8]Representatives from various departments and the Harbours
Board were
present, as well as a consultant employed by Ove Arup and
Partners, the
firm engaged to conduct the Port Moresby Road Needs Study.
This study
later concluded that construction of a link through Burns Peak
would have
a beneficial effect on the Port Moresby economy and that
traffic flow on
the Three Mile Hill section of the Sir Hubert Murray Highway
would
consequently be reduced by almost 50%.[42] ISSUES UNDER CONSIDERATION
During this meeting, two crucial issues were addressed:
Chapter 4
19
1. The method of construction of the Bums Peak link
Once it had been decided that the route for the new road
would pass through Burns Peak, the next thing to decide was
the best way of getting through. Should a tunnel be
constructed or would it be better to make a “cut” through the
mountain? -
Page 25 of 397
-
2. The method of financing the project
The other crucial issue discussed at the meeting was the
method of financing the project. One proposal, closely linked
with the tunnel option, was that part of Spring Garden Road
would become a tollway.This later became transformed into the Build-Operate-Transfer
(BOT) concept. Under this method of financing, it was
envisaged that the Government would engage a contractor
to build and operate the road as a tollway, holding the ‘title’
to it for, say, twenty years, until the contractor made a
reasonable return on its investment, and then returning the
road to the State. elThe Minister for Transport favoured this option, though he
was also willing to consider other options, provided they
involved no financial cost to the Government.Chapter 4
20
[4.3] NO FIRM POUCY DECISIONS MADE
No firm decisions were made on either the method of
construction or the
method of financing the project at the meeting of 22 May 1990.
The most
important outcome was that the Minister for Transport directed
the
Department of Transport to advertise the project so that
interested parties
could express their interest.The Minister also announced that he intended to direct the
Department of
Works to commence detailed design of the project immediately
and to
complete the design within six months. This was confirmed in
writing the
following day, 23 May 1990, in a letter to the Acting
Secretary of the
Department of Works, Mr G Morea. [EXHIBIT 9] -
Page 26 of 397
-
[4.4] MINISTER FOR TRANSPORT EXCEEDED HIS POWERS
It should be noted that the Minister for Transport had no
power to give this
direction to the Department of Works.Section 148 of the Constitution states that Ministers only
have such titles,
portfolios and responsibilities as are given to them, from
time to time, by
the Prime Minister. During 1990, Mr Temo had no responsibility
for the
Department of Works and therefore it was wrong of him to
direct the
Department to finish the design within six months. We are not
suggesting
there was anything improper about getting the design phase
underway;
but if the Minister for Transport wanted to expedite the
project, he should
have gone about it the right way, by liaising with the
Minister for Works,
Secretary for Works and Secretary for Transport.Chapter 4
21
When we made this finding in our preliminary report, Mr Temo
responded
as follows:‘The direction to Secretary for Works was a result of a
suppose to be ministerial
committee meeting. When the respective ministers did not
turn up their
respective secretaries or their nominees turned up.
The Department of Works representative suggested the
idea that it would take
up to 6 months to have the Geo-Technical report ready
and he wanted the
decision to be relayed officially as a result of this
meeting.
This letter was drafted by my staff relaying the
decision of the meeting.
I was also acting as Chairman of ministerial committee
on infrastructure_
[10331BIT 257, page 1] -
Page 27 of 397
-
Mr Temo’s response does not address the thrust of our
criticism. His
direction to the Department of Works was unlawful and wrong,
in that it
was contrary to Section 148 of the Constitution..5] MINISTERS DO NOT HAVE THE POWER TO DIRECT DEPARTMENTS IN 1
THEIR DAY-TO-DAY ACT1VMESThere is an important aspect of Sectior 148 of the
Constitution that muss
be emphasised here: though Section 148 gives Ministers
“political.
responsibility for particular Departments, it does not give
them any power
to direct or control a Department in its day-to-day
activities.A Minister is not the boss of a Department – the Head of the
Department
is the boss. The Ministers job – in conjunction with the
National Executive
Council – is to set the Department’s policy on important
issues. It is not his
job to give directions to the Departmental Head or to
Departmental officers
on day-to-day matters. The only exception is where a Minister
is specifically
empowered by an Act of Parliament to give directions or make
certain
decisions. 1Chapter 4
22
This important constitutional principle was explained
by the Supreme Court
in Supreme Court Reference No. 1 of 1982: Re Bouraga
[1982] PNGLR
178. We discuss it further in Chapter 39 of this
report.So, even if Mr Temo had had political responsibility
-
Page 28 of 397
-
for the Department of
Works, it still would have been wrong for him to direct
the Secretary for
Works to complete the design within six months. He
could only request
that that be done and ensure that there were sufficient
funds available for
that purpose.[4.6] IGNORANCE OF SECTION 148 OF THE CONSTITUTION: A MAJOR
PROBLEM
There is a lot of misunderstanding of Section 148 of
the Constitution in the
Public Service, and some Ministers appear to know
little about it.The Ombudsman Commission often finds that Ministers
believe that, simply
because they are Ministers, they have the right to give
directions to anyone
in “theirs Department, or even, as shown in the present
case, in a
Department for which they have no responsibility. This
is wrong. It is
unconstitutional and it leads to chaos.Unfortunately, there were many occasions during the
life of the Spring
Garden Road/Poreporena Freeway project when the
Minister for Transport
exceeded his powers as a Minister. This was the first
of them.* * * * * * * * * *
Chapter 4
23
5. ADVERTISEMENT INVITING EXPRESSIONS OF INTEREST:
JUNE 1990[5.1] ADVERTISEMENT PUBLISHED IN POST COURIER AND NATIONAL
GAZEnE
Advertisements inviting expressions of interests in the “Burns
Peak/Spring -
Page 29 of 397
-
Garden Road Link” were published in the Post Courier on 20 and
22 June
1990 and the National Gazette on 28 June 1990. [EXHIBITS 12 &
18]There are three points that should be noted about the
advertisement. They
concern:the scope of the project;
co-ordination of the project; and
financing of the project.
I. THE SCOPE OF THE PROJECT
[5.2] TERMS OF THE ADVERTISEMENT
The advertisement stated that the National Executive Council
had decided
that “the section of Spring Garden Road in the National
Capital District
between Waigani Drive and Kaevaga/Konedobu … is to be
constructed as
soon as possible”.Chapter 5
24
This statement was a little misleading.What precisely had the National Executive Council decided?
What the National Executive Council had, in fact, decided by
Decision No.
14/90 was that “plans for the construction of Burns Peak Road”
be
formulated.This was a very vague decision. The only road in Port Moresby
that is
called “Burns Peak Road” is the dirt track running from Spring
Garden
Road, near Walnut Place, Hohola to the top of Burns Peak where
the
telecommunications transmitters are located.Despite the vagueness of Decision No. 14/90 it was assumed by
everyone
concerned that the National Executive Council was actually
referring to -
Page 30 of 397
-
Spring Garden Road. However, this interpretation still caused
problems,
because the National Executive Council did not specify (and
has never at
any stage specified) the particular parts of Spring Garden
Road it wanted
constructed and/or upgraded.[5.3] WHAT WAS MEANT BY ‘THE BURNS PEAK ROAD” OR “SPRING GARDEN
ROAD”?This was not just a small side issue – it concerned the scope
of the whole
project. Did the National Executive Council want the upgraded
road to
begin at the junction of Stanley Esplanade and Cuthbertson
Street in
downtown Port Moresby or was the network to begin at the
junction of
Champion Parade and Spring Garden Road in Konedobu? Was the
road
to go through Burns Peak to Wards Road? Or one stage further,
to
Waigani Drive? Or to the end of Spring Garden Road at Boroko
Drive? Or
further still, to the Sir Hubert Murray Highway, at Erima? Or
was the road
required to go all the way to Jacksons Airport?Chapter 5
25
Any of these options could conceivably have been brought
within the
terms of the decision that “plans for the construction of the
Burns Peak
Road” be formulated.The Policy Submission which had generated the decision did not
shed any
light on this issue. It simply made reference to the scope of
the project in
general terms such as:The purpose of the Submission is to request the National
Executive Council
to direct Department of Works, Department of Transport and
Department of -
Page 31 of 397
-
Finance and Planning to adopt special procurement
procedures to undertake the construction of Burns Peak Road
(Spring Garden Road). The measures could
construction of Burns Peak Road (Spring Garden Road). The
measures could
include turnkey arrangements.-
Construction of the BUMS Peak will involve considerable
financial commitment’ [EXHIBIT 6, page 1]
[EXHIBIT 6, page 1]5.4] THE DEPARTMENT OF TRANSPORTS INTERPRETATION OF THE
5.4] THE DEPARTMENT OF TRANSPORTS INTERPRETATION OF THE
NATIONAL EXECUTIVE COUNCIL DECISIONThe Secretary for Transport, Mr B K Amini CBE, interpreted the
decision
as applying only to the section of Spring Garden Road between
Konedobu
and Waigani Drive. This is evident from a letter dated 7 June
1990 he
wrote to the Secretary for Works, Mr A Temu. Mr Amini
described the
scope of the project in the following terms:‘I wish to restate that the scope has not change except the
grade and the
elimination of the design of the tunnel option. Basically
the scope of works am-
am-8% grade
4 lanes (2 lanes in each direction)
80 km/ph
Establishment of a highway link between Rohola (Junction of
Waigani Drive
and Spring Garden Road East) and Konedobu (Junction of
Champion Parade
and Spring Garden Road West) by improving and extending
Spring Garden
Road over Burns Peak, Intersecting and crossing Wards
Road.’
[EXHIBIT 10, page 1]Chapter 5
-
Page 32 of 397
-
26
[5.5] CHANGE OF SCOPE WITHOUT EXPLANATION
The Secretary for Transport’s interpretation of the National
Executive
Council decision was reflected in the advertisements inviting
expressions
of interest. But that interpretation did not remain constant.Two years after the advertisement was published, the State had
entered
into a contract for construction of a freeway all the way from
downtown
Port Moresby to Jacksons Airport. This was a considerable
expansion in
the original scope of the project. [EXHIBITS 231 A, 231 B,
232][5.6] WHO MADE THE DECISION TO EXPAND THE SCOPE OF THE PROJECT?
In the course of this investigation, the Ombudsman Commission
was never
able to identify when the decision was made to alter the scope
of the
project. Nor can we say who made it. It seems to have “just
happened’
that way.Mr Amini’s explanation
When we raised this matter in our preliminary report, the
Secretary for
Transport, Mr Amini, responded in the following terms:For every major project undertaken by the Department of
Transport, there is
a feasiblity study that defines the scope in general terms.
The outcome of the
feasibility study is a three-part report – a summary
containing the main findings -
Page 33 of 397
-
and recommendations, – a main report containing the main
issues and – technical
appendices or working papers. These serve as working papers
on each project,
including this one and there is minimum of paperwork. After
these reports,
follows the detailed design that pins down the last
centimetre of the project’s
scope – where it starts and where it ends. It should be
noted that, for this
project, the detailed design had not been done as it was
part of the turn-key –
the consortium was going to do that as part of the
contract.Chapter 5
27
The project feasibility report prepared by the
consultants, Ove Arup of Australia
– entitled ‘Spring Garden Road Economic Assessment’ –
contained the detailed
scope of the project and it is a reference point and not a
file. The scope was
extended to connect the new DCA road from the airport
(note this is normal to
extend the scope – Department of Works almost invariably
extend every project
they implement). The end of the DCA project was known
because it had been
designed and that is where we were to end this project.
The DCA project was
two-lane and wisely we decided to widen it to four to
conform with the
Freeway. Both the start and the end of the project were
clearly known. The
Department followed its set procedures and this cannot be
construed as
defective administration.” [EXEUBIT 254, pages 2-3]Unsatisfactory explanation
-
Page 34 of 397
-
In our view, Mr Amini has not given a satisfactory explanation of
his
Department’s failure to make a careful and reasoned and properly
documented decision as to the scope of the Spring Garden
Road/Poreporena Freeway project.His reference to the ‘Spring Garden Road Economic Assessment’ report
by Arup Australia is, with respect, misleading. Mr Amini suggests
that the
scope of the project was determined in accordance with that report.
Even
if that were true, we would still expect to find evidence that at
some stage
the Department of Transport had made a formal decision to adopt the
recommendations of the report.However, the Arup report entitled ‘Spring Garden Road Economic
Assessment’ did not provide any basis for the decision to extend the
scope of the project to Jacksons Airport along the route envisaged
in the
contract with the Kinhill Kramer/Curtain Bros consortium.Despite Mr Amini’s claim that the start and end of the project were
clearly
known, the ‘Spring Garden Road Economic Assessment Report’ only
contemplated a four-lane road from downtown Port Moresby to the
intersection of Spring Garden Road and Waigani Drive (see Chapter 2Chapter 5
28
map, points “A” to “H”), plus other associated works. The Spring
Garden
Road project, according to that report, did not include the
upgrading of
Spring Garden Road from Waigani Drive to Boroko Drive (see map, “H”
to
“I”). The project also did not include a four-lane arterial road
from the
intersection of Spring Garden Road and Boroko Drive to Jacksons
Airport,
via Geauta Road, which was the route envisaged in the contract
entered
into with the Kinhill Kramer/Curtain Bros consortium (see map,
points “I”
to “K”). [EXHIBIT 9A, page 10, para 5.12; EXHIBIT 233, Part Z
Description of Concept]In Arup’s Study Report, which was separate from the Spring Garden
-
Page 35 of 397
-
Road
Economic Assessment Report, it was recommended that, in addition to
the
Spring Garden Road project, many other road construction and
improvement projects should be undertaken in the city of Port
Moresby.
These included widening the section of Spring Garden Road between
Waigani Drive and Boroko Drive to four lanes (see map, “H” to “I”).
However, the Study Report did not recommend the widening or
upgrading
of Geauta Road, from Boroko Drive to the Sir Hubert Murray Highway
(see
map, “I” to “J”). The Study Report, in fact, recommended that the
most
direct route between downtown Port Moresby and Jacksons Airport
should
be via Sir John Guise Drive, which was proposed to be extended as a
two-lane arterial road. [EXHIBIT 69A, para 7.0, table 1]Thus, neither the Spring Garden Road Economic Assessment Report nor
the Study Report recommended a four lane arterial road along the
route
contained in the contract executed with the Kinhill Kramer/Curtain
Bros
consortium.Mr Hitola’s explanation
When our criticism of the Department of Transport’s failure to
specify the
scope of the project was conveyed to the Secretary for Works, Mr
HitoloChapter 5
29
(who was responsible for this project for a considerable time in the
Department of Transport) he offered a different explanation.Mr Hitolo said that because the project was to be implemented using
Build-Operate-Transfer financing, it was up to the private sector to
determine the financial viability of the project before proposing
the scope
to the Government for approval. Mr Hitolo also said that a careful
and
reasoned and properly documented decision about the scope of the
project required a feasibility study costing between K200,000.00 and
K400,000.00, which had not been budgeted for.
[EXHIBIT 265, page 2]Explanation rejected
We find Mr Hitolo’s explanation unconvincing. Even if we accept
-
Page 36 of 397
-
that, in the
case of a Build-Operate-Transfer project, the scope is determined by
the
developer, the fact is that no Build-Operate-Transfer proposal was
ever
lodged for the Spring Garden Road/Poreporena Freeway project. All of
the
proposals involved turnkey financing.This meant that inevitably – at some stage – the Government would be
paying for the freeway. It was therefore necessary for the
Government to
know exactly where it wanted the freeway to go and how long the
freeway
would be.No proper comparison of competing proposals could be made unless
everyone concerned knew the beginning and end points of the freeway
and its route.It was the Department of Transport’s responsibility to make a
careful and
reasoned decision on this basic issue. However, it failed to do
this.Chapter 5
30
[5.71 CHANGE OF FUNDAMENTAL DESIGN ALSO WITHOUT EXPLANATION
We make a similar observation on the decision about the
tunnel/cut option.
Mr Amini’s letter to the Secretary for Works of 7 June 1990
makes mention
of the fact that the tunnel option had been eliminated.
[EXHIBIT 10, third
paragraph] But, at an interdepartmental meeting on 31 July
1990, it was
decided that a geotechnical investigation was required, before
a final
decision could be made (see Chapter 7).Throughout 1991, when negotiations were taking place with
likely
contractors, it was assumed the project would include a
tunnel. When the
National Executive Council made Decision No. 36/92 in favour
of IGnhill
Kramer Pty Ltd in February 1992, one of the key criteria (and
one on
which Knhill Kramer was rated “excellent”) was the “expected -
Page 37 of 397
-
quality of
tunnel”. But when the contract was signed, on 27 May 1992,
there was
no mention of a tunnel.MrAminarasmnrA
In our preliminary report, we were critical of the Department
of Transport
for the haphazard manner in which the tunnel/cut issue was
addressed.
The Secretary for Transport, Mr Amini, replied that the
geotechnical
investigation undertaken by Coffey Partners International (see
Chapter 8)
was meant to give a conclusive answer; but he said it turned
out to be
inconclusive. As to the eventual decision to opt for the cut,
rather than the
tunnel, Mr Amini said it was made by the Department of Works.
[EXHIBIT
254, page 3]Chapter 5
31
Mr Hitolo’s response
Mr Hitolo’s explanation of the confusion over the tunnel/cut issue
was that
it was an investment decision, to be made by the consortium selected
to
undertake the project. [EXHIBIT 254, page 2]Neither response was satisfactory
Having considered the responses of Messrs Amini and Hitolo, we
conclude
that neither offered a satisfactory explanation for the Department
of
Transport’s failure to make a careful, reasoned and properly
documented
decision on the tunnel/cut issue.Mr Hitolo’s claim that it was an “investment decision” could only
possibly
make sense if the project were based on Build-Operate-Transfer
financing. -
Page 38 of 397
-
But, as pointed out earlier, no such proposal was ever put to the
Department of Transport. The Government of Papua New Guinea was
always going to pay for this project and therefore it should have
decided
whether a tunnel or a cut through Burns Peak was preferable.We accept Mr Amini’s description of the geotechnical report as
inconclusive. But that report was made available in May 1991 – the
Department of Transport had ample time after that to make a
determination
on this basic technical issue. Though the Department of Works was
eventually consulted, this should have been done on a formal and
methodical basis – not by means of casual conversation between
officers
of the two Departments.We simply do not regard it as an acceptable administrative practice
for the
Department of Transport to have prepared a Policy Submission which
assumed the project would include a tunnel and then – without any
recordChapter 5
32
of consultation or any record of any different decision – to
allow a situation
to develop in which the project included a cut through Burns
Peak, rather
than the tunnel.[5.8] ADMINISTRATIVE INCOMPETENCE BY THE DEPARTMENT OF
TRANSPORTIt is stating the obvious to say that decisions concerning
Papua New
Guinea’s transport infrastructure should not be made as they
were in the
case of the Spring Garden Road/Poreporena Freeway project.Decisions such as the length of a freeway and its fundamental
design
should not be made haphazardly. These decisions involve the
expenditure
of large amounts of public money. They must be made carefully
and
methodically and they must be properly documented. If
Government
departments make important policy decisions haphazardly, it is
virtually
impossible to keep a check on the expenditure of public money.
And it -
Page 39 of 397
-
creates an environment ripe for corruption.
When an investigatory agency such as the Ombudsman Commission
does
a check on a decision-making process which led to the
commitment of
millions of kina of public money, it should be able to find
evidence of a
series of reasoned and methodical steps and the careful
evaluation of
alternatives. But the evidence we have gathered shows the
exact
opposite: it was as if decisions – like the route of the
freeway – were falling
out of the sky.The Ombudsman Commission has concluded that this situation
arose
because of the administrative incompetence of the Department
of
Transport.Chapter 5
33
IL CO-ORDINATION OF THE PROJECT
[5.9] EXPRESSIONS OF INTEREST CO-ORDINATED BY DEPARTMENT OF
WORKS
■Despite the Minister for Transport’s direction at the
meeting of 22 May
1990 that the project be advertised by the Department of
Transport, the
advertisements were actually organised by, and the
responses had to be
made to, the Department of Works.Apparently, this turnaround occurred because the First
Assistant Secretary
(Planning and Research) in the Department of Transport, Mr
Amoako, •
asked the Department of Works for assistance in drafting
the
advertisement. The Principal Engineer (Roads), Mr
Newberry, prepared a
draft which was forwarded to the Department of Transport -
Page 40 of 397
-
for review and
issue. However, Mr Amoako returned the document to Mr
Newberry,
advised him that it was satisfactory and requested that it
be published by
the Department of Works. [EXHIBIT 51, page 2 and EXHIBIT
52, page 2][5.10] A SIGNIFICANT LACK OF CO-ORDINATION
Though there was nothing improper in what was done by Mr
Amoako, this
incident is significant because it typified what was, and
continued to be,
a confusing state of affairs regarding the implementation
of the whole
project: there was a great deal of confusion as to the
respective roles of
the Department of Transport and the Department of Works,
which we
consider was ultimately detrimental to the overall
interests of the State.Chapter 5
34
III. FINANCING OF THE PROJECT
[5.11] TERMS OF THE ADVERTISEMENT
The advertisement of June 1990 alluded to the issue of
financing the
project, in the following terms:“The work may be financed by a combination of
any or all of the following:a toll on the new road link
commercial leases on reclaimed -
Page 41 of 397
-
land
grant funding by external agenciesOther means of funding will be considered but
it is not intended that the
Government will contribute to any major
extent.”[EXHIBITS 12 & 18]
The advertisement did not stipulate that the
successful contractor would
have to itself finance the project.This is significant, because, as the Commission was to
discover in the
course of the investigation, there were a number of
interested parties that
were later summarily rejected because of the
inadequacy of their financing
proposals.We consider this to have been quite unfair, because,
though the
advertisement stated that the Government would
probably not finance the
project, it did not stipulate that any company which
failed to submit a
“financial package” would be automatically excluded
from consideration.* * * * * * * * * *
Chapter 5
35
RESPONSES TO THE ADVERTISEMENT: JULY 1990
-
Page 42 of 397
-
6.1] RESPONSES SENT TO DIFFERENT PLACES
The Ombudsman Commission discovered that some of the
expressions of
interest were sent to the Department of Works, whereas others
went to the Department of Transport.
Department of Transport.[6.2] EXPRESSIONS OF INTEREST SENT TO THE DEPARTMENT OF WORKS
We have been able to confirm, by examining the files of the
Department
of Works, that ten expressions of interest were registered
with it, on or before 31 July 1990, as required by the
advertisement:
before 31 July 1990, as required by the advertisement:Coecon Pty Ltd [EXHIBITS 13, 21]
Barclay Bros (PNG) Pty Ltd [EXHIBIT 14]
Connell Wagner (Old) Pty Ltd [EXHIBIT 17]
Willing and Partners Pty Ltd [EXHIBIT 20]
Robert Laurie Company Pty Ltd [EXHIBIT 20AA]
Maunsell Consultants PNG/Hornibrook
Constructions Pty Ltd [EXHIBIT 22]Chapter 6
36
Curtain Bros (PNG) Pty Ltd [EXHIBIT 23]
LKN Construction Pte Ltd [EXHIBIT 25]
Cardno & Davies PNG Pty Ltd [EXHIBIT 26]
Juara Ltd [EXHIBIT 29]
(A number of documents we obtained referred to an expression
of interest
being received from Frame Harvey West (e.g. EXHIBITS 24, 38,
50, 148).
However, we could find no evidence of this. The consulting
firm of Frame
Harvey West & Maso later joined with Periquan International
Resources
and submitted a proposal to the Minister for Transport in July -
Page 43 of 397
-
1991, but
it appears not to have formally expressed any interest before
that.)[6.3] EXPRESSIONS OF INTEREST SENT TO THE DEPARTMENT OF
TRANSPORTDespite the clear statement in the advertisement that
expressions of
interest be registered with the Department of Works, five
groups wrote to
the Department of Transport. These were:Executive Decisions Inc Pty Ltd [EXHIBIT 1 OA]
Kumagai Gumi Co Ltd/Kinhill Kramer Pty Ltd
[EXHIBITS 15, 16]Pan Asia Management Consultants Center [EXHIBIT 27]
Chapter 6
37
Ove Arup & Partners (Pacific) Pty Ltd [EXHIBIT
21A]Sabina Ltd/Peter Chen & Partners Pty Ltd
[EXHIBIT 35][6.4] MOST EXPRESSIONS OF INTEREST HELD BY DEPARTMENT OF WORKS
The Department of Works was made aware of all but one of
these
expressions of interest (from the Singapore-based
Executive Decisions Inc
Pty Ltd) when the Department of Transport faxed copies to
them on 1 and
2 August 1990. [EXHIBITS 34, 35] MilIn light of the above, we are satisfied that as at 2
August 1990, the II
Department of Works had at least fourteen expressions of
interest in its
possession and that they were held by the Principal
Engineer (Roads), Mr IN
E Newberry, who was the Department of Works co-ordinator
of the project. -
Page 44 of 397
-
IR
[6.5] NO ACKNOWLEDGEMENT OF THE EXPRESSIONS OF INTERESTDuring the first week of August 1990, Mr Newberry
prepared a summary
of the expressions of interest and delivered it to the
Department of
Transport. No attempt was made at this stage to rank them
in any way.
We are not critical of this, because the advertisement
had not called for
firm proposals – all that was required were expressions
of interest.We consider, however, that the Department of Works should
have at least
sent an acknowledgment to each of the interested groups,
indicating when
a more detailed information package would be available,
which could be
used to formulate firm proposals for the project.Chapter 6
38
When we expressed this opinion in our preliminary report, the
Department
of Works advised that, in fact, several of the expressions of
interest were
acknowledged. We were referred to letters sent to Connell Wagner and
Ove Arup and Partners Pacific and to a telephone call made to the
Robert
Laurie Company. [EXHIBIT 261, page 1]We accept that acknowledgements were given to each of these
companies
in the manner described. [EXHIBITS 17A, 19A AND 20AA]However, acknowledgements were not given to the other twelve
interested
parties. In his response to the Ombudsman Commission, the Secretary
for Works, Mr Hitolo, gave an explanation for this:‘It seems that the major reason that E0Is were not acknowledged
was the rush
that things were done in. This meant that a proper terms of -
Page 45 of 397
-
reference (TOR)
was not sent out, so most EOI’s came in, not so much as
expressions of interest,
but as queries about the project. Concurrently, Mr Newberry was
singlehandedly writing a further TOR (which would have involved a
full team
of !specialists for a project of this scope and magnitude) and
handling all of
the other National Road Design Projects. For a period Mr Newberry
was (or
very nearly was) the only Road Engineer in the Roads & Bridges
Branch, where
the work load is more than 10 engineers ems could handle. He
probably ran out of
time to perform everything. This staff shortage still plagues the
branch…One further complication was that Department of Transport
contacted some of
the parties independently, asking for different information and
receiving their
expressions of interest. These were then passed on to Department
of Works two
weeks after the dosing of expressions of interest.These factors all contributed to the overlooking of the
acknowledgement of
most of the Expressions of Interest. There is no indication that
the failure to
acknowledge them was purposeful.’ [EXHIBIT 263, page 1]While we appreciate the difficulties faced by any Department
suffering
from shortages of staff or other resources, the Ombudsman Commission
remains critical of the Department of Works for not sending
acknowledgements to all the companies which had expressed interest
in
the project. It was a simple administrative task to perform. It was
wrong
of the Department of Works not to carry it out.Chapter 6
39
[6.6] BREAKDOWN IN COMMUNICATION BETWEEN DEPARTMENT OF WORKS
AND DEPARTMENT OF TRANSPORTWe noted earlier that despite the Minister for Transport’s
direction that the project be handled by his Department, the -
Page 46 of 397
-
advertisements calling for
project be handled by his Department, the advertisements
calling for
expressions of interest were actually organised by the
Department of
Works.This was very surprising because it is clear that the Minister
for Transport, Mr Temo, and the Secretary for Transport, Mr
Amini, both genuinely
Mr Temo, and the Secretary for Transport, Mr Amini, both
genuinely
believed that the project “belonged” to the Department of
Transport.The Ombudsman Commission formed this view after interviewing
both Mr
Temo and Mr Amini in the course of the investigation. It was
also apparent
from correspondence between the Minister and the Secretary for
Transport, that the project was regarded as belonging to the
Department
of Transport. We refer, for example, to a letter from Mr Amini
to Mr Temo
on 28 June 1990 in which, only a few days after publication of
the
advertisement, Mr Amini gave Mr Temo an update on the
expressions of
interest for his “advice and directive”. [EXHIBIT 1 9][6.7] DEPARTMENT OF TRANSPORT SUDDENLY INVITES DETAILED
PROPOSALSThe closing date given by the advertisements for registration
of
expressions of interest was 31 July 1990. The Ombudsman
Commission
was surprised to find that before that date, the Department of
Transport
decided – without consulting the Department of Works -to
contact a
selected group of companies and invite detailed proposals for
the project.Chapter 6
40
[6.8] ONLY A SELECT GROUP OF COMPANIES WERE INVITED TO SUBMIT
PROPOSALS IN JULY 1990 -
Page 47 of 397
-
This surprising turn of events occurred around the period
17-20 July 1990.
A pro-forma letter headed “HEARING FOR DEVELOPMENT OF THE
SPRING GARDEN ROAD” was drafted within the Department of
Transport
[EXHIBIT 20A]. It was apparently meant to be sent to all the
companies
which had lodged expressions of interest. We infer this from
the “List of
Interested Companies” attached to the pro-forma letter in the
Department
of Transport file. [EXHIBIT 20A, page 3]However, the Ombudsman Commission is not satisfied that the
letter was
in fact sent to all of those companies. There is no evidence
on file
verifying the postage or facsimile transmission of the letter
to all of the
companies that had lodged expressions of interest.Furthermore, the list in the Department of Transport file
excludes four
groups that had registered interest with the Department of
Works:Curtain Bros (PNG) Pty Ltd;
Cardno & Davies (PNG) Pty Ltd;
Maunsell Consultants/Hornibrook
Constructions Pty Ltd; andJuara Ltd.
Chapter 6
41
[6.9] WHY WERE SOME COMPANIES DROPPED FROM THE UST?
[6.9] WHY WERE SOME COMPANIES DROPPED FROM THE UST?Perhaps the reason for these companies not being on the
Department of
Transport’s list was that their expressions of interest were
received later
than the others (the four referred to above were received by
the
Department of Works during the period 27 July 1990 to 1 -
Page 48 of 397
-
August 1990).
But other than the expression of interest from Maunsell/
Hornibrook (which
was one day late) all were received within the period
specified in the
advertisement.There was therefore no justification for these companies
being dropped
from the list and deprived the opportunity to submit a formal
proposal.During the course of the Commission’s investigation,
representatives of
both Cardno & Davies and the Maunsell/Hornibrook consortium
were
questioned and they confirmed that they had never received
any formal
acknowledgement of their expressions of interest, or been
invited to submit
a formal proposal.It is surprising that these particular companies were omitted
from the short- list, even though they all have permanent
bases in Papua New Guinea and
list, even though they all have permanent bases in Papua New
Guinea and
their expressions of interest were among the most detailed of
those
received by the Department of Works.Indeed, it is ironic that the company which provided the
least amount of
information in its expression of interest – Curtain Bros
(PNG) Pty Ltd – was ultimately selected to be closely
involved in construction of the freeway.
ultimately selected to be closely involved in construction of
the freeway.
[EXHIBIT 23]Chapter 6
42
[6.1 0] RESPONSE BY THE SECRETARY FOR TRANSPORT
When we made these findings in our preliminary report, the
-
Page 49 of 397
-
Secretary for
Transport, Mr Amini, responded in the following terms:‘The Department did not receive any complaint from any
developer. I will urge
the Ombudsman Commission to be cautious in promoting any
particular
developer. If it was unreasonable, at least one or two of
the developers would
have made suggestions as they always do. No developer was
ever stopped or
prevented from submitting a proposal. They were actively
encouraged. In any
case, the submission date was extended twice to
accommodate late bids. This
is not defective administration.’ [EXHIBIT 254, page 31The Ombudsman Commission does not regard Mr Amini’s response
as
satisfactory. His assertion that no developer was ever
prevented from
submitting a proposal is not borne out by the facts.We are not suggesting the Department rejected or refused to
accept any
proposal. What the Department did wrong was to invite
proposals from
only a select group of companies, thus excluding a number of
companies
from consideration.[6.11] OTHER MATTERS OF CONCERN
The Ombudsman Commission is not only concerned about the
Department
of Transport letter being sent to only a select group of
companies. What
is also disconcerting is the timing of the letter and the
demands placed
upon the companies chosen to receive it.The Ombudsman Commission has been able to confirm that the
letter
inviting proposals was sent, during the second half of July
1990, to at least
five of the companies and consortiums referred to on the -
Page 50 of 397
-
Department of
Transport list:Chapter 6
43
Coecon Pty Ltd [EXHIBIT 20B]
Willing and Partners Pty Ltd [EXHIBIT 22A]
Ove Arup & Partners Pacific Pty Ltd [EXHIBIT 28]
Sabina Ltd/Peter Chen & Partners Pty Ltd [EXHIBIT 30]
Kumagai Gumi Co Ltd/Kinhill Kramer Pty Ltd. [EXHIBIT
31][6.12] THE DEPARTMENT’S REQUIREMENTS COULD NOT BE MET
Unreasonable and unrealistic demands were imposed by the
Department
of Transport. The letter stated:“Dear Sir
HEARING FOR DEVELOPMENT OF THE SPRING GARDEN ROAD
This is to inform you of the fact that the Steering
Committee administering
the above-mentioned project will be meeting to consider
your proposals and
you are advised to send the details to this Department
before the 25/7/90.The following planning information is required from you to
assist the
Government in selecting the developer. -
Page 51 of 397
-
I. Technical Feasibility Report
2. Preliminary Design or Plans.
3. Financial Viability for a Toll System.
4. Details of Financial Arrangements.5. Involvement of Landowners in the Development
Chapter 6
44
Since the Government is anxious to complete this project
by September next
year in preparation for the South Pacific Games, it is
important that you state
very clearly whether you can achieve this time frame.Yours faithfully
[Signed]
BRIAN K AMINI CBE
Secretary’. [EXHIBIT 20A]The Ombudsman Commission is at a loss to see how the
Department of
Transport could reasonably have expected these requirements
to be met
within one week. The only specifications available to the
companies were
those in the June 1990 advertisements. How could they be
expected to
submit meaningful technical feasibility reports, preliminary
designs and
financial arrangements, as well as give a proper assessment
of the financial
viability of a toll system and the involvement of landowners,
in the space
of a few days? -
Page 52 of 397
-
As one consultant explained to the Ombudsman Commission, a
detailed
feasibility study of the type being sought by the Department
of Transport
would cost thousands of kina and it would take considerably
longer to do
than the few days suggested in the letter.In sending this letter, the Department of Transport gave the
impression it
had no idea at all of what was involved in a project of this
magnitude.[6.13] MR HETOLO’S EXPLANATION
In his response to our preliminary report, the former head of
the Policy
Secretariat in the Department of Transport, Mr Hitolo, made
these
comments:Chapter 6
45
‘The unreasonable and unrealistic demands were placed on
the plight&
developers because the department was under pressure to
meet the September
1991 Games as mentioned in the letter. This letter was
sent to a selected few
which was a normal practice and usually is called
selective tendering. As long
as three or more proposals are tendered a selection can be
convened. The
whole purpose was for interested and so-called reputable
companies to propose
a plan of execution of the tasks mentioned in the letter
and propose an
alternative if they cannot meet the deadline of September
Games stated in the -
Page 53 of 397
-
letter. It was not mandatory to include all those that
showed interest because
some of the companies saw me personally or phoned to find
out whether
funding was available and when it was explained otherwise
they indicated
disinterest as most of them are not financiers. They only
offer their engineering expertise and were unable to
finance such a big project.•
expertise and were unable to finance such a big project.•
[EXHIBIT 265, page 3]Mr Hitolo’s explanation that representatives of some companies
had seen
him personally or telephoned to find out whether funding was
available is
not considered satisfactory. There were no file notes kept of
the occasions
on which these companies signalled their loss of interest in
the project. We
are also unimpressed by the suggestion that, provided at least
three
proposals were received, a proper selection could be made.The private and undocumented “selective tendering” evident in
the limited
dispatch of the letters of July 1990 is very, very dangerous,
because it can
easily lead to corruption. It is vitally important that the
public tendering
procedures in the Public Finances (Management) Act are
strictly adhered
to, especially in projects which involve millions of kina of
public money (see
Chapter 35).6.14] LETTERS WERE SENT LATE
The unreasonableness of the demands contained in the letters
of July 1990
was exacerbated by the fact that the letters were sent late. -
Page 54 of 397
-
Chapter 6
46
Of the five companies we verified as receiving the letter,
only one received
it before the deadline for submission of proposals. [See the
reference in
each of EXHIBITS 28, 30 and 31 to the letter having arrived
late and the
date-received stamp of 26 July 1990 on EXHIBIT 22k]An example of the confusion caused by the Department of
TransportCoecon Pty Ltd received its letter by facsimile transmission
at 9.32 am on
20 July 1990, but the company was obviously (and
understandably)
confused as to what was required of it. At 2.25 pm on the
same day, the
General Manager, Mr P J Neville, sent a facsimile message to
the Principal
Engineer (Roads), Mr Newberry, at the Department of Works:‘Please advise us of present stage of development for
Burns Peak. For instance:
any technical reports such as preliminary design plans
etc.’ [EXHIBIT 711There is a handwritten note at the foot of that document
(though it is not
clear who its author is, it was probably made by an officer
of the
Department of Works) that typifies the general state of
confusion:‘The information requested of Department of Works by
Coecon is what is
requested of Coecon by Department of Transport. We seem to
be going around
in circles? [EXHIBIT nj -
Page 55 of 397
-
[6.15] ADMINISTRATIVE INCOMPETENCE BY THE DEPARTMENT OF
TRANSPORTTo sum up, the Ombudsman Commission is of the view that the
conduct
of the Department of Transport in dispatching the pro-forma
letter dated
17 July 1990, advising companies that they had to send
details of their
proposals by 25 July 1990, was unfair, unrealistic and
incompetent
administratively for the following reasons:Chapter 6
47
(a) the letter was sent to only a select group of
companies and,
furthermore, excluded the two PNG-based companies
which
had submitted detailed expressions of interest;(b) the Department of Transport failed to advise the
Department
of Works (which was co-ordinating the expressions
of interest)
that it was sending the letter;(c) the letter placed unrealistic demands on the
companies,
which made it impractical for them to respond by
the
deadline;(d) the deadline for submission of proposals was on a
date It
before the closing date given in the
advertisements for
registration of expressions of interest; and(e) the letter was sent late, which resulted in most
of the
companies not receiving it until after the
deadline set for
submission of proposals. -
Page 56 of 397
-
[6.16] SOME COMPANIES WERE NEVER GIVEN ANOTHER OPPORTUNITY TO
SUBMIT PROPOSALSThe conduct of the Department of Transport during July 1990
cannot be
dismissed as a mere administrative hiccup. It would have
been possible
to *forgive” the Department for its unfairness and
incompetence if, at some
later time, a proper opportunity to submit detailed
proposals was given to
a companies which had expressed genuine interest in the
project. But this
never happened.f’hRpter 6
48
As we show later in the report, a number of companies
were never
considered or even contacted by the Department of
Transport again. This
was a disgraceful state of affairs.When this sort of thing goes on, how can honest and
responsible
companies have confidence in the Department of
Transport, or any other
Department for that matter? How can anybody have
confidence in the
integrity of government in Papua New Guinea? The
selective picking-
and-choosing of companies to submit proposals must be
avoided at all
costs, since it is unfair and not in the best interests
of the State and such
practices breed corruption.[6.17] LITTLE RESPONSE TO THE REQUEST FOR PROPOSALS
The Department of Transport’s attempt, in July 1990, to
get the “selected”
companies to submit proposals, was so badly
implemented, that hardly
any of those companies responded. This meant that in
1991, the -
Page 57 of 397
-
shortlisting process had to begin again.
But as we show in Chapter 9, the shortlisting process
in 1991 was also
carried out in an arbitrary, unfair and unsatisfactory
way.* * * * * * * * * *
Chapter 6
49
SIGNIFICANT INTERDEPARTMENTAL MEETING:
31 JULY 19907.1] ORIGINAL PURPOSE OF MEETING
An interdepartmental meeting, involving representatives of
the Departments
of Transport, Works, Finance and Planning and Attorney-
General, was held
on 31 July 1990. It was jointly chaired by the Secretary
for Transport, Mr
Amini, and the Secretary for Works, Mr Temu.It was originally intended that the meeting would consider
proposals invited
by the Department of Transport’s letters of 17-20 July
1990. [See the
minute from the Director of the Department of Transport’s
Policy
Secretariat, Mr Hitolo, to Mr Amini dated 27 July 1990 at
paragraph 2 and
the handwritten notes which refer to the “selection
criteria”: EXHIBIT 24.] -
Page 58 of 397
-
However, because the letters were sent late, the companies
could not
respond in time. Rather than being a forum for assessment
of proposals
the meeting therefore focused on other important issues
concerning the
project.2] ISSUES DISCUSSED AT THE MEETING OF 31 JULY 1990
The minutes of the meeting record discussion of the
following issues:Chapter 7
50
The name of the project – the Secretary for Transport
favoured the name “Spring Garden Road (Burns Peak) Link”.Funding of the project – Mr Hitolo advised that the World
Bank had been approached.The Port Moresby Roads Needs Study – the First Assistant
Secretary of the Department of Transport’s Planning and
Research Division, Mr Parakei, advised that the Burns Peak
project was part of the Study.Engineering details – the Department of Works’ Principal
Engineer (Roads), Mr Newberry, addressed the tunnel/cut
option, particularly the problems associated with disposal of
the cut.Landowner issues – Mr Hitolo advised that preliminary
discussions had been held with landowners, some of whom
were claiming lump sum payments prior to commencement
of the project.Scope of the project – some consideration was given to
upgrading other sections of the Spring Garden Road network,
particularly Wards Road to Waigani Drive. -
Page 59 of 397
-
Target date for completion – it was generally agreed the
project could not be completed by the original target of
September 1991, coinciding with the South Pacific Games.
[EXHIBIT 33]Chapter 7
51
[7.3] FUTURE ACTION
[7.3] FUTURE ACTIONAs to the next action to be taken, two things were decided:
1. The National Executive Council was to be informed that the
project
could not be completed for the South Pacific Games.2. Further geological investigations would have to be
undertaken, so
that a decision could be made on the tunnel/cut option.
[EXHIBIT
33, paragraph 5 and EXHIBIT 51, page 4, para 3][7.4] PROPOSALS WERE NOT CONSIDERED AT MEETING ON 31 JULY 1990
[7.4] PROPOSALS WERE NOT CONSIDERED AT MEETING ON 31 JULY 1990
MAIAITLOILEBIEIEIIING
We note there is a reference to this meeting of 31 July 1990
in the Policy Submission presented to the National Executive
Council in February 1992,
Submission presented to the National Executive Council in
February 1992,
which led to the decision to award the project to Kinhill
Kramer Pty Ltd
(see Chapter 21).It was suggested in the Policy Submission that the various
expressions of interest and proposals had been presented at
the meeting of 31 July 1990.
interest and proposals had been presented at the meeting of 31
July 1990.However, it is quite dear, from the minutes of the meeting and
other
documents considered by the Ombudsman Commission, that the
proposals were Dot presented at that meeting. There were no
proposals,
as at 31 July 1990, that could be considered. -
Page 60 of 397
-
Moreover there was never, in the life of the Spring Garden
Road/Poreporena Freeway project, any interdepartmental meeting
at which
all the proposals were considered. Neither was there a meeting
within theChapter 7
52
Department of Transport at which all the proposals were
considered. There
was not even a meeting at which all the expressions of
interest were
considered.The Department of Transport’s failure to methodically consider
all options
available to the Government was one of the worst aspects of
the decision-
making process that led to the National Executive Council
decision in
favour of IGnhill Kramer Pty Ltd in February 1992.It was very unfair of the Department of Transport to
arbitrarily reject
expressions of interest from other companies that had put
considerable
time and effort into responding to the June 1990
advertisement.[7.51 SECRETARY FOR TRANSPORT CLAIMS THAT ALL OPTIONS WERE
CONSIDEREDWhen we put these allegations to the Secretary for Transport,
he claimed
that all options were considered:“As I have said, all options were considered, including the
Barclay proposals.
Mr Lohia Hitolo with his immense breath of experience and
qualifications, did
the assessment. Although he did not use the preferred
approach, nevertheless,
the approach he used has been used quite often by the -
Page 61 of 397
-
Department of Works
Design Branch. In addition, an NEC sub-committee reviewed
his assessment
This is not defective administration.”[EXHIBIT 254, page 4][7.6] MR HITOLO CONCEDES THAT SOME COMPANIES WERE REJECTED ON
THE BASIS OF THEIR EXPRESSION OF INTERESTIn contrast to Mr Amini’s response, the former head of the
Department of
Transport Policy Secretariat, Mr Hitolo, conceded some
companies had ngt
been seriously considered. The reason, he said, was that their
expressionsChapter 7
53
of interest did not state that they were willing to
finance the project.
[EXHIBIT 265, page 3, para 5].7] FAILURE TO CONSIDER ALL OPTIONS
In our view, Mr Hitolo’s response is testimony to the
lack of effective
communication which pervaded the whole project.As we pointed out in Chapter 5, the June 1990
advertisement did rat state
that the successful contractor had to itself finance the
project. Nor had
such a requirement been imposed by the National Executive
Council.It was therefore unfair and wrong of the Department of
Transport to
summarily reject companies, simply because they had not
indicated an
ability to provide finance.In the opinion of the Ombudsman Commission, by failing to
convene a
meeting at which all expressions of interest could be
formally considered,
the Department of Transport failed to consider all of the -
Page 62 of 397
-
options available
to the Government. This was wrong and defective
administration.* * * * * * * * * *
Chapter 7
54
8. PROGRESS DURING SECOND HALF OF 1990
[8.1] A PERIOD OF INACTION 1
The period between the meeting of 31 July 1990 and the
beginning of
1991 was significant in three respects:1. There was little action taken to follow-up the
expressions of
interest.2. The geotechnical survey was initiated by the
Department of
Works, but not completed.3. A draft information paper was prepared for the
National
Executive Council, but not presented.LACK OF ACTION FOLLOWING INVITATION FOR EXPRESSIONS OF INTEREST
[8.2] DEPARTMENT OF WORKS GUILTY OF DEFECTIVE ADMINISTRATION
Other than the unsuccessful attempt by the Department of
Transport in
July 1990 to obtain firm proposals from some companies, no
further action -
Page 63 of 397
-
was taken by either the Department of Transport or the
Department of
Works during the second half of 1990 to follow-up the
expressions of
interest.Chapter 8
55
It is apparent that Mr Newberry, of the Department of Works,
drafted a
letter of acknowledgment around the end of October 1990, which
was
intended to be sent to all companies which had expressed
interest.
[EXHIBIT 50]. But this was not done. The letter was drafted
very late and
shows incompetence by the Department of Works. In a minute to
the
Secretary of the Department of Works, Mr Temu, on 11 January
1991, Mr
Newberry conceded “an acknowledgement should have been sent’,
and
added “… but I wished to advise them what was happening or
going to
happen. There was/is considerable confusion over the
acceptability of a
tunnel proposal.” [EXHIBIT 51, page 5, paragraph 3]In our view, this was not an acceptable reason for not sending
the
acknowledgments. A number of companies had invested time and
expense in formulating their expressions of interest and the
very least they deserved was an acknowledgment. Mr Newberry’s
draft letter of 31
deserved was an acknowledgment. Mr Newberry’s draft letter of
31
October 1990 correctly and succinctly stated the position as
at that date
and we can see no good reason for it not being dispatched,
although it
was very late.Since the Department of Works was at that time co-ordinating
the
expressions of interest, it should be held responsible for
this bad
administrative error.THE GEOTECHNICAL INVESTIGATION
THE GEOTECHNICAL INVESTIGATION -
Page 64 of 397
-
[8.3] PROS AND CONS OF TUNNEL AND CUT
[8.3] PROS AND CONS OF TUNNEL AND CUTThe most important outcome of the interdepartmental meeting of
31 July
1990 had been the decision to conduct a comprehensive
geotechnical
investigation of the Burns Peak Saddle.Chapter 8
56
The rationale for this decision was explained in a minute
from Mr Newberry
to the Secretary for Works on 11 January 1991:‘Confusion was increased by the letter/fax sent by DOT to
some of the
registrants on 20 July. The DOW/DOT meeting on 31 July did
clarify some of
the issues.
Since that time Works has proceeded on the basis that no
requests can be made
for detailed proposals until the additional geotechnical
investigation provides
data sufficient to allow a developer to make a reasoned
choice between a tunnel
and a cut.The concept of the project if a tunnel is chosen is
entirely different from that
if a cut is to be constructed. A tunnel provides very
little material for filling
or for use in other parts of the construction. If any
reclamation is to be carried
out it would have to be from imported materiaL The road
pavement and fill
materials would also have to be imported. The tunnel also
has a continuing
high operation and maintenance cost. The tunnel option
also carries a higher
risk of damage, closure or operational loss as a result of
an accident or
vandalism particularly with only a single two lane tunnel
for the initial period.
The presently proposed tunnel cross section may be
inadequate for safe use by -
Page 65 of 397
-
trucks carrying containers. Trucks with dangerous
materials would not be
allowed to use the tunnel but would have to use an
alternate route.It has been claimed that the tunnel would allow a grade of
only 3% for the
road connection. This is possible but would require a
tunnel of much greater
length and cost than that presently proposed. The present
proposal has grades
of over 8% on the western approach road.The cut provides considerable, possibly excessive,
material for use in the
construction of the project and connecting roads
embankments and pavements
and also for port and other reclamation. The cut would
provide an immediate
four lane road connection. The provision of four-lanes
reduces the risk of
accident, damage and operational loss. However the risk of
loss from collapse
of part of the cut wall still exists with the level of
risk increasing as the cut
slopes are steepened and the volume and cost of the cut
decrease. There is
however increased opportunity for early financial return
from port and harbour
reclamation works which may reduce the financial risks in
the project.The developer has a difficult choice to make between the
tunnel and cut options
and the government also has to make an assessment of the
risks it is prepared
to take and the charges (eg. toll) it is prepared to allow
the developer to make
for provision of facilities.’ (Emphasis added) [EXHIBIT
511[8.4] WHY WAS A FURTHER GEOTECHNICAL INVESTIGATION NECESSARY?
A preliminary study in 1977 by consultants Dames and Moore
had found
it was geologically feasible to build a tunnel, but the
Department of Works -
Page 66 of 397
-
Chapter 8
57
obviously felt that a more detailed investigation should be
carried out. This
point was explained in a press statement drafted by Mr
Newberry on 18
January 1991 (which apparently was not released):The last time a detailed investigation was made of the
underground conditions
along the Spring Garden Road Link from Hohola to Konedobu
was in 1977.
Then holes were drilled in the rock and samples of the
rock taken for
examination. These holes were generally along the line of
a proposed deep cut
It was then decided that the sides of the cut may fall
down unless flatter side slopes were used so a tunnel was
proposed. However tunnels are expensive as
slopes were used so a tunnel was proposed. However tunnels
are expensive as
the rock in the tunnel roof must be supported so that it
does not fall into the tunnel Ventilation also becomes
important as air can only enter and leave at
tunnel Ventilation also becomes important as air can only
enter and leave at
the ends of the tunnel and fans may be necessary.Since 1977 there have been other geological investigations
around Port Moresby
and it is now believed that the underground rock
conditions may be more
complicated than was thought in 1977. It is now considered
too risky to decide
on building either a tunnel or a rock cut without further
investigation of the
underground conditions. This is particularly important
since the estimated cost of the rock cut for a 4-lane mad
is about 1(20 million, 2-lane tunnel would cost about 1(20
million and a 4-lane tunnel would cost about IC40 million with about
another KS million for improvements to Champion Parade, Wards Road,
Waigani
of the rock cut for a 4-lane mad is about 1(20 million, 2-
lane tunnel would cost about 1(20 million and a 4-lane
tunnel would cost about IC40 million with about another KS
million for improvements to Champion Parade, Wards Road, Waigani
about 1(20 million and a 4-lane tunnel would cost about
IC40 million with about another KS million for
improvements to Champion Parade, Wards Road, Waigani
another KS million for improvements to Champion Parade, -
Page 67 of 397
-
Wards Road, Waigani
Drive and the existing sections of Spring Garden
Road.’ [EXHIBIT 52A][8.5] CO-ORDIANATION OF THE GEOTECHNICAL INVESTIGATION
[8.5] CO-ORDIANATION OF THE GEOTECHNICAL INVESTIGATIONThe geotechnical investigation was co-ordinated by Mr
Newberry and also
involved the Senior Engineering Geologist from the Geological
Survey of
PNG in the Department of Minerals and Energy. It was decided
the project
would be offered to a private consultant, so the first step
was to formulate
terms of reference for the project. This was done during
August 1990 by
Mr Newberry. [EXHIBIT 51, page 4][8.6] THE PROCEDURE USED TO SELECT THE CONTRACTOR
[8.6] THE PROCEDURE USED TO SELECT THE CONTRACTORTerms of Reference
The terms of reference was sent to the Department of
Transport for
ratification during August 1990. The Secretary for Transport
replied thatChapter 8
58
his Department agreed with the course of action proposed by the
Department of Works.
[EXHIBIT 42A]Invitations, accompanied by a document entitled “Sub Surface
Exploration
and Assessment for Spring Garden Road Link between Hohola and
Konedobu Via Burns Peak Saddle: Terms of Reference for Consultants
Brief’, were sent in September 1990 to the following companies: -
Page 68 of 397
-
Engineering Geology Ltd, of Lae.
Coffey Partners International Pty Ltd, of Australia.
Cardno & Davies Pty Ltd, of Port Moresby.
Kinhill Kramer Pty Ltd, of Port Moresby
Maunsell Consultants PNG Pty Ltd, of Port Moresby.
Ove Arup & Partners Pacific Pty Ltd, of Port Moresby.
Snowy Mountains Engineering Corporation, of Australia.
Hollingsworth, Dames & Moore (PNG) Pty Ltd, of Port
Moresby. [EXHIBITS 44A, 44B1Failure to publicly invite tenders
We note that there was no public advertisement inviting tenders for
the
geotechnical project. Nor was a “certificate of inexpediency” –
which could
have authorised the selective tendering procedure – issued under
SectionChapter 8
59
40(3)(b) of the Public Finances (Management) Act. This meant that,
though the matter was ultimately referred to a Supply and Tenders
Board,
there had been a breach of the Public Finances (Management) Act.Section 40(1) of the Act requires that tenders be publicly invited
for the
supply of works and services expected to cost more than the
prescribed
amount (which at the relevant time was K5,000.00). The public tender
procedures of the Public Finances (Management) Act are discussed in
detail in Chapter 35 of this report.We are satisfied that none of the exceptions to the general rule
imposed
by Section 40(1) applied in the case of the geotechnical project.The Department of Works therefore acted wrongly, by engaging in the
process of selective tendering without obtaining a certificate of
inexpediency in accordance with the Public Finances (Management)
Act.Evaluation of proposals
-
Page 69 of 397
-
The closing date for submission of proposals was 25 October 1990
and,
according to Mr Newberry’s minute to the Secretary for Works of
January
1991, this was when the task of evaluating the proposals began.
[EXHIBIT
51, page 4] However, because of ambiguity in the wording of the
terms
of reference, due to the incompetence of the Department of Works, it
was
necessary to obtain supplementary proposals from a number of
respondents. This delayed the selection process by at least a month.
[EXHIBITS 48A, 50A, 50B]Submission to Design Priorities Committee and Tender Board
On 5 December 1990, Mr Newberry presented a detailed submission to
the Design Priorities Committee and Tender Board, recommending theChapter 8
60
contract for the geotechnical investigation be awarded to
Coffey Partners
International of Sydney, Australia, at a cost of K184,000.00.
[EXHIBIT 500].
The recommendation was endorsed by the Board at its meeting on
11
December 1990. [EXHIBIT 50F] Coffey Partners International was
subsequently advised it had won the contract and arrangements
were
made to commence the seismic field work during January 1991
[EXHIBITS
50G, 51A][8-7] GEOTECHNICAL INVESTIGATION DURING JANUARY – MAY 1991
The investigation took approximately four months to complete.
A “Burns
Peak Geotechnical Steering Committee” was established to
monitor the
project and progress reports were provided during the course
of the
investigation [EXHIBITS 55A, 64A, 66A, 79A, 80A, 84A]. The
final report
was presented to the Department of Works at the end of May
1991.
[EXHIBITS 87A, 87B]It was recommended that “the deep open cut option through
Burns Peak
Saddle will involve greater financial uncertainty than the -
Page 70 of 397
-
tunnelling option”.
[EXHIBIT 87B, page 29, paragraph 8]The time it took to organise the geotechnical investigation
was a cause of
frustration to some people, including the Minister for
Transport, Mr Temo.
On the EM TV news bulletin of 8 January 1991 he was reported
to be
highly critical of the Department of Works and apparently
blamed the
Department for delaying the project. This prompted a detailed
response
from the Secretary for Works, Mr Temu, which was forwarded to
the
Secretary for Transport in a letter dated 11 January 1991
[EXHIBIT 52]Chapter 8
61
.8] THE GEOTECHNICAL INVESTIGATION CAUSED A DELAY OF NINE
MONTHSIn retrospect, it can be seen that the decision to undertake the
geotechnical investigation delayed the planned commencement of
the
project by about nine months. After the interdepartmental
meeting on 31
July 1990:It took five weeks for the terms of reference for the
consultancy brief to be finalised and invitations for
proposals
to be dispatched.The consultants were given six weeks to lodge their
proposals.Six weeks were spent on clarifying and evaluating the
proposals.The recommendation favouring Coffey Partners International
was before the Design Priorities Committee and Tenders
Board for about a week before a decision was made and
announced.It took Coffey Partners International about five weeks to
mobilise its equipment and personnel and commence the -
Page 71 of 397
-
seismic field work.
The actual investigation, including laboratory testing of
core
samples, took four months to complete (from late January
1991 to late May 1991).Chapter 8
11
62
[8.9] FINDINGS IN RELATION TO THE GEOTECHNICAL INVESTIGATION
1. The need for the investigation
We do not question the need for the investigation.
Irrespective of whether
a tunnel or a cut is built through Burns Peak, safety
considerations
obviously must be paramount.2. IMaltinSIII .cgAngthatthQinvgggigatcKLI8MINKMEM:Y.
investigation
However, we are critical of the Department of Works for the
delay in
making the decision that a geotechnical investigation was
necessary.The decision to go ahead with the Spring Garden Road project
was
conveyed to the Department of Works in late January 1990. The
Department of Works, amongst others, was directed to
“formulate detailed
plans for the construction of the Burns Peak Road”. [EXHIBIT
61■] We
have already noted the impreciseness of that decision and
criticised the
National Executive Council for not being more explicit in its
requirements.
However that does not excuse the Department of Works for its
failure to
expeditiously implement the decision.Nor is it an excuse to say that the Department of Works was
waiting for
an indication from the Department of Transport as to the route
of the road.
The geotechnical investigation was a matter that was clearly
within the
jurisdiction of the Department of Works. -
Page 72 of 397
-
When we raised these matters in our preliminary report, the
Secretary for
Works responded in the following terms:Chapter 8
63
‘What caused the delay in deciding to perform the Geotechnical
Investigation?
Initially it was not projected to perform a further Geotechnical
Investigation.
However, Department of Transport wanted to jump in and build the
project
without any significant planning, while Works was pushing for as
much
planning and advise from specialists as possible. Several times
Mr Newberry
(then Principal Engineer Roads) met with the Geological Survey
Section of
DME to discuss the project. Of specific concern was the “ICold
Fault’ which
was known to run right through the ‘saddle’. It appears that the
requirement
for further investigation was not seriously considered until
advised accordingly
by a Senior Engineering Geologist at an inter-departmental
working group on
19 July 1990 [see Exhibit 51]—This seems to be the conception of
the requirement
for further geotechnical investigation to give a degree of
confidence to any
decision regarding ‘Open Cut” or ‘Tunnel”‘ [OCKIBIT 263, page 1]Having considered this response, the Ombudsman Commission retains
the
view that the Department of Works should have, by itself, raised the
issue
of the need for a geotechnical investigation sooner than it did,
since it is
the appropriate Department responsible for such matters in the
interests
of the State.The excavation of the Burns Peak Saddle was clearly going to be a
complex engineering task. It was up to the Department of Works to -
Page 73 of 397
-
find
out whether any further geotechnical investigation was necessary as
soon
as possible and take follow-up action. The need for this should have
been
raised at least as early as the interdepartmental meeting on 22 May
1990
(see Chapter 4).
NThe Ombudsman Commission considers that the six month delay in
making the decision to undertake the geotechnical investigation was
unjustifiable. Furthermore, in the absence of a certificate of
inexpediency,
invitations to submit tenders for this work should have been
publicly
advertised – not selectively issued.Once the decision was made, on 31 July 1990, to undertake the
investigation, there were some further delays but – with the
exception of
the failure to publicly invite tenders – the Department of Works
handled the
matter well from then on.Chapter 8
64
We note that various proposals were carefully and
methodically evaluated.
The proposal made by Coffey Partners International was
detailed and well
presented [EXHIBIT 48A]. There was a sharp contrast between
the quality
of that document and some of the atrocious documents [eg
EXHIBIT 115]
that were later to be paraded as serious proposals for
construction of the
freeway.Indeed, the professional way in which the geotechnical
investigation
proposals were evaluated was in stark contrast to the events
which later
led to the execution of the contract for the design, finance
and
construction of the Poreporena Freeway. -
Page 74 of 397
-
THE MINISTER FOR TRANSPORTS DRAFT POLICY SUBMISSION OF AUGUST 1990
[8.10] DECISION TO ADVISE NATIONAL EXECUTIVE COUNCIL OF PROGRESS
Besides the decision to undertake the geotechnical
investigation, the other
important outcome of the interdepartmental meeting of 31 July
1990 was
the decision to advise the National Executive Council of
progress on the
project, in particular to clarify the fact that it would be
impossible to finish
the Burns Peak link in time for the South Pacific Games in
September
1991. To this end, a document headed “Policy Submission For
Members
of the National Executive Council” was drafted within the
Department of
Transport in August 1990. [EXHIBIT 36]Chapter 8
65
18.11] CONTENT OF THE DRAFT POLICY SUBMISSION
This document gave an update of the status of the project
as at August1990, and referred to the decision to undertake a further
geotechnicalinvestigation of the Burns Peak Saddle. The bulk of the
document,however, was devoted to explaining the need for public
participation in theplanning process and the preparation of an environmental
impact -
Page 75 of 397
-
statement.
The document concluded as follows:
It is recommended that the Spring Garden Road
project scope includes
the commencement point (Cuthbertson and
Stanley Esp. Junction) at the
Port Moresby main overseas wharf and
termination at the Jackson’s
AirPort-2. It is recommended that an Environmental
Impact Statement be made
of the whole route using the N.S.W. manuals
including soil erosion
guide for the assessment.3. It is recommended that the upgrading to the
Waigani Road and any
other spot improvements along the main
arterial network be done as
a matter of urgency in preparation for the
South Pacific Games in 1991.4. It is recommended that the savings be
immediately identified in the
current capital works and studies votes in
order to implement these
projects.5. It is recommended that the Council note that
advice of the experts for
delay in the opening of the Burns Peak link
and approve the new scope
to be implemented in three stages.6. It is recommended that this project be
developed through involvement
of the private sector and the landowners
using toll for financing.” -
Page 76 of 397
-
.12] WIDE CIRCULATION OF THE DRAFT POLICY SUBMISSION
This document was widely circulated and comments were
received froma number of Government departments. [EXHIBITS 39, 40, 41,
42, 43, 44,48]
Chapter 8
66
Some departments expressed serious reservations about its
recommendations. The Secretary for Finance, Mr Morea Vele,
for example,
was particularly concerned about the economic viability and
the security
risk of the tunnel/toll road proposal. [EXHIBIT 42]The Secretary of the Department of Environment and
Conservation, Mr
Barney Rongap, pointed out that Papua New Guinea had its own
environmental impact legislation – the Environmental Planning
Act (Chapter
No. 370) – and therefore it was inappropriate to rely on the
New South
Wales model for this purpose.The draft policy submission was also sharply criticised
within the
Department of Transport itself. [EXHIBITS 46, 47] The First
Assistant
Secretary (Land Transport Division), Mr M Ume, went so far as
to say:‘It is very difficult to follow what the Submission is
about and perhaps if it is
on Burns Peak then more discussion should be on Burns Peak
Road itself.* -
Page 77 of 397
-
[8.13] RE-DRAFTING OF THE JULY 1990 DOCUMENT
In January 1991, after receiving the views and comments from
various
departments, the Department of Transport redrafted the
National Executive
Council submission. This time, the document was entitled
“Information
Paper For Members of the NEC: Burns Peak Link of Spring
Garden Road”.
[EXHIBIT 54]This document also emphasised the need for an environmental
impact
statement. But it was different to the earlier document in a
significant
respect: whereas the July 1990 document contained very little
discussion
of the method of financing the project, the January 1991
document was
dogmatic in its assertion that “this project will be
constructed under Build,
Operate and Take-over (BOT) system”. [EXHIBIT 54, page 5,
para 2.12]Chapter 8
67
[8.14] POUCY SUBMISSION AND INFORMATION PAPER NOT PRESENTED TO
NATIONAL EXECUTIVE COUNCILThe Ombudsman Commission was surprised to discover that,
despite the
time and effort put into the drafting and redrafting of the
National Executive
Council submission and the wide circulation of the first
draft, neither the
first nor the second draft submission was actually filed with
the National
Executive Council.That is, despite the fact that draft submissions had been
circulated for
more than six months, the National Executive Council was not
fully
informed – as it should have been – of progress on the
project and the
reasons for delay in its commencement. -
Page 78 of 397
-
We note that the Department of Transport complied with the
normal
administrative requirement to give status reports to the
Secretary of the
Department of Prime Minister and National Executive Council.
[EXHIBITS 6C, 25A, 63A, 77A, 87C & 124A]However, the Ombudsman Commission considers that, because of
the
magnitude of the project, the Minister for Transport had an
administrative
obligation to ensure the National Executive Council was fully
and formally
advised of the important developments that were taking place.
In our view,
this duty was not discharged.[8.15] MINISTER FOR TRANSPORT FAILED TO PROPERLY ADVISE NATIONAL,
EXECUTIVE COUNCIL OF PROGRESSThere were some aspects of the August 1990 document which
should
have been brought to the attention of the National Executive
Council as aChapter 8
68
matter of priority, particularly the recommendation that the
scope of the
project be expanded. But this important policy matter was
very poorly
documented and was eventually put before the National
Executive Council,
in February 1992, without explanation or justification. The
scope of the
project, being essentially important, should have been
explained and
defined in detail for the benefit of the members of the
National Executive
Council.The August 1990 document was widely circulated for views and
comments.
The failure to present it reveals a lack of regard for proper
administrative
procedures by the Minister for Transport, Mr Temo. He did not
appreciate
the importance of keeping his colleagues, at the National
Executive Council
level, fully informed of progress of the project and
explaining significant -
Page 79 of 397
-
changes in policy.
[8.16] THE NEED TO KEEP THE NATIONAL EXECUT1VE_COUNCIL FULLY
INFORMEDThere is a lesson to be learned here by all departments and
ministries: if
delays are experienced in the implementation of Government
policies, the
National Executive Council must be advised of the delay and
the reasons
for it.Often there are justifiable reasons for projects not being
implemented as
soon as originally planned. But if the National Executive
Council is not
advised why there has been a delay, it will naturally be
assumed that there
are no good reasons for further delay. The National Executive
Council will
become frustrated and impatient and the environment will be
ripe for the
making of rash and ill-considered decisions in the end.Chapter 8
69
All of these things happened in the case of the Spring Garden
Road/Poreporena Freeway project.3.17] SCOPE OF THE PROJECT
The first recommendation of the August 1990 “Policy
Submission” was that
the scope of the project should be expanded, so as to create a
direct link,
via Spring Garden Road, between downtown Port Moresby and
Jacksons
Airport. [EXHIBIT 36, page 5, para 11.1]However, there was no discussion or analysis – in fact, hardly
a mention –
of this crucial policy decision in the text of the Submission.As we emphasised in Chapter 5, the Ombudsman Commission found
ft
extraordinary that in the course of this investigation we were
not able to -
Page 80 of 397
-
pinpoint when the decision was made to expand the scope of the
project,
from the original proposal to link the two unconnected
sections of Spring
Garden Road between Konedobu and Hohola.The way in which this recommendation was added to the document
–
giving the appearance that it was an afterthought – simply
adds to the
mystery surrounding that decision.18] THE BUILD-OPERATE-TRANSFER CONCEPT
Another feature of the January 1991 draft “Information Paper’
is that it is
the first Department of Transport document which referred to
the Build-
Operate-Transfer method of financing the project.Chapter 8
70
However, just as the August 1990 document failed to explain
or discuss
the pros and cons of expanding the scope of the project, the
January
1991 document failed to weigh the pros and cons of different
methods of
financing the project. [EXHIBIT 54, page 5, paragraphs 2.12 –
2.13]These failures clearly indicate lack of consultation
resulting in the poor
drafting of the documents for the National Executive Council.[8.19] DEFICIENT POUCY MAKING BY THE DEPARTMENT AND MINISTRY OF
TRANSPORTThe fact that both the August 1990 Policy Submission and the
1991
Information Paper documents were only in draft form and never
actually
filed with the National Executive Council means that the
Ombudsman
Commission cannot be overly critical of their contents.But, in the absence of evidence to the contrary, these
documents support -
Page 81 of 397
-
our conclusion that important policy decisions such as the
length of the
freeway and the method of financing were being made by the
Department
and Ministry of Transport without proper analysis or
documentation.SUMMARY OF DEVELOPMENTS DURING 1990
[8.20] PROGRESS DURING 1990
Progress on the project during 1990 can be summarised as
follows:Chapter 8
71
In late January 1990 the National Executive Council directed
the Department of Transport, the Department of Works and
the Department of Finance & Planning to formulate detailed
plans for the project.Nothing was done until 22 May 1990, when the Minister for
Transport chaired an interdepartmental meeting and directed
that design of the project be finalised within six months and
expressions of interest be publicly invited.An advertisement inviting expressions of interest was
published in June 1990 by the Department of Works.Around 17 – 20 July 1990, the Department of Transport invited
a select group of companies to lodge proposals for the
project, but this exercise was incompetently handled, hence
there was little response.On 31 July 1990, it was decided that the Department of
Works would arrange a further geotechnical investigation of
the Burns Peak Saddle.A draft policy submission, intended to provide an update on
progress, was circulated for comment during August and
September 1990. The submission was subsequently revised
but never presented to the National Executive Council.The first version of the submission proposed that the scope
of the project be considerably expanded, but there was no
documented discussion or analysis of this proposal. -
Page 82 of 397
-
Chapter 8
72
On 11 December 1990, the contract for the
geotechnical
investigation was awarded to Coffey
Partners International Pty
Ltd of Australia after invitations were
sent to selected
companies by the Department of Works.[8.21] STATUS OF THE SPRING GARDEN ROAD PROJECT AT THE END OF
1990By the end of 1990:
The National Executive Council had not
been fully and
formally advised of the delay in
commencement of the project
or the apparent proposal to expand its
scope.The geotechnical investigation had not
begun, so no decision
had been made on the tunnel/cut option.No decision had been made on the exact
route or length of
the road.No decision had been made on the method
of financing the
project.* * * * * * * * * *
Chapter 8
73
9. PREPARATION OF SHORTLIST: FEBRUARY 1991
-
Page 83 of 397
-
9. PREPARATION OF SHORTLIST: FEBRUARY 1991
[9.1] FIFTEEN GROUPS HAD EXPRESSED INTEREST
[9.1] FIFTEEN GROUPS HAD EXPRESSED INTERESTThe advertisements in June 1990 inviting expressions of
interest in the
“Burns Peak/Spring Garden Road Link” had attracted fifteen
interested
parties. In July 1990, the Department of Transport made an
abortive
attempt to get some of them to submit firm proposals.It was later decided that the Department of Works would
organise a
detailed geotechnical investigation of Burns Peak, so a firm
decision could
be made on the tunnel/cut option. This investigation began in
January
1991 and continued until May 1991. While that investigation
was still in
progress, a shortlist of prospective developers was prepared.In this chapter we record our findings as to the preparation
of the shortlist.
.MINISTER FOR TRANSPORT PREPARES SHORTLIST
MINISTER FOR TRANSPORT PREPARES SHORTLIST[9.2] WHEN WAS THE SHORTLIST PREPARED AND WHO PREPARED IT?
[9.2] WHEN WAS THE SHORTLIST PREPARED AND WHO PREPARED IT?The Ombudsman Commission has concluded that the shortlist was
prepared in February 1991 by the Minister for Transport, Mr
Anthony
Temo.Chapter 9
74
On 27 February 1991, Mr Temo wrote to the Secretary of the
Department
of Transport in the following terms: -
Page 84 of 397
-
“My Dear Secretary
A total of 15 (Fifteen) companies have shown or
registered expressions
of interest to design and construct the Burns Peak
Road..This is under Turnkey arrangement meaning financing
will be done
by them.The following Companies have been selected for short
list-1. Outlet Year Limited
2. Sietco
3. Barclay Bros and Maunsell Joint
4. Curtain Bros
5. L.K.N. Construction
6. Kumagai Gumi
7. Sabina Group Consortium
Please inform them respectively by way of fax and
organise a bid walk
in 3 weeks from 27/2/91.” [EXHIBIT 631[9.3] A LATE ADDITION TO THE SHORTLIST
On 28 March 1991, the Minister for Transport wrote another
letter to the
Secretary for Transport:‘My dear Secretary
I refer to my letter dated 27 February, 1991 in which I
short listed a number of
companies for the Burns Peak Project. -
Page 85 of 397
-
Chapter 9
75
I now wish to include the following on the short list-
Tasman Pacific International
Please inform the Company accordingly” [F3CIBB1T 69]
[9.4] THE MINISTER PREPARED THE SHORTLIST WITHOUT ADVICE OR
CONSULTATIONIn his response to our preliminary report Mr Temo
emphatically denied
that he had prepared the shortlist. He said the letter to the
Secretary for
Transport of 27 February 1991 was simply a list of companies
which had
sent written expressions of interest to his office. He said
his staff in the
Ministry did not understand the term “shortlist”:‘The various expressions of interest in the Burns Peak
Road project by different
companies was sent by way of letter or verbal to 3
different place:(a) Department of Works
(b) Department of Transport
(c) Chairman of Ministerial Committee and Minister for
Transport.Some companies about 15 contacted my office. About half of
them verbally and
the other half by way of letter or fax.It was the Department of Transport in consultation with
Department of Works
that prepared the short list not me or my office. -
Page 86 of 397
-
Department of Works and the Department of Transport did
their short list and
Chairman of the Ministerial Committee did their own short
list”
[EXHIBIT 257, page 1]With due respect to Mr Temo, the Ombudsman Commission cannot
accept
what he says about the preparation of the shortlist. The
terms of his letter
to the Secretary for Transport on 27 February 1991 were quite
clear: he
advised that seven companies “have been selected for
shortlist”. There is
no evidence the companies on the Minister’s list had written
directly to him,
rather than the Department of Transport.Chapter 9
76
The Ombudsman Commission is satisfied that neither the
Department of
Transport nor the Department of Works had any involvement in
the
preparation of the shortlist. The Minister prepared the
shortlist without
consulting either Department.[a5] MINISTERS SHOULD NOT BE INVOLVED IN IMPLEMENTATION MATTERS
The Minister for Transport’s preparation of the shortlist in
February 1991
was defective administration in a number of respects.First, there was no need for a shortlist to be prepared. The
interested
parties had only submitted expressions of interest in the
project and had
not been given the opportunity to submit firm proposals, so
preparation
of a shortlist was premature.Even if it had been an appropriate time to prepare a
shortlist, this job
should have been done by officers of the Department of -
Page 87 of 397
-
Transport and/or
the Department of Works. It is not the function of a Minister
to prepare a
shortlist for a public works project.Too often in Papua New Guinea, Ministers make unilateral
decisions without
calling on their qualified and experienced Departmental
officers for advice.
This is very bad. If Ministers cut themselves off from their
Departments –
by always giving directions, rather than asking for advice –
it is inevitable
they won’t always have the best information before them on
which to make
decisions.It was very naive of the Minister for Transport to believe he
had the
necessary technical knowledge to prepare a shortlist of
developers without
the advice of his Department.Chapter 9
77 O
Whenever a Minister makes an important decision in this way,
it inevitably
leads to suspicion about his motives. People start to ask
questions. Why
were some companies selected for the shortlist and others left
out? Did
some companies make the shortlist because the people running
them
were friends or wantoks of the Minister? Was anyone bribed? Et
cetera.The only way the People can have confidence in their
Government
departments and Ministers is if normal, established procedures
are
followed.The decision-making process must be above suspicion.
[9.6] SOME COMPANIES WERE SHORTLISTED WITHOUT JUSTIFICATION
The Ombudsman Commission makes the following findings in
relation to
the eight groups shortlisted by the Minister for Transport: -
Page 88 of 397
-
1. Outlet Year Ltd
This Hong Kong-based company had not lodged an expression of
interest.
It first became interested in the project in February 1991,
when the Minister
for Transport travelled to Taiwan and Hong Kong and was
entertained by
the company’s officers and its associates (see Chapter 12).As a result of the Minister’s visit, the company’s Managing
Director, Mr
Leung Keung, wrote a letter dated 12 February 1991 to Prime
Minister
Namaliu. Outlet Year Ltd offered to “design and build Southern
Highlands
Kikori Road and Burns Peak Road in Port Moresby’ and “invest
up to US
dollars 5 billion in Papua New Guinea.” [EXHIBIT 57]Chapter 9
78
On 13 February 1991, Outlet Year Ltd wrote similar letters addressed
to:
“Hon. Anthony Temo, Minister for Transport or Hon. Ted Diro, Deputy
Prime Minister, Acting Transport Minister”. [EXHIBITS 59 & 60]Soon after that, on 19 February 1992, Mr Diro wrote to the Secretary
for
Transport, advising that he had received advice from Mr Temo that
Outlet
Year Ltd be “included in the pre-qualification for all tenders in
Erave-Kikori
and Burns Peak roads in Port Moresby”. Mr Diro directed the
Secretary
to take “necessary actions” in relation to the “pre-qualification”
of Outlet
Year Ltd. [EXHIBIT 61]The Ombudsman Commission was to discover in the course of this
investigation that the Minister for Transport’s trip to Hong Kong,
where he
held discussions with Outlet Year Ltd, was paid for by associates of
that
company. This is wrong.The shortlisting of this particular company was therefore improper.
It should also be noted that the Deputy Prime Minister does not have
power to give directions to a Departmental Head, unless such a power -
Page 89 of 397
-
is
expressly given by an Act of the Parliament or some other law. The
office
of Deputy Prime Minister is created by Section 2 of the Prime
Minister Act
(Chapter No. 27 of the Revised Laws). However it does not carry with
it
any greater power of direction and control than those held by other
Ministers. The purpose of the office of Deputy Prime Minister is to
enable
a Minister to step into the shoes of the Prime Minister whenever the
Prime
Minister is unable to perform the duties of his office or any of the
other
situations in Section 143 of the Constitution exist.Chapter 9
79
That is, the person holding the office of Deputy Prime Minister
is not the
“second-in-charge” of the Ministry and does not have any powers
of
direction and control by virtue of holding that office. His
powers and
responsibilities are at all times constrained in accordance with
Section 148
of the Constitution (see Chapter 39).2. Sietco
The company known as Sietco (PNG) Pty Ltd is a PNG off-shoot of a
government agency in the People’s Republic of China, known as the
“China Sichuan Corporation for International Techno-Economic Co-
operation”. Neither of these groups had lodged an expression of
interest.Sietco is interested in road construction projects in the
Southern Highlands
Province and, during 1991, the company had a very close business
connection with the Minister for Transport, Mr Temo. In fact,
just a few
weeks before directing that Sietco be included on the shortlist,
the
Minister’s family company, Outskirts Construction Pty Ltd, had
entered into
a “partnership agreement” with Sietco, whereby the two companies
agreed
to jointly invest in Papua New Guinea and set up a “partnership
enterprise” -
Page 90 of 397
-
to undertake “construction and maintenance of roads and some
other civil
engineering projects as contractor or sub – contractor’. This
agreement
was signed by the Minister, on behalf of Outskirts Construction
Pty Ltd.
[EXHIBIT 55B]The closeness of the relationship between the Minister and Sietco
is further
demonstrated by the fact that only five days before including the
company
on the shortlist, the Minister had visited China and signed an
agreement
with Sietco’s Chinese parent company, which was intended to
clarify the
partnership contract signed just a couple of weeks before in
Papua New
Guinea. [EXHIBITS 62k 62B]Chapter 9
80
When the Minister was interviewed by the Ombudsman Commission, he
was asked whether he thought it improper a company he was so
closely
involved with, was asked by him to lodge a proposal for
construction of
the freeway. He did not deny his close relationship with Sietco
but stressed
that, as soon as the company had expressed an interest, he had
instructed
that it not be further considered because it might not look
right.But, if that is the case, why did the Minister put the company on
the
shortlist?The Ombudsman Commission cannot accept Mr Temo’s explanation and
is forced to conclude that his decision to shortlist this company
was
improper.3. Barclay Bros and Maunsell Joint
Both of these groups had lodged expressions of interest -but not
as joint
venturers. Maunsell Consultants were linked with Barclay Bros in
1988
(see Chapter 2), but had actually lodged a joint expression of
interest with -
Page 91 of 397
-
Baulderstone Hornibrook in response to the June 1990
advertisement.The Minister’s decision to link Maunsell with Barclay Brothers
therefore did
not make sense.4. Curtain Bros
This company – though it ultimately became closely involved with
the
consortium selected to undertake the project – had submitted the
expression of interest with the least amount of detail.Chapter 9
81 ■
While it is an established construction company, with experience
in Papua
New Guinea, we query its inclusion at the expense of other
companies
which had expressed their interest in the project in a more
active and
detailed manner.5. LKN Construction
This Singapore-based company, represented by LKN (PNG) Pty Ltd,
had
lodged a two page expression of interest in July 1990.6. Kumagai Gumi
This Japanese company had lodged a joint expression of interest
with
Kinhill Kramer Pty Ltd in 1990. The company had shown interest
in the
project for some time.7. Sabina Group Consortium
Peter Chen and Partners, of Brisbane Australia, had lodged an
expression
of interest on behalf of the Sabina Group Consortium, in July
1990. A
brochure, giving details of the consortium’s previous
activities, was
enclosed, but otherwise no details concerning the Spring Garden
Road
project were provided.8.. TagitaL.PagifiCalea
-
Page 92 of 397
-
This PNG company is essentially a K2.00 shelf company, which
operates
a small consultancy business in Port Moresby. It was added to
the
shortlist one month late. At the relevant time, its 100%
shareholder was
Mr Sam Pepena.The Ombudsman Commission also became aware that the Deputy Clerk
of the National Parliament, Mr Ano Pala, had a close association
with the
company.Chapter 9
82
Tasman Pacific International has few assets and no employees.
It has no
experience in road construction or design. It had not lodged
an
expression of interest.The company later joined with the Australian company Cooks
Mitchell
Peacock Stewart Pty Ltd to lodge a formal proposal for the
project.However, in March 1991, there was little justification for
Tasman Pacific
International being on the shortlist at the expense of other
established
PNG companies.[9-7] PREPARATION OF THE SHORTLIST WAS IRRESPONSIBLE AND
QUESTIONABLEThree of the groups on the shortlist had not submitted an
expression of
interest. Of these, the Ombudsman Commission discovered that
the
Minister for Transport, Mr Temo, had direct negotiations with
two of them
(Outlet Year and Sietco) outside Papua New Guinea, just a
couple of
weeks before he gave the shortlist to the Secretary for
Transport. The
other one – a Port Moresby shelf company with no experience in
road
construction or design, Tasman Pacific International – was
added to the -
Page 93 of 397
-
shortlist one month later.
Question-marks also surround the decision to put companies
such as
Curtain Bros and Sabina on the shortlist, because their
expressions of
interest were flimsy compared with the carefully documented
expressions
of interest submitted in July 1990 by established PNG
consulting firms
such as Cardno & Davies and Maunsell Consultants.Chapter 9
83
In the opinion of the Ombudsman Commission the most favourable
view
that can be taken of the Minister for Transport’s shortlist is
that it was
unfair and arbitrary. But unfortunately the way in which it was
prepared
leaves room for suspicion that the Minister for Transport was
compromised.
Whether this was, in fact, the case, the Ombudsman Commission
cannot
say, because we found no hard evidence of bribery.However, the evidence shows that, if the Minister was not
compromised,
he was at least naive and irresponsible in believing that he
alone – and not the officers of the Department of Transport or
the Department of Works –
the officers of the Department of Transport or the Department
of Works –
had the necessary technical expertise to decide which companies
were
to be shortlisted.VENTS AFTER PREPARATION OF SHORTLIST
).8] WHAT ACTION WAS TAKEN FOLLOWING PREPARATION OF THE
MINISTER’S SHORTLIST?Shortly after preparation of the shortlist, a standard letter
was drafted
within the Department of Transport, over the signature of the -
Page 94 of 397
-
Secretary for
Transport, Mr Amini.Copies of this letter – dated 8 March 1991 – were apparently
intended to
be dispatched to each of the shortlisted companies, explaining
the
information to be contained in their proposals.Chapter 9
84
The letter read, in part:
Your company has been short-listed for the above-
mentioned project and you
are hereby requested to send K40.00 … for cost of
reproducing the Terms of
Reference and preliminary “Economic’ and “Financial
Assessment’ reports plus
air mail to your address if you do not have an
Office here in Port Moresby —Your proposal should contain the following
information:-Financial Plan
1.1 Traffic Forecasts
Traffic throughout estimates and
anticipated growth of Pori
Moresby with your estimate of timing for
maximum capacity,1.2 Design, construction and other
associated costs for suggested
alternative schemes must be on a fixed
prize [sic] basis.These conceptual designs should
estimated Bills of Quantifies
for our guide only.
The estimate of total project cost must
include the engineering -
Page 95 of 397
-
elements of the work as well as costs
payable to Government,
including a land premium for area
occupied if and when needed,
An estimate cost of setting up the
project company for this
project and training the operatives
prior to opening _11
[EXHIBIT 64, page 1]The letter concluded by stating:
It must be pointed out very clearly that all
financing will be your
responsibility.” [EXHIBIT 64, page 3][9.9] MISSING DOCUMENTS
There are some perplexing things to note about the
standard letter drafted
by the Department of Transport. In particular, there are
no copies of it on
any Department of Transport files that the Ombudsman
Commission
inspected: there is simply no Departmental record that
these letters were
sent, or even that they were drafted.Chapter 9
85
We only became aware of their existence when the former Minister for
Transport, Mr Temo, was summoned to appear before the Commission
and produce relevant documents. Mr Temo had fourteen copies of the
letter in his possession, addressed to the following companies:1. Barclay Bros (PNG) Pty Ltd 1
2. Cardno & Davies PNG Pty Ltd
3. Coecon Pty Ltd -
Page 96 of 397
-
4. Connell Wagner (Old) Pty Ltd
5. Curtain Bros (PNG) Pty Ltd
6. Frame, Harvey and West
7. Juara Ltd
8. Kumagai Gumi/Kinhill Kramer
9. LKN (PNG) Pty Ltd – •
10. Maunsell Consultants PNG
11. Ove Arup & Partners Pacific Pty Ltd ■
12. Robert Laurie Pty Ltd
13. Sabina Group Consortium
14. Sietco (PNG) Pty Ltd
[EXHIBITS 64, 64B – 64N] •I
We also became aware that a copy of the same letter – dated 28 March
1991 – was sent to Tasman Pacific International, the company that
was a
late addition to the Minister’s shortlist. There was also no copy of
this
letter in the Department of Transport’s files. [EXHIBIT 68B]Chapter 9
86
[9.10] FURTHER MYSTERY SURROUNDING THE LETTERS OF MARCH 1991
Each of the letters dated 8 March 1991 began by stating:
“Your company
has been short-listed for the above-mentioned project” (but
the letters in
fact had no title). This was very strange. The Minister had
short-listed
seven companies for the project on 27 February 1991. Why were
fourteen
companies being advised by a letter dated 8 March 1991 that
they had
been short-listed? This simply did not make sense.Upon discovering the existence of the fourteen letters dated
8 March
1991, each of which bore the signature of the Secretary for
Transport, the
Ombudsman Commission conducted interviews with -
Page 97 of 397
-
representatives of
four Port Moresby-based companies, among the list of
fourteen:Barclay Bros (PNG) Pty Ltd
Maunsell Consultants PNG
Cardno & Davies (PNG) Pty Ltd
Frame Harvey and West.
Some companies did not receive the Secretary’s letter
Each of the persons interviewed had knowledge of the Spring
Garden
Road project and their company’s interest in it. They each
stated that they
had never seen the letter of 8 March 1991 before. Not only
that, they had
never received acknowledgment of their company’s expression
of interest
in the project, let alone been advised that their company had
been short-
listed.Chapter 9
87
9.11] OTHER COMPANIES DID RECEIVE THE LETTER
Some companies did receive a copy of the letter of 8 March
1991. A
representative of LKN Construction (PNG) Pty Ltd, for
example, was able
to confirm, by checking the company’s files, that the letter
had been
received. [EXHIBITS 66B, 70]It is also likely that Sabina Ltd, of Brisbane Australia,
received a copy of
the letter. [See the letter from Sabina to Mr Amini of 8
April 1991, which
refers to a letter dated 18 March 1991: EXHIBIT 71]9.12] THE SECRETARY FOR TRANSPORTS EXPLANATION
-
Page 98 of 397
-
Mr Amini’s explanation of the confusion over the letters of
March 1991 was
as follows:‘Normally for a common letter meant for more than one
addressee, the original
is signed and then photocopied for the different
addressees to be typed on. In
so doing, the clerks were missing out mating additional
copies for files. In the
end, only one copy was left for filing. This practice was
discovered and
corrected. As far as I am aware, all those short-listed
were sent an invitation.
Some were by facsimile. To suggest that such a simple
mistake could not occur
is just being unrealistic. This is not defective
administration.’ [EXHIBIT 254,
para 71(9.13] DEPARTMENT OF TRANSPORT GUILTY OF DEFECTIVE ADMINISTRATION
We accept Mr Amini’s point that simple mistakes can occur in
any
organisation. But we find it difficult to understand why the
Department of
Transport files contain no record at all of the existence of
these letters.
And why were fourteen letters drafted, when only seven
companies had
been shortlisted? Why did some companies not receive the
letter? Why is
there no record of the existence of the Tasman Pacific
International letter
in the Department’s files?Chapter 9
88
If no proper records are maintained, especially in projects
such as this,
how can the decision-making process be properly put in place
and
justified? -
Page 99 of 397
-
One of the themes of this report is that unequal treatment
was given to
companies which had expressed interest in the project. Some
were treated
very favourably, whereas others did not even have their
expressions of
interest acknowledged.There are too many unanswered questions surrounding the
letters of
March 1991 to dismiss the above matters as a minor
administrative bungle.
We are surprised that the Minister for Transport had copies
of the letters
and not the Department of Transport – though they were signed
by the
Secretary for Transport.We can only conclude that the Department of Transport’s
failure to retain
any record of these letters and the failure to ensure that
all the letters
were sent was a serious case of defective administration,
which had the
effect of denying a number of companies the opportunity of
making a bid
for the project.[9.14] THE STATE OF THE SHORTLIST IN MARCH 1991
In light of the above evidence, the situation with the
Minister’s shortlist, as
at March 1991, can be summarised as follows:In February 1991 the Minister short-listed seven
companies,
two of which had not lodged expressions of interest,
without
the advice of his Department.Chapter 9
89
One month later, the Minister added another company to
the
shortlist, even though it also had not lodged an
expression
of interest. This company had no experience in road
design -
Page 100 of 397
-
or construction. It was advised in writing it had been
shortlisted, but there is no copy of the letter in the
Department’s files.In the meantime, standard letters advising fourteen
companies they had been short-listed, were signed by
the
Secretary for Transport.However, there is no record of the existence of these
letters
in the Department’s files.At least four of the fourteen letters were not
received.At least one of the companies on the Minister’s
shortlist –
Barclay Bros (PNG) Pty Ltd – did not receive the
letter.This was all quite bizarre. However, even stranger things
were to
happen in the months ahead. •[9.15] THE FATE OF THE SHORTLISTED COMPANIES
As at the end of March 1991, the Minister had shortlisted
eight
consortiums for the project. However, when the Ministerial
Committee on
Spring Garden Road met on 18 July 1991, it had a shortlist of
five:Chapter 9
90
Topbay Investment Limited & China Ample
Development Ltd, the Second Surveying & Designing
Institute, Ministry of Railways, People’s Republic of
China, together with Moore’s Investment Group.Kumagai Gumi-Kinhill Kramer consortium.
Periquan’s International Resources Pty Ltd and Pty Ltd
Asia Management Consultants Centre.Tasman Pacific International and Crooks Mitchell
Peacock Stewart Pty Limited. -
Page 101 of 397
-
McConnell Dowell.
Only two of these were on the original shortlist of eight.
So, what
happened to the six groups that disappeared from the list?
And
where did the three new ones come from?[9.16] THE COMPANIES WHICH LEFT THE SHORTLIST
The Ombudsman Commission makes the following observations
in
relation to the six companies which disappeared from the
shortlist:1. Outlet Year Ltd – in June 1991 it was “substituted” by
Topbay
Investment Ltd, another Hong Kong-based company (see
Chapter 12).Chapter 9
91
III2. Sietco (PNG) Pty Ltd – there is no evidence that
this U
company was advised it was on the shortlist. In
fact, there
is no evidence on the Department of Transport
files of any
correspondence from or to this company.III
3. Barclay Bros (PNG) Pty Ltd/Maunsell Consultants
PNG Pty
Ltd – neither of these companies were advised
they had la
been shortlisted.FE
4. Curtain Bros – there is no evidence that either
Curtain Bros
(PNG) Pty Ltd or Curtain Bros (Old) Pty Ltd were
advised II
they had been shortlisted.
5. LKN Construction – on 8 April 1991 LKN (PNG) Pty
Ltd wrote II -
Page 102 of 397
-
to the Department of Transport and advised that
it was
withdrawing its expression of interest. [EXHIBIT
70]6. Sabina Group Consortium – this group was
definitely aware
it had been shortlisted, but was unable to meet
the deadline
for submission of proposals. [EXHIBITS 76, 82,
83][9.17] THE THREE NEW GROUPS “ADDED ” TO THE SHORTLIST
The Ombudsman Commission makes the following
observations in
relation to the three groups included in the July
1991 shortlist, but
not in the March 1991 shortlist:1. Topbay Investment Ltd – this company replaced
Outlet Year
Ltd, but essentially the same group of Asian
businessmen
was involved (see Chapter 12).Chapter 9
92
2. Periquan’s International Resources Pty Ltd – this
company
joined with the Port Moresby consulting firm, Frame
Harvey
West & Maso, and submitted a late proposal. But no
formal
expression of interest had been lodged before this.3. McConnell Dowell – this Brisbane-based company only
heard
about the project in April 1991. On the basis of a
half-page
fax to the Department of Transport and two telephone
conversations with the Director of the Policy
Secretariat, Mr
Hitolo, a letter was dispatched to the company,
advising it
had been shortlisted. [EXHIBITS 74, 75, 77] -
Page 103 of 397
-
SUMMARY OF PREPARATION OF SHORTLIST
[9.18] UNEQUAL TREATMENT WAS GIVEN TO COMPANIES WHICH HAD
EXPRESSED INTEREST IN THE PROJECTThere was a great disparity in the treatment given to the
various
companies that had expressed interest in the Spring Garden
Road project
since July 1990:Some companies were shortlisted, even though they had
not
lodged an expression of interest (e.g. Outlet Year Ltd,
Topbay Investment Ltd, Tasman Pacific International and
McConnell Dowell) whereas others which had lodged
detailed expressions of interest in July 1990 were
excluded
and never received acknowledgement of their interest
(e.g.
Cardno & Davies and Maunsell Consultants).Chapter 9
93
Some shortlisted companies were allowed extensions of
time
to submit proposals [see EXHIBITS 67, 72, 76, 78, 79,
81,
83, 93, 94] whereas others (e.g. Barclay Bros) were
not even
advised they had been shortlisted.The result of this arbitrary and unsatisfactory process was that, by
July
1991, a shortlist of five had been prepared for the consideration of
the
Ministerial Committee on Spring Garden Road.* * * * * * * * * *
-
Page 104 of 397
-
Chapter 9
94
10. TERMS OF REFERENCE FOR THE PROJECT: EARLY 1991
[10.1] PURPOSE OF THE TERMS OF REFERENCE
In early 1991, a document was drafted within the Department
of Transport,
entitled ‘Terms of Reference-Spring Garden Road”. The purpose
of this
document was to describe the requirements of the Department
of
Transport and assist potential developers in the formulation
of proposals.
[EXHIBIT 55]In the Ombudsman Commission’s view, the document was
seriously
flawed and very confusing. It failed to specify the scope of
the project
and its technical parameters. The timing of the document’s
release, its
limited circulation and. its stipulation concerning Build-
Operate-Transfer
financing are also matters for concern.[10.2] THE SCOPE OF THE PROJECT
We reported in Chapter 5 that, despite extensive
investigations, we were
never able to pinpoint who made the decision to extend the
scope of the
Spring Garden Road/Poreporena Freeway project from the
original plan to
link Konedobu, through Burns Peak, with Hohola. -
Page 105 of 397
-
Nor could we determine when the decision was made that a
freeway
should be built all the way from downtown Port Moresby to
Jacksons
Airport.Chapter 10
95
The problem of defining the scope of the project was
exacerbated by the
Terms of Reference document. Whereas the advertisements
published by
the Department of Works in June 1990 had specified
(arbitrarily) that the
new road would link Konedobu and Waigani Drive, the
Department of
Transport’s Terms of Reference simply spoke in vague terms
such as “the
Spring Garden Road Link near the Burns Peak”.[10.3] WHAT DOES THE “SPRING GARDEN ROAD UNK” MEAN?
This term can mean at least three things:
a link between Champion Parade Konedobu and Wards
Road Hohola; ora link between Champion Parade Konedobu and Waigani
Drive; ora link between Champion Parade Konedobu and Boroko
Drive. [See the map at the end of Chapter 2]All of the above alternatives would “link” various
unconnected sections of
Spring Garden Road, which runs from Champion Parade Konedobu
to
Boroko Drive, Gordons.The Terms of Reference document was seriously deficient in
its failure to
specify exactly what was required of prospective developers.
The
qualifying words which appear in the document – “near the
Bums Peak” –
suggest the scope of the project was intended only to be the
link between
Champion Parade and Wards Road. -
Page 106 of 397
-
Chapter 10
96
But if that was the case, why did the State eventually enter
into a contract
for the construction of a freeway going all the way from
downtown Port
Moresby to Jacksons Airport?[10.4] THE TERMS OF REFERENCE DEFIED COMMON SENSE
It seems common sense that when the Government commissions
the
building of a road, one of the first things to decide is
where the road is
going to go and how long it should be. How can a company
lodging a
proposal to build a road estimate the total project cost
(inclusive of design
and construction) when it doesn’t know where the road is
supposed to
go or how long it is supposed to be?In his response to our preliminary report, the Secretary for
Works, Mr
Hitolo, who was responsible for the project for a
considerable time in the
Department of Transport, stated that the scope of the project
was
deliberately not specified in the Terms of Reference
document, because
this was to be a Build-Operate-Transfer project:“Government’s role is purely to create the business
atmosphere conducive to
the private company to become interested in investing on a
scale and scope it
believes it can get a profitable return.” [EXHIBIT 265,
page 3]Mr Hitolo said it would have been premature to specify the
scope of the
project in the Terms of Reference. He also suggested that the
Ombudsman Commission did not understand the Build-Operate-
Transfer -
Page 107 of 397
-
concept.
By contrast, when the Secretary for Transport, Mr Amini,
responded to our
preliminary report, he maintained that the detailed scope of
the project
was contained in the Terms of Reference document. However,
when
asked to point to the section of the document which specified
the scope,
Mr Amini was unable to do so. [EXHIBIT 254, page 4]Chapter 10
97
Quite dearly, the Terms of Reference did nol specify the
scope of the
Spring Garden Road project. It did not state where the road
was
supposed to begin and end. We reject Mr Amini’s claim that it
did. We
also reject Mr Hitolo’s claim that it was unnecessary for the
scope of the
project to be specified.The Ombudsman Commission concludes that the Terms of
Reference
document was vague and confusing, especially because of its
failure to
specify what was required of prospective developers.The inadequacy of the document is borne out by the fact that,
despite its
insistence that proposals be based on Build-Operate-Transfer
financing,
no such proposal was ever lodged with the Department of
Transport.[10.5] THE TERMS OF REFERENCE ALSO FAILED TO SPECIFY THE
TECHNICAL PARAMETERS OF THE PROJECTAnother serious defect in the Terms of Reference document was
its failure
to specify the fundamental technical parameters of the -
Page 108 of 397
-
project. This point
was made by the World Bank Mission which visited Port Moresby
in
September 1991 to monitor the Spring Garden Road project:Mu technical parameters are left =claw as to whether Papua
New Guinea
was seeking a two or four lane road, one or two tube
tunnels, and whether the road surface would be of
compacted gravel or asphalt concrete, and whether an open
cut or tunnel was desired.’
road surface would be of compacted gravel or asphalt
concrete, and whether an open cut or tunnel was desired.’
open cut or tunnel was desired.’
[EXHIBIT 111, at page 1 and see generally Chapter 15J[10.6] TIMING OF THE RELEASE OF THE TERMS OF REFERENCE
The Terms of Reference document was first released in March
1991. This
was before the results of the geotechnical investigation
undertaken byChapter 10
98
Coffey Partners International was completed. However, the
interdepartmental meeting on 31 July 1990 had decided that
firm
proposals would not be called for, until after that
investigation was
complete (see Chapter 7).The Ombudsman Commission therefore seriously questions the
timing of
the release of the document0.7] LAVED CIRCULATION OF THE TERMS OF REFERENCE
An even more serious concern is the fact that the Terms of
Reference
document was only circulated to a limited number of
developers. It was
only those companies shortlisted by the Minister for
Transport, Mr Temo,
in February/March 1991, that were eligible to receive a -
Page 109 of 397
-
copy.
We have already commented on the unsatisfactory and
arbitrary way in
which that shortlist was prepared (see Chapter 9). It would
have been far
better to publicly advertise the availability of the Terms
of Reference,
rather than selectively offer it to only a few companies.Whenever investment opportunities are offered to companies
“selected” by
a Minister, there are bound to be suspicions of corruption.
The best way
to avoid this is to give all interested companies an equal
opportunity to
submit proposals through public advertisements..8] BUILD-OPERATE-TRANSFER FINANCING
A feature of the Terms of Reference document. is that it
dictated that the
project be undertaken using the Build-Operate-Transfer (BOT)
method of
financing.Chapter 10
99
The Ombudsman Commission has been unable to establish how or, even,
when this important policy decision was made, because the Terms of
Reference document is undated and the Department of Transport files
did
not disclose this information. It was certainly never the stated
policy of the
National Executive Council that the project be financed in this way.In the absence of such a policy directive, the Ombudsman Commission
expected to find some evidence that, before stipulating the project
would
be financed in this way, the Department of Transport had carefully
and
methodically considered all the policy options available and
formally made
a decision to invite proposals on the basis of Build-Operate-
Transfer
financing. However, our examination of their files revealed that
Build-
Operate-Transfer financing was addressed only in the following
documents: -
Page 110 of 397
-
the Information Paper that was supposed to be presented to
the National Executive Council, but which never was (see the
final part of Chapter 8); andthe Terms of Reference document. [Exhibits 36 & 55]
Neither document could satisfy us that the decision concerning
Build-
Operate-Transfer financing for the Spring Garden Road project had
been
made carefully or competently.In our preliminary report we suggested that the Department of
Transport
had failed to make a careful, reasoned and properly documented
decision
on financing the Spring Garden Road project. The Secretary for
Transport,
Mr Amini, responded by stating:Chapter 10
100
‘The concept of BOT was debated at length at our Executive
Meetings. It was
introduced by Mr Hitolo. I do not encourage new concepts which
are not fully
assessed for implications and impacts to be put before the NEC.’
[EXHIBIT 254, page 31However, when Mr Amini was pressed on this issue, the only evidence
he
could provide was the minutes of a Department of Transport Executive
Staff Meeting on 14 September 1990. The minutes stated:“Director (Policy Secretariat) said he will prepare a submission
to NEC for
discussion when considering plans for the project on the BOT
system. HOT
stands for Build, Operate and Takeover.The system simply means that the company awarded the contact will
build the
mad (project) and operate it in a bid to recover costs and -
Page 111 of 397
-
expenses. Then hands
the mad back to National Government.” [EXHIBIT 45A, page 4]Mr Amini also provided copies of two papers presented at a Transport
Sector Seminar held in Port Moresby in 1991, which addressed the
issue
of Build-Operate-Transfer financing. One of them was prepared by Mr
Hitolo, then Director of the Policy Secretariat in the Department of
Transport, entitled “Spring Garden Road BOT Concept’. Mr Hitolo
stated:‘The main reason to get Spring Garden Road to be proposed for
financing
through private sector was the fact that the Government’s
intention for this
project to attract aid was not successful despite its good
economic justifications.
Hence the Government, decided to get private funding by directing
the
Department of Transport to assess the turn-key concept as the
basis for
implementing the project. This simply meant that a particular
company be
selected on a competitive basis and get it to arrange a private
loan on behalf
of the Government. As the general policy and understanding was to
use the
private sector for the total financing, construction and
operation so that
efficiency in the private sector may be tapped in the provision
of infrastructure
services.In actual fact the BOT (Build, Operate and Transfer) or the
alternative BOO
(Build, Own and Operate) systems were implied in the above-
mentioned policy.
Hence the concept of BOT system came into consideration followed
by an
invitation for interests in this sort of scheme. Unfortunately,
the concept was
not very well known in this country and therefore the responses
were not
satisfactory.’ [EXHIBIT MA, page 303]Chapter 10
-
Page 112 of 397
-
101
The Ombudsman Commission does not dispute Mr Hitolo’s
expertise. Nor
do we take issue with the Build-Operate-Transfer concept, as
such. As an
innovative method of financing it deserved to be closely and
widely
considered.What we are critical of is the Department of Transport’s
failure to carefully consider all the financing options
available and its failure to formulate a
consider all the financing options available and its failure
to formulate a
policy and advise the Minister for Transport to table it
before the National
Executive Council so that a formal Cabinet policy decision
could be made
on this important issue.10.9] SUMMARY OF THE TERMS OF REFERENCE: INCOMPETENT
ADMINISTRATION BY THE DEPARTMENT OF TRANSPORTThere were many unsatisfactory aspects of the Terms of
Reference
document prepared by the Department of Transport in early
1991:As a document which was supposed to indicate to developers
what
was required in their proposals, it was very vague. It did
not
mention where the road would go, or how long it would be.It also failed to specify basic engineering aspects of the
project.It was prematurely released.
It dictated that the proposals incorporate Build-Operate-
Transfer
financing, however no formal decision in favour of this
method of
financing had been made by the Department of Transport, the
Minister for Transport or the National Executive CouncilChapter 10
102
-
Page 113 of 397
-
It was made available – unfairly – to only a selected group of
companies.
In the opinion of the Ombudsman Commission the preparation and
distribution of this important – but defective – document was
another
example of incompetent administration by the Department of
Transport.* * * * * * * * *
Chapter 10
11. THE MINISTERIAL COMMITTEE MEETING
OF 18 JULY 1991[11.1] PERSONS PRESENT AT THE MEETING
The Minister for Transport Mr Anthony Temo convened a meeting
of “the
Ministerial Committee on Spring Garden Road” in his
Parliamentary office
on 18 July 1991. Present at the meeting were:Mr Temo, MP;
the Minister for Lands and Physical Planning, Sir Hugo
Berghuser MP; -
Page 114 of 397
-
the Minister for Works, Lukas Waka OBE, MP;
the Parliamentary Secretary for Finance and Planning,
Thomas
Negints MP;the Head of the Policy Secretariat in the Department of
Transport, Lohia Hitolo; andthe First Assistant Secretary (Planning & Research) in
the
Department of Transport, Henry Paraket.Chapter 11
104
[11.2] WHAT WAS THE PURPOSE OF THE MINISTERIAL COMMITTEE
MEETING?The purpose of the meeting was to select a developer to
undertake the
Spring Garden Road project. As a result of the arbitrary and
unsatisfactory
shortlisting process between February and July 1991
(considered in
Chapter 9) five consortiums were to be considered.THE MINISTERIAL COMMITTEE ON SPRING GARDEN ROAD
[11.3] STATUS OF THE MINISTERIAL COMMITTEE
Before we address the deliberations of the Ministerial
Committee, there is
one important point to note: in the course of its
investigation the
Ombudsman Commission was unable to find any document showing
how
or when this Committee was established or who its members
were.The Secretary to the National Executive Council testified
there was no
record of the establishment of such a committee and the
Secretary for
Transport said his Department had also tried in vain to find
some record
of the Committee’s existence. -
Page 115 of 397
-
When we put the issue to Mr Temo, he was adamant that the
Committee
had been duly authorised by the National Executive Council to
report back
to it on the preferred method of implementing the project. He
could not,
however, provide any details of the Committee’s
establishment.Chapter 11
105
Mr Temo stated:
“My mind is quite clear that there was a NEC
decision which authorised the
Minister for Transport to be Chairman of the
Ministerial Committee on
infrastructure. Also the same Ministerial Committee
used NEC decision to
bypass normal tender procedures to construct Enga
Highway Stage 2 or 3. If
NEC did not make this decision), Porgera mine would
not have started
production on time because normal department tender
procedures normally
takes a very long time even the normal political
will does not work.One should understand that if there was no such
Ministerial Committee
established why was NEC recognising and expecting
Ministerial Committees
recommendations?Therefore obviously I acted with some lawful
authority even if we are unable
to get the records. See letter from NEC Secretary
dated 19 November 1992′
[EXHIBIT 257 para 2] -
Page 116 of 397
-
When we questioned Sir Hugo Berghuser on this point, he
stated that theCommittee had been established at his initiative. But Sir
Hugo, also, couldnot point to any formal record of its existence.
[11.4] THE MINISTERIAL COMMITTEE ACTED WITHOUT AUTHORITY
The Ombudsman Commission concludes that the “Ministerial
Committeeon Spring Garden Road” was never formally established by
the NationalExecutive Council and had no authority to make decisions
binding orpurporting to bind the National Executive Council.
At this juncture, we note that Section 149(4) of the
Constitution provides:‘Except where the contrary intention appears,
nothing in this
Constitution prevents the powers, functions, duties
or responsibilities
of ti e [National Executive Council] from being
exercised, as determined
by t, through a Minister.” -
Page 117 of 397
-
Thus, the Constitution does allow the powers of the
National ExecutiveCouncil to be delegated to Ministers.
Chapter 11
106
But this does not mean that any group of Ministers can
appoint
themselves to “committees” of the National Executive Council
and clothe
that “committee” with powers or status.A Ministerial Committee – even one which only intends to make
recommendations to the National Executive Council – must have
its powers
and responsibilities properly delegated and controlled by the
National
Executive Council under Section 149(4) of the Constitution
before it makes
any decisions or holds itself out as having any powers or
responsibilities.This did not occur in relation to “the Ministerial Committee
on Spring
Garden Road”. It therefore had no lawful status or power or
authority.[11.5] WHAT DOCUMENTS WERE CONSIDERED AT THE “MINISTERIAL
COMMITTEE” MEETING?The Head of the Policy Secretariat in the Department of
-
Page 118 of 397
-
Transport, Mr
Hitolo, brought the following documents to the meeting on 18
July 1991,
for the consideration of the Ministerial Committee:the proposals of the five shortlisted consortiums; and
a document dated 17 July 1991 entitled “Financing the
Construction of the Spring Garden Freeway”.Chapter 11
107
LOSS OF DOCUMENTS
[11.6] MOST OF THE FIVE PROPOSALS HAVE BEEN LOST
It has been very difficult for the Ombudsman Commission to
ascertain
exactly which proposals the Ministerial Committee had before
it. By the
time we conducted our investigation, most of the proposals
had been lost.The investigation was also hampered by the fact that the
meeting is poorly
documented in the files of the Department of Transport. In
fact, the only
evidence of the meeting taking place is a letter from the
Minister for
Transport to the Secretary for Transport asking him to attend
the meeting
and a one-page memorandum of the decisions made at the
meeting.
[EXHIBITS 97,102][11.7] HOW WERE THE PROPOSALS LOST?
Mr Hitolo testified that at the end of the meeting he had
left all five
proposals in the Minister for Transport’s office at the
request of Sir Hugo
Berghuser, who said that he wanted to study them further
before making
a decision. -
Page 119 of 397
-
When Sir Hugo was questioned on this point, he agreed the
proposals
had been left, at his request, in the office. But he said he
only asked that
copies be made for him. He was dissatisfied with the
proposals before
the Committee and he said as much to the other members of the
Ministerial Committee. ‘When I left the office, the proposals
were still there
and I have never seen them since’, Sir Hugo said.Chapter 11
108
Correspondence between Mr Hitolo (who became Secretary for
Works in
early 1992) and Mr Amini in March 1992 confirmed that this
incident took
place [EXHIBIT 160, final paragraph]. But the Ombudsman
Commission
has not been able to trace the whereabouts of the proposals
left in the
Minister’s office.The Ombudsman Commission concluded that the proposals were
lost by
the Minister for Transport, Mr Temo.When we made this allegation in our preliminary report, Mr
Temo claimed
that, in fact, the proposals had been lost by Sir Hugo
Berghuser.
However, even if this were, in fact, the case, Mr Temo was
the Minister of
the State entrusted with custody of these important and
confidential
documents. It was his responsibility to take adequate steps
to ensure the
documents were in safe hands.[11.8] THE DEPARTMENT OF TRANSPORT FAILED TO KEEP COPIES OF THE
PROPOSALSSurprisingly, the Department of Transport had not kept copies
of the
proposals, except the one made by the Chinese consortium –
which was
the group selected by the Ministerial Committee to undertake
the project. -
Page 120 of 397
-
This meant, therefore, that most of the proposals had been
lostTM.This particular administrative mistake was to have far-
reaching
consequences several months later, when pressure was put on
the
Department to expedite the project and the Department had
second-
thoughts about supporting the Chinese proposal (see Chapter
18).Chapter 11
109
It meant that when the Department was required to prepare a
National
Executive Council Policy Submission in February 1992,
recommending a
consortium to undertake the project, it only had one proposal
in its
possession.[11.9] DEPARTMENTAL RECORDS SHOULD NOT BE GIVEN TO MINISTERS
As a general rule the Ombudsman Commission believes that
official
Government records and files should not be left in the
possession of
Ministers. An official Government file is the property of the
State – it does
not belong to a Minister. A Minister has the right to be
fully and objectively
briefed by his or her Departmental Head. But he does not have
the right
to keep possession of official files.If this principle of sound public administration had been
followed in the
present case, the proposals probably would not have been
lost.EVALUATION OF PROPOSALS
[11.10]la
SPRING GARDEN FREEWAY -
Page 121 of 397
-
This document was the focus of discussion ac the Ministerial
Committee
meeting of 18 July 1991. It is dated 17 July 1991, i.e. one
day before the
Ministerial Committee meeting. were in fact two versions of
it:Chapter 11
110
One version was addressed to “the Members of the
Resource Management Committee”. It was drafted as a
submission by the Department of Transport and shows the
submitter as “B K Amini CBE Secretary”; however, it was
unsigned. [EXHIBIT 100]The other version of the document was drafted as a Policy
Submission to the National Executive Council by the Minister
for Transport; it was signed by Mr Temo. [IXHIBIT 99]Although there are some minor variations, both versions of the
document
are essentially the same:They outline the background of the Spring Garden Road
project.The scope of the project is described as being from
downtown Port Moresby to Jacksons Airport.The five short-listed proposals are evaluated, according to
ten criteria.The conclusion is reached that the Second Surveying and
Designing Institute of the Peoples’ Republic of China (which
lodged a proposal in conjunction with Topbay Investment
of Hong Kong) be “appointed” to commence negotiations
with the Department of Transport for the development of the
Spring Garden Road.Chapter 11
111
[11.11] THE METHOD USED TO EVALUATE THE SHORTLISTED PROPOSALS
-
Page 122 of 397
-
The “Financing the Construction of the Spring Garden
Freeway” document
evaluated the five proposals according to ten criteria:1. Interpretation of the Terms of Reference.
2. Logical Phasing of Tasks in the Methodology.
3. Environment Impact Statement.
4. Financier’s Credibility.
5. Main Contractor’s Relevant Experience.
6. Local Partner Participation.
7. Proposed Equity Distribution.
8. Personnel Proposed in General.
9. Team’s Experience in B.O.T. System.
10. Funding Proposal for the Project.The proposals were given a rating of “Excellent”, “Very
Good”, “Good”,
“Fair” or “Satisfactory” on each criteria.The proposals were then given an overall ranking, as
follows:1st: Topbay Investment Ltd/Second Surveying & Designing
Institute, People’s Republic of China.2nd: Periquan’s International Resources.
3rd: Kumagai Gumi/Kinhill Kramer.
4th: Tasman Pacific International.
5th: McConnell Dowell.
Chapter 11
112
In light of these rankings, the document concluded that the
project be
awarded to the Chinese consortium.(11.12] FURTHER UNSATISFACTORY ADMINISTRATION BY THE DEPARTMENT
OF TRANSPORTWe have noted elsewhere in this report that the standard of
documentation of important policy decisions by the
Department of
Transport was extremely poor. We made that finding in
relation to a
number of issues, e.g. the decision to extend the freeway to
Jacksons -
Page 123 of 397
-
Airport, the tunnel/cut issue and the Build-Operate-Transfer
method of
financing (see Chapters 5 & 10).We make a similar finding in relation to the evaluation of
the five proposals
shortlisted for consideration by the Ministerial Committee.
The
Ombudsman Commission considers that a much more detailed and
methodical comparison of the alternative proposals was
required than the
one page table attached as an appendix to the “Financing the
Construction of the Spring Garden Freeway” document.The subjective rankings on the basis of the ten selected
criteria were
vague and meaningless.This situation occurred because the Department of Transport
did not have
any established procedures for evaluating proposals for
construction of
roads or other transport infrastructure. The Department of
Transport, on
the instructions of the Minister for Transport, had wrongly
assumed
responsibility for a task that should have been carried out
by a Supply
and Tenders Board, in accordance with the Public Finances
(Management)
AMChapter 11
113
[11.13] OTHER DEPARTMENTS NOT INVOLVED IN THE RANKING OF
PROPOSALSA feature of the decision-making process which led to the
selection of the
consortium to build the Spring Garden Road/Poreporena
Freeway, is the
flagrant disregard of normal tender procedures (see Chapter
35).If the project had been properly put to public tender in the
first place, the
Ministerial Committee would not have had to deliberate on
the matter and
the Department of Transport would not have been required to
rank the
proposals shortlisted by the Minister. -
Page 124 of 397
-
Though these mistakes were made, the maladministration would
not have
been so serious, if the Minister for Transport and the
Department of
Transport had been willing to consult other Departments when
ranking
the shortlisted proposals. However, no consultation took
place.We are particularly concerned that the Department of Works
was not
consulted. This Department has far more experience in
selection of
contractors to undertake road projects than the Department
of Transport.It was also wrong for the Department of Transport not to
consult the
Department of Finance and Planning. There is no evidence
that any proper
checks were made by the Department of Transport on criteria
such as
“Financier’s Credibility” and “Funding Proposal for the
Project”. We note the
Chinese proposal was rated “excellent” on both these
criteria. Yet six
months later the Department of Transport found it necessary
to seriously
question the bona fides of the proponents (see Chapter 15).Chapter 11
114
[11.14] DID THE PROJECT “BELONG” TO THE DEPARTMENT OF TRANSPORT?
We have no doubt many mistakes were made because the
Minister for
Transport and the Secretary for Transport believed that the
Spring Garden
Road/Poreporena Freeway project was “a Department of
Transport project”
– not “a Department of Works project”.However, the terms of National Executive Council Decision
No. 14/90 were
that “the Department of Transport, the Department of Works
and the
Department of Finance and Planning formulate detail plans -
Page 125 of 397
-
for the
construction of Burns Peak Road”. [EXHIBIT 6A]We could therefore see no justification for the Minister for
Transport or the
Department of Transport shutting out these two other
departments from
the decision-making process.Though it was within the policy prerogative of the
Department of Transport
to determine where the freeway would go, whether there would
be a
tunnel or cut through Burns Peak and whether the project
would be
undertaken using Build-Operate-Transfer financing, it was
wrong for the
Minister for Transport and the Department of Transport to
exclude the
other key Departments from the decision on who was going to
design,
finance and build the freeway.[11.15] THE FORMAL RECORD OF THE MINISTERIAL COMMITTEE’S DECISION
In his oral testimony to the Ombudsman Commission, Sir Hugo
Berghuser
stated that the Ministerial Committee meeting lasted not
much longer than
30 minutes and that the discussion had been confined to the
contents
the “Financing the Construction of the Spring Garden
Freeway” document.Chapter 11
115
No minutes of the meeting were kept and the only record
of the
Committee’s decision is a document, under Ministry of
Transport
letterhead, that was signed by Mr Temo, Mr Waka and Mr
Negints. It
stated:‘On the 18th day of July 1991, the Ministerial
Committee On The Spring Garden -
Page 126 of 397
-
Road Development met at the Transport Minister’s
office in the National
Parliament House and authorized and approved the
following recommendation:That the Chairman of this Committee seek
National Executive Council
(NEC) endorsement for the appointment of
The Second Surveying and
Designing Institute, Ministry of Railways
of Peoples Republic China to
commence negotiation for the development
of the Spring Garden Road.2. That the Chairman of the Committee seek
National Executive Council
endorsement to authorize the Attorney-
General’s Department and the
Department of Finance and Planning to
negotiate and execute the
principle terms and conditions of the
contract emerging from their
proposals.3. That the Chairman of this Committee seek
National Executive Council
endorsement to negotiate and use B.O.T. or
turnkey as the basis of
funding the Spring Garden Road
Development.4. That the Chairman of the Ministerial
Committee seek National
Executive Council endorsement in order to
authorize Department of
Finance and Planning to negotiate and
execute the Franchise agreement
and any other necessary and desirable
documents relating thereto on
behalf of the State? [EXHIBIT 102]Sir Hugo testified that this document was not signed at
the meeting of 18
July 1991 and we accept that that was in fact the case.[11.16] WHAT HAPPENED AFTER THE MEETING?
-
Page 127 of 397
-
The document recording the decisions of the Ministerial
Committee
appears to have been signed a day or two after the
meeting took place.Chapter 11
116
Sir Hugo stated that, though he had seen this document, he
had
deliberately not signed it because he did not agree with its
contents. He
was very suspicious about the negotiations that had already
taken place
with the Chinese. In fact, Sir Hugo alleged that he had been
invited to a
Chinese restaurant in Port Moresby, and asked to sign the
document in
the presence of other members of the Ministerial Committee
and
representatives of the Chinese consortium. He said that he
refused to sign
the document and walked out of the restaurant.The Ombudsman Commission has been unable to obtain any
corroborating evidence of this particular incident. However,
we share Sir
Hugo’s concern about the propriety of the decision to favour
the Chinese
consortium.WAS THERE AN OBJECTIVE EVALUATION?
[11.17] HAD THERE BEEN A GENUINE ATTEMPT TO EVALUATE THE
ALTERNATIVES?On the face of it, the selection of the Chinese consortium
was yet another
example of the type of haphazard and careless decision -
Page 128 of 397
-
making that had
come to characterise the Ministry and Department of
Transport’s handling
of the Spring Garden Road/Poreporena Freeway project. But
our
investigations revealed that there was more to the selection
of the Chinese
than just slipshod administration.Chapter 11
117
[11.18] THE DECISION HAD ALREADY BEEN MADEIn the opinion of the Ombudsman Commission, the Ministerial
Committee
meeting of 18 July 1991 was really just a rubber-stamping
exercise for a
decision already made by the Minister for Transport, Mr
Temo, to award
the project to the Chinese consortium.Both versions of the “Financing the Construction of the
Spring Garden
Freeway” document actually referred to “the Ministerial
Committee’s
decision to appoint the SSDI to commence negotiations …for
the
development of the Spring Garden Road”. But the document was
dated
17 July 1991 – one day before the Ministerial Committee made
that
decision!The Ombudsman Commission discovered that, in fact, the
Minister for
Transport had formed a close association with members of the
Chinese
consortium well before the meeting. He had entertained a
delegation from
the consortium, in Port Moresby, only one week before the
Committee’s
decision to favour them (see Chapter 12). 1In light of that evidence, the Ombudsman Commission was
forced to
conclude that the deliberations of the Ministerial Committee
were not a
genuine attempt to objectively evaluate the five short-
listed proposals. -
Page 129 of 397
-
[11.19] MR TEMO’S RESPONSE
When we suggested in our preliminary report that Mr Temo had
improperly arranged the selection of the Chinese consortium,
he
responded in the following terms:Chapter 11
118
“Most of the companies that showed or expressed interest either did
not
understand the terms of reference of the project or did not bother
to re-check
with the Committee or Departments of Transport or Works.As you can see in NEC decision or purpose of the NEC submission No.
14/90
it was the wish of the NEC to speed up the project. That is why the
NEC
submission’s purpose was to bypass normal tender procedures in order
to speed
up the project to be completed in time for the SP Games. Also there
was a
criticism against me in NEC or Parliament every time there was a
traffic
problem along Sir Hubert Murray Highway even by public what are you
doing
Mr Chairman or Mr Minister for Transport.While I was being pressured by the public NEC and Parliament I had
to
negotiate with any of these companies that showed interest as a
Chairman of
Committees I was left to look like a fool if I did not report back
to NEC with
a positive report I would have failed my duty and I was scared I
could loose
my job.No companies complained because it was a new concept proposed by
Barclay
Bros. before my time. I had to carry on from that initiative. It has
been a very -
Page 130 of 397
-
tough job trying to get the best companies to do the job.
Some companies responded again when it was convenient to them. We
had to
follow them because PNG does not have the resources in monetary and
manpower.The companies that came up with fancy proposals and sort of got in
touch with
my office or the Secretary’s office kept getting our attention.At least I was given a responsibility to present to NEC. I did not
discriminate
other companies against that showed interest It was a mere who comes
first
with the best proposal for PNG.I have a feeling that the Chinese companies were not consortium but
they were
selling their information from one company to another.The Department was very uncooperative to me or NEC.
I, Mr Temo was not hiding any transactions from the Department. I
always
notified of the progress that is why I have them all information. I
therefore
regardless whether I had meeting or not prior to not really relevant
in the
situation of this new confused situation as there was no better
proposals and
interest shown other than that of the Chinese.All the time the Department was aware I did not organise any secret
de–11c an
my mine was dear all the time.” [EXHIBIT 257, page 2]Chapter 11
119
[11.20] CONCLUSION AS TO THE DELIBERATIONS OF THE MINISTERIAL
COMMITTEE -
Page 131 of 397
-
With due respect to Mr Temo, he has not satisfactorily
answered our
criticism of the way in which the Chinese consortium
was favoured by the
Ministerial Committee. We conclude that he convened the
meeting of the
Ministerial Committee for the purpose of facilitating
the Chinese consortium
selected by himself to undertake the project.The closeness of the relationship between Mr Temo and
the Chinese
consortium is explored further in the next chapter.* * * * * * * * * *
Chapter 11
120
12. THE RELATIONSHIP BETWEEN THE CHINESE
CONSORTIUM AND THE MINISTER FOR TRANSPORT -
Page 132 of 397
-
[12.1] A MATTER OF CONCERN
The manner in which the Chinese consortium was chosen by the
Ministerial Committee was a matter of concern to the
Ombudsman
Commission.We therefore wanted to find out who was actually behind the
proposal of
the “Second Surveying and Designing Institute, Ministry of
Railways,
People’s Republic of China”. We were also interested to know
whether the
Minister for Transport had any particular association with
those negotiating
on behalf of the Chinese.WHO WAS IN THE CHINESE CONSORTIUM?
[12.2] KEY PARTIES IN THE PROPOSAL INVOLVING THE SECOND SURVEYING
AND DESIGNING INSTITUTEMr Leo Moore of Taiwan
Our investigations revealed that a key person was Mr Leo
Moore, a citizen
of the Republic of China (Taiwan). Mr Moore is a businessman,
with
interests in the Taiwanese fishing industry, who had made a
number of
visits to Papua New Guinea during 1991 and 1992.Chapter 12
121
Mr Moore was called to give evidence under oath on several occasions
in
the course of this investigation. We formed the view that he was a
co-
operative and reliable witness. His evidence shed considerable light
on
the events leading to the selection of the Chinese consortium.Outlet Year Ltd and Mr Leung Keung of Hong Kong
Mr Moore stated that he had first become interested in Papua New
Guinea
in September 1990, after a meeting in Taiwan with another -
Page 133 of 397
-
businessman,
Mr Leung Keuno (hereafter referred to as Mr Leung).. Mr Leung is the
head of a Hong Kong-based company known as Outlet Year Ltd, which
was supposedly considering making large investments in Papua New
Guinea. The meeting between Mr Moore and Mr Leung was arranged by
Mr To Ken Chung (Mr Moore’s godfather and Mr Leung’s close friend)
and Mr Stephen Zohr (one of Mr Moore’s business advisers).At that meeting it was agreed that an invitation would be extended
to a
group of government officials from Papua New Guinea to come to
Taiwan
to discuss business opportunities in Papua New Guinea.Business relationship between Outlet Year Ltd and the SSDI
Mr Moore explained that Outlet Year Ltd had business connections
with
a number of government authorities in the Peoples’ Republic of China
(ie
mainland China); one of them being the Second Surveying and
Designing
Institute (SSDI).The SSDI is a civil engineering agency involved in design and
construction
of railways and highways. Mr Moore supplied the Ombudsman
Commission with a brochure describing its activities. [EXHIBIT 102A]Cnapter 12
122
Mr Moore explained that, as a result of overtures made by Mr
Leung, the
SSDI had contacted Mr Moore on 27 January 1991. In a one page
facsimile transmission, a representative of the SSDI
indicated that they
were a very strong and influential government company in
China and that
they were keen to go into business with Mr Leung and Mr Moore
for the
purpose of building a freeway in Port Moresby, which they had
been
informed about by Mr Leung. [EXHIBIT 53]OVERSEAS TRIP PAID FOR BY CHINESE CONSORTIUM
[12.3] VISIT TO TAIWAN AND HONG KONG BY PAPUA NEW GUINEA
-
Page 134 of 397
-
PARLIAMENTARIANS IN FEBRUARY 1991: A MATTER OF CONCERN
Mr Moore testified that on 6 February 1991 he purchased four
return
tickets from Port Moresby to Hong Kong, which were later
picked up at
the Cathay Pacific office in Port Moresby.After being invited to Taiwan and Hong Kong, a “delegation”
from Papua
New Guinea arrived in Taipei on 8 February 1991. The
delegation
comprised:the Minister for Transport, Mr Anthony Temo;
the Member for Gulf Province, Mr Aaron Noaio;
the Member for Sohe Open, Mr David Beu; and
Chapter 12
a member of the Official Personal Staff of the
Minister for
Fisheries & Marine Resources (who at that time was the
Deputy Prime Minister Mr Akoka Doi) Mr Chris Maravis.The Ombudsman Commission interviewed Mr David Beu in
connection
with this trip and the evidence he gave corroborated that
given by Mr
Moore.[12.4] STATUS OF THE PNG DELEGATION
Before we address the events that transpired during and after
the trip,
there is one important matter to emphasise: the Papua New
Guinea
“delegation” had no official status. Although the members of
the group
were, in a sense, representing the Government of Papua New
Guinea, the
delegation was privately sponsored. All the expenses,
including airfares,
accommodation and meals, were paid for either by Mr Leo Moore
or
Outlet Year Ltd. -
Page 135 of 397
-
[12.5] PRIVATELY SPONSORED OVERSEAS TRIPS CAN BE UNLAWFUL
It is important for all leaders of Papua New Guinea who
contemplate
privately sponsored trips to bear in mind that it is a
requirement of the
Leadership Code that permission from the Ombudsman Commission
be
obtained before accepting the benefits of such a trip.This is a principle of Papua New Guinea law that should also
be
considered by any person or company thinking about offering
such a trip
to a leader.Chapter 12
124
[12.6] THE MINISTER ALLOWED HIMSELF TO BE ENTERTAINED BY ONE OF
THE COMPANIES BIDDING FOR THE PROJECT AT THE SAME TIME HE
WAS PREPARING THE SHORTLISTThe Ombudsman Commission is concerned that the Minister for
Transport,
Mr Temo, made his trip to Taiwan and Hong Kong and involved
himself
in negotiations for the Spring Garden Road/Poreporena Freeway
project
at the same time be was preparing the shortlist of
prospective developers
(see Chapter 9).The Ombudsman Commission emphasised earlier in this report
that
Ministers should not be preparing shortlists for public works
projects. In
this case, the Minister for Transport was not only preparing
the shortlist,
he was, at the same time, allowing himself to be wined and
dined
overseas, at the expense of one of the companies interested
in getting the
contract for construction of the freeway.When this sort of thing happens, it is very difficult to
conclude that the
decision-making process was legitimate, fair and proper.It is also difficult to say there was no bribery or
corruption. -
Page 136 of 397
-
[127] THE MINISTER FOR TRANSPORTS DEFENCE
When we suggested in our preliminary report that it was wrong
of Mr
Temo to make an overseas trip, paid for by one of the
companies bidding
for the project, at the same time he was preparing a
shortlist of
prospective developers, he denied any impropriety. He said he
did not
realise it was a privately sponsored trip until after he
accepted the
invitation to go to Hong Kong:Chapter 12
125
“The trip to Taiwan and Hong Kong was organised by a Chris
Maravis in Mr
Akoka Dors office. Mr Doi was the Deputy Prime Minister so I took
it that
I was going on an official trip. later I realised that it was a
PAP fishing trip
paid by Mr Leo Moore and some fishing people.While in Taiwan and Hong Kong as I was not Minister for Fisheries
so I was
asked about Transport Projects and I said we have a 10 year plan
that need to
be completed. However, we did not have finance and manpower it
was paid
by Mr Leo Moore not short listed company.I did not prepare the final short list.
While in Hong Kong I told the company representative to let the
Prime
Minister, Minister for Finance and the other senior ministers
know of their
investment proposal in PNG.According to me I did not hide anything and I told them, if you
want to invest
for the trip and accommodation while in Taiwan and Hong Kong. I
did this
after learning that it was a PAP fishing trip. Therefore, I -
Page 137 of 397
-
notified the
Ombudsman in writing about who was paying for the trip and
accommodation
while in Taiwan and Hong Kong. I did this after learning it was a
PAP fishing
trip.” [F.XHIBIT 257, page 3]The Ombudsman Commission, with respect, does not consider Mr Temo’s
explanation to be satisfactory. We find it difficult to believe that
a Ministerof the State would legitimately travel overseas without knowing what
the
purpose of the trip was.As to the claim that he advised the Ombudsman Commission of the trip
and who was paying for it, we refer to a letter dated 28 March 1991
received by the Commission from Mr Temo:Mr Temo stated:
‘Thank you for your very helpful Leadership Manual received
today. I note
that I must declare to the Commission every time I leave for
overseas be it
official or unofficiaLI therefore wish to inform the Commission that from the 22
February, 1991 until
4 March, I was on an official visit paid for by M.T.L
Organisation. This trip
was approved by the National Government to lead a delegation to
Taiwan.’
[EXHIBIT 68B]Chapter 12
126
[12.8] POOR ADMINISTRATION BY THE MINISTER FOR TRANSPORTOne thing is certain: irrespective of whether Ministers and
other
Government officials breach the Leadership Code when they -
Page 138 of 397
-
accept
benefits such as free travel, free accommodation and gifts
from foreign
enterprises, it is a very bad administrative practice.It undermines the integrity of the decision-making processes
of
Government. It creates the impression that to get Government
approval for
a project in Papua New Guinea, it is necessary to be on
friendly terms
with the right Minister. It attracts the wrong sort of
foreign investors to
Papua New Guinea. It creates a bad image of Papua New Guinea.If this sort of administrative practice continues, instead of
honest and
genuine investors coming to our country, we will be overrun
by fly-by-
night operators, only too willing to bypass normal procedures
in the quest
for easy money for themselves and not for the People of Papua
New
Guinea. Papua New Guinea has had enough of them already.Since it is not in the best interests of the People of Papua
New Guinea
and our country, such practices must be stopped at all costs.[12.9] WHAT HAPPENED DURING THE TRIP TO TAIWAN AND HONG KONG?
Mr Moore testified that Messrs Temo, Noaio, Beu and Maravis
spent three
days in Taipei, followed by four days in Hong Kong.Three days in Taipei
In Taipei, the members of the PNG “delegation” were
entertained by Mr
Moore.Chapter 12
127
Mr Moore testified that during this visit there was a lot
of talk about road
projects, particularly “the 8.8 km road in Port Moresby”,
as well as other
investment opportunities in Papua New Guinea. The Papua
New Guinea
people described their country as a good place to invest –
particularly in -
Page 139 of 397
-
mining, oil, fishery and forestry projects – but they said
the road network
was not very good and that is why Papua New Guinea is a
poor country.Mr Moore told the Minister for Transport he would like to
come to Papua
New Guinea and see the country for himself.
Four days in Hong KongAfter spending three days in Taiwan the group from Papua
New Guinea
travelled to Hong Kong, leaving Mr Moore behind. Mr Moore
stated that
throughout their stay in Hong Kong, the group from Papua
New Guinea
was looked after by Mr Leung of Outlet Year Ltd. He said
that, as it was
Chinese New Year, much of the time was taken up in social
activities and
the group from Papua New Guinea was housed at the Sheraton
Hotel.It was during this visit to Hong Kong that Mr Temo, in his
capacity as
Minister for Transport, signed a quite extraordinary
document: a
“memorandum of agreement” for the construction of the
Southern
Highlands-Kikori Road. [EXHIBIT 58][12.10] THE MEMORANDUM OF AGREEMENT FOR THE CONSTRUCTION OF
THE SOUTHERN HIGHLANDS – GULF ROADThe Minister for Transport, Mr Temo, signed this agreement
in Hong Kong
on 12 February 1991, on behalf of “the Ministry of
Transport, National
Government of Papua New Guinea”. The other signatory was
Mr Leung
Keung, who entered into the agreement on behalf of Outlet
Year Ltd ofChapter 12
128
Hong Kong. The document was witnessed by Mr Aaron Noaio, the
Member for Gulf Province and Mr To Ken Chung (Mr Leo Moore’s
godfather). -
Page 140 of 397
-
Terms of the agreement for the construction of the Southern
Highlands
Gulf RoadThe terms of this agreement, which appeared under the letterhead of
Outlet Year Ltd, were as follows:‘MEMORANDUM OF AGREEMENT
‘KNOW ALL MEN BY THESE PRESENTS:
This Memorandum of Agreement is entered into and executed this
12th day of
February, 1991, by and between:Ministry of Transport, National Government of Papua New Guinea
with
principal offices of P.O. Box 457 Konedobu, National Capital
District, Papua
New Guinea represented by Hon. Anthony Temo, Minister for
Transport
(hereinafter referred to as NPG).and
Outlet Year Limited, a duly registered Hong Kong Corporation
with principal
offices at No. 20, HOK Yuen Street, Block FL 3/F Hunghom,
Kowloon, Hong
Kong, herein represented by Mr Leung Keung, Managing Director
(hereinafter
referred to as HK).1NITNESSETH:
WHEREAS, the National Government of Papua New Guinea has fully
authorized NPG to implement an Infrastructure Development PlanWHEREAS, NPG is willing to undertake this job per engineering
details and
specifications, contained in the NPG’s Cost Study (Gulf-Southern
Highlands
Province – ERAVE to KEREMA [sic]).WHEREAS, NPG has found the credentials of HICG to be financially
qualified
and technically capable to execute this project in a manner
consistent with the
technical standards set forth by engineering standards. -
Page 141 of 397
-
WHEREAS, HEW has offered to undertake construction of this
project.NOW, THEREFORE, for and in consideration of the above premises
and of the
mutual covenants heretofor set forth, the parties have agreed,
as they hereby
agree, on the following terms and conditions:Chapter 12
129
1. PROJECT
NAME Southern Highlands Kikori Road
LOCATION From ERAVE to KIKORI
SPECIFICATION AND INSPECTION
Per Cost Study (Gulf-Southern
Highlands Province – ERAVE to KEREMA)DURATIONFrom May 1st, 1991 to May 1st, 1993.
BONUS AND PENALTY.2. CONTRACT PRICE : HKG shall submit within 60 days after
signing of this Memorandum a price, to
be forwarded to and acceptable to PNG.3. PAYMENT Payment plan to be negotiated between
PNG and HKG on an equitable and
acceptable basis to both parties4. PERFORMANCE Upon signing of Contract by both parties
BOND MG shall provide to PNG a
Performance Bond in the form of cash,
bank guarantee or other form of
guarantee acceptable to PNG, for an
amount not less than 10% of the Contract
value, to warrant the performance of
EKG’s obligation under the Contract
(Gulf-Southern Highland Province –
ERAVE TO KEREMA). This -
Page 142 of 397
-
Performance Bond shall be returned
HKG without interest, when HKG shall
have fulfilled its obligations under the
Contract.5. FORCE MAJEURE HKG is not responsible for delay or non-
performance of its contractual obligation
to construct, caused by war, blockade,
revolution, insurrection, civil commotion,
riots, mobilization, strikes, Act of God,
plague, or other epidemic, fire, flood,
action or acts of government or public
enemy.Chapter 12
130
6_ CANCELLATION & : PNG may cancel the Contract, and
ALTERATION OF confiscate the Performance Bond,
if
CONTRACT IIKG is unable to deliver in
accordance
with the stipulated time schedule
or
breath of Contract.Postponement or alteration of the
Contract if required, should be
agreed
by both parties in writing.IN WITNESS WHEREOF, the parties hereto have hereunto
affixed their
signatures at Hong Kong this 12th day of February
1991.MINISTRY OF TRANSPORT
[signed]
-
Page 143 of 397
-
HON. ANTHONY TEMO
MINISTER FOR TRANSPORTWITNESS: MEMBER OF PARLIAMENT
[signed]
HON. AARON NOAIO
MP For Gulf ProvinceFor and on behalf of
OUTLET YEAR LIMITED
[signed]
Authorized Signature
LEUNG KEUNG
MANAGING DIRECTORWITNESS:
[signed]
TO KEN CHUNG” [EXHIBIT 58][12.11] THE AGREEMENT OF 12 FEBRUARY 1991 DID NOT MAKE SENSE
Any person with a basic knowledge of contracts and the
English language
would realise that this document is very poorly drafted. The
grammar is
atrocious and, in places, the document just does not make
sense. ForChapter 12
131
instanLe though the subject of the agreement is described
in Clause 1 as
“Southern Highlands Kikori Road from Erave to Kikori”,
there are three sai
other references in the document to the “Erave to Kerema”
Cost Study or
Contract. -
Page 144 of 397
-
1111
The Ombudsman Commission is left wondering whether the
parties to this
agreement actually knew what they were agreeing to. In
view of this, it is
very doubtful whether the agreement could have ever been
regarded as
valid or enforceable.But that does not, in our view, excuse the Minister for
Transport for his
actions in signing this agreement.[12.12] THE PROPRIETY OF THE MINISTER FOR TRANSPORTS ACTIONS
In the opinion of the Ombudsman Commission, it is very
embarrassing for
our country when persons holding official positions sign
documents as
amateurish as the agreement for the construction of the
Southern
Highlands-Kikori Road. It is terrible administration for
any office-holder,
particularly a Minister of the State, to unilaterally
decide to enter into such
agreements.The Ombudsman Commission believes that whenever any
Minister goes
overseas to engage in negotiations on behalf of Papua New
Guinea, he
should be accompanied by at least one senior Departmental
adviser. If
that had happened in this case, we have no doubt the
Minister for
Transport would have been advised not to sign the
agreement for the
construction of the Southern Highlands-Guff Road.Having said that, the Ombudsman Commission still finds it
remarkable
that, during the course of being entertained by foreign
businessmen, andChapter 12
132
while outside Papua New Guinea, the Minister for Transport
-
Page 145 of 397
-
would have
signed an agreement for the carrying out of an extremely
important
national road project without the advice or knowledge of the
Department
of Transport or the Government he was supposed to be
representing.This sort of thing simply should not happen. It raises
questions of legal
authority and breeds the atmosphere and environment ripe for
bribery
and corruption.[12.13j COULD THE MINISTER’S ACTIONS BE JUSTIFIED?
During the course of this investigation, the Ombudsman
Commission
questioned the former Minister for Transport on his actions.
He agreed hehad been to Hong Kong and signed the Memorandum of
Agreement. In
his view, however, he had done nothing improper. His
explanation wasthat it was not intended to be a binding document:
“While in Hong Kong I signed a couple of pages
documents as memorandum
of understanding. This a Chinese Government policy that
before they leave
to go out of R.O. China it is a mandatory that they
must have some form of
agreement of some sort so they be allowed to leave
their country. They had
no choice but to show their Government information why
they were leaving
for PNG. I was authorised by NEC to negotiate on Burns
Peak Road.Therefore, I had some authority to negotiate not make a
decision. The
Department was made known as usual.”
[EXHIBIT 257, pages 3-4] -
Page 146 of 397
-
In the opinion of the Ombudsman Commission, that is not a
satisfactory
explanation.A Minister should not sign any document which purports to
bind himself
or his Department or the Government of Papua New Guinea to
any course
of action unless he has been expressly and lawfully
authorised to do so.
LChapter 12
133
There is no evidence, as Mr Temo claims, that he was
authorised by theNational Executive Council to conduct any negotiations.
Nor is there anyevidence he advised the Department of Transport what he
was doing.The Secretary for Transport’s evidence was to the
contrary. 11The Minister for Transport had no authorisation to conduct
negotiations 11concerning the Southern Highlands-Gulf Road or the Spring
GardenRoad/Poreporena Freeway project. He had no right to sign
this -
Page 147 of 397
-
document He signed it without the advice or knowledge of
hisDepartment or the National Executive Council. tt was very
wrong of him tosign it.
[12.14] OTHER EVIDENCE OF OUTLET YEAR LTD’S INTEREST IN PAPUA NEW
GUINEA
a
Mr Leo Moore’s oral evidence of Outlet Year Ltd’s interest
in Papua NewGuinea is corroborated by three documents that the
Ombudsman111
Commission has obtained:a
(i) A letter from Outlet Year Ltd. dated 12 February
1991, to the thenPrime Minister. Mr Rabbie Namaliu. The letter states:
‘Your Excellency:
-
Page 148 of 397
-
A delegation from your Government headed by
Hon. Anthony Temo,
Minister for Transport, approached our Company
seeking funds and
technical assistance to develop – an
infrastructure Development Plan –
in your country Papua New Guinea. We are
interested to invest up to
US Dollars 5 billion in Papua N. G.As per our meetings, [with Mr Terns)] we wish
to design and build
Southern Highlands ICikori Road and Burns Peak
Road in Port Moresby.
We shall build these roads under a Turnkey
arrangement, which means
we shall supply manpower as well as financing.
111Should your Government endorse this idea,
please send me an
invitation so our delegation consisting of the
undersigned and Mr
Steven Zohr and Mr Leo Moore, could assist your
Country in the
nearest future.Chapter 12
1111
134
We are taking this as a matter of urgency and priority,
and hope to
meet you personally.Respectfully yours,
[signed]
LEUNG ICEUNG
MANAGING DIRECTOR” -
Page 149 of 397
-
This letter was marked:
“c.c. His Excl. Ted Biro [sic], Deputy Prime Minister
His Excl. Sir Michael T. Samare, [sic], Foreign Minister
His Excl. Hon. Paul Bora [sic], Finance Minister
His Excl. Hon Anthony Temo, Minister for Transport’.
[EXHIBIT 57](ii) A letter from Outlet Year Ltd dated 13 February 1991 to Mr
Temo
(also addressed to Deputy Prime Minister Mr Ted Diro, who was
described as the Acting Transport Minister).This letter was headed “Application for pre-qualification of
Southern
Highlands Kikori Road’ and states:“We wish to design and construct Southern Highlands/
Kikori Road in
Port Moresby [sic] under a Turnkey arrangements which
means we will
supply manpower and finance’. [EXHIBIT 59](iii) Another letter from Outlet Year Ltd dated 13 February 1991 to
Mr
Temo (also addressed to Mr Diro).This letter was headed “Application for Pre-qualification of
Bums
Peak Road” and states:‘We wish to design and construct Burns Peak Road in Port
Moresby
under a Turnkey arrangements which means we will supply
manpower
and finance”. [EXHIBIT 60]Chapter 12
-
Page 150 of 397
-
135
[1215] THE TRIP TO TAIWAN AND HONG KONG WAS A VERY BAD PIECE OF
ADMINISTRATIONThe three letters from Outlet Year Ltd were written at the
time of the
Minister for Transport’s visit to Hong Kong. When the
letters are
considered, together with the signing of the “Memorandum
of Agreement”
for the Southern Highlands-Gulf road, they show that, by
shortlisting Outlet
Year Ltd, the Minister had given that company favoured
treatment.It would not be unreasonable for any person knowing these
facts to
wonder whether the Minister’s actions were a result of his
trip to Hong
Kong and Taiwan.The Minister had compromised his own impartiality by
allowing his airfares
and accommodation to be paid by foreign enterprises at a
crucial time in
the decision-making process.By taking it upon himself to become actively involved in
the selection of a
contractor for the Spring Garden Road/Poreporena Freeway
project the
Minister had a duty, as a matter of administration, to be
totally impartial in
his evaluation of the competing proposals. Not only that,
he had to be
seen to be totally impartial and objective.The Minister for Transport failed, in our view, to fulfil
this basic
administrative duty. The trip to Taiwan and Hong Kong and
the signing a
of the agreement on 12 February 1991 was a very bad piece
of
administration. -
Page 151 of 397
-
Chapter 12
[12.16] THE FINANCIAL STATUS OF OUTLET YEAR LTD136
The three Outlet Year Ltd letters referred to
earlier give the impression
that the company is large and influential, with
huge financial resources at
its disposal. Mr Leo Moore’s evidence, however,
suggests that this was far
from being the case.Mr Moore testified that Outlet Year Ltd was quite
a small company which
simply did not have the sort of money to invest in
Papua New Guinea it
made out it had. He said this had first been
brought to his attention in a
facsimile message received on 27 March 1991 from a
business adviser, Mr
Stephen Zohr. [EXHIBIT 68]Mr Zohr was concerned about the uncertain
financial background of Outlet
Year Ltd and advised Mr Moore to be cautious in
making any decisions
about investing in Papua New Guinea.[12.17] OUTLET YEAR LTD HAD NO EXPERTISE IN ROAD PROJECTS
AND NO
EXPERIENCE IN PAPUA NEW GUINEAMr Moore further testified that Mr Leung, of
Outlet Year Ltd, had realised,
soon after he wrote those letters, that his
company would find it very
difficult to raise the finances necessary to
undertake projects such as
Spring Garden Road and the Southern Highlands-Gulf
Road. Mr Moore
stated that the Minister for Transport, in all of
his negotiations, had insisted
on a 10% performance bond being given to the
Government of Papua -
Page 152 of 397
-
New Guinea.
Nevertheless, Outlet Year Ltd continued to be
involved in the negotiations,
at least until July 1991. And it was not until
September 1991 that the
company formally dropped out of the negotiations
(see Chapter 13).Chapter 12
137
The Ombudsman Commission was unable to question Mr Leung in
the
course of this investigation. However, on the basis of
evidence available,
we are satisfied that Outlet Year Ltd was quite a small
company with no
expertise in road construction or design and no prior
experience in Papua
New Guinea.THE MINISTER FO9 TRANSPORT AND MR LEO MOORE
[12.18] MR LEO MOORE’S FIRST VISIT TO PAPUA NEW GUINEA
Mr Moore first came to Papua New Guinea in May 1991. He was
accompanied by his wife, Ida Moore, and Mr Leung of Outlet
Year Ltd.
They were met at Jacksons Airport by the four men who formed
the
delegation to Taiwan and Hong Kong in February 1991. Mr
Moore said
that on the second day of their visit, they had a meeting
with the Minister
for Transport to discuss the Spring Garden Road project. The
cost was
estimated to be US$50 million.The Minister wanted the Outlet Year consortium to build the
road first and
to pay them 5 to 10 years later. But Mr Leung was not very
interested.
In fact, he went home early, while Mr and Mrs Moore stayed
behind for
another week. During this time, the Minister introduced Mr
Moore to the
then Deputy Prime Minister and Minister for Fisheries and
Marine -
Page 153 of 397
-
Resources, Mr Akoka Doi, and various other investment
projects were
discussed.Chapter 12
138
[12.19] MINISTER FOR TRANSPORT APPEALS FOR LOAN FUNDS ON BEHALF
OF PAPUA NEW GUINEABefore he returned to Hong Kong, Mr Moore was handed a
letter from the
Minister, under Ministry of Transport letterhead, in
which he asked Mr
Moore to arrange a loan to develop Papua New Guinea’s
“ten year
development plan”. The Ombudsman Commission obtained a
copy of this
letter. It is dated 24 May 1991 and reads as follows:“Mr Leo Moore,
Papua New Guinea is a Country, full of all Natural
Resources renewable and
non renewable.At this stage Papua New Guinea requires Financial
assistance badly.Our Economy will pick up in 1993 onwards.
Until then Papua New Guinea requires at least US$50
million dollars in
infrastructure development in the next five (5)
years from 1992 or sooner the
better.Should you require my department’s ten (10) year
development plan I will bring
it with me.By this letter I am appealing on behalf of PNG
Government that you arrange
for a loan in kind or cash to develop and implement
our ten (10) year -
Page 154 of 397
-
development plan.
Should you arrange for same, please try to make the
loan finance cheaper than
Asian Development bank and World Bank.I thank you and your group in advance, with kind
regards.[Signed)
ANTHONY TEMO
Minister for Transport” [EXHIBIT 871The purpose of this letter was to enable Mr Moore to go
back to Taiwan
with some proof he had negotiations with a Minister of
the State in Papua
New Guinea.chapter 12
139 II
[12.20] MR MOORE RETURNS TO TAIWAN AND NEGOTIATES DIRECTLY WITH
THE SSDIMr Moore testified that, on his return to Taiwan in May
1991, he contacted
Mr Leung in Hong Kong and told him that, despite Mr Leung’s
reservations, he was still very keen to see the Port Moresby
road project
go ahead, with the assistance of the SSDI.Mr Moore then started (with Mr Leung’s knowledge) to
negotiate directly
with Mr Lee Chong Chan, who was the link-man between the
SSDI and
the Government in Bejing. These negotiations resulted in the
Bejing
Government approving a visit to Port Moresby by
representatives of the
SSDI in July 1991.[12.21] ANOTHER VISIT TO HONG KONG BY THE MINISTER FOR TRANSPORT
-
Page 155 of 397
-
Prior to the visit to Port Moresby by the SSDI observation
group, the
Minister for Transport made another unofficial trip to Hong
Kong, at Mr
Leo Moore’s expense.This visit took place between 7 and 14 June 1991. The
Minister was
accompanied by his wife, whose airfare was paid for by Mr
Leo Moore;
the Minister for Transport had his own airfare on this
occasion. The
Minister and his wife again stayed at the Sheraton Hotel and
all their
expenses in Hong Kong, including meals and accommodation,
were paid
for by Mr Leo Moore.Chapter 12
140
[12.22] MINISTER FOR TRANSPORT HOLDS PRIVATE DISCUSSIONS WITH
TOPBAY INVESTMENT LTD IN HONG KONGDuring this visit to Hong Kong, the Minister for Transport
met with Mr Leo
Moore and six representatives of a Hong Kong-based company
called
Topbay Investment Ltd.Mr Moore testified they had discussed the Spring Garden Road
project for
almost two days. Mr Moore arranged the meeting himself. By
this stage,
he had formed the view that Outlet Year Ltd may not have the
ability to
undertake the Spring Garden Road project. He had had
previous business
dealings with Topbay Investment Ltd and saw them as a good
substitute
for Outlet Year Ltd.The Ombudsman Commission asked Mr Moore whether Topbay
Investment Ltd had any experience in road construction or
design: they
did not. The company had never done any business in Papua
New
Guinea and none of the company’s principals had ever been to -
Page 156 of 397
-
Papua
New Guinea.[12.23] EVIDENCE OF THE MINISTER FOR TRANSPORT’S PRIVATE
DISCUSSIONS IN HONG KONGIn the course of this investigation the Ombudsman Commission
obtained
from Mr Temo, a copy of a letter from Topbay Investment Ltd
addressed
to the Secretary for Transport, dated 14 June 1991. The
letter reads:Chapter 12
141
“My Dear Secretary,
Re: Burns Peak Freeway
Please enclose our proposal as requested.
We would like to show our interest to support
funding this Freeway project
subject to all details of construction plan will be
released to us as soon as
possible.Funding [illegible] US$50,000,000.00 (US Dollars,
Fifty Million) will be available
on receipt of our acceptance notification from PNG
Government.Final terms and condition to be discussed on
acceptances of our proposaLNote: The Company has changed from Outlet Year
Company to Topbay
Investment Ltd.
Thank you and we are waiting your favourable reply.Yours sincerely,
[Signed]
W.C. Dave Kwok
Group General Manager”
[EXHIBIT 89] -
Page 157 of 397
-
The date of this letter coincides with the date of the
Minister’s visit to
Hong Kong, which the Commission has confirmed by checking
the
Minister’s passport.We are satisfied, therefore, that the evidence given by Mr
Leo Moore as
to the Minister’s visit to Hong Kong between 7 and 14 June
1991 is true
and correct.[1224] WRONG CONDUCT BY THE MINISTER FOR TRANSPORT
We have emphasised how important it is for Ministers of
the State not to
go on privately sponsored overseas trips, especially when
they are
provided by foreign enterprises which may expect to reap
rewards by
showing hospitality to a Minister.Chapter 12
111
142
In our preliminary report, we suggested it was wrong for Mr
Temo to
make this second trip to Hong Kong. His response was as
follows:“I met the expenses for my second trip to Hong Kong,my
wife’s expenses were
paid for by Mrs L Moore and were on a family business
trip.
While there I may have talked to somebody about Burns -
Page 158 of 397
-
Peak as a total 10 year
plan. However, the trip was for my private co. business
and I have also advised
the Ombudsman Commission about that trip.” [EXHIBIT 257,
page 4]Mr Temo’s excuse that he was on a family business trip is
not considered
acceptable. As the Minister who had assumed primary
responsibility for
the Spring Garden Road/Poreporena Freeway project, he
compromised
his impartiality by accepting the benefits associated with
this trip from an
associate of one of the companies bidding for the project.
There is also
no evidence that the Department of Transport knew anything
about the
trip or the negotiations the Minister had with Topbay
Investment Ltd.In the circumstances, it was wrong of Mr Temo to conduct
these
negotiations. It was another very bad piece of
administration.CHINESE CONSORTIUM VISITS PORT MORESBY
[12.25] SSDI VISITS PORT MORESBY IN JULY 1991
An observation group from the Second Surveying & Designing
Institute
visited Port Moresby from 6 to 10 July 1991 – just a week
before the
Ministerial Committee decided to favour their proposal. The
group, which
consisted of about seven engineers, was led by Mr Sun Young
Hse, who
described himself as the “Executive Director on behalf of
the Observation
Group of the Second Surveying and Designing Institute
Ministry of
Railways”. [EXHIBITS 95, 96, 102B]. -
Page 159 of 397
-
Chapter 12
143
Mr Moore, his wife Ida Moore, Mr Leung and Mr Leung’s son
also
travelled to Port Moresby for the occasion. Mr Moore said
that his group
and the SSDI group were met at the Port Moresby Travelodge
Hotel by
the Minister and they spent considerable time inspecting the
route of the
Spring Garden Road/Poreporena Freeway project.12.26] CONFUSING ASPECTS OF THE OBSERVATION GROUP’S VISIT
The Ombudsman Commission wonders why Mr Leung of Outlet Year
Ltd
would have made this trip to Port Moresby, in view of Mr
Moore’s
evidence that Mr Leung had already realised his company
didn’t have the
financial capability to undertake the project. There are also
other aspects
of the SSDI’s visit that the Ombudsman Commission finds very
confusing:Evidence obtained by the Commission suggests that
another
agreement was signed by the Minister for Transport
during
the visit of the Chinese consortium. However, no such
agreement appears in the files of the Department of
Transport.We are also confused by the fact that two different
proposals
for the design, finance and construction of the freeway
appear to have been submitted around this time on
behalf
of the Chinese consortium.Chapter 12
-
Page 160 of 397
-
144
[12.27] WERE ANY AGREEMENTS SIGNED DURING THE VISIT BY THE
CHINESE CONSORTIUM?Mr Leo Moore testified that during the July 1991 visit by
the Chinese
consortium, the Minister for Transport signed a document,
about two or
three pages in length, which summarised the financial
terms on which the
Government of PNG would engage the consortium.The document was also signed by Mr Zhu Chuanhua, a member
of the
SSDI observation group. [A copy of a business card in the
name of this
person is located in the Department of Transport’s files:
EXHIBIT 102B]According to Mr Moore, the signing of this agreement took
place at the
Port Moresby Travelodge Hotel.Mr Moore described this document as a “pre-agreement”. The
Ombudsman Commission has tried unsuccessfully to obtain a
copy of it.
The document is not in the Department of Transport’s
files. But, there is
a reference to it in a letter to the Minister for
Transport from the China
Huashi Enterprises Corporation dated 6 September 1991.This letter reads:
Your Excellency,
Attached please find a CERTIFICATE issued by Bank of
China Chengdu
Branch, which we hope will provide you with a brief
description of our firm’s
financial status. We, China Huashi Enterprises Corp,
(CHECO) joint with the
Second Surveying & Designing Institute, Ministry -
Page 161 of 397
-
Railways are very willing
and fully capable to undertake the surveying,
designing and construction of the
proposed Spring Garden Road Link projectIn order to release current traffic congestion as
soon as possible based on
suggestion made by observation group of the Second
Surveying & Designing
Institute, Ministry of Railways, the proposed road
will be constructed in
following stages.Chapter 12
145
1. completion of engineering survey, design
and geological work of above
road project;construction of the first of a twin tunnel
through the Burns Peak;3. construction of the missing sections (i.e.
nonexisting sections) along the
proposed route from Moresby Harbour in
Konedobu to Jackson Airport;4. construction of the second of the twin
tunnel and upgrading the
existing road to 4-lane highway.If you agree the above-mentioned arrangement in
principle, we intend to sign
a main contract of contracting the Spring Garden
Road Link project with you
based on the Pre-agreement signed by you and Mr
Zhu Chuanhua in P.N.G.
And then to sign execution sub-project contract
stage by stage, and provide you
Bank Guarantee according to the stipulization of
sub-project contractPlease do not hesitate to contact us should you
desire more information about -
Page 162 of 397
-
our firm or clarification of the points in this
letter.With best regards.
Yours sincerely,
Liu Shouning Mau Shesheng
Deputy General Manager Second Surveying
& Des-
China Huashi Enterprises Corp. igning
Institute, Ministry
of
Railways.” [11XIIIBTY 106][12.28] WHAT IS THE CHINA HUASHI ENTERPRISES CORPORATION?
Mr Leo Moore stated that this was another agency of the
Peoples’Republic of China – a Government company closely linked
with the SSDI.In Mr Moore’s view it was not unusual that the letter
of 6 September 1991had come from it, rather than the SSDI, because the
SSDI is not itselfauthorised to enter into contracts outside China. Only
a company such asthe China Huashi Enterprises Corporation can do this,
he said.Chapter 12
146
-
Page 163 of 397
-
[12.29] THE MINISTER HAD SIGNED A PRE-AGREEMENT
The letter of 6 September 1991 confirms Mr Moore’s evidence
as to the
signing of some form of “pre-agreement” by the Minister for
Transport
during the visit of the SSDI in July 1991.When we made this finding in our preliminary report, it was
not disputed
by Mr Temo.In the opinion of the Ombudsman Commission it was wrong of
Mr Temo
to sign any “pre-agreement’. He had no authorisation from
the National
Executive Council to conduct negotiations, let alone sign an
agreement.
Even the so-called Ministerial Committee on Spring Garden
Road had not
authorised its signing. The Minister signed the agreement
without the
knowledge or advice of his Department.CONFUSION CAUSED BY LODGMENT OF DIFFERENT PROPOSALS
[12.30] WHAT PROPOSALS WERE ACTUALLY SUBMITTED TO THE
DEPARTMENT OF TRANSPORT DURING THE COURSE OF THE SSDI’S
VISIT TO PORT MORESBY?As we noted in Chapter 11, it has been impossible to
precisely ascertain
which proposals were considered by the Ministerial Committee
when it
decided that the project be awarded to the Chinese
consortium. Most of
the proposals were lost after they were left in the Minister
for Transport’s
office, and the Department of Transport did not keep copies
of them.Chapter 12
147
The confusion was made worse by our discovery of two
different
proposals on behalf of the Chinese consortium. -
Page 164 of 397
-
Of course, it must be appreciated that whenever the term
“Chinese
consortium” is used in this report there is bound to be some
confusion.
This cannot be avoided because the composition of the
consortium kept
changing.Even with the benefit of hindsight it has been very
difficult to ascertain
which companies comprised the consortium at different times.
Nevertheless, it is appropriate to always refer to the loose
grouping of
companies and individuals as ‘the Chinese consortium”
because, despite
frequent changes in its composition, it usually had some
common
elements, viz the SSDI and Mr Leo Moore.[12.31] THE PROPOSAL BY OUTLET YEAR LTD AND THE SSDI
The files of the Department of Transport show a joint
proposal being
made by Outlet Year Ltd and the SSDI. The proposal was
submitted
under cover of a letter on SSDI letterhead addressed to the
Secretary for
Transport.This letter is undated. Also, there is no date-received
stamp on it, which
makes it doubly difficult to determine when it was
submitted. [EXHIBIT 95]In the course of his interrogation by the Ombudsman
Commission, Mr Leo
Moore indicated that this letter had been typed on 8 or 9
July 1991 at the
Port Moresby Travelodge Hotel. It is poorly written and
difficult to
understand. It reads:Chapter 12
148
“Dear Sir,
OBSERVATION REPORT (Draft)
-
Page 165 of 397
-
ON A PROPOSED FREEWAY PROJECT FROM PORT
MORESBY TO JACKSON’S AIRPORT IN PNGIt is really a pleasure to send you the Observation Report
(Draft) on a proposed
freeway project from Port Moresby to Jackson’s Airport in PNG.
After having
received your invitation letter and scrutinizing all relevant
documents available,
we, the Second Surveying and Designing Institute, Ministry of
Railways P.ILC,
immediately sent a observation group to your beautiful Country,
(4 Senior
Engineers and a Senior economist), together with Mr Leung Keung
(Managing
Director of Outlet Year Limited) and his partly. From July 6,
arriving day, to
July 10, we have made a on-the-spot investigation to the
proposed freeway
project. The Observation Report (draft) is attached to the
Financial Proposal.The total project including the tunnel could cost almost US$50
million are
included. We believe it is unwise at this stage because the
traffic lights can
function just as effectively, but off cause it is negotiable.Hence, your government gives the approval of the construction
of this project
at a total cost of US$50 million which will become a loan to
the Government
in principle with the following Principal terms and conditions.Borrow: The Independent State of PNG on behalf of the
Spring Garden Toll Road Corporation.
Lender, The Bank of China and our Corporation
Maturity: 10 years
Grace Period: 3 years (including construction period)
Amount: US$50 million (approx K million)
Interest Rate: Nil
Commitment Fee: Nil
Management Fee: Nil
Performance Bond 10% to be issue by the Bank of China.We hope all these reports and conditions for the funding are
acceptable for
your requirement.With Best Regards.
Yours faithfully
[Signed]
MOORE’S INVESTMENT GROUP
Sun Young HSE (Executive Director) -
Page 166 of 397
-
On Behalf of
Observation Group of
The Second Surveying and Designing
Institute
Ministry of Railways.” [palIBIT 95]This undated letter was accompanied by an “Observation Report’. It
states:Chapter 12
149
“This proposal has been prepared in response to an
invitation from the
Department of Transport to Outlet Year Ltd to submit
a proposal for the
development of the Spring Garden Road through BOT
system…Outlet Year Ltd
in joint partnership with the Ministry of Railways of
People’s Republic of
China will assume full responsibility to the
Department of Transport for the
successfully completion of the required services from
planning, design,
financing and implementation.” [EXHIBIT 951Curiously, most of this twenty-eight page “observation
report’ was almost
exactly the same (i.e. word-for-word) as another document
the
Ombudsman Commission obtained during the investigation.
This other
document is entitled “Spring Garden Road through BOT
System Technical
Proposal Submitted by Topbay Investment Limited Kowloon
Hong Kong
June 1991”. [EXHIBIT 91][12,32] THE PROPOSAL BY TOPBAY INVESTMENT LTD
-
Page 167 of 397
-
The “Technical Proposal” in the name of Topbay Investment
Ltd is not in
the files of the Department of Transport. The Ombudsman
Commission
was not aware of its existence until it was produced under
summons by
Mr Temo. Although the greater part of this document
[EXHIBIT 91] is
exactly the same as the “Observation Report’ submitted by
Outlet Year Ltd
[EXHIBIT 95] there are significant differences between the
two documents.[12.33] DIFFERENCES BETWEEN TOPBAY PROPOSAL AND THE OUTLET YEAR
PROPOSAL
11The most obvious difference is in the identity of the
proponents. Whereas
the “Observation Report” in the possession of the
Department of Transport
refers to Outlet Year Ltd and the SSDI, the document we
obtained from
the Minister for Transport states, in the corresponding
paragraphs:Chapter 12
150
“This proposal has been prepared in response to an
invitation from the
Department of Transport to Topbay Investmented [sic] to
submit a proposal for
the development of the Spring Garden Road through the
BOT system… Topbay
Investmented [sic] in joint partnership with the
Ministry of Foreign Economic
Relations and Trade of the People’s Republic of China
will assume full
responsibility to the Department of Transport for the
successfully completion
of the required services from planning, design,
financing and implementation.”
[EXHIBIT 91] -
Page 168 of 397
-
It will be observed that not only is there a different Hong
Kong -based
company referred to here, there is also a different agency
of the Chinese
Government: the Ministry of Foreign Economic Relations and
Trade, rather
than the Ministry of Railways. And at another point in the
Topbay
Investment Ltd document, there is a reference to yet another
mysterious
entity called the “China Guangzhou International Economic
and Technical
Co-operation Company”. [EXHIBIT 91, third last page]The “Financial Proposals” included in the two documents are
also different.
[Compare EXHIBIT 95, folios 96-101 with the last 3 pages of
EXHIBIT 91.]However, the Topbay and Outlet Year proposals do have some
things in
common. They are equally vague and poorly drafted and they
both
contain bald assumptions about involvement of Motu-Koita
landowners in
the project. They both assume (alarmingly) that as part of
the deal, the
Chinese consortium will be awarded contracts for other major
road
projects in Papua New Guinea.[12.34] THE MYSTERY SURROUNDING THE TWO DIFFERENT PROPOSALS ON
BEHALF OF THE CHINESE CONSORTIUM IS A MATTER OF SERIOUS
CONCERNAlthough the bulk of the two proposals was exactly the same,
they were
in fact two separate documents. The Ombudsman Commission is
mystified
and seriously concerned by the fact that only one of the
proposals was
in the possession of the Department of Transport.Chapter 12
-
Page 169 of 397
-
151
It is also a mystery why the Topbay Investment Ltd Technical
Proposal
was linked with a Ministry of the Chinese Government different to
the one
which had consistently been referred to in earlier documentation.Even after closely examining the files of the Department of
Transport and
questioning two of the key persons in the negotiations at length
(i.e. the
Minister for Transport and Mr Leo Moore) it is impossible for us to
say
exactly what negotiations had taken place, when they took place and
with
whom.The mystery surrounding these two proposals is a small indication of
how
unprofessionally the whole negotiating process was being handled. tt
was
nothing short of a farce.The sad thing is that a group of well-intentioned foreign
businessmen and
representatives of the Government of the People’s Republic of China,
were
being given false expectations by a Minister of the State.The Minister was acting without the advice of his Department and had
assumed far too much control over a decision-making process that
should
have been carried out objectively and fairly by other bodies using
the
normal and lawful procedures under the Public Finances (Man -gement)
Act and other laws regulating public works projects (see Part Ill of
this
report).Chapter 12
152
-
Page 170 of 397
-
[12.35] WHAT IMPRESSION WAS GIVEN TO THE CHINESE CONSORTIUM BY
THE END OF THEIR VISIT IN JULY 1991?The Ombudsman Commission has no doubt that the observation
group
of the SSDI left Port Moresby at the end of their visit in
July 1991 with the
firm belief that, subject to confirmation of financing
arrangements such as
the 10% performance bond, they had “won” the contract for
the Spring
Garden Road/Poreporena Freeway project.This is evident from the undated letter to the Secretary for
Transport which
the SSDI delivered just before its departure. It stated:“Hence, your government gives the approval of the
construction of this project
at a total cost of US$50 million…”. [EXHIBIT 95, page
1]The letter to the Minister for Transport from the China
Huashi Enterprises
Corporation of 6 September 1991 was in similar terms:“If you agree the above-mentioned arrangement in
principle, we intend to sign
a main contract of contracting the Spring Garden Road
Link project with you
based on the Pre-Agreement signed by you and Mr Zhu
Chuanhua in PNG.”.
[EXHIBIT 106, page 2]The Ombudsman Commission questioned Mr Leo Moore as to his
view of
the situation at the end of the observation group’s visit.
He testified that
the group appreciated the Minister’s decision had to be
ratified by the
National Executive Council. But they understood this to be
only a formality.
The Minister had told them he foresaw no problems. As long
as they
could arrange for a bank guarantee of the performance bond,
the final
contract would be signed. -
Page 171 of 397
-
Chapter 12
153
IMPROPER RELATIONSHIP BETWEEN THE MINISTER AND THE CHINESE
CONSORTIUM[12.36] SUMMARY OF THE RELATIONSHIP BETWEEN THE MINISTER FOR
TRANSPORT AND THE CHINESE CONSORTIUM PRIOR TO THE
MINISTERIAL COMMITTEE MEETING OF 18 JULY 1991In light of the evidence outlined above, the Ombudsman
Commission is
satisfied that, prior to the meeting of the Ministerial
Committee on 18 July
1991, the Minister for Transport had formed a very close
association with
members of the Chinese consortium.In particular we draw attention to the following
unsatisfactory aspects of
that relationship:1. The Minister had twice been on all-expenses-paid
overseas trips to
personally negotiate deals concerning the Spring Garden
Road/Poreporena Freeway project and other national road
projects.
Both trips were paid for by one of the key persons
involved in the
bid by the Chinese consortium.2. On the first of these trips, the Minister signed a
contract for
construction of the Southern Highlands-Kikori Road with
a company
that was part of the Chinese consortium. He did this
without
authorisation and without the advice or knowledge of the
Department of Transport.3. The first trip took place at the same time the Minister
himself was
preparing the shortlist for the Spring Garden Road/ -
Page 172 of 397
-
Poreporena
Freeway project.Chapter 12
154
4. The Minister invited representatives of the Chinese
consortium to
Port Moresby on two separate occasions before the Ministerial
Committee (which he chaired) made its decision on which
consortium to favour. On both occasions the Minister engaged
in
detailed negotiations concerning the Spring Garden
Road/Poreporena Freeway project, as well as other national
road
projects.5. On the second visit to Port Moresby by the Chinese
consortium, the
Minister signed a “pre-agreement” and gave the clear
impression
that, subject to finance, they had won the contract for the
Spring
Garden Road/Poreporena Freeway project.6. Furthermore, the Minister had formed a personal friendship
with one
of the key persons involved in the Chinese bid, Mr Leo Moore.
This
friendship was strengthened in the second half of 1991: the
Minister had another visit to Hong Kong paid for by Mr Moore
and
the Minister went into business with Mr Moore.By forming this association with the Chinese consortium and entering
into
private negotiations without consulting the Department of Transport
before
the Ministerial Committee met on 18 July 1991 and before the matter
was
considered by the National Executive Council, the Minister for
Transport,
Mr Temo, had transformed the decision-making process for the Spring
Garden Road/Poreporena Freeway project into a sham.* * * * * * * * * *
Chapter 12
-
Page 173 of 397
-
155
13. FURTHER CHANGE IN COMPOSITION OF THE
CHINESE CONSORTIUM: SEPTEMBER 1991[13.1] THE NEGOTIATING PATTERN IN THE FIRST HALF OF 1991
During the first half of 1991 the Minister for Transport
had been negotiating
with a number of different companies and individuals, in
relation to the
Spring Garden Road/Poreporena Freeway project. In
particular, the
Minister had been negotiating with:Mr Leo Moore;
the Second Surveying and Designing Institute,
represented
by Mr Sun Young Hse; andOutlet Year Ltd, represented by Mr Leung
Keung.[13.2] WHO ELSE FORMED ‘THE CHINESE CONSORTIUM’?
However, these were not the only parties that formed,
what the
Ombudsman Commission has termed in this report, “the
Chinese
consortium”. The following parties were also, at
different times, involved:Topbay Investment Ltd: a Hong Kong-based
company. The
proposal endorsed by the Ministerial
Committee on Spring
Garden Road was actually in the name of this -
Page 174 of 397
-
company.
[EXHIBIT 99, at page 13]. However, the
company had never
conducted business in PNG and the principals
of the
company had never been to PNG.Chapter 13
156
China Guangzhou International Economic and Technical
Cooperation Company and Ministry of Foreign Economic
Relations and Trade of the Peoples’ Republic of China:
referred to as joint partners in the Technical Proposal of
Topbay Investment Ltd. [EXHIBIT 91] Their role in the
negotiations is a complete mystery.China Ample Development Lid: also linked with Topbay
Investment Ltd and the SSDI in the summary of proposals
contained in the draft NEC Submission of July 1991. [EXHIBIT
99, at page 13, discussed in Chapter 8] However, the name
does not appear in any other documents in the records of
the Department of Transport obtained by the for the purposes
of this investigation. Its role in the negotiations is also a
complete mystery.Moore’s Investment Group: a name used in two letters written
by Mr Sun of the SSDI. It appears to be a name of
convenience only, used to describe the consortium, of which
the SSDI was an integral part.
[EXHIBITS 95, 110]China Huashi Enterprises Corporation: from the evidence of
Mr Moore, this Chinese Government company is closely linked
with the SSDI. It was apparently intended that it would
formally enter into the contract for the Spring Garden project
Road/Poreporena Freeway with the PNG Government.Chapter 13
157
-
Page 175 of 397
-
[13.3] THE ROLE OF MR LEO MOORE
Mr Leo Moore’s role in the negotiations was not well defined,
but it is clear
he had an active and vested interest in everything that was
happening in
relation to the project.The Ombudsman Commission does not suggest there was anything
illegal
or improper in Mr Moore’s involvement. He was, however, at
all times, an
important link between the Minister for Transport and the
other parties
involved.[13.4] ANOTHER HONG KONG COMPANY JOINS THE CONSORTIUM
During September 1991 there was a significant change in the
negotiating
pattern: another Hong Kong-based company was appointed to act
on
behalf of the SSDI. This company was called Tunson
Engineering Co Ltd.News of this change of plan was conveyed to Mr Temo in a
letter from the
SSDI dated 28 September 1991. The letter reads as follows:‘Dear Mr. Temo:
Our second surveying & designing Institute, ministry of
Railways Prc. Now
has pass the burns peak project to our contractor in Hong
Kong under the
name of Tnnson Engineering Co. Ltd, 1-3/F, 21-23 Han Wong
Road, Kowloon
City, Kowloon Hong Kong. Who has the experience of
contracting the Mordem
constructions both in peoples republic of China as well as
Hong Kong. -
Page 176 of 397
-
Chapter 13
158
It would be much appreciated if your department will change
your record
Accordingly.Yours faithfully
[Signed]
MOORS INVESTMENT GROUP
SUN YOUNG HSE (EXECUTIVE DIRECTOR)
ON BEHALF OF OBSERVATION GROUP OF THE
SECOND SURVEYING AND DESIGNING
INSTITUTE, MINISTRY OF RAILWAYS [sic]. [EXHIBIT 110]The Minister for Transport made a handwritten note at the bottom of
the
letter, dated 10.10.91.“SECRETARY
PLEASE TAKE NOTE OF ABOVE CHANGE AS I HAVE NO OBJECTION AS
LONG AS THEY ARE MEETING OUR CRITERIA.
ALSO PREPARE THE FINAL SUBMISSION TO CABINET. WORK CLOSELY
WITH FINANCE DEPARTMENT.
THANK YOU
A. TEMO”. [EXHIBIT 110]In his response to the Ombudsman Commission’s preliminary report, Mr
Temo also claimed that he had asked the Secretary for Transport to
do
a company search on all the companies that put in a bid: -
Page 177 of 397
-
even instructed the Secretary to send someone to Hong Kong
to find out in
case we mislead the NEC.” [EXHIBIT 257, page 4]We have been unable to find any evidence to corroborate this claim.
Chapter 13
159
[13.5] SIGNIFICANCE OF CHANGE IN COMPOSITION OF THE CONSORTIUM
Tunson Engineering Co Ltd was at least the third Hong
Kong-based
company to join the Chinese consortium in less than six
months. In the
opinion of the Ombudsman Commission, the fact there had
been yet
another change in the composition of the consortium should
have been
a matter of great concern, both to the Minister for
Transport and the
Department of Transport.During the course of this investigation, the Ombudsman
Commission found
it impossible to identify the precise legal relationships
between the various
parties that, at different times, constituted the Chinese
consortium. We are
left to wonder how confusing it must have been at the
time, with
companies such as Outlet Year Ltd, China Ample Development
Ltd and
Topbay Investment Ltd, as well as “Moore’s Investment
Group”, all being
linked with the proposal of the SSDI and various other -
Page 178 of 397
-
agencies of the
Chinese Government.The addition of Tunson Engineering Co Ltd to the
consortium in
September 1991 could only have added to the utter
confusion that any
reasonably cautious administrator would have experienced
at that time.[13.6] THE CONFUSION CAUSED BY A FURTHER CHANGE IN THE
CONSORTIUM SHOULD HAVE LED TO A HALT IN NEGOTIATIONSThere were some obvious questions to ask about the arrival
of Tujison
Engineering Co Ltd:Why was the change in composition of the
consortium
necessary?Chapter 13
160
Were the companies previously in the consortium
disreputable?Did they have financial problems?
If so, what guarantee was there that the same problems
wouldn’t be encountered with this new company?Who was behind Tunson Engineering Co Ltd?
Was it a reputable company?
How long had it been established?
Did it have any experience operating in PNG?
Had any of its principals been to PNG?
What was the company’s asset base?
-
Page 179 of 397
-
Did the company have experience in civil engineering
projects?Was it registered with the National Investment and
Development Authority (NIDA)?It later transpired that the Department of Transport did begin to
ask some
of these questions (see Chapter 15). The Minister’s reaction,
however, was
not the same as the Department’s.Chapter 13
161
[13.7] THE MINISTER’S LACK OF CONCERN WAS IRRESPONSIBLE
The Ombudsman Commission considers that the Minister
for Transport’s
direction to the Secretary of the Department of
Transport on 10 October
1991 to “take note of the change” and the Minister’s
comment that he had
“no objection as long as they are meeting our criteria”
was an ill-
considered, inadequate and reckless response to the
addition of Tunson
Engineering Co Ltd to the Chinese consortium.The Minister for Transport showed a total disregard for
all the normal and
proper legal and administrative procedures regulating
public works projects
in Papua New Guinea.The Minister should have been deeply concerned about
this development.
But he was not concerned. Far from it. As we show in
the next chapter of
this report, only a few days after advising the
Secretary for Transport about
Tunson Engineering Co Ltd, the Minister signed a
contract with that
company for construction of the freeway.* * * * * * * * * *
-
Page 180 of 397
-
Chapter 13
162
14. MINISTER FOR TRANSPORT SIGNS CONTRACT FOR
CONSTRUCTION OF FREEWAY: OCTOBER 1991[14.1] NEGOTIATIONS WITH TUNSON ENGINEERING CO LTD
During October 1991, the Managing Director of Tunson
Engineering Co
Ltd, Mr Siu Chu Yen, visited Port Moresby and had
negotiations with the
Minister for Transport, concerning the Spring Garden Road/
Poreporena
Freeway project.Mr Siu was accompanied by four other Hong Kong businessmen,
as well
as Mr Leo Moore.Mr Moore testified that the Tunson group visited Port Moresby
for one
week and stayed at the Port Moresby Travelodge Hotel. He came
on the
same flight as the Tunson group and returned with them to
Hong Kong
in mid-October 1991.The Ombudsman Commission is satisfied that the negotiations
between the
Minister for Transport and Tunson Engineering Co. Ltd
occurred without
the knowledge of the Secretary for Transport, Mr Amini.[142] RESULT OF NEGOTIATIONS
The result of the negotiations was that, on 15 October 1991,
the Minister
for Transport, purporting to act on behalf of the Department -
Page 181 of 397
-
of Transport,
Chapter 14
163
signed a contract for the construction of the Spring Garden
Road/Poreporena Freeway. The contract was entered into with
Tunson
Engineering Co. Ltd. of Kowloon Hong Kong. [EXHIBIT 115THE CONTRACT OF 15 OCTOBER 1991
[14.3] TERMS OF THE CONTRACT
The contract dated 15 October 1991 is nine pages in length
and is entitled:‘CONTRACT AGREEMENT ■
The agreement for the construction of (Burnspeak-Spring
Garden Road) (from
Port Moresby to Jackson Airport [sic].’
■The document states, amongst other things:
To change the traffic condition from Port Moresby to
Jackson airport, design
the construction of the Spring Garden Road Link project
from Port Moresby to
jacksons Airport in PNG.From June 1991, we have invited by the Ministry of
Transport of PNG to realize
the work and make the agreement as following item.A. This agreement will be signed between the
Transportation of PNG as
Party A and Tunson Engineering Co., Ltd. as Party.B. Project Description:
-
Page 182 of 397
-
Bl(a) The proposed mad link will start from Moresby
Harbour in Konedobu,
along the existing Spring Garden Road crossed the Bums
Peak saddle (by
tunnel) and intersects with Wards, Waigani, Boroko Roads,
and then along the
Geauta Drive Road intersects with Hubert Murray Highway,
finally to Jackson
airport total length 8.8 km.B1(b) Based on the economic Assessment for Spring Garden
Road on Port
Moresby Road needs study and requirements pointed out by
the Department
of Transportation. The main technical standards are as
follows:Chapter 14
164
Length of new mad : 4.6 kilometer
Length of existing mad: 3.5 kilometer
Number of Lanes : 4
Width of each Lanes : 35m
Medium 2m
Width of each pedestrian
(earth surface) (for : 3.5 m
each side, not including
tunnel)
Width of Subgrade 23m
Pavement Bituminous Concret
Including Traffic Sign Board.’
[EXHIBIT 115][14.4] A POORLY DRAFTED AND BARELY INTELLIGIBLE DOCUMENT
This is quite a remarkable document. It purports to be a
contract for
construction of the Spring Garden Road/Poreporena Freeway
project. But -
Page 183 of 397
-
it is so vague and poorly drafted, it is difficult to
believe it was prepared
by anyone with legal qualifications or, indeed, anyone
reasonably fluent in
the English language.Mr Moore testified the contract had been drafted and typed
in a rush, and
was not finished until the early hours of one morning at
the Port Moresby
Travelodge Hotel. This is evident from the quality of the
document.It is riddled with bizarre and barely intelligible terms.
For example, Clause
E quotes a total construction cost of US$49,383,000.00.
Clause F then
states:Not including:
F(1) Unexpected (nn-limited) cost etc.
F(2) The cost for land acquisition and removal of
existing structures,
houses, electrical power cables, underground
pipes and cable etc.Chapter 14
165 1
F(3) Party A shall be responsible for the net profit,
import materials
machinery and daily equipment taxes that can be
omitted.F(4) Changing price for the requirements the money or
other unexpect
cost.
From above F(1) and F(4) mentioned about the price
will be
written in details in construction agreement. -
Page 184 of 397
-
F(5) The construction of channel, drainage, manhole,
traffic lights and
all E & M services works.’
[EXHIBIT 115, page 4]It is stating the obvious to say that many of these
provisions – which
presumably represent additions to the “total construction
cost” – simply defy
comprehension.[14.5] THE MINISTER FOR TRANSPORT AGREED TO AWARD OTHER ROAD
CONTRACTS TO TUNSONAn alarming part of the Contract is Clause G, which relates
to ‘Terms of
Payment”. Its states:“G(1) Party A must pay in U.S. dollars and it must make
promise from bank
guarantee of (The Bank of Papua New Guinea).G(2) Payment to be paid with 10th years including
construction period. Any
default over 10th years % (percent) will be charge per
year.G(3) In the meantime, Part A and Part B intend to sign
other contract.G(4) If Party B sign more than one contract with Part A
(Transportation
Department of Papua New Guinea Government), the
aforesaid item of
G(2) must be voided and payment will according to the
following
payment terms, details as shown on G(7), (8), (9). -
Page 185 of 397
-
Chapter 14
166
G(5) Party B is agree [sic] to sign one more contract for
45 kilometer [sic]
of Roadway with Party A (Minis’ try of Transport) Than
the payment
must be according to the Original Contract.G(6) Furthermore, Party B also intend to sign the another
contract of
construction for 147 kilometer length mad link will
start from Bereina
to Lae and Malalna to Erave with Party A after their
future site
investigation and other preparation works [sic].•
[EXHIBIT 115, page 4]It is apparent from these terms that, in the course of
negotiating
construction of the Spring Garden Road/Poreporena Freeway,
the Minister
for Transport was also negotiating other road projects,
including a road
between Erave, Southern Highlands Province, and Malalaua,
Gulf Province.The Department of Transport was not aware the Minister was
conducting
negotiations for the Erave-Malalaua road. Nor is there
evidence the
Minister was authorised by the National Executive Council to
do so.[14.6] THE SCOPE OF THE PROJECT IN THE CONTRACT OF 15 OCTOBER
1991The scope of the project is very poorly defined in the
contract with Tunson
Engineering Co Ltd.Clause B(1)(a), for example, describes the route of the
proposed road link
in very general terms and describes the total length as 8.8
kilometres.Clause B1(b) then states the length of new road will be 4.6
kilometres, and
the existing road 3.5 kilometres, ie a total of only 8.1
kilometres: 700 -
Page 186 of 397
-
metres of road has disappeared in the space of one paragraph.
Chapter 14
167
Clause B1 (b) further states that there will be one
tunnel, four bridges,sixteen cross road drainages and four junctions, but does
not specifywhere any of them will be.
These are only a few of the many defects in this woefully
inadequatedocument The Ombudsman Commission is at a loss to find
any goodreason why a Minister of the State would have signed it.
[14.7] COULD THE MINISTER’S ACTIONS BE JUSTIFIED?
We emphasised in Chapter 12 that, in the opinion of the
Ombudsman
Commission, it is very wrong for any Minister of the
State to sign contractson behalf of his Department or the Government without
expressauthorisation.
In this case, the Minister for Transport repeated the
mistake he made eight -
Page 187 of 397
-
months earlier in Hong Kong: he signed a contract for a
mufti-million kinatransport project of national significance, without the
authorisation of theNational Executive Council and without the knowledge or
advice of hisDepartment This was unlawful and wrong, and was not in
the bestinterests of the Government and the State.
[14.8] WAS THE CONTRACT MERELY A *MEMORANDUM OF
UNDERSTANDING’?
The only conceivable way the signing of the contract with
TunsonEngineering Co Ltd could be acceptable is if it were
regarded as merelya record of an “understanding” reached between Mr Temo
and theManaging Director of that company. This was the view
taken by theDepartment of Transport, when it discovered the signing
of the agreement.Chapter 14
168
In his response to our preliminary report, Mr Temo also claimed the
-
Page 188 of 397
-
contract was only meant to be a memorandum of understanding:
The Secretary for Transport or in his absence there was always
someone to
give me advice in fact we had a morning briefing every week on
Burns Peak
and other matters.The contract was a documentation of some sort required by Chinese
Government
before they leave out of China.Because it was mentioned that they did not have office in PNG so
they required
a form and reason paper to show their Government so they could
come again
to PNG many times. This was very important to them as a
requirement.’
[EXHIBIT 257, page 41The Ombudsman Commission regards this as a very charitable
assessment
of the Minister for Transport’s actions, which were wrong and
unacceptable.The document of 15 October 1991 is entitled “Contract Agreement”.
Though it is poorly drafted and barely intelligible, it gives the
appearance –
at first glance – of being intended to be a binding agreement. It
has a
number of specific terms and sets a “total construction cost” of
US$49,383,000.00. The document has been signed and witnessed in a
way
contracts are normally executed.The Ombudsman Commission therefore cannot accept that the “Contract
Agreement” of 15 October 1991 was only intended to be a memorandum
of understanding.Nor do we accept Mr Temo’s spurious claim that it was necessary to
sign
the contract, so that members of the consortium based in the
People’s
Republic of China would be allowed to leave their country. If there
were -
Page 189 of 397
-
such a requirement, then the only proper way to comply with it was
toChapter 14
169
formally advise and liaise with the Chinese Embassy in Port
Moresby.
However, there is no suggestion that that was done.111[14.9] THE DANGERS OF ENTERING INTO UNAUTHORISED AGREEMENTS
WITH FOREIGNERSWe do appreciate that, in his own mind, the Minister for
Transport might
have believed that the contract with Tunson Engineering Co
Ltd was not
enforceable without National Executive Council approval. But
that does not,
in our view, provide an excuse for his actions.When foreign enterprises enter into written agreements with
Ministers, they
expect those agreements to be honoured. If the agreements
are not
honoured, the time and money of the foreign enterprises can
be wasted.
This gives Papua New Guinea a bad name and the investment
climate
becomes uncertain, if not bad. Our image abroad is very
importantForeigners who are not familiar with our laws and our
Constitution won’t
always understand that the Minister they were dealing with
had no authority
to sign the agreement entered into. Nor do they always know
that an
agreement will require the approval of the National
Executive Council or
a Supply and Tenders Board or the Public Works Committee.
This is
especially the case with businessmen from Asia, where
accepted methods
of doing business are often different from those applying in
Papua New
Guinea.In addition to the embarrassment that these *specie’
agreements with -
Page 190 of 397
-
Ministers can cause for the whole Nation when not honoured,
such
agreements create an environment for sweetheart deals,
bribery and
corruption. It is just plain common sense that Ministers –
and any other
persons holding official positions – must not sign these
documents.Chapter 14
170
In the opinion of the Ombudsman Commission it was grossly
irresponsible
of the Minister for Transport to sign the Contract Agreement
with Tunson
Engineering Co Ltd on 15 October 1991.[14.10] REACTION OF THE DEPARTMENT OF TRANSPORT TO THE SIGNING OF
THE CONTRACT WITH TUNSON ENGINEERING CO LTDThe Department of Transport became aware of the contract
with Tunson
soon after it was signed. Not surprisingly, the news that
the Minister had
signed a contract for the building of the freeway without
National Executive
Council approval caused alarm and bewilderment within the
Department.[14.11] MR HITOLO ADVISES MR AMINI ABOUT THE CONTRACT OF 15
OCTOBER 1991In a minute to Secretary Amini dated 17 October 1991, the
Director of the
Policy Secretariat, Mr Hitolo stated:‘… Now I am at a loss, as to how to proceed on this
project because your verbal
instruction which is consistent with the World Bank
advice seem to be in direct -
Page 191 of 397
-
conflict with this signed contract agreement.
I do not know the legality of it but it seems our
procurement procedures are
being short-circuited by the use of the delegated powers
of the NEC in his
capacity as the Chairman of the Special Ministerial
Committee on Spring
Garden Road. Even so, I think there are other legal
aspects like registration
of the company in PNG and also the professional
requirement to practice as
Engineers in PNG needs to be completed…I am trying to get this circulated to the Members of the
Steering Committee
so that we are able to get proper advice as to how to
proceed, because it seems
our Minister is determined to pursue the project with
the Chinese. In other
words, the policy from him is loud and clear as I
interpreted it, but let us make
it our business to get the best and the most cost
effective solution for Papua
New Guinea.’ [EXHIBITS 117,1181Chapter 14
171
[14.12] SECRETARY FOR TRANSPORT ADVISES MINISTER TO EXERCISE
CAUTIONShortly after receiving Mr Hitolo’s advice, Secretary Amini
wrote to the
Minister in the following terms:“My Dear Minister
I have just browse through an agreement on the Bums Peak
project (attached)
which you have signed with the proposed developers. -
Page 192 of 397
-
It comes across to me that it may not be accepted as a
legal binding document
for the following reasons:-As Chairman of the Ministerial Committee, you made
recommendation for the construction contract to be
awarded to
The Second Surveying and Designing Institute,
Ministry of
Railways of China’ but the agreement sign is with
Tunson
Engineering Co. Ltd, Hong Kong a completely new
company;2. It is my understanding that such agreements are
between the
State and the developers, in which case the
Finance Minister
or the Governor General is the one that has the
delegated
powers to sign;3. Some of the conditions and terms are not in the
best interest
of the State. Our Attorney General Department
should review
the document;I am inclined to suggest that perhaps it wads meant to be
a Memorandum of
Understanding, in which case you are right to sign but it
should be made clear
that it is so, and that it has no legal binding on the
State.On these basis, I would advise you strongly that you do
not pursue the
document as an agreement.In this regard, I would suggest that you write to the
developers and advise
them of this position. I have attached a draft letter for
your perusal.In the meantime, I will seek legal advice from the
Attorney General Department
to assist you in dealing with this situation. -
Page 193 of 397
-
ale; tiar 14
172
I am available to discuss this further with you at your
convenience.Yours sincerely
[Signed]
BIC AMINI, CBE
Secretary’ [EXHIBIT 122 ][14.13] PROPRIETY OF THE SECRETARY’S ACTIONS
Like Mr Hitolo’s letter to Mr Amini, Mr Amini’s letter to
the Minister madea number of pertinent points about the propriety of the
Minister’s signingof the contract with Tunson. It is, in our view, quite
proper and necessaryfor the Secretary of a Department to bring such matters to
the attentionof his or her Minister.
Mr Amini deserves praise, at this point, for his prompt
action in advisingthe Minister to write to Tunson and tell them not to rely on
-
Page 194 of 397
-
the contract as
a binding agreement.
There was one very important matter, however, which Mr Amini
neglectedto mention: the signing of the contract was in direct
conflict with the adviceof the World Bank. This had been brought to Mr Amini’s
attention by MrHitolo and Mr Amini should have spelt it out in clear and
unambiguousterms to the Minister.
Only a couple of weeks before the Minister signed the
contract withTunson Engineering Co Ltd, the World Bank had strongly
advised that theSpring Garden Road/Poreporena Freeway project be re-
tendered. Thisdevelopment is documented in Chapter 15.
Chapter 14
173
MINISTER CONTINUES NEGOTIATIONS WITH CHINESE CONSORTIUM
[14.14] FURTHER DIRECT NEGOTIATIONS BETWEEN THE MINISTER FOR
TRANSPORT AND THE SECOND SURVEYING AND DESIGNING
INSTITUTE -
Page 195 of 397
-
Though he signed a contract for construction of the freeway
on 15 October
1991, the Minister for Transport continued to conduct
negotiations with the
Chinese consortium.Letter written on 21 October 1991
On 21 October 1991, the Minister for Transport wrote a
letter to Mr Zhu
Chuanmua, a Senior Engineer with the Second Surveying and
Designing
Institute and a member of the SSDI team that had visited
Port Moresby
three months earlier, in July 1991.It appears the Minister was trying to communicate his
concern about some
of the terms in “the final contract” which, the Minister
says, the SSDI had
sent on 13 and 23 September 1991.The letter reads as follows:
“SUBJECT: REGARDING THE COMMENT OF FINAL CONTRACTS OF
THE FREEWAY PROJECT FROM PORT MORESBY TO
JACKSON AIRPORT (OR) BURNS PEAK PROJECTDEAR MR. ZHU,
I acknowledge in receiving the final contract which your
institute had written
on 13th and 23rd of September 1991 passed thru Mr. Sun
Young Use with
Appreciation. I and my department had review it and would
like to apply as
follow.Chapter 14
174
-
Page 196 of 397
-
According to our Government policy there are four 1/2
pint to be mentioned.1. the total cost of the contraction cannot be over US
$50 millions, and
your cost for the contract which you had put in the
final contract is
over US$64 million dollars, that is more than the
other contractors from
Japan, America, Australia and Hong Kong.2. In regards to the supervision of the project, it
should be supervised by
our transportation department, as discussed in
meetings.3. The systems of the Surveying, and Designing should
be in three systems,
British, Australian, and Papua New Guinean system.According to our policy, before construction our
Government cannot
per any deposit or advance to the contractor, even
Moore’s Investment
Group willing to pay, it would not be accepted,
what our Government
will do, will be seeking our bank to guaranty the
payment thru Bank
of Papua New Guinea accordingly.S. The contract must seek their bank to put up 10%
Performance bond,,
and your bank certificate is not accepted.Your engineer were here in July, and went thru all the
meeting, it seems that
your interpreter had his interpret the whole meaning I
hope your Institute
can re-check and advise as soon as possible, awaiting
for your reply, thanking
you.Yours sincerely
[Signed]
HON. ANTHONY TEMO, MP – Minister for Transport,
Transportation
Department.• [EXHIBIT 123] -
Page 197 of 397
-
[14.15] WHAT DID THE MINISTER MEAN BY THE ‘FINAL CONTRACT’?
It is unclear what the Minister was referring to as “the
final contract whichyour institute had written on 13th and 23rd of September
1991”. There isno contract bearing either of those dates in the files of
the Department ofTransport. Perhaps the Minister was referring to the
observation reportand the financial proposal sent to the Department of
Transport under coverof the undated letter from the SSDI, referred to in Chapter
12 of this report.[EXHIBIT 95]
Chapter 14
175
Perhaps there was a final contract signed with the SSDI,
that the Ministerfor Transport failed to advise anyone else about.
-
Page 198 of 397
-
We have been unable to ascertain what the Minister meant
by “the finalcontract”.
[14.16] SIGNIFICANCE OF THE LETTER OF 21 OCTOBER 1991
Irrespective of whether the Minister had signed a
contract with the SSDI,the significant thing about this letter is that it was
written six days after theMinister signed the contract with Tunson Engineering Co.
Ltd. That is,though he had already signed a contract for construction
of the freewaywith that company, the Minister was continuing to
negotiate the terms ofthe deal with its consortium partner.
[14.17] MR TEMO’S DEFENCE
When we made this finding in our preliminary report, Mr
Temo responded -
Page 199 of 397
-
as follows:
‘NEC had authorised my Ministerial Committee to
negotiate the best deal for
PNG by following special tender procedures. There
was no legal agreement in
place for any company to proceed everyone knew
that.’ [EXHIBIT 257, page 51Mr Temo consistently claimed the National Executive
Council had approved“special procedures” for this project. He suggested he
had beenencouraged to bypass normal tender procedures. If normal
procedureswere followed, he said, the project would have taken too
long to come tofruition. He said he was constantly being harangued in
the Parliamentabout the traffic problems in Port Moresby. Whenever
there was anChapter 14
176
accident on Three Mile Hill, he was blamed. He saw it as his
duty to the
Nation to get the project implemented as soon as possible. -
Page 200 of 397
-
He didn’t
always get the support he should have received from other
members of
the Ministerial Committee on Spring Garden Road or the
Department of
Transport. It was therefore necessary to conduct
negotiations himself.[14.18] Mr TEMO’S EXPLANATION REJECTED
In the opinion of the Ombudsman Commission, none of these
things
satisfactorily explain the Minister’s continuing to
negotiate the terms of the
agreement with the SSDI, when he had signed a contract for
construction
of the freeway just prior to this, with another member of
the SSDI
consortium. His actions could only have caused confusion to
the various
members of the Chinese consortium, if they had known what
the Minister
was doing. It was very bad for the Government and the
country.THE MINISTER FOR TRANSPORT ACTED IRRESPONSIBLY
[14.19] SUMMARY OF DEVELOPMENTS DURING OCTOBER 1991
Prior to October 1991, the Hong Kong-based company known as
Tunson
Engineering Co. Ltd had no involvement in the Spring Garden
Road/Poreporena Freeway project. However, during October
1991,
representatives of that company travelled to Port Moresby to
discuss the
project with the Minister for Transport.Chapter 14
177
Following these discussions the Minister wrongly entered into a
contract
with the company for the construction of the Spring Garden -
Page 201 of 397
-
Road/Poreporena Freeway, without the advice or knowledge of the
Department of Transport.Despite doing this, the Minister continued to negotiate the terms of
the
contract with another member of the Chinese consortium.As a matter of administration, the Minister’s conduct during October
1991
was, in the opinion of the Ombudsman Commission, naive, incompetent
and irresponsible.* * * * * * * * * *
Chapter 14
178
15. ROLE OF THE WORLD BANK IN THE SPRING
GARDEN ROAD/POREPORENA FREEWAY PROJECT[15.1] TWO WORLD BANK MISSIONS
The World Bank has an on-going interest in the development of
Papua
New Guinea’s transport infrastructure. In 1991, at least two
World Bank -
Page 202 of 397
-
Missions visited Port Moresby and made recommendations
concerning the
Spring Garden Road/Poreporena Freeway project.[15.2] THE FIRST MISSION: JUNE 1991
The first Mission was carried out from 21 to 26 June 1991 and
consisted
of Mr Heins Unger, a municipal engineer. The draft Aide
Memoire prepared
following this Mission (we were unable to obtain a final
version of the
document) shows that the Mission met with officials from the
Department
of Transport, the Office of International Development
Assistance and the
National Capital District Commission.The purpose of the Mission was to give advice on a wide range
of World
Bank-sponsored transport projects, one of which was Spring
Garden Road.
The Aide-Memoire dated 26 June 1991 records the following
observations:“The Coffey Geotechnical Investigation of the Spring
Garden Road scheme
was reviewed in summary form by the mission and found to
be thcm3ugh,
comprehensive and clear in its findings and
recommendations…Chapter 15
179
[Regarding] the need of Department of Transport for expert
-
Page 203 of 397
-
advice and
assistance with solicitation, evaluation and negotiation
of private sector BOT
proposals for the construction of the Spring Garden Road
link. In the mission’s
view, short term, intermittent support may be the
preferable option, because
different expertise is needed at the various stages of the
project the costs of the
assistance could also be kept down, since a suitable
source of funding is still
being explored. Further advice will be given from Bank
HQ.” [EXHIBIT 92]It is apparent from this document that the idea of getting
more expert
advisers from the World Bank to assist the Department of
Transport in the
evaluation of proposals for the Spring Garden Road/Poreporena
Freeway
project had been raised.As a consequence, another World Bank Mission was dispatched
to Port
Moresby a few months later.[15.3] THE SECOND MISSION: SEPTEMBER 1991
The second World Bank Mission visited Port Moresby from 24 to
28
September 1991. On this occasion, attention was focused
solely on the
Spring Garden Road/Poreporena Freeway project.The Aide-Memoire of 28 September 1991
The Mission’s findings and recommendations are contained in
an Aide-
Memoire dated 28 September 1991, signed by Ms M C Nguyen, on
behalf
of the World Bank, and Mr Amini, on behalf of the Department
of
Transport. -
Page 204 of 397
-
Chapter 15
180
The Aide Memoire states:
“a) The private sector proposals do not meet the requirements of
the TOR
[i.e. Terms of Reference], including the selected proposal;b) The inability of interested parties to respond adequately to
the request
is in part due to unclear distinction between the concepts
of Build-
Operate-Transfer (BOT) and the turnkey procurement;c) While the economic viability of the project is established,
the financial
plan of the project based on recovery through tolls alone is
unrealistic
and unworkable;d) The untested and novel concept of BOT and toll (in PNG)
prevented
respondents from submitting responsive bids;e) The technic-Al parameters are left unclear as to whether PNG
was
seeking a two or four lane road, one or two tube tunnels,
and whether
road surface would be of compacted gravel or asphalt
concrete, and
whether an open cut or tunnel was desired;f) Land acquisition and environmental impact issues were not
addressed
in the request for proposaL Given the land tenure problems
in PNG
and potential environmental problems if an open cut is
desired,
specifications on these points could help get a more -
Page 205 of 397
-
responsive interest
to the project; andg) Finally, the uncertain environment in PNG for private sector
investments
also contributes to the lack of responsive bids.’
[EXHIBIT 111, at page 1]Other significant findings and recommendations of the World Bank,
recorded under the heading “Retendering of Spring Garden Road”, were
as follows:‘An environmental impact study should be prepared to determine
the
environmental parameters that should be considered in the design
of the link
road- An investigation of the land aquisition in the area to
determine the
degree of difficulty in obtaining the right of way.Following these studies which could be undertaken in three
months, Department
of Transport should issue a new request for proposal (RFP)
including
specifications that would help solicit responsive proposals from
PS [the Private
Sector]…Chapter 15
181
If there is no responsive interest from private
investors after the new tendering,
it is proposed that Department of Transport seeks public
funds for financing the
above project” [EXHIBIT pages 3-41 -
Page 206 of 397
-
[15.4] SUMMARY OF WORLD BANK RECOMMENDATIONS
Put simply, the World Bank was saying that:
The Terms of Reference document prepared by the
Department of Transport in early 1991 was vague and
inadequate (see Chapter 10).If the Government was intent on pursuing private
sector
funding of the Spring Garden Road project, further
studies
would have to be undertaken to address the problem of
financial returns and environmental and land
acquisition
issues.Once these studies were completed – which would take
about three months – it would be necessary to issue a
new
“request for proposal”.If the private sector was still not interested in
funding the
project, the Department of Transport would have to
seek
public funding.In other words, the World Bank was advocating a ” back-to-
the-drawing-
boards” approach: the project should be re-tendered.Chapter 15
182
[15.5] WERE THE WORLD BANK’S RECOMMENDATIONS FOLLOWED?
-
Page 207 of 397
-
The recommendations contained in the Aide-Memoire of 28
September
1991 were completely ignored. No further financial or
environmental studies
were undertaken and the project was not re-tendered.Only a couple of weeks after the Aide-Memoire was delivered,
the Minister
for Transport signed a contract for construction of the
freeway with Tunson
Engineering Co Ltd (see Chapter 14). This contract was not
pursued,
however, and in February 1992, the National Executive Council
approved
the awarding of the project to another company.[15.6] WAS THE MINISTER ADVISED ABOUT THE RECOMMENDATIONS OF THE
WORLD BANK?The Ombudsman Commission asked the Secretary for Transport
whether
the World Bank’s recommendations were brought to the
attention of the
Minister for Transport.His reply was that “any major document is always referred to
the Ministers
for their information”. Thus, the Secretary was saying that
the normal
practice of his Department is to bring such major documents
to the
attention of the Minister.The Secretary also said:
The Minister was aware of the World Bank advice but took
the view that this
was just an advice and not binding on an Independent State
and implied that
NEC has the final say: [EXHIBIT 254, pant 131 -
Page 208 of 397
-
Chapter 15
183
However, the Secretary could not convince us he had
formally briefed the i
Minister on the World Bank’s advice. There is no
documentary evidence
in any of the Department of Transport files that this had
been done.The Minister for Transport, Mr Temo, said he had not seen
the World Bank
report until it was shown to him by the Ombudsman
Commission and that
the Secretary had never mentioned it to him.The Ombudsman Commission is not necessarily concerned
about the
World Bank recommendations not being followed. It was the
prerogative
of the National Government to decide whether or not to
adopt the
recommendations.Our concern is that the Secretary of the Department of
Transport did not
bring the recommendations immediately and formally to the
attention of the
Minister.(15.7] THE IMPORTANCE OF INDEPENDENT ADVICE
The World Bank recommendations were obviously crucial to
the future of
the Spring Garden Road/Poreporena Freeway project. It was
the duty of
the Secretary for Transport to immediately and forcefully
bring them to the
attention of the Minister: The only way this could
properly have been done
was officially, i.e. in writing.The Secretary for Transport failed to do this.
Chapter 15
-
Page 209 of 397
-
184
It is not relevant, in our view, to suggest that the Minister would
have
ignored the World Bank recommendations. In the opinion of the
Ombudsman Commission, it is never an excuse to say that advice was
not
given to a Minister because it was thought, or even known, that the
advice
would not be followed.The integrity and efficiency of our Public Service depends upon
Ministers
being promptly and fearlessly advised of all relevant matters – even
when
the advice is something the Minister does not want to hear. If we
get to
the stage where our Ministers only get the advice that they want to
hear,
we will be in a very sorry state. The professionalism of the Public
Service
will deteriorate.The Ombudsman Commission concludes that the failure of the Secretary
for Transport to formally convey the World Bank recommendations
immediately to the Minister for Transport in late September 1991 was
a
bad piece of administration.* * * * * * * * * *
Chapter 15
185
-
Page 210 of 397
-
16. FATE OF THE POLICY SUBMISSION FAVOURING THE
CHINESE CONSORTIUM: DECEMBER 1991[16.1] BACKGROUND TO NATIONAL EXECUTIVE COUNCIL SUBMISSION OF 17
JULY 1991In July 1991 the Department of Transport had prepared a
Policy
Submission entitled “Financing the Construction of the Spring
Garden
Freeway” (see Chapter 11).This document contained an evaluation of five proposals. It
concluded by
recommending the project be awarded to a Chinese consortium
consisting
of the Second Surveying and Designing Institute of the
People’s Republic
of China and various Hong Kong-based companies.The document was the focus of discussion at the meeting of
the Ministerial
Committee on 18 July 1991. It was used by the Committee as
the basis
for its decision to recommend negotiations be commenced with
the
Chinese consortium. (Though the Minister for Transport had,
on his own
accord, already commenced private negotiations with the
consortium.)In Chapter 11 the Ombudsman Commission criticised that
decision and the
document on which it was based. The method used in the
document to
select the Chinese consortium was vague and unsatisfactory.
There had
not been a genuine attempt to objectively evaluate the five
short-listed
proposals.Chapter 16
186
In this chapter, we trace the fate of the document of 17 July
1991, after its
consideration by the Ministerial Committee. -
Page 211 of 397
-
SUBMISSION FAVOURING THE CHINESE CONSORTIUM FILED IN OCTOBER 1991
[16.2] THE POUCY SUBMISSION DATED 17 JULY 1991 WAS FILED IN THE
NATIONAL EXECUTIVE COUNCIL IN OCTOBER 1991The document considered by the Ministerial Committee was not
amended
following the meeting of 18 July 1991. It was filed in the
National Executive
Council during October 1991.Though there is no record of this in the files of the
Department of
Transport, we are satisfied, after considering the evidence
of the Secretary
for Transport, that the document was filed during October
1991 by the
Head of the Policy Secretariat, Mr Hitolo.[16.3] SECRETARY FOR TRANSPORT CLAIMS THE POUCY SUBMISSION WAS
FILED WITHOUT HIS KNOWLEDGEMr Amini testified that in October 1991 he attended an
International
Maritime Conference in London. He was accompanied by the
Minister for
Transport, the Prime Minister’s personal secretary, the
Principal of the
Madang Nautical College and the First Assistant Secretary in
the Maritime
Division of the Department of Transport, Mr Zurenuoc.Chapter 16
187
Mr Amini said the Minister for Transport was supposed to
present the case
for Papua New Guinea at the Council held in conjunction with
the
conference. However, he claimed the Minister left the
conference early and
returned to Port Moresby via Hong Kong, where he stayed for a
few days.The Ombudsman Commission discovered that on this visit to
Hong Kong –
the Minister’s third in 1991 – he was again accommodated and -
Page 212 of 397
-
entertained
at the expense of members of the Chinese consortium bidding
for the
Spring Garden Road/Poreporena Freeway project.Mr Amini said he was forced to present the case for Papua New
Guinea
at the International Maritime Organisation conference in the
absence of the
Minister for Transport; and the case was lost, Mr Amini said.Mr Amini testified that when he returned from the conference
he discovered
that the Policy Submission dated 17 July 1991 had been filed
in the
National Executive Council in his absence on the direction of
the Minister
for Transport. Mr Amini said he was very annoyed about this,
because the
Submission had not been considered by the Resource Management
Committee. Also, he said, it was wrong for any Policy
Submission to leave
the Department without his approval.[16.4] MR TEMO’S EVIDENCE
When we questioned Mr Temo, his recollection of these events
was less
precise than Mr Amini’s.In his response to our preliminary report, Mr Temo stated:
Chapter 16
188
“The Secretary for Transport
was always aware of this even when he was in
London or USA. His
Department was briefing him all the time. Mr. Amini
knew the progress of such
event. If his Department was aware then Brian
Amini could not deny. He
could not carry the Department with him around.Mr. Amin and all FAS in the
Department were summoned to explain about -
Page 213 of 397
-
the Burns Peak project in
NEC 3 times. Mr. Amini was seen by NEC members
all the time.There was so many different
Chinese companies and when they come to see
me, I do not go and talk
into them in a secret place. I call on the Secretary
and other Department
officials to brief us.I got advice from the
Department before proceeding to do the work of Chairman
of Ministerial Committee.All NEC submissions are
prepared by the Department, checked and signed by
Mr. Brian Amini or his
delegate.I never put in any input in
wording or selection criteria. If a company group
come to me I refer the to
the Department or jointly have a meeting.•
[EXHIBIT 257, page 51Mr Temo also stated that he had, in fact,
presented the papers on behalf
of Papua New Guinea at the International
Maritime Organisation
conference.[16.5] SUMMARY OF CIRCUMSTANCES SURROUNDING FLUNG
OF THE
POUCY SUBMISSION FAVOURING THE CHINESE
CONSORTIUMThe Ombudsman Commission finds the
evidence of the Secretary for
Transport more convincing than that of Mr
Temo. Mr Amini’s evidence as
to the movements of the Minister during
October 1991 is corroborated by
evidence given by Mr Leo Moore, who
entertained the Minister on his
Hong Kong stopover. The Ombudsman
Commission has also examined
the entries appearing in the Minister’s -
Page 214 of 397
-
passport for the relevant period.
Chapter 16
189
We therefore accept Mr Amini’s version of events as correct.
That is:The Policy Submission dated 17 July 1991 was filed in
the
National Executive Council during October 1991.It was filed by Mr Hitolo at the direction of the
Minister for
Transport.It was filed without the knowledge or approval of the
Secretary for Transport.IMPROPRIETY BY MINISTER FOR TRANSPORT
[16.6] MATTERS FOR CONCERN
The Ombudsman Commission shares the concerns raised by the
Secretary
for Transport as to the way in which the Policy Submission
favouring the
Chinese went to the National Executive Council. tt is sound
administrative
practice that, whenever a Minister contemplates making an
important Policy
Submission to the National Executive Council, it should be
presented in
close consultation with the head of his Department.There are also other matters which concern the Ombudsman
Commission
about the filing of this particular Policy Submission.On 5 October 1991 the Minister for Transport had signed a
-
Page 215 of 397
-
contract for the
construction of the freeway with Tunson Engineering Co Ltd of
Hong Kong
(see Chapter 14).Chapter 16
190
So, the impropriety that had developed was this: the Minister
for Transport
was attempting to present a submission to the National
Executive Council,
authorising his Department to commence negotiations with the
Second
Surveying and Designing Institute, when he had already, just
prior to this,
signed a contract with the SSDI’s consortium partner, Tunson
Engineering
Co Ltd, for the construction of the freeway.Not only that, on 21 October 1991 he wrote directly to the
SSDI in China
trying to renegotiate the terms of their financial proposal
(which was
different to the one in the contract he had signed with
Tunson Engineering
Co Ltd).These disturbing developments show how important it is for
normal and
established public tender procedures to be followed in
projects of this
nature.[16.7] THE POLICY SUBMISSION WAS NOT ACCEPTED BY THE NATIONAL
EXECUTIVE COUNCILAs it turned out, the National Executive Council did not get
the opportunity
to debate the Policy Submission favouring the Chinese
consortium. The
Minister’s actions were short-circuited by the diligence of
the Secretary to
the National Executive Council, Mr P M Eka OBE. Mr Eka
rejected the
submission, because proper procedures for filing of National
Executive
Council submissions had not been followed.In a letter to the Secretary for Transport dated 4 December
1991, Mr Eka -
Page 216 of 397
-
advised that he was returning the fifty copies of the Policy
Submission
entitled “Financing the Construction of the Spring Garden
Freeway.
[EXHIBIT 127]Chapter 16
191
Mr Eka rejected the Submission because comments from the
Department
of Finance and Planning and the Department of Attorney-
General had not
been sought. [EXHIBIT 127][16.8] NATIONAL EXECUTIVE COUNCIL PROCEDURES
Chapter 2 of the National Executive Council Submissions
Handbook
prescribes the requirements for presentation of Policy
Submissions.
Paragraph 2.7(d) states:“Comments from the five Central Agencies and all other
Ministries affected by
the Proposal must be included. Particular care should be
taken to ensure that
views of all affected Ministries are obtained in writing
prior to the Submission
being referred to the NEC Secretariat Submissions
requiring views to be sought
in the NEC Meetings are not accepted,’ [E7GIIBIT 1]The “five central agencies” are prescribed in Paragraph 1.14
of the
Handbook. They are:the Department of Attorney-General;
-
Page 217 of 397
-
the Department of Finance and Planning;
the Department of Personnel Management;
the Department of Provincial Affairs; and
the Department of Prime Minister and National
Executive
Council.Chapter 16
192
The Ombudsman Commission notes that Section D of the Policy
Submission of 17 July 1991, under the heading “Views of other
Ministers
Affected”, simply states:°Being sought.• [EXHIBIT 99, at page 7 ]
Clearly, there had been a failure to comply with the proper
NationalExecutive Council’s procedures. We therefore find that the
Secretary to the
National Executive Council acted properly in rejecting the
PolicySubmission.
-
Page 218 of 397
-
SUBMISSION FAVOURING CHINESE CONSORTIUM WAS NOT RE-PRESENTED
[16.9] WHAT HAPPENED TO THE POLICY SUBMISSION AFTER IT WAS
REJECTED BY THE SECRETARY TO THE NATIONAL EXECUTIVE
COUNCIL?Following rejection of the Policy Submission, the Secretary
for Transporttook immediate steps to obtain the views of other Departments.
To hiscredit, he went further than required. In a handwritten note
dated 6
December 1991, addressed to one of his First Assistant
Secretaries, theSecretary issued an instruction in the following terms:
‘As discussed with you 5/12, I’m disappointed that this
paper went through
Minister without my approvaL The procedures required by NEC
mg be done
without exception. All comments from other Departs must be
included esp the
World Bank, DFP, Foreign Affairs, Lands, DOW, PM’s Dept,
Personnel Mgt Dept,
Environment, NCDC, Attorney General, OIDA etc. Urgent
action.’
[EXHIBIT 1271Chapter 16
193
[16.10] CIRCULATION OF THE POLICY SUBMISSION
The Policy Submission of 17 July 1991 was subsequently
circulated to the -
Page 219 of 397
-
Departments specified by Mr Amini, as well as to the
Department of Trade
and Industry. This was done under cover of standard letters
dated 6
December 1991. [EXHIBIT 128][16.11] SLACK RESPONSE BY OTHER DEPARTMENTS, PARTICULARLY FINANCE
AND PLANNINGOnly one of the Departments which had been asked to comment,
did so:
the Department of Trade and Industry. [EXHIBIT 133]This was a disappointing response. In particular, we single
out the
Department of Finance and Planning for its failure to take
the opportunity
to demand more information. The Policy Submission indicated
that the
total cost of the project would be in the vicinity of $US 50
million.
Obviously the financial and budgetary implications were
going to be
enormous.In the opinion of the Ombudsman Commission it was
irresponsible of the
Department of Finance and Planning not to respond to the
Policy
Submission. It is that Department’s responsibility and
therefore should be
its practice to comment on the budgetary implications of all
major projects
undertaken by or on behalf of the State.Chapter 16
194
[16.12] WAS THE POLICY SUBMISSION OF 17.7.91 RE-PRESENTED?
On the surface, the circulation of the Policy Submission to
the other
Departments in December 1991 meant that proper procedures
were being
complied with. But that was not, in fact, the case.The Policy Submission circulated in December 1991 was never
-
Page 220 of 397
-
re-
presented to the National Executive Council. There was
another Policy
Submission presented to the National Executive Council in
February 1992,
resulting in the decision to award the project to Kinhill
Kramer Pty Ltd. But
this Policy Submission was not circulated for the comments
of other
Departments.The February 1992 submission was not the same as the one
circulated in
December 1991. The February 1992 submission differed from
the one
circulated in December 1991 (i.e. the one dated 17 July
1991) in a very
significant way.The February 1992 submission gave a choice between two
proposals: the
Tunson/SSDI proposal and a proposal by Kinhill Kramer. The
submission
which the various Departments were invited to comment on had
unequivocally favoured the SSDI proposal. The name “Tunson”
was not
referred to and the only reference to “Kinhill Kramer” was
as a consortium
partner in an old proposal promoted by Kumagai Gumi.[16.13] MORE MATTERS OF CONCERN
This state of affairs gave rise to some obvious questions:
Chapter 16
195
Why didn’t any of the other Departments get the chance
to
comment on the February 1992 submission?How could a National Executive Council submission
change
so dramatically in a short space of time?Why was Kinhill Kramer permitted to lodge a late
proposal?Why was Kinhill Kramer given equal ranking to the
Chinese -
Page 221 of 397
-
proposal in the 1992 submission, when previously it was
part
of the Kumagai Gumi proposal and ranked number three?
We will address these questions later in this report.* * * * * * * * * *
Chapter 16
196
17. CONCERNS ABOUT CREDENTIALS OF
TUNSON ENGINEERING CO LTD:
DECEMBER 1991 – JANUARY 1992[17.1] DEPARTMENT OF TRANSPORT CONCERNED ABOUT BONA FIDES OF
TUNSON ENGINEERING CO LTDIn December 1991, concerns were being raised within the
Department of
Transport as to the bona fides of the Tunson Engineering Co
Ltd proposal,
especially its financial aspects. These concerns were, of
course, quite
legitimate.Apart from the obvious technical defects in the contract the
Minister had
signed with the company on 15 October 1991 (see Chapter 14)
the
Tunson proposal did not comply with the Terms of Reference
which the
Department of Transport had circulated. The Terms of
Reference had
required the project to be implemented on a Build-Operate- -
Page 222 of 397
-
Transfer basis,
whereas the Tunson contract involved turnkey financing.[1 7 21 THE MOST IMPORTANT CONCERN
Not only that, nobody in the Department of Transport knew
anything about
Tunson Engineering Co Ltd or any of the people involved in
it. Tunson had
never operated in Papua New Guinea before. It was not known
whether
it was a reputable company, whether it had any experience in
design,
financing, construction or management of road projects or
whether it had
sufficient financial resources to undertake a task of the
magnitude of the
Spring Garden Road/Poreporena Freeway project.Chapter 17
197
This alarming situation had arisen because the negotiations
which led to
the contract of 15 October 1991 were conducted secretly by
the Minister
for Transport, Mr Temo.INVESTIGATIONS CARRIED OUT BY THE DEPARTMENT OF TRANSPORT
[17.3] DEPARTMENT OF TRANSPORT CONDUCTS ITS OWN INVESTIGATION
Quite fortuitously, at the time these concerns were being
aired, the
Department of Transport had acquired the services of a
technical adviser
from Hong Kong, Mr Amin Ebrahim, who was engaged from the
consulting organisation Wilbur Smith Associates.The Department had entered into an arrangement with Mr
Ebrahim
whereby he worked in Port Moresby on a fortnight-on-
fortnight-off basis;
at the end of each fortnight, he returned home to Hong Kong.
So, Mr
Ebrahim was requested to conduct inquiries into Tunson
Engineering Co
Ltd on one of his visits to Hong Kong. -
Page 223 of 397
-
[17.4] COMPANY SEARCH OF TUNSON ENGINEERING CO LTD
Mr Ebrahim arranged a company search of Tunson Engineering Co
Ltd
in early January 1992. He also attempted (unsuccessfully) to
arrange a
meeting with the company’s managing director, Mr Siu Chu
Yuen.
[EXHIBIT 131]Chapter 17
198
The company search revealed very little. Mr Ebrahim
discovered the
company had only recently been incorporated (in June 1990)
and all but
one of its 500,000 shares had been allocated to Mr Siu Chu
Yen. However,
the search did not show what the company’s paid-up capital
was. Other
details about the company (eg the state of its bank accounts
and its
balance sheets and other financial statements) were also
unavailable.
[EXHIBIT 130]Consequently, this company search was practically useless.
Tunson
Engineering Co Ltd could well have been a one-man shelf
company, with
a letterhead as its major asset, and the Department of
Transport would not
have known.[17.5] TECHNICAL ADVISER RECOMMENDS RE-TENDERING OF THE PROJECT
When Mr Ebrahim returned to Port Moresby in early January
1992, he
reported his concerns in a brief to the Secretary for
Transport dated 9
January 1992. He gave a detailed analysis of the numerous
defects in the
Tunson contract and recommended that the World Bank’s advice
be
followed, ie that the project be “re-tendered”. [EXHIBIT 132] -
Page 224 of 397
-
This recommendation was not followed. Instead, the Department
of
Transport persisted with the task of trying to find out more
about Tunson
Engineering Co Ltd.Chapter 17
[17.6] DEPARTMENT OF TRANSPORT OFFICERS MEET
REPRESENTATIVES OF199
TUNSON ENGINEERING CO LTD IN PORT MORESBY:
14 JANUARY 1992Since February 1991 (when the Minister for
Transport first went to Taiwan
and Hong Kong) Mr Leo Moore had maintained
a watching brief over all
negotiations concerning the Spring Garden
Road/Poreporena Freeway
project. His role in the project was never
clearly defined. However, from
the oral evidence he gave to the Ombudsman
Commission, it is clear he
had ties with all the various Hong Kong-
based companies that had been
a part of the Chinese consortium. He had an
interest in the outcome of all
negotiations.Mr Moore was regarded by the Department of
Transport as the Port
Moresby representative of Tunson
Engineering Co Ltd, even though the
Department had been advised that Port
Moresby-based consulting
company Tauwala Consultants Pty Ltd had
been appointed by Tunson to
act as their agent. [EXHIBITS 120, 121]When the officers of the Department decided
to intensify their efforts to
check the bona fides of the Tunson
proposal, they decided to interview Mr
Moore. He and his wife were called to a
meeting with Department of
Transport officials in the office of the -
Page 225 of 397
-
Secretary on 14 January 1992. The
meeting was chaired by the Acting Secretary
for Transport, Mr Zurenuoc.[17.7] THE REPRESENTATIVES OF THE CHINESE
CONSORTIUM STILL
BELIEVED IN JANUARY 1992 THAT THE PROJECT
WAS THEIRSThe officers of the Department of Transport
informed Mr and Mrs Moore
of the fundamental problem they saw in the
contract signed by the Minister
for Transport on 15 October 1991: Tunson
Engineering Co Ltd expected
to be paid for building the freeway – but
this had not been budgeted for.Chapter 17
200
It was explained that the project was supposed to be financed
on a Build-
Operate-Transfer basis. The contract did not meet this
requirement. The
Department also interrogated Mr and Mrs Moore on the
background of
Tunson Engineering Co Ltd. They asked the sort of questions
that should
have been asked by the Minister for Transport before he
entered into any
serious negotiations with this company.Following this meeting, the request for more information on
Tunson
Engineering Co Ltd was put in writing. [EXHIBITS 135, 141]In his evidence to the Ombudsman Commission, Mr Leo Moore
said he
was completely taken aback by the attitude of the Department
of Transport
officers at that meeting. As far as he was concerned, the
deal between
Tunson and the Minister for Transport had already been
finalised. He
therefore did not understand why the Department of Transport
was
seeking further details about the company. He was offended by
the
aggressive manner in which questions were put to him and his
wife. -
Page 226 of 397
-
The Ombudsman Commission accepts that this was Mr Moore’s
genuine
reaction to this incident. For many months he had been
involved in
negotiations with the Minister for Transport. He was shocked
to find that
officers in the Minister’s Department would be asking him
detailed
questions about things that were really, as he understood the
situation, the
business of the Minister.[17.8] DID THE DEPARTMENT OF TRANSPORT ACT RESPONSIBLY?
While this may have been an understandable reaction for a
person of Mr
Moore’s background, the Ombudsman Commission does not
criticise the
officers of the Department for their actions. The Acting
Secretary, MrChapter 17
201
Zurenuoc, is to be congratulated for realising the dangerous
situation
created by execution of the contract of 15 October 1991 and
for taking the
initiative and calling the meeting with Mr Moore.The Ombudsman Commission’s only criticism is that this
meeting should
have been called a couple of months earlier, as soon as the
Department
discovered what the Minister had done.[17.9] THE DECISION-MAKING PROCESS HAD BROKEN DOWN
The meeting between the Department of Transport and Mr and
Mrs Moore
gives an indication of the farce that had developed by the
beginning of
1992: the Minister had already signed a contract for the
construction of the
freeway, but three months later his Department was still
trying to find out
whether the proposal was genuine. In the course of doing
that, officers of
the Department were interrogating a foreigner who – though
having a -
Page 227 of 397
-
vested interest in the project – had no formal connection
with the company
*selected” by the Minister, and who was totally confused and
offended by
their attitude.This was all happening just six weeks before the National
Executive
Council decided to award the contract for the construction of
the freeway
to a completely different company!The decision-making process had become a complete shambles
and it is
an embarrassment to our country that this sort of thing was
allowed to
happen, because the Minister for Transport took it upon
himself to handle,
negotiate and sign agreements without consulting his
Department.Chapter 17
202
[17.10] DEPARTMENT OF TRANSPORT SEEKS HELP FROM OTHER
DEPARTMENTSDespite the wide circulation of the draft submission
“Financing the
Construction of the Spring Garden Freeway”, the only
Department to
respond to the request for comments was the Department of
Trade and
Industry (see Chapter 16).As stated earlier, it is disappointing that other
Departments did not
comment on the draft submission. It is most irresponsible of
those
Departments, especially the “key” Departments.It is also disappointing that, when the Department of
Transport formally
sought advice from two Departments on the contract the
Minister for
Transport signed with Tunson, no useful assistance was
given. -
Page 228 of 397
-
OTHER DEPARTMENTS GUILTY OF DEFECTIVE ADMINISTRATION
[17.11] ADVICE SOUGHT FROM DEPARTMENT OF FINANCE AND PLANNING
AND DEPARTMENT OF ATTORNEY-GENERALOn 15 January 1992, the Acting Secretary, Mr Zurenuoc, wrote
to the
Office of International Development Agency in the Department
of Finance
and Planning. He enclosed a copy of the Tunson contract and
asked that
it be reviewed, so the Department of Transport would be in a
better
position to advise the Minister for Transport. [EXHIBIT 137]Chapter 17
203
On the same day, Mr Zurenuoc wrote a similar letter to the
Department of
Attorney-General. [EXHIBIT 138]Mr Zurenuoc advised the Minister for Transport that he had
requested this
advice. [EXHIBIT 136][17.12] INADEQUATE RESPONSE TO REQUESTS FOR ADVICE
Each of these letters requesting advice should have sent
alarm bells
ringing within the Departments which received them. it
should have been
obvious to anyone with basic Knowledge of public works
contracts and the
requirements of public sector financing that the contract
with Tunson
Engineering Co Ltd was seriously and dangerously flawed and
that the
Minister for Transport had no right to sign it.Any Department reasonably alert to its responsibilities to
the State, would
have realised – by a quick examination of the contract –
that something
was very, very wrong.Unfortunately, however, the responses were inadequate.
-
Page 229 of 397
-
[17.13] DEPARTMENT OF FINANCE AND PLANNING GUILTY OF DEFECTIVE
ADMINISTRATIONThe Director of the Office of International Development
Agency in the
Department of Finance and Planning, Mr Pepson, responded in
a letter
dated 13 February 1992:Chapter 17 ■
204
“I regret to inform you that we are not in a position to
comment as we
note the Minister has already signed the contract and
also we are not
in the full picture on the status of the
proposaL” [EXHIBIT 146This was a poor response by the Department of Finance and
Planning.
The Minister for Transport obviously had no right to sign
the contract with
Tunson Engineering Co Ltd. Furthermore, the contract
purported to
commit the State to a minimum outlay of $US 50 million,
which was
entirely un-budgeted expenditure.By failing to offer any advice, the Department of Finance
and Planning was
acting in dereliction of its duties to the State and
therefore was guilty of
defective administration.[17.14] DEPARTMENT OF ATTORNEY-GENERAL ALSO GUILTY OF DEFECTIVE
ADMINISTRATIONThe only response made by the Department of Attorney-General
was in a
letter dated 30 January 1992, from Senior Legal C Mr Singin.
He -
Page 230 of 397
-
acknowledged receipt of the contract documents and said the
Department’s comments would be forwarded in due course. But
they
never were. [EXHIBIT 144]The Acting State Solicitor, Mr Z Gelu, conceded to the
Ombudsman
Commission that written advice was not given to the
Department of
Transport about the Tunson contract. In his response to our
preliminary
report, Mr Gelu said:‘Though I failed to offer written advice, my officers
namely Messrs. Robert
‘rung and Sumasy Singin provided verbal advice to the
Department of
Transport during their consultative meeting. The officers
were representing
the Department of Attorney General in these
meetings.’ [EXHIBIT 2621Chapter 17
205
We do not regard this as an adequate explanation. The
meetings referred
to by Mr Gelu were the meetings held in March and April 1992
during the
course of negotiations with Kinhill Kramer. Our concern,
however, at this
point, is with the period in January 1992.In January 1992, the Department of Attorney-General was
given notice of
a contract that was manifestly flawed, which contained
provisions
purporting to bind the State to large and long term
financial commitments
concerning a number of road projects of national
significance and which
had been signed by a Minister clearly acting contrary to the
Public
Finances (Management) Act.In these circumstances, there was a duty to act immediately
and give
written advice to the Department of Transport on what it -
Page 231 of 397
-
should do. The
Department of Attorney-General failed to discharge this duty
and was
guilty of defective administration.[17.15] SUMMARY OF THE DEPARTMENT OF TRANSPORTS ATTEMPTS TO
INVESTIGATE CREDENTIALS OF TUNSON ENGINEERING CO LTDDuring December 1991 and January 1992 the Department of
Transport
tried in vain to find out essential background information
on the company
with which the Minister for Transport had signed a contract
for
construction of the freeway.Assistance was also sought from the Department of Finance
and Planning
and the Department of Attorney-General. Both of these
Departments failed
in their duty to offer assistance, even though it was clear
that the Minister
for Transport had acted unlawfully in signing the contract.Chapter 17
206
As a result, in January 1992, the Department of Transport was still
in a
quandary as to what to do about that contract.That problem was soon to become irrelevant, however, because on 13
February 1992 the Minister for Transport put pressure on his
Department,
that was to lead the project in an entirely different direction: he
suddenly
instructed his Department to prepare a Policy Submission to the
National
Executive Council and consider a very late proposal by Kinhill
Kramer Pty
Ltd of Port Moresby. These developments are recorded in Chapters 18
and 19.* * * * * * * * * *
-
Page 232 of 397
-
Chapter 17
207
18. MINISTER FOR TRANSPORT EXPEDITES PREPARATION
OF NEW POUCY SUBMISSION:
FEBRUARY 1992[18.1] ASSUMPTION THAT THE PROJECT WOULD BE AWARDED TO CHINESE
CONSORTIUMEver since the Ministerial Committee decided to recommend
awarding the
contract to the Chinese consortium, it had been assumed that
decision
would go to the National Executive Council for ratification.The Minister for Transport pre-empted this process by
negotiating directly
with the Chinese consortium on a number of occasions (see
Chapters 12
and 14). But it seems to have been assumed that the matter
would
eventually go to the National Executive Council and that the
Minister would
recommend that the project be formally awarded to the Chinese
consortium. This had been the purpose of the draft submission
‘Financing
the Construction of the Spring Garden Freeway’ (see Chapters
11 and
16).18.2] A SIGNIFICANT TURN OF EVENTS
In February 1992 there was a significant turn of events: a
new National -
Page 233 of 397
-
Executive Council Policy Submission was prepared. But rather
than
favouring the Chinese consortium, the new submission gave the
National
Executive Council a choice of two proposals: the Chinese
proposal and
a proposal by Kinhill Kramer Pty Ltd of Port Moresby.Chapter 18
208
In this chapter we trace the events that led to this new
submission being
presented to the National Executive Council.SECRETARY FOR WORKS BRIEFS THE MINISTER FOR TRANSPORT
[18.3] MINISTER FOR TRANSPORT ASKS SECRETARY FOR WORKS FOR
BRIEFING ON SPRING GARDEN ROAD PROJECT
In early February 1992, the Minister for Transport asked the
Secretary for
Works, Mr Hitolo, for a briefing on the Spring Garden Road
project.Mr Hitolo did not advise the Secretary of the Department of
Transport, Mr
Amini, that he was briefing the Minister for Transport.[18.4] MINISTERS SHOULD NOT OBTAIN “SECRET’ BRIEFS FROM
DEPARTMENTS FOR WHICH THEY HAVE NO RESPONSIBILITYThe Ombudsman Commission regards this as a bad administrative
practice. If the head of a department is requested to provide
a brief to a
Minister other than the one carrying political responsibility
for the
department he is in charge of, he should advise the head of
that Minister’s
department that he has been asked to provide the brief,
either before or
immediately after it is given.Chapter 18
-
Page 234 of 397
-
209
This basic administrative procedure is necessary to ensure
consistency in
the advice given to Ministers and to avoid the chaos that
inevitably results
when Ministers receive uncoordinated advice from a number of
different
sources.[18.5] WHY DID THE MINISTER FOR TRANSPORT ASK THE SECRETARY FOR
WORKS FOR ADVICE?The Minister for Transport acted as he did because the
Secretary for
Works, Mr Hitolo, until a short time beforehand, had headed
the Policy
Secretariat in the Department of Transport. He had been
responsible for
the Spring Garden Road/Poreporena Freeway project for a
considerable
time and had briefed the Minister for Transport on a number
of occasions.
From the evidence given by Mr Leo Moore, it is also apparent
Mr Hitolo
knew a lot more about the negotiations with the Chinese
consortium than
did the Secretary for Transport.[18.6] IT WAS WRONG OF THE SECRETARY FOR WORKS NOT TO ADVISE
THE SECRETARY FOR TRANSPORTWhen we suggested in our preliminary report that Mr Hitolo
had erred in
briefing the Minister for Transport, he said that he had done
so because,
at that time, Mr Temo was the Acting Deputy Prime Minister.
He also gave
a number of other reasons for his actions. These were:Chapter 18
210
that presentation of a draft National Executive Council
submission recommending involvement of Motu-Koitabu -
Page 235 of 397
-
landowners in the project had been delayed by the
Office of
the Secretary for Transport; andthat landowners were becoming frustrated and suspicious
about delays in getting the project started and their
co-
operation was critical to the smooth implementation of
the
project; andthat the Government had to make a quick decision on the
type of financing required for the project. [EXHIBIT
261]The Ombudsman Commission appreciates that the Secretary for
Works
genuinely believed he was acting properly in briefing the
Minister for
Transport. Our concern is not so much that he provided the
brief. What
we are critical of is Mr Hitolo’s failure to advise the
Secretary for Transport
of what he had done.As a matter of sound administrative practice and common
courtesy, the
Secretary for Works should have advised the Secretary for
Transport he
had received the request from the Minister for Transport. His
failure to do
so was defective administration.[18.7] THE POSITION OF ACTING DEPUTY PRIME MINISTER IS NOT
RECOGNISED BY LAWOne of the reasons given by the Secretary for Works for
briefing the
Minister for Transport was that the Minister was, at the
time, Acting Deputy
Prime Minister. However, there is no such position recognised
by theChapter 18
211
Constitution or any Act of the Parliament. The Prime Minister
Act (Chapter
No. 27 of the Revised Laws) which creates the office of
Deputy Prime
Minister and allows the office-holder to be Acting Prime
Minister in certain -
Page 236 of 397
-
situations, does not refer to an “Acting Deputy Prime
Minister”.Though the Minister for Transport may have carried the
unofficial title of
Acting Deputy Prime Minister, he had no extra official powers
or
responsibilities beyond those conferred on him as Minister
for Transport.One of the themes of this report is that there is a need for
all our Ministers
and Departmental Heads to become fully acquainted with the
limits of
Ministerial powers imposed by the Constitution. The briefing
of the Minister
for Transport by the Secretary for Works is an example of the
type of
confusion about Ministerial powers that seems to exist. This
important
issue is dealt with further in Chapter 39.[18.8] PURPOSE OF THE SECRETARY FOR WORKS’ BRIEF TO THE MINISTER
FOR TRANSPORTThe purpose of Mr Hitolo’s brief was to bring the Minister
for Transport up
to date on what was happening with the project. But Mr Hitolo
did not
have a great deal to report. He noted that the draft National
Executive
Council submission favouring the Chinese had been prepared by
the
Department of Transport in July 1991, but stated that the
Department was
still “holding onto it” because views of other Departments
had not been
received. [EXHIBIT 145, at page 3]Chapter 18
212
[18.9] NO MENTION OF KINHILL KRAMER
The most significant aspect of Mr Hitolo’s brief was that he
assumed the -
Page 237 of 397
-
Chinese proposal was still the favoured option. There was no
indication
that the Kumagai Gumi/Kinhill Kramer proposal was being
reconsidered or
that Kinhill Kramer was to be given the opportunity to lodge
a fresh
proposal.In retrospect this is very interesting, because it was only
eighteen days
after this brief was presented to the Minister for
Transport, that Kinhill
Kramer was selected by the National Executive Council to
undertake the
project. It is apparent therefore that, iess than three
weeks before that
decision, the Secretary for Works was completely unaware of
the Kinhill
Kramer proposal.But it was not only the Department of Works that was
ignorant of the
Kinhill Kramer proposal. The Department of Transport was
also unaware
of it, until at least seven days before the National
Executive Council’s
decision in favour of that company.MINISTER INSTRUCTS DEPARTMENT OF TRANSPORT TO EXPEDITE POLICY
SUBMISSION[18.10] MINISTER FOR TRANSPORT INSTRUCTS HIS DEPARTMENT TO FINALISE
SUBMISSION TO NATIONAL EXECUTIVE COUNCILOn 13 February 1992 the Minister for Transport wrote to the
Secretary for
Transport in the following terms:Chapter 18
213
‘RE: BURNS PEAK NEC SUBMISSION
This matter has been dragging on for quite sometime. I
would like to have the
matter discussed at the next NEC meeting which is on the
19th of February,
1992, -
Page 238 of 397
-
You are required to have the submission in order for
presentation on the above date. Discuss with me on any hold
up on the matter.’ [EXHIBIT 147]i.11] NO INDICATION THAT KINHILL KRAMER PTY LTD WOULD BE
CONSIDEREDThere is no indication in the Minister’s instruction that he
had changed his
mind about favouring the Chinese consortium. There is no
suggestion an
invitation would be extended to any other consortium to put in
a late bid.
The Secretary was simply required to have “the submission”
ready for
presentation.The fact that the Minister did not ask that the submission be
altered adds
to the mystery surrounding the subsequent lodgment of the
Kinhill Kramer
proposal.The Minister’s instruction was received in the Department of
Transport
Secretariat the following day, 14 February 1992, and the
Secretary made
the following handwritten notation on it:‘Pis action urgently
Finance and Attorney General Depts views must be
obtained.’ (EXHIBIT 147) -
Page 239 of 397
-
Chapter 18
214
[18.12] VIEWS OF OTHER DEPARTMENTS WERE NOT OBTAINED
It is interesting to note the Secretary’s insistence that
views be obtained
from the Department of Finance and Planning and the
Department of
Attorney-General. They never were. Both these Departments
were given
the opportunity to comment on the previous draft submission
(the one
circulated in December 1991 favouring the Chinese
consortium) – but they
failed to respond.Neither Department was given the opportunity to comment on
the
submission which led the National Executive Council to the
decision in
favour of Knhill Kramer Pty Ltd.[18.13] DEPARTMENT OF TRANSPORT’S IGNORANCE OF THE KINHILL KRAMER
PROPOSALOn 17 February 1992 the Secretary for Transport wrote to the
Secretary
for Works.This was, in effect, a protest note. Mr Amini had just
obtained a copy of
the brief Mr Hitolo gave to the Minister for Transport and
was obviously
very cross that the Secretary for Works had prepared it,
rather than
himself. Mr Amini stated:‘The matter of Spring Garden Road is the responsibility
of the Department of
Transport until such time as the consortium is selected
and all the detailed -
Page 240 of 397
-
contracting arrangements are completed. At the time of
design and
construction, the DOW will be fully involved.” [EXHIBIT
149]Chapter 18
215
Later in this letter, Mr Amini made a very frank and startling
admission:“In the draft NEC submission dated 17 July 1991 on the financing
of Spring
Garden Road prepared by you while you were with the Department of
Transport, you evaluated five consortiums, however, we do not
have any
proposals from any companies except the Chinese consortium- If
you do have
any of the information, please arrange to send it to me at your
earliest
convenience.” [EXIBBIT 149, emphasis added]In other words, Mr Amini was saying this: of the five proposals
short-
listed for the consideration of the Ministerial Committee in July
1991, only
one was still in the possession of the Department of Transport as at
17
February 1992 – the Chinese one.This was only seven days before the National Executive Council
decision
in favour of Kinhill Kramer. -
Page 241 of 397
-
This disturbing situation prompted two questions for the Ombudsman
Commission during the course of the investigation:What had happened to the remaining four proposals? and
Was the Kinhill Kramer proposal that was eventually
approved by the National Executive Council one of the four
“lost”, or was it a new proposal?Chapter 18
216
[18.14] WHAT HAD HAPPENED TO THE FOUR LOST PROPOSALS?
This question has already been addressed in Chapter 11: the
proposals
were left in the Minister for Transport’s office on 18 July
1991 and have
never been seen since. The Department of Transport had not
kept copies
of them, nor requested copies from the companies which
submitted them.[18.15] WAS THE KINHILL KRAMER PROPOSAL A NEW PROPOSAL?
The Ombudsman Commission put this question to the Executive
Chairman
of Kinhill Kramer Pty Ltd, Mr Frank Kramer. He testified
that previously
Kinhill Kramer had submitted a joint proposal with Kumagai
Gumi Ltd. But
Kumagai Gumi had lost interest in the project and Kinhill
Kramer decided
to submit its own proposal. -
Page 242 of 397
-
This candid response begged other questions:
Was Kinhill Kramer invited to submit a new proposal?
If so, when?
Who invited Kinhill Kramer to submit their proposal?
These important issues are explored in Chapter 19.
Chapter 18
217
19. HISTORY OF THE PROPOSAL BY
KINHILL KRAMER PTY LTD[19.1] INITIAL INTEREST OF KINHILL KRAMER
The Executive Chairman of Kinhill Kramer Pty Ltd, Mr F M
Kramer CBE,
said his company first became interested in the Spring Garden
Road/Poreporena Freeway project as early as 1987 or 1988,
when Mr Roy
Yaki was the Minister for Transport in the Government led by
the Rt. Hon.
Paias Wingti. Mr Yaki had sent Kinhill Kramer a letter
explaining the priority to be given to the project.
to be given to the project.However, nothing came of this and, according to Mr Kramer,
the project
“went quiet for several years”.INTEREST SHOWN IN THE PERIOD 1990 – FEBRUARY 1992
[19.2] TECHNICAL FEASIBILITY REPORT SUBMITTED IN 1990
The next time Kinhill Kramer showed interest was the first
half of 1990, -
Page 243 of 397
-
when it submitted a ‘Technical Feasibility Report’ to the
Department of
Transport. [EXHIBIT 7B]Chapter 19
218
Mr Kramer said this document was given to the Department of
Transport
on an unsolicited basis. Its purpose, he said, was to
demonstrate the
advantages of constructing an arterial road link from
downtown Port
Moresby to Jacksons Airport, to provide a comparison of the
tunnel/cut
options and to give an estimate of the project cost.The cost of the project was estimated to be K40 million.
[EXHIBIT 7B at page 15][19.3] NEXT EXPRESSION OF INTEREST: JUNE 1990
The next time Kinhill Kramer expressed interest was June
1990, following
the advertisement inviting expressions of interest.By this time Kinhill Kramer had come to an arrangement with
Kumagai
Gumi Co Ltd of Japan, a company which Kinhill Kramer had
worked with
on other projects in Papua New Guinea: the Morobe Sports
Complex in
Lae and PTC Haus and Revenue Haus in Port Moresby.A letter dated 25 June 1990 was sent to the Department of
Transport by
the “Kumagai Gumi-Kinhill Kramer Consortium”. It stated:‘Dear Sir,
-
Page 244 of 397
-
RE PROPOSED SEAPORT – AIRPORT ARTERIAL LINK
(INCORPORATING THE BURNS PEAK TUNNEL)We refer to various meetings during the past few weeks
(HTTOLO/ICIMURA)
regarding the above proposed project.We are pleased to advise that Kumagai Gumi Co. Ltd. of
Japan and ICinhill
Kramer Pty. Ltd. of P.N.G. have formed a consortium for
this project.Chapter 19
219
The Consortium offers the following advantages to the Department.
(i) Attractive semi-concessional finance package which is already
known
and acceptable to the Department of Finance and Planning and
which
is currently being used by the P.N.G. Government for a variety
of
projects.Through Kumagai Gumi Co. Ltd., the Consortium offers tunnelling
and
construction expertise from one of Japan’s leading companies in
these
fields.Through Kinhill Kramer, the Consortium offers the region’s
largest
engineering design capabilities for major engineering projects.(iv) The Consortium has already commenced a Toll/Revenue Study which
is expected to be completed in approximately 3 weeks.(v) Given the above factors, this Consortium is the only one who
may be
in a position to complete the project by the end of 1991. -
Page 245 of 397
-
For your information, we enclose herewith our two company’s
brochures, Terms
and Conditions of the Finance Package available, and a set of
drawings for the
projectThe basic proposal is to divide the project into three stages as
follows:Stage 1: From the sea-port area to Wards Road including the first
barrel
of a twin-barrel tunneLStage 2 Section from Wards Road to the Kennedy Rd/Boroko Dr./Geauta
Dr. Curie.Stage 3: The Section from Kennedy Rd./Boroko Dr./Geauta Dr. Circle
to the Airport., including the second barrel of the tunneLDetails of the total proposal can be finalised by mutual
arrangement.The offer is for a full TURN-KEY package comprising design,
construction and
finance.Should you be interested in our offer, please contact the
undersigned.Yours faithfully,
KUMAGAI GUMI KIN LL KRAMER CONSORTIUM
[Signed]
MR Y. KIMURA
General MANOWI
[EXHIBIT 16]Chapter 19
220
• [19.4] TERMS AND CONDITIONS OF THE KUMAGAI GUMI-KINHILL KRAMER
-
Page 246 of 397
-
FINANCE PACKAGE NOT IN POSSESSION OF THE DEPARTMENT OF
TRANSPORTThe letter of 25 June 1990 suggests the terms and
conditions of the
finance package were to be enclosed with the letter.
However, when we
examined the files of the Department of Transport, no
record of these
terms and conditions could be found.When Mr Kramer was asked to produce this letter and its
enclosures, he
produced the letter, but the only enclosures attached
were two identical
drawings entitled “Moresby-Jacksons/Airport Arterial
Link Through Burns
Peak”. [EXHIBIT 16 ]The Ombudsman Commission was left in a quandary as to
what the terms
and conditions of Kumagai Gumi-Kinhill Kramer’s 1990
finance package
actually were. It was only when all the files of the
Department of Works
were made available, that we could piece together what
appeared to be
the true situation.[19.5] WHAT WAS THE KUMAGAI GUMI_KINHILL KRAMER ‘FINANCIAL
PACKAGE’?The files of the Department of Works suggest that there
were four one-
page documents attached to the letter of 25 June 1990.
These were:Chapter 19
221
1 A document entitled “Information Received from the Export-
Import Bank of Japan”. This document stated that the typical
terms and conditions of EXIM financing included an interest
rate of 7.6% per annum, repayable 5-8 years after the
completion of the project. [EXHIBIT 16A] -
Page 247 of 397
-
2. A flowchart entitled “Kumagai Gumi Co Ltd Overview Flow”.
This document purported to show some financial
relationships between the PNG Government, Kumagai Gumi
Ltd, an un-named Japanese trading company and the EXIM
Bank. However, as the flowchart was not referred to in the
letter of 25 June, 1990, it was difficult to understand its
relevance to the expression of interest. [EXHIBIT 16B]3. A document entitled “Operational Framework”. This document
appeared to describe the various lending schemes available
from the EXIM Bank. However, the EXIM Bank was not
actually referred to and so a person reading the document
could easily have been confused about its relevance.
[EXHIBIT 16C]4. A document entitled “Note to the EXIM Bank Loan
Conditions”. Like the first document referred to above, the
purpose of this document appears to have been to describe
the conditions attached to EXIM Bank financing. The copy of
the document we obtained from the Department of Works’
files is confusing, as various sections have been crossed-
out and others inserted, in an unknown person’s handwriting.
We are unclear whether the document was presented to the
Department of Transport in this form. [EXHIBIT 16D]Chapter 19
222
These four documents were appended to the letter of 25 June
1990 in a
way that was, in our view, quite confusing.When we suggested this in our preliminary report, Mr Kramer
replied that
the documents were appended in a way that was the “industry
norm”
given the circumstances. He described the expression of
interest as a
“carefully considered business communication prepared by and
with one
of the world’s great engineering enterprises”.
[EXHIBIT 253 paragraphs 5 and 8]Be that as it may, our view is that the Department of
Transport or any
other governmental body receiving proposals from private
corporations for -
Page 248 of 397
-
kina projects should insist on a much higher standard
of
documentation.[19.6] MR HITOLO’S EXPLANATION
When we suggested in our preliminary report that the Kumagai
Gumi-
Kinhill Kramer proposal was vague and should not have been
regarded as
acceptable, we received the following response from Mr
Hitolo, the former
head of the Policy Secretariat in the Department of
Transport:“Kumagai Gami-lCinhfil Kramer consortium proposal is the
classical example
of the other three proposals that got lost except for the
Chinese. In fact they
never submitted a definite proposal consistent with the
B.O.T. concept of the
Terms of Reference. So in fact most of them were vague and
unprofessionally
done purely letter show of interest or trying to buy time
for them to organise
finandng. Hence, the deadline was extended 2 or 3 times as
I cannot recall
properly but I know I had discussions with some of the 5
short listed
companies. The deadline had expired and the so-called
Ministerial Committee
was to be briefed. The Secretary of Department of
Transport directed Mr
Parakei and me to brief them and the so-called proposals
were taken up to
Parliament. At least he should have stopped it or attend
himself but this is the
type of attitude he has been portraying throughout the
project’.
[EXHIBIT 265, pant 12]Chapter 19
-
Page 249 of 397
-
223
Mr Hitolo is suggesting the Department of Transport was put
under
pressure by the Minister for Transport to rank the proposals
for the
Ministerial Committee meeting in July 1991. He concedes that
most of the
proposals, including Kinhill Kramer’s, were only letters of
interest, rather
than firm proposals. Under normal circumstances, most of the
proposals
would not have been regarded as acceptable.[19.7] THE KINHILL KRAMER FINANCIAL PROPOSAL WAS NEVER PUT IN
PRECISE TERMSThere was no other occasion on which Kinhill Kramer’s
financial proposal
was formally put to the Department of Transport in more
precise terms
than in the letter of 25 June 1990. Mr Kramer said that
further details were
delivered to the relevant persons and departments on
numerous
occasions after June 1990. [EXHIBIT 253, paragraph 5]However, this must have been done on an informal basis, as
there is no
record of these events in any of the Departmental files and
Mr Kramer did
not provide us with any record of the meetings.[19.8] FURTHER CORRESPONDENCE IN JULY 1990
The next occasion on which Kumagai Gumi-Kinhill Kramer
expressed
interest was in a letter dated 31 July 1990. This was in
response to a
letter from the Department of Transport, inviting a detailed
proposal from
the consortium. [EXHIBIT 31]Chapter 19
224
We reported in Chapter 6 that the Department of Transport was
-
Page 250 of 397
-
wrong to
only invite proposals from a select group of companies. The
Kumagai
Gumi-Kinhill Kramer consortium was among the selected group.However, the letter of 31 July 1990 did not elaborate on the
financial
proposal that had earlier been given to the Department.[19.9] TRAFFIC REVENUE STUDY: AUGUST 1990
Mr Kramer stated to the Ombudsman Commission that around
August
1990, he had submitted a document to the Department of
Transport
entitled “Port Moresby to Jacksons Airport Arterial Road Link
Via Burns
Peak Tunnel Preliminary Traffic and Revenue Report”. This
document was
prepared by Kinhill Cameron McNamara Pty Ltd of Milton,
Queensland,
Australia. [EXHIBIT 37]The report provided an analysis of expected revenue on the
assumption
that certain parts of the Spring Garden Road network would
become a
tollway.Mr Kramer indicated that, like the “Technical Feasibility
report” presented
to the Department of Transport in the first half of 1990, the
Traffic and
Revenue Report had been given to the Department of Transport
on an
unsolicited basis as an indication of the seriousness of the
interest in the
project by the Kumagai Gumi-Kinhill Kramer consortium.Chapter 19
225
[19.10] FURTHER INTEREST EXPRESSED BY KUMAGAI GUMI-KINHILL KRAMER;
MAY 1991In early 1991 the Department of Transport had prepared a
-
Page 251 of 397
-
document
entitled ‘Terms of Reference for Spring Garden Road”. In
Chapter 10 we
criticised this document: it was vague and poorly prepared.
These
concerns were also expressed by the World Bank (see Chapter
15).Another concern was that, like the July 1990 invitation for
proposals, the
Terms of Reference document was only circulated to a few of
the
companies which had expressed interest in the project. The
Kumagai
Gumi-Kinhill Kramer consortium was again among the selected
group.On 20 May 1991 the Kumagai Gumi-Kinhill Kramer consortium
wrote a
brief letter to the Department of Transport, in response to
the Terms of
Reference document. The letter, again, did not elaborate on
earlier
correspondence and stated that the details of the finance
could be
“finalised by mutual arrangement.” [EXHIBIT 86][19.11] NO FURTHER CORRESPONDENCE AFTER MAY 1991
There was no further correspondence between the Kumagai
Gumi-Kinhill
Kramer consortium and the Department of Transport after the
letter of 20
May 1991.Kumagai Gumi Ltd had no further involvement in the project.
As to Kinhill
Kramer Pty Ltd, their next involvement was in February 1992
when they
were invited to submit another-proposal.Chapter 19
226
[19.12] FINDINGS REGARDING THE KUMAGAI GUMI-KINHILL KRAMER
PROPOSALIn light of the above, the Ombudsman Commission makes the
following -
Page 252 of 397
-
findings regarding the proposal by the Kumagai Gumi-Kinhill
Kramer
Consortium:1. The consortium formally expressed interest in the
project on
three occasions: June 1990, July 1990 and May 1991.2. On the first occasion, the consortium’s financial
proposal was
attached to the letter of interest. The proposal
should not,
in the opinion of the Ombudsman Commission, have been
regarded by the Department of Transport as a firm
proposal
for financing the project. It should only have been
regarded
as an expression of interest. The next two letters of
interest
failed to give further details.3. As a result of the Minister for Transport’s arbitrary
shortlisting
procedure in the first half of 1991, Kumagai Gumi-
Kinhill
Kramer was one of five consortiums considered by the
Ministerial Committee at the meeting of 18 July 1991.
It was
ranked number three. (See Chapter 9.)4. It is impossible to conclude precisely the form in
which the
Kumagai Gumi/Kinhill Kramer proposal was presented to
that
meeting, because it was one of the four proposals
subsequently lost. However, it is clear there was
never at any
time a single document which embodied the Kumagai
Gumi
Kinhill Kramer proposal.Chapter 19
227
5. It appears the proposal consisted of the three
letters of
interest, the collection of documents which
constituted the
financial proposal and the Technical Feasibility
Report
prepared by Kinhill Kramer in April 1990. -
Page 253 of 397
-
6. Thus, the proposal submitted by Kinhill Kramer Pty
Ltd in
February 1992 was an entirely new proposal, in which
Kumagai Gumi Ltd had no involvement at all.THE FEBRUARY 1992 PROPOSAL
[19.13] NO RECORD OF LODGMENT IN DEPARTMENT OF TRANSPORT FILES
As the Commission has remarked many times in this report,
the extent to
which important decisions, policies and events were being
documented by
the Department of Transport left a great deal to be desired.
We make the
same comment in relation to the events of February 1992,
when Kinhill
Kramer Pty Ltd lodged the proposal which resulted in it
being awarded
the contract for the Spring Garden Road/Poreporena Freeway
project.There is no record in the Department’s files of when that
proposal was
lodged or why IGnhill Kramer was permitted to lodge it. Nor
is there any
record of its evaluation by officers of the Department. In
fact, the only
record of its existence is its inclusion as an appendix to
the Policy
Submission which led to the decision by the National
Executive Council in
the company’s favour on 24 February 1992.When we made these allegations in our preliminary report,
the Secretary
for Transport responded in the following terms:Chapter 19
228
The Department received this additional information from
the Minister, who
requested the information direct from the developer for
clarification purposes
at a meeting with the consortium. As I have said above,
if a proposal has the -
Page 254 of 397
-
potential to deliver the services, but lacks details,
additional information can be
sought.” [EXHIBIT 254, pars 141With due respect to Mr Amini, he has not addressed the point
of our
criticism.A full and proper record should have been made of the
receipt of the
Kinhill Kramer proposal. At the very least, a date-received
stamp on the
proposal should have indicated when it was received. There
should have
been some indication of when, how and by whom the proposal
was
evaluated. However, there was just no record of its
lodgment.In the opinion of the Ombudsman Commission this is not good
enough.
The lodgment of a proposal for a multi-million kina project
– especially the
proposal which is successful – should not be shrouded in
mystery. The
Department of Transport failed in its duty to keep a proper
public record
of this important event.[19.14] ORAL EVIDENCE GIVEN TO THE OMBUDSMAN COMMISSION
Because of the gap in the Departmental records, the
Ombudsman
Commission was forced to rely on oral evidence given in the
course of the
investigation to determine the circumstances in which the
proposal was
lodged. We considered evidence from the Executive Chairman
of Knhill
Kramer, Mr Kramer, the Minister for Transport, Mr Temo and
the Secretary
for Transport, Mr Amini. -
Page 255 of 397
-
Chapter 19
The evidence of Mr Kramer
Mr Kramer stated that the February 1992 proposal was submitted as a
result of a telephone call by an officer of the Department of
Transport. He
said the caller advised him that, of all the consortiums which had
bid for
the project, there were only two that the Government was still
interested
in: the Kumagai Gumi-Kinhill Kramer consortium being one of them. Mr
Kramer said the caller invited him to update his bid or re-confirm
it.Mr Kramer could not recall who the caller was. Inquiries by the
Ombudsman Commission during this investigation have also failed to
reveal the identity of the caller. There is no evidence on the
Department
of Transport’s files of this important phone call being made.As to the date of the telephone call, Mr Kramer stated, after
checking
records kept in his company’s office, that it was on or about 17
February
1992.Evidence of the Secretary for Transport
Mr Amini said the Department had reluctantly considered this late
proposal
because they had been instructed to do so by the Minister for
Transport.
There had been a meeting between the Minister for Transport and
representatives of Kinhill Kramer which had taken place before the
Klnhill
Kramer proposal was lodged.As to the date of lodgment, Mr Amini stated that it was at “the last
minute”.
By that, he meant that it was only a day or so before the meeting of
the
Resource Management Committee which was held on 20 February 1992
(see Chapter 20).Chapter 19
230
-
Page 256 of 397
-
Evidence of the Minister for Transport
Mr Temo’s recollection of these events was not very clear,
but he
indicated that all of the consortiums which had been
shortlisted in 1991
were invited to update their proposals. Mr Temo said only
Kinhill Kramer
was “still interested”.Mr Temo denied giving Kinhill Kramer favoured treatment:
‘Kinhill Kramer proposal was brought in by the
Department’s advise that the
Chinese proposals were confusing because of change of
companies. Also we
need to have 1 or 2 companies who are already based in
PNG and who have
registered interest and have a reasonable grading in the
Department’s criteria.The Secretary advised that the Chinese wanted to bring in
a lot of Chinese to
be as labourers they did not have reputation. The
Secretary advised we should
give the NEC a choice of expensive, neat and quality work
and cheap and poor
Pe°Ple-
As a result the NEC decision to go for Kinhill Kramer, I
did not favour any
company after the Department’s advice` [EXHIBIT 257 pages
5-61[19.15] FINDINGS OF THE OMBUDSMAN COMMISSION REGARDING THE
FEBRUARYAN2TROPOSAL: KINHILL KRAMER PTY LTD WAS INVITED
TO LODGE A LATE PROPOSALWe do not accept Mr Temo’s claim that all shortlisted
consortiums were
given the opportunity to update their proposals. There is no
evidence in
the Department of Transport’s files that this was done and
Mr Temo was
unable to produce any documentary evidence to corroborate -
Page 257 of 397
-
the claim.
We found Mr Amini’s evidence to be more credible than Mr
Temo’s.Chapter 19
231
We accordingly conclude that Kinhill Kramer was invited by
the
Department of Transport to submit a late proposal and that
the invitation
was issued on the instructions of the Minister for
Transport.The opportunity given to Kinhill Kramer to lodge a late
proposal was 1o1
given to any other company which had expressed interest in
the projectWhen Mr Kramer was invited to comment on this finding in
our preliminary
report, he denied his company had been invited to submit a
fresh bid. The
invitation, he said, was only to “update” the 1990
proposal.Irrespective of the exact wording of the invitation – i.e.
whether the
telephone caller asked Mr Kramer to “update” the proposal
or to submit Ia fresh bid – we conclude that Kinhill Kramer took the
opportunity to lodge
a fresh proposal. -
Page 258 of 397
-
19.16] KINHILL KRAMER PTY LTD WAS GIVEN FAVOURED TREATMENT
In his written response to the Ombudsman Commission’s
preliminary
report, Mr Kramer denied that it was unfair to other
interested parties, to
allow Kinhill Kramer to lodge a proposal in February 1992:‘Your investigators miss the point in rejecting
Minister Temo’s ‘claim’ that all
shortlisted consortiums were given the opportunity to
update their proposals.The Tunson Engineering proposal, for one, needed no
updating. It was only a
matter of months old – by contrast with the Kumagai
Gumi proposal (some 2
years out of date). There could have been no
unfairness in inviting novation
of our proposal, in those circumstances.” (EXHIBIT
253, paragraph 11]We accept Mr Kramer’s point that the proposal by Tunson
Engineering Co
Ltd did not need updating. But many other proposals di d
need updating.Chapter 19
232
[19.17] WHY WERE OTHER CONSORTIUMS NOT CONTACTED?
We do not understand why other companies whose proposals
were also
out of date were not given the opportunity to update them.
None of the
three consortiums shortlisted for consideration by the
Ministerial
Committee in July 1991, were given this opportunity. Those
consortiums
were:Periquan’s International Resources Pty Ltd and Pan
Asia
Management Consultants Centre -
Page 259 of 397
-
Tasman Pacific International and Crooks Mitchell
Peacock
Stewart Pty LtdMcConnell Dowell. [See Chapter 11]
In particular, it is very strange the Periquan consortium –
ranked ahead of
Kumagai Gumi-Kinhill Kramer in July 1991 – was not invited
to update its
bid.The Ombudsman Commission concludes that Kinhill Kramer Pty
Ltd was
given favoured treatment.It was unfair to the other companies which had expressed
interest in the
project for only IGnhill Kramer to be allowed to submit a
late proposal. It
was a totally unsatisfactory situation. It was wrong of the
Minister for
Transport to direct his Departmental Head to consider a late
proposal
from only one company.When this sort of thing happens, it is hardly surprising
that allegations of
bribery and corruption surface.Chapter 19
233
WHEN WAS THE KINHILL KRAMER PROPOSAL LODGED?
[19.18] DATE OF LODGMENT OF THE PROPOSAL
The Ombudsman Commission is satisfied that by the time the
Resource
Management Committee met on 20 February 1992, the Kinhill
Kramer
proposal had been lodged. The records of that meeting reveal
that the
Kinhill Kramer proposal was considered. [EXHIBITS 151A &
152]This means the proposal was lodged at some time before 20
February
1992.The Ombudsman Commission also concludes that the proposal
-
Page 260 of 397
-
was
lodged no earlier than 17 February 1992, for the following
reasons:Mr Kramer testified he had received the phone call
inviting
the proposal on or about that date.Mr Amini’s letter to the Secretary for Works of 17
February
1992, clearly shows that the only proposal in the
possession
of the Department of Transport on that date was the
proposal by the Chinese consortium (see Chapter 18
and
EXHIBIT 149).Thus, the Kinhill Kramer proposal was in all probability
lodged on 18 or 19
February 1992: only five or six days before the National
Executive Council
decided to award the project to this company.Chapter 19
234
The Ombudsman Commission finds it incredible that following a
decision-
making process that had been proceeding for more than two years
(since
NEC Decision 14/90 on 24 January 1990) the decision on such an
important project, with its huge financial implications for the
State, could
be made in this way.* * * * * * * * * *
-
Page 261 of 397
-
Chapter 19
-
Page 262 of 397
-
235
20. RESOURCE MANAGEMENT COMMITTEE RECOMMENDS
RE-TENDERING OF PROJECT: 20 FEBRUARY 19921
[20.1] MEETING HELD TO DISCUSS THE PROJECT
On 20 February 1992 a meeting of the Resource Management
Committee
was held to discuss the Spring Garden Road/Poreporena
Freeway project.
This meeting was necessary because of the administrative
requirement
that submissions to the National Executive Council
involving un-budgeted
allocation of resources be considered by the Resource
Management
Committee and the National Planning Committee, before
being finally
presented. [National Executive Council Submissions
Handbook, paragraph
1.23, Exhibit 1]The Secretary for Transport, Mr Amini, was present at the
meeting and
introduced the Policy Submission entitled “Financing the
Construction of
the Spring Garden Freeway”.
1It is clear that, by this stage, the version of the Policy
Submission being
discussed was the one actually presented to the National
Executive
Council on 24 February 1992, i.e. the one which gave a
choice of two 1
consortiums: the Chinese and Kinhill Kramer. [NEC Policy
Submission No.
33/92, EXHIBIT 148] -
Page 263 of 397
-
I
Chapter 20
236
[20.2] RECOMMENDATIONS OF THE RESOURCE MANAGEMENT COMMITTEE
After the meeting, the Chairman, Mr B Bai CBE, prepared a
submission
from the Resource Management Committee to the National
Planning
Committee. [EXHIBIT 151 A]The submission expressed the following views:
The Resource Management Committee was not impressed
with either the Chinese (Tunson Engineering) proposal
or the
Kinhill Kramer proposal: neither was considered
suitable as
they were based on turnkey financing, ‘Which is too
expensive for the Government” (paragraph B3).Rather than build a freeway from downtown Port Moresby
to
the Airport, it would be better to proceed in stages;
the first
stage being the Champion Parade-Wards Road section,
through Burns Peak: “this will enable financing for the
construction to be easily secured” (paragraph B4).The project should be re-tendered: “the Department of
Transport in calling for tenders should specify and
advertise
widely on both Build-Operate-Transfer and Turnkey
proposals. It should also specify that the Government
would
prefer the Build-Operate-Transfer proposal” (paragraph
B5).If the Government cannot secure finance, a loan could
be -
Page 264 of 397
-
negotiated to fund the project (paragraph B7).
Chapter 20
237
[20.3] RECOMMENDATIONS CONVEYED TO MINISTER BY SECRETARY FOR
TRANSPORTThe Secretary for Transport conveyed the recommendations of
the
Resource Management Committee to the Minister for Transport
on 21
February 1992. Mr Amini stated:Both the proposals, namely the Chinese and the Kinhill
Kramer’s are turn-
key proposals. The country has had very bad experience
from turn key projects.
Normally, Papua New Guinea does not benefit from turnkey,
and the benefits
are derived by the country which provides the funding.
Also, the turnkey
financing is very expensive. Although turnkey method of
financing as proposed
by the Chinese and Kinhill’ Kramer is convenient, it is
not in the interest of
PNG’ [EXHIBIT 152, paragraph 5]In the opinion of the Ombudsman Commission, Mr Amini acted
property
in bringing these matters to the attention of the Minister.
As we have
emphasised throughout this report, the Government’s top
advisers have
a duty to give advice fearlessly and forcefully at all times,
which means it
is usually necessary to give the advice in writing or confirm
verbal
briefings or advice in writing. -
Page 265 of 397
-
[20.4] SECRETARY FAILED TO ADVISE MINISTER OF REQUIREMENTS OF
PUBUC FINANCES (MANAGEMENT) ACTHowever, we find it necessary to make a criticism of Mr
Amini’s advice to
the Minister.We point out that this is a criticism of the Secretary for
Transport – not a
condemnation. We appreciate the difficult position he had
been put in by
the Minister for Transport’s indiscretion in October 1991,
when he signed
the contract for construction of the freeway with Tunson
Engineering CoChapter 20
238
Ltd. We do not intend to cast all the blame on the Secretary for a
wrongful act of the Minister. The Minister must, clearly, carry
responsibility
for his decision to sign that contract (see Chapter 14).Our criticism is that, though the Secretary properly suggested to
the
Minister in February 1992 that the Champion Parade to Wards Road
section of the project be put to tender, he did not say why it was
so
important to do this.As we show in Chapter 35, this project was subject to the normal
public
tender procedures in the Public Finances (Management) Act. The
Secretary should have pointed this out to the Minister. The message
should have been clearly and unambiguously given to the Minister
formally, in writing – that his signing of the contract in October
1991 had
been unlawful and that it was necessary to follow normal tender
procedures.Mr Amini responded to this allegation in the following terms:
-
Page 266 of 397
-
‘The Minister was appropriately advised and, as further step, I
sought advice
from the Department of Attorney General, Department of Finance
and Planning
and the Loans Borrowing Committee but none responded. As far as I
am
concerned, what was critical was that the Minister did not have
the delegated
powers to sign the contract. That is what I highlighted to him.
That advice did
work and no harm was done. The effectiveness of my actions should
be
acknowledged.’ [EXHIBIT 254, para 161In the opinion of the Ombudsman Commission, this does not adequately
explain the Secretary’s failure to advise the Minister of the
requirements of
the Public Finances (Management) Act, either on this occasion (the
brief
of 21 February 1992) or any other occasion.Chapter 20
239
We have found that the Secretary for Transport did not at any
time during
the life of the project, advise the Minister in writing of
the need to follow
the public tender procedures in the Public Finances
(Management) Act.As permanent head of the Department of Transport, it was the
Secretary’s
duty to ensure that the provisions of the Act were complied
with in relation
to his Department. He failed to discharge this important
duty.[20.5] THE SECRETARY’S ADVICE WAS TOO LATE
The Ombudsman Commission concludes that, while the Secretary
-
Page 267 of 397
-
for
Transport acted properly in bringing the recommendations of
the
Resource Management Committee to the attention of the
Minister, it really
was a case of “too-little-too-late”.The crucial advice he gave on 21 February 1992 – only three
days before
the National Executive Council decided to award the project
to Kinhill
Kramer – should have been given in much clearer terms and a
long time
before it eventually was.[20.6] CHAIRMAN OF RESOURCE MANAGEMENT COMMITTEE PRESENTS
RECOMMENDATIONS TO THE NATIONAL EXECUTIVE COUNCILThe usual procedure with recommendations of the Resource
Management
Committee is that they are presented to the National Planning
Committee,
before going to the National Executive Council. [EXHIBIT 1,
para 1.23]Chapter 20
240
In this case, however, the National Planning Committee
was by-passed
and the recommendations were forwarded direct to the
National Executive
Council.The recommendations were tabled in the National
Executive Council and
the Chairman of the Resource Management Committee, Mr
Bai, on
direction from the Prime Minister, presented the
Committee’s views at the
National Executive Council meeting on 24 February 1992.
[EXHIBITS 151 A – 151 B][20.71 RESOURCE MANAGEMENT COMMITTEE RECOMMENDATIONS
REJECTEDAll the recommendations of the Resource Management
-
Page 268 of 397
-
Committee were
rejected. Instead, the National Executive Council
decided to award the
project – a freeway from downtown Port Moresby to
Jacksons Airport – to
Kinhill Kramer Pty Ltd.* * * * * * * * * *
Chapter 20
241
. THE MINISTER FOR TRANSPORT’S POLICY
SUBMISSION OF FEBRUARY 199221.1] POLICY SUBMISSION NO. 33 OF 1992: A NEW SUBMISSION
The Minister for Transport presented Policy Submission No.
33/92 to the
National Executive Council at its meeting on 24 February
1992.
[EXHIBIT 148]
Though this document carried the same title as the
submission dated 17 I
July 1991 and filed in October 1991, it was a
fundamentally different
document (see Chapter 16).
Whereas the submission dated 17 July 1991 strongly
favoured the I
Chinese consortium and ranked a joint proposal from
Kumagai Gumi and
Kinhill Kramer as number three in a short-list of five,
Policy Submission No.
33/92 gave a choice of two proposals: the Chinese proposal -
Page 269 of 397
-
and a
proposal dated February 1992 from Kinhill Kramer Pty Ltd.21.2] THE HURRIED PREPARATION OF THE POUCY SUBMISSION
The Secretary for Transport testified that Policy
Submission No. 33/92 was
prepared by his Department on the instructions of the
Minister for
Transport. He further stated that the views expressed in
it were those of
his Department.
11]Chapter 21
242
Mr Amini conceded the Policy Submission was prepared in a
rush. Indeed,
it must have been. The Commission found in Chapter 19 that a
proposal
from Kinhill Kramer had been lodged on 18 or 19 February 1992
and in
Chapter 20 it was shown that Policy Submission No. 33/92 –
which
evaluated the Kinhill Kramer proposal – was considered by the
Resource
Management Committee at its meeting on 20 February 1992.So, the Policy Submission must have been prepared by the
Department
of Transport on 18 or 19 February 1992 after the proposal had
been
lodged. We note that it carries the date 14 February 1992.
However, that
date cannot be accurate because the proposal was not lodged
until after
17 February 1992.[21.3] THE SUBMISSION WAS POORLY PREPARED AND DEFECTIVE
The fact that Policy Submission No. 33/92 was prepared
-
Page 270 of 397
-
hurriedly is borne
out by the quality of the document. It was poorly prepared
and seriously
defective in a number of important areas.When we made findings to that effect in our preliminary
report, the
Secretary for Transport responded as follows:‘NEC Secretariat follows strict guidelines, if it was
poorly done as alleged they
would have rejected it. Again when it went -to NEC, no
such comments were
made I was there. The submission was prepared by Mr
Parakei, assisted by a
World Bank technical assistant. This person is now in
charge of the multi-
billion dollar new Hong Kong Airport project’ [EXHIBIT
254, para 171Chapter 21
243
With due respect to Mr Amini, he has not answered our
criticism of the
Policy Submission. The fact that it was not rejected by the
National
Executive Council Secretariat and not adversely commented on
by
members of the National Executive Council is no guarantee of
its quality.The Ombudsman Commission retains the view that Policy
Submission No.
33/92 was poorly prepared and seriously defective. In this
and the
succeeding chapter, we explain our reasons for making this
finding. -
Page 271 of 397
-
POOR PRESENTATION OF ISSUES
[21.4] THE COLLECTION OF CONFUSING APPENDICES
In finding that Policy Submission No. 33/92 was poorly
presented, we are
not referring to the cosmetic appearance of the document. If
the
document were to be judged on its appearance, it would have
to be said
it appears to be well presented. But the appearance is
deceptive: a book
must not be judged by its cover.In terms of its presentation of issues, the document is very
weak. It
contains numerous appendices, none of which are marked
alphabetically
or numerically and none of which are referred to in the text
of the
submission. As a consequence, it would have been extremely
difficult for
anyone without an intimate knowledge of the project to
appreciate the
significance of the appended documents.Chapter 21
244
All Policy Submissions to the National Executive Council
should be
carefully and professionally compiled, so as to present
issues in a lucid
and methodical manner to avoid confusion.Policy Submission No. 33/92 failed to meet these
requirements. The ten
page text of the submission was accompanied by a collection
of twenty-
two appendices. The Ombudsman Commission has examined each of
these and found most to be meaningless and confusing and in
some
cases very misleading. -
Page 272 of 397
-
[21.5] EXAMINATION OF THE DOCUMENTS APPENDED TO THE POLICY
SUBMISSIONThe twenty-two appendices (which the Ombudsman Commission has
itself
numbered for the purpose of this report) and our comments on
each of
them, are as follows:Appendix 1: this was the document recording the decisions of
the
Ministerial Committee on 18 July 1991.
It related to paragraph 24 of the submission. However there
was no cross-
reference in that paragraph to this document. Readers of the
submission
were therefore left to their own devices to assess its
significance.Appendix 2: the contract agreement between Tunson Engineering
Co Ltd
and the Minister for Transport of 15 October 1991.
This document related to paragraph 26 of the submission, but
again there
was no cross-reference to the document in the text of the
submission.Chapter 21
245
Appendix 3: a letter from the Secretary for Transport to the
Secretary for
Works dated 5 December 1991.
This letter was presumably meant to show that the views of the
Department of Works on Policy Submission No. 33/92 were sought. But
the letter of 5 December 1991 was actually seeking views on the
previous
draft National Executive Council submission (ie the one dated 17
July
1991) – not Policy Submission No. 33/92. It was very misleading to
include
this letter as an appendix to the submission.Appendix 4: an undated memorandum from Tunson Engineering Co Ltd
to the Minister for Transport regarding the details of a bank
account.
This document is not referred to in the text of the submission. It
is an
entirely meaningless and irrelevant document. -
Page 273 of 397
-
Appendix 5: the World Bank Aide-Memoire of 28 September 1991. This
document related to paragraph 26 of the submission, but there was no
cross-reference to the document in the text of the submission. The
text
also failed to draw attention to the most significant recommendation
in the
Aid-Memoire: that the project be re-tendered.■
Appendix 6: a two page undated and unsourced document entitled
“Information Received from the Export-Import Bank of Japan”.
This is a completely meaningless document. It bears no relation to
anything discussed in the submission.Appendix 7: a one page unsourced and undated document headed
“Operational Framework”.
This is also a completely meaningless document. It bears no relation
to
anything discussed in the text of the submission.Chapter 21
246
Appendix 8: a letter from the Secretary for Transport to the
Secretary of
the Department of Prime Minister dated 5 December 1991.
Like Appendix 3, it gives the impression that the views of another
Department had been sought. But the only occasion on which the views
of the Department of Prime Minister were sought on Policy Submission
No.
33/92 was during the course of the Resource Management Committee
meeting on 20 February 1992. And the Resource Management Committee
recommended that the project be re-tendered.Appendix 9: an unsourced and undated document headed “Appendix B
Preliminary Traffic and Revenue Report”.
This document is not referred to in the text of the submission. In
the way
it is presented, it is just a meaningless set of toll revenue
figures
estimated by an unknown person.Appendix 10: an unsourced sixteen page document entitled “Port
Moresby
to (Jacksons) Airport Arterial Road Link Via Burns Peak Tunnel
Technical
Feasibility Report April 1990”.
This document actually forms a part of the February 1992 Turnkey
Proposal by Kinhill Kramer Pty Ltd. But in its presentation, it
appears to
be yet another unsourced document, bearing no necessary relation to -
Page 274 of 397
-
any
of the proposals referred to in the text of the submission. Without
a
proper explanation of its relevance, the inclusion of this document
as an
appendix is utterly confusing.Appendix 11: a map of the City of Port Moresby.
There were no maps referred to in the text of the submission. This
map
does not show with any precision the scope of the project the
National
Executive Council was being asked to approve.Chapter 21
247
Appendix 12: an unsourced line drawing no. 75024, entitled “Moresby-
Jacksons/Airport Arterial Link Through Burns Peak: Typical Section &
Details”.
The Ombudsman Commission is at a loss to understand the relevance of
this document. It is entirely meaningless.Appendix 13: an unsourced line drawing no. 75025, entitled “Moresby-
Jacksons/Airport Arterial Link Through Burns Peak: Dual Lane Bridge
Typical Cross Section”.
Yet another meaningless appendix.Appendix 14: an unsourced line drawing no. 75026, entitled “Moresby
–
Jacksons/Airport Arterial Link Through Burns Peak: Typ Tunnel Cross
Sections”.
This document was also not referred to in the text of the
submission.
Perhaps this document and Appendices 11 and 12 were appended to
give the appearance that the technical aspects of the project had
been
addressed. But they were nothing more than a confusing collection of
meaningless technical drawings of no relevance whatsoever to the
text of
the submission.Appendices 15. 16. 17 and 18: standard letters from the Secretary
for
Transport to the Departments of Lands and Physical Planning, Trade
and
Industry, Attorney-General and Finance and Planning inviting
comments on
a draft NEC Submission.
We have already commented above on the illusion created by including -
Page 275 of 397
-
these types of letters as appendices. The letters were seeking
comments
on the previous submission, i.e. the one which did not favour the
selection
of Kinhill Kramer Pty Ltd.Chapter 21
248
Appendix 19: a letter from the Acting Secretary for Transport to the
Department of Attorney-General dated 15 January 1992 seeking advice
on the contract agreement signed by the Minister with Tunson
Engineering
Co Ltd.
This document was not referred to in the text of the Policy
Submission.
Its inclusion could only confuse readers of the Policy Submission.Appendix 20: a letter from the Acting Secretary for Transport to the
Office
of International Development Agency dated 15 January 1992.
This document was also not referred to in the text of the
Submission. It is
another meaningless document.Appendix 21: an unsourced two page document entitled “Financial
Terms”.
This document was actually quite important. When the Executive
Chairman
of Kinhill Kramer Pty Ltd gave evidence to the Ombudsman Commission,
he testified that this particular two page document, which he
referred to
as ”the financial envelope”, had been enclosed – as a separate
document –
when the Kinhill Kramer proposal was lodged with the Department of
Transport. It therefore represented the financial terms on which the
company was offering to undertake the project.
The Policy Submission gave no indication that this is what the
document
was. It appears – like most of the other appendices – to be yet
another
unsourced, undated, meaningless, irrelevant document.Appendix 22: the February 1992 Turnkey Proposal by the Kinhill
Kramer
Consortium.
This thirteen page document was probably the most important
appendix.
However, it was not expressly referred to in the text of the
submission. -
Page 276 of 397
-
Any person – especially a busy Minister – who was required to
quickly
read the text of the submission may not have realised the
significance of
this document and could quite easily have skipped over it.Chapter 21
249
As we explain below, the Kinhill Kramer proposal was, in
fact, quite vague.
With respect, if the members of the National Executive
Council had
realised how vague the proposal really was, they may not
have voted in
favour of it.[21.6] WAS THE POUCY SUBMISSION MEANT TO BE CONFUSING?
Policy Submission No. 33/92 was so confusing in its
presentation, the
question must be raised whether this was intentional.
We refrain from making that finding. Our view of the
situation is that,
following the Minister for Transport’s direction of 13
February 1992, the
Department of Transport was required to hurriedly compile
the submission.
The Department’s efforts to put together a proper
submission were
hampered by the Minister’s instruction that it include the
late proposal by
Kinhill Kramer Pty Ltd.That proposal had to be evaluated and the Department’s
assessment of
it incorporated in the submission. This assessment was
also done in a
hurry. With the Minister putting pressure on the
Department and the
deadline for filing the submission fast approaching, it
appears that a
number of documents were hastily and carelessly appended
to the text of
the submission to give it a bulky appearance. The members
of the
National Executive Council were expected to find their own
way through
the jungle of papers.In addition to the confusion that the presentation of the
-
Page 277 of 397
-
document must
have caused, the Ombudsman Commission is surprised the
National
Executive Council entertained it, when its contents were
seriously
defective.Chapter 21
250
DEFECTS IN THE POLICY SUBMISSION
[21.71 SEVEN SERIOUS DEFECTS IN THE POLICY SUBMISSION 1992
In the opinion of the Ombudsman Commission, the text of
Policy
Submission No. 33/1992 is seriously defective in a number of
important
areas.The Ombudsman Commission has identified seven serious
defects. These
relate to:1. The establishment of the Ministerial Committee.
2. The illusion that an equal opportunity had been given
to
numerous companies and consortiums to submit proposals.3. The failure to properly advise the National Executive
Council
of the recommendations of the World Bank.4. The failure to give any explanation of non-compliance
with
the Public Finances (Management) Act and the Public
Works
Committee Act.5. The failure to refer to the recommendations of the
Resource
Management Committee.6. The failure to properly explain the history of the
Kinhill Kramer
proposal.7. The favourable assessment of the Kinhill Kramer
proposal. -
Page 278 of 397
-
Chapter 21 II
i
251
a[21.8] FIRST DEFECT: ESTABLISHMENT OF THE MINISTERIAL COMMITTEE
I
Paragraph 7 of the Policy Submission No. 33/92 refers to
“a special ■
Ministerial Committee” being established by the National
Executive Council
to speed up development of this project. However, no such
Committee ■
was ever established (see Chapter 11).The members of this committee assumed powers and
responsibilities
which they did not lawfully have.[21.9] SECOND DEFECT: ILLUSION THAT AN EQUAL OPPORTUNITY HAD
BEEN GIVEN TO ALL COMPANIES AND CONSORTIUMS TO SUBMIT
PROPOSALSParagraphs 8 and 9 refer to the various expressions of
interest that were
lodged and clearly give the impression that all of the
companies and
consortiums were given a fair opportunity to lodge
proposals for the
project. As the Ombudsman Commission explained earlier in
this report,
that was far from the truth (see particularly Chapter 9).The shortlist for this project was arbitrarily prepared by
the Minister for
Transport without advice or consultation. Some companies
which had
expressed interest did not even receive an acknowledgement
from the
Department of Transport. Some unknown foreign companies
which had no
experience operating in Papua New Guinea were given
special treatment
by the Minister for Transport. Other companies were
shortlisted, though
they had no experience at all in road construction or
design. -
Page 279 of 397
-
Chapter 21
252
The statement in paragraph 8 that the proposals of fifteen
consultants
were presented to a Steering Committee meeting on 31 July
1990 is false
and misleading (see Chapter 7).There was never any meeting at which all of the proposals
were fairly and
objectively evaluated[21.10] THIRD DEFECT: FAILURE TO PROPERLY REPORT THE
RECOMMENDATIONS OF THE WORLD BANKThe World Bank reccommended in September 1991 that the
Spring Garden
Road/Poreporena Freeway project be re-tendered (see Chapter
15).Paragraph 25 of the Policy Submission referred to the World
Bank Mission
which made this recommendation but did not make any mention
of that
recommendation.The National Executive Council was not advised of this
crucial piece of
advice from the World Bank.[21.11] FOURTH DEFECT: FAILURE TO EXPLAIN NON-COMPLIANCE WITH
NORMAL TENDERING PROCEDURESThe decision-making process which led to the State entering
into the
contract with Kinhill Kramer Pty Ltd on 27 May 1992 was
fundamentally
unlawful. Legislation such as the Public Finances
(Management) Act and
the Public Works Committee Act was completely ignored (see
Chapters 35
and 36).Chapter 21
-
Page 280 of 397
-
253
The Policy Submission should have given some explanation as
to why
these laws were by-passed. It did not do this.[21.12] FIFTH DEFECT: FAILURE TO REFER TO THE RECOMMENDATIONS OF
THE RESOURCE MANAGEMENT COMMITTEE
Only four days before the National Executive Council decided
to award the
project to Kinhill Kramer Pty Ltd, the Resource Management
Committee
recommended that the project be implemented in three
distinct phases
and put to tender.The Policy Submission failed to refer to either of these
crucial
recommendations.[21.13] SIXTH DEFECT: FAILURE TO EXPLAIN THE HISTORY OF THE KINHILL
KRAMER PROPOSALParagraph 8 claimed that some of the fifteen original
companies which
expressed interest in the project had sought an extension of
time to lodge
their proposals, but that these requests had been rejected.
Paragraph 13
stated that of the original fifteen, only the Kinhill Kramer
consortium
presented a detailed technical and financial proposal. These
statements
were very misleading and false.The truth is that many of the original fifteen companies
were not given a
fair opportunity to submit proposals. Also, in its original
proposal, Kinhill
Kramer Pty Ltd was linked with Kumagai Gumi Ltd of Japan.
The proposal
which was before the National Executive Council in February
1992 was a
new proposal, not involving Kumagai Gumi Ltd. Kinhill Kramer
had beenChapter 21
254
given a considerable extension of time. In fact, as we
revealed in Chapter -
Page 281 of 397
-
19, the new proposal was lodged only five or six days
before the National
Executive Council met.The Policy Submission should have carefully explained
all this for the
benefit of the members of the National Executive
Council.[21.14] SEVENTH DEFECT: FAVOURABLE ASSESSMENT OF THE KINHIll,
KRAMER PROPOSALThe most serious defect in National Executive Council
Policy Submission
No. 33/92 was its unjustified favourable assessment of
the Kinhill Kramer
proposal.This unrealistic assessment is something which, we
believe, affected the
integrity of the whole decision-making process
concerning this project. It
is dealt with as a separate matter in the next chapter.* * * * * * * * * *
Chapter 21
255
22. FAVOURABLE ASSESSMENT OF THE
-
Page 282 of 397
-
KINHILL KRAMER PROPOSAL
[22.1] THE NATIONAL EXECUTIVE COUNCIL POLICY SUBMISSION WAS
SERIOUSLY DEFECTIVE
We have concluded that the Policy Submission which
resulted in theproject being awarded to Kinhill Kramer Pty Ltd was
poorly prepared andseriously defective (see Chapter 21).
One of the most serious defects was the favourable
assessment of theI
Kinhill Kramer proposal. That assessment was
unjustified.I
When this opinion was expressed in our preliminary
report, we receivedresponses from two persons: the Secretary for
Transport, Mr Amini andI
the Executive Chairman of Kinhill Kramer Pty Ltd, Mr
Kramer.Mr Amini’s response was as follows:
I -
Page 283 of 397
-
I
‘This is a matter of professional judgement.
The detailed proposals were all
put before National Executive Council. Nothing
was hidden from them. I
believe National Executive Council always make
an informed decision. My
Department, however, did argue for more time
but this request was rejected I
by National Executive Council. This is not
defective administration.’
[EXHIBIT 254, para 18]1
Chapter 22
256
Mr Kramer’s response was similar to Mr Amini’s:
“Are you suggesting that the most serious defect(s)” was
the “favourable
assessment of the Kinhill Kramer proposal”. What does this
mean? The
assessment was made by the Department of Transport and
presumably proper
advice was obtained in respect of such assessment The
statements in the
report in relation to this heading are made without any
proper evidence of same
and show, with respect, a very limited understanding of -
Page 284 of 397
-
the bureaucratic
procedures in respect of matters such as this.” [EXHIBIT
253, pars 131Having considered these responses, the Ombudsman Commission
retains
the view that the favourable assessment of the Kinhill Kramer
proposal in
the Policy Submission was unjustified. In this chapter, we
explain the
reasons for drawing that conclusion.Before we do that, it is necessary to specify what the
Kinhill Kramer
proposal consisted of, when it was evaluated by the
Department of
Transport.OUTUNE OF THE KINHILL KRAMER PROPOSAL
[22.2] WHAT DID THE KINHILL KRAMER PROPOSAL CONSIST OF?
This is not a straightforward issue, because there is no
official record of
the Department of Transport receiving the Kinhill Kramer
proposal (see
Chapter 19). It was therefore difficult to conclude, by just
looking at the
Department’s files, what exactly the Kinhill Kramer proposal
was. In
addition, because of the confusing manner in which Policy
Submission No.
33/92 was compiled, it was virtually impossible for anyone
reading it to
work out what the Kinhill Kramer proposal consisted of.Chapter 22
-
Page 285 of 397
-
257
However, after questioning the Executive Chairman of
Kinhill Kramer Pty
Ltd, Mr Kramer, we are satisfied that the proposal
lodged on 18 or 19
February 1992 actually consisted of two separate
documents:1. A spirally-bound document, consisting of twenty-
nine pages (not
numbered consecutively), entitled:“Independent State of Papua New Guinea
Department of
Transport Seaport/Airport Link
Incorporating Burns Peak
Tunnel and Spring Garden Road Turnkey
Proposal The IGnhill
Kramer Consortium February, 1992”.
[EXHIBIT 150]2. A stapled document of two pages, entitled:
“Financial Terms”. [EXHIBIT 151]
[223] THE TURNKEY PROPOSAL DOCUMENT
This document consisted of twelve pages of text, which
formed the main
part of the proposal, and two appendices.[22.4] THE TEXT OF THE PROPOSAL
The proposal was introduced in the following terms:
‘The Joint Venture Consortium of Kinhill Kramer
and a Major Contractor
through their many years of construction
involvement in Papua New Guinea.
Fully appreciate the environmental, social,
political and financial aspects of a -
Page 286 of 397
-
project of this magnitude. In response to known
Terms of Reference the Joint
Venture Consortium shall assemble in the
Preliminary Planning Phase an
experienced multi-disciplined team to fully
investigate and develop an economic
solution in which in the social and environmental
criteria will take precedence.’
[EXHIBIT 15O, para. I.0)Chapter 22
258
The text of the proposal continued:
“The Joint Venture Consortium shall consist of two
principle partners being
Kinhill Kramer and a Major Civil Engineering and
Construction and Consulting Engineering. [sic]
The Project Management and preliminary design
phase followed by detail
design and construction supervision will be
undertaken by Kinhill Kramer the
background of Kinhill Kramer is set out in the
attached appendices.During the Construction Phase, Kinhill Kramer
shall act as the Superintendent
of the Works. Any disputes between the
Government’s Executing Agency and
the Construction Consortium shall be resolved at
the sole discretion of the
Superintendent.Construction works including detailed tunnel
design shall be undertaken by
a Major contractor (yet to be named). The
Contractor shall also arrange the
financing of the project. The background of the
Contractor shall be provided
at a later stage.” [EXHIBIT 150, pars 2.0,
emphasis added][22.5] KINHILL KRAMER DID NOT HAVE A CONSORTIUM
-
Page 287 of 397
-
The significant thing to note is that, though the
proposal was lodged in the
name of “the Kinhill Kramer consortium”, Kinhill Kramer
did not have a
consortium at all. It was a sole proposal by Kinhill
Kramer Pty Ltd. At the
time of lodgment of the proposals, the other member(s)
of “the
Consortium” did not existWhen this point was made in our preliminary report, the
Executive
Chairman of Kinhill Kramer Pty Ltd responded in the
following terms:‘The fact that the Kinhill Kramer Consortium did
not have a company to do
the contracting work is not surprising. There are
any number of major
contractors available who are qualified and have
expertise to carry out this
type of work. There is no attempt by myself in the
proposal to mislead the
State. My statements envisaged “a consortium*.
This was accepted by the
State. At all times, our nomination of the
contractor was subject to National
Executive Council approval. Selection of the
contractor would have been, in
the circumstances, a condition precedent to
overseas funding (as you are
obviously aware).” [EXHIBIT 253, pars 15]Chapter 22
259
[22.6] FINANCIAL TERMS IN THE TURNKEY PROPOSAL
a -
Page 288 of 397
-
The other feature of the text of the Turnkey Proposal
document is thesection headed “Financial Terms”. It states:
‘The Lump Sum Cost of the Project shall be Sixty
Million Kina (IC60,000,000) for
stages 1, 2 and 3 which consist of a four (4) lane
road link between downtown
Port Moresby and Jackson’s Airport including a 2
lane single barrel tunnel
through Burn’s Peak.In addition to this Lump Sum Cost a Five Million
Kina (K5,000,000) contingency
sum has been allowed for. The use of the
contingency sum shall be jointly at
the discretion of the Secretary of the Department
of Transport and the
Executive Chairman of Kinhill Kramer.The Consortium shall arrange a loan for the entire
construction cost of Sixty
Million Kina together with the Five Million Kina
contingency sum. The terms
of the repayment shall be 10 – 15 years repayment
period with a 3 year initial
grace period and at an interest rate not exceeding
10%.The commencement of loan period and the grace
period shall coincide with
the signing of formal contract between the
Consortium and the Government’s
Executing Agency. The contract shall be exempt from
all Government Import
Duties and taxes.” [EXHIBIT 150, para. 6.0]It will be observed that the conditions on which the lump
sum price of theproject would be paid by the State were expressed in very
broad terms:the interest rate was not specified, except to say it
would not exceed 10% -
Page 289 of 397
-
and the period for repayment of the loan was stated
generally to be “10 –15 years”.
[22.7] THE APPENDICES
There are two appendices which also formed part of the
Turnkey Proposaldocument. (The contents page of the proposal indicated
there were threeappendices, but the first one – “Company Profiles” – is
missing; perhapsbecause, when the proposal was completed, Kinhill Kramer
did not havea consortium partner.)
Chapter 22
260
The two appendices are:
“Appendix B: Preliminary Traffic and Revenue Report”.
This is a one page summary of the document of August
1990, [EXHIBIT 37] which gives an analysis of expected
revenue on the assumption that certain parts of the
Spring
Garden Road network would become subject to a toll.“Appendix C: Port Moresby to (Jacksons) Airport
Arterial
Road Link via Burns Peak Tunnel Technical Feasibility -
Page 290 of 397
-
Report
April 1990″. [EXHIBIT 7B]
This is the document which, Mr Kramer said, had been
submitted to the Department of Transport in 1990.[22.8] THE “FINANCIAL TERMS” DOCUMENT
This was the second part of the Kinhill Kramer proposal.
Mr Kramer stated that this two-page stapled document – which
he referred
to as “the Financial Envelope” – was “attached” to the
“Turnkey Proposal”
document. Though the “Financial Envelope” was physically
separate from
the spirally bound main proposal, the two documents were
clearly meant
to be read together.It is apparent that the purpose of the “Financial Envelope”
was to
elaborate on the rather general terms in which the
corresponding section
of the “Turnkey Proposal” document was expressed.Chapter 22
261
[22.9] THE KINHILL KRAMER PROPOSAL WAS PREPARED IN A RUSH
It is also apparent, from the way in which the Kinhill
Kramer proposal was
presented (e.g there were a number of typographical errors
and the “Key
Personnel” section did not mention the company’s Executive
Chairman) •
that the Kinhill Kramer Proposal was prepared in a rush.Also, the fact that the Financial Terms document was
physically separate
from the Turnkey Proposal document, shows that the
proposal was
hurriedly put together.
Mr Kramer admitted as much in his evidence to the
Ombudsman ■
Commission. He testified that, as soon as he got the phone
call from the
Department of Transport on 17 February 1992, inviting him -
Page 291 of 397
-
to “update” the
Kinhill Kramer bid, he contacted Kumagai Gumi Ltd to see
if they were still
interested.When Kumagai Gumi said they were not still interested, Mr
Kramer was
put in quite a predicament: he had to lodge a proposal
without a
consortium partner. And because he didn’t have a
consortium partner, he
could not say who the financier would be.Kinhill Kramer Pty Ltd had always intended to arrange
finance for the
project through an export finance corporation such as the
EXIM Bank of
Japan or the Export Finance Insurance Corporation of
Australia. But these
institutions invariably insist that the major contractor
is a resident of the
country exporting finance for the project. So, if Kinhill
Kramer didn’t have
a contractor, they also didn’t have a financier.When these findings were made available in our preliminary
report, Mr
Kramer made the following comments:Chapter 22
‘The heading under this section [Le.’the Kinhill Kramer
proposal was prepared
in a male] is subjective and improper. It is further
evidence of the bias shown
in the report. Paragraph 2 under this heading is absurd.
I do not understand
how the physical presentation of a document could show
‘that it was hurriedly
put together’. Indeed if it was ‘hurriedly put together’
what does this mean?.
Presumably it means it was done in a hurry.’ [EXHIBIT
253, paraWe note that Mr Kramer did not deny that the proposal was
done in a
hurry. There is no other conclusion that can be drawn.The finding that the proposal was prepared in a rush is not
meant as a -
Page 292 of 397
-
criticism of Kinhill Kramer or its Executive Chairman. It is
simply a finding
of fact, which is reported here to illustrate the unusual
circumstances
leading to and in which the National Executive Council came
to make its
decision on 24 February 1992.THE PRICE OF THE PROJECT
[22.10] DIFFICULTIES IN PRICING THE PROJECT
As to the task of quoting a lump sum price for the project,
this also
presented Mr Kramer with some difficulty. He stated to the
Ombudsman
Commission that he was concerned that the company did not
have
sufficient information on which to base a price. He said
that Kinhill Kramer
Pty Ltd, was reluctant to submit a price to the Department
of Transport
without having had an opportunity to consider the
geotechnical report of
Coffey Partners International, which had been arranged by
the Department
of Works (see Chapter 8).Chapter 22
263
[22.11] DEPARTMENT OF TRANSPORT HAD CONSISTENTLY FAILED TO
SPECIFY THE SCOPE OF THE PROJECTMr Kramer’s claim that he had insufficient information on
which to base a
price is an understatement. As we have noted a number of
times -
Page 293 of 397
-
previously, the scope of the Spring Garden Road/Poreporena
Freeway
project was poorly defined from the very beginning – when
the National
Executive Council decided that “the Burns Peak Road” should
be
constructed.It was, by February 1992, more than two years since that
vague decision
was made and in all that time the Department of Transport
had been
unable to define, with any precision, the route of the
freeway or its basic
engineering characteristics. Even in February 1992 – almost
a year after
the results of the geotechnical investigation were released
– no decision
had been made on the tunnel/cut option.Mr Kramer said that, when the Kinhill Kramer proposal was
lodged, the
company had not seen the results of the geotechnical
investigation. In
these circumstances, any figure that Kinhill Kramer Pty Ltd
were to quote
would, at best, have to be a rough “guesstimate”.This was a very unsatisfactory situation. In the opinion of
the Ombudsman
Commission it is very poor administrative practice – and it
defies common
sense – to expect companies to submit firm proposals when
the exact
scope of a project is not known. The Department of Transport
must be
held responsible for allowing this unsatisfactory situation
to develop. The
Terms of Reference released – selectively – in early 1991
did not specify
the end points of the freeway. Twelve months after that, the
Department
of Transport still hadn’t specified exactly what it wanted.Chapter 22
264
[2212] K25 MILLION INCREASE IN THE PRICE OF THE PROJECT
-
Page 294 of 397
-
There is one part of Kinhill Kramer’s February 1992 proposal
that needs
to be specially noted: the substantial increase in the price
of the project.When Kinhill Kramer submitted its “Technical Feasibility
Report” to the
Department of Transport in April 1990 it quoted a price for
the Spring
Garden Road/Poreporena Freeway project of K40 million (see
Chapter 19
and Exhibit 7B, page 15).But, when the February 1992 proposal was submitted, the price
had
increased to K65 million.This obviously should have been a matter of concern to the
Department
of Transport when it was evaluating the February 1992
proposal. How can
the cost of a road project increase – without explanation –
by more than
60% in less than two years? How could such a huge increase be
overlooked by the Department of Transport in its evaluation?The following explanation of the K25 million increase in the
price of the
project was provided by Mr Kramer:‘The 1990 figure (MOM) was a highly qualified ESTIMATE or
the likely cost
of the project, on 1990 prices.
A price produced some 2 years later must, first, be
adjusted for inflation
(escalation) at 10%.That, alone, escalates the K4OM to around the project bid
calculated to the
medium point of actual constructions period.Much more importantly, the February 1992 bid was no longer
an ESTIMATE
but fl2(1:2AMMMAPMa accepting liability for all and any
increases and
contingencies’. [EXHIBIT Z53, para 181 -
Page 295 of 397
-
Chapter 22
265
[22.13] 1990 PRICE ALTERED BY KINHILL KRAMER
We noted earlier in this chapter that the 1990 document was
included asone of the appendices to the February 1992 proposal.
However, pages 10and 15 of the 1990 document – which deal with the project
cost – werealtered when these pages were annexed to the. 1992
proposal.Page 10 of the 1990 document stated:
“Subject to prevailing costs, at the time of
commissioning of the new proposed
Arterial Road and Tunnel the cost of construction
would be in the range of
KINA 40.0 million, and the cost breakdown is given in
Table 3.’
[EXHIBIT 7B, page 15]By contrast, the altered version, attached to the February
1992 proposal,stated:
-
Page 296 of 397
-
“Subject to prevailing costs, at the time of
commissioning of the new proposed
Arterial Road and Tunnel the cost of construction
would be in the range of
KINA 60,0 million, and the cost breakdown is given in
Table 3 based on 1992
construction rates.” [EXHIBIT 150, page 15 of Appendix
C]Page 15 of the 1990 document, which contained the cost
breakdown, wasalso altered when it appeared in the February 1992
proposal. Acomparison of the different versions of the cost breakdown
reveals that allcost items were increased markedly, as follows:
Chapter 22
-
Page 297 of 397
-
266
DESCRIPTION COST SHOWN IN COST SHOWN IN ALTERED
ORIGINAL 1990 VERSION ANNEXED TO 1992
DOCUMENT PROPOSALRelocation cost K 500,000.00 K 750,000.00
Roadworks K12,600,000.00 K 24,250,000.00
Bridgeworks K 2,100,000.00 K 7,000,000.00
Tunnel Works K16,250,000.00 K 20,000,000.00
Traffic Lights K 1,500,000.00 K 2,000,000.00
Contingencies K 3,295,000.00 K 5,000,000.00
Fees K 2,295,000.00 K 6,000,000.00
Total Say K40,000,000.00 K 60,000,000.00
[See EXHIBIT 7B, page 15 & EXHIBIT 150, page 15 of Appendix C]The point to be emphasised here is that, since the April 1990
document
was attached as an appendix to the February 1992 proposal, it was
reasonably to be expected it would be a replica of the April 1990
document. There was no indication that the figures in the appendix
had
been altered or ‘updated’.Mr Kramer stated that the amendment of the 1990 schedule to 1992
values was made expressly at the direction of the Department of
Transport, which had the 1990 document. He rejected the suggestion
that
the alteration of the figures could have been misleading.
[EXHIBIT 253, para 18]Chapter 22
-
Page 298 of 397
-
267
[2214] DEPARTMENT OF TRANSPORT SHOULD HAVE EXPLAINED K25 MILLION
PRICE INCREASEHaving considered Mr Kramer’s explanation, we still do not
believe it was
right for the Department of Transport to allow a document
dated April
1990 to be annexed to a 1992 document and altered without
any
indication being given that the 1990 document had been
altered.
[EXHIBIT 253, para 18]The Department of Transport should not have asked for or
accepted the
document in that form. At the very least, the Department
should have
indicated in the Policy Submission to the National Executive
Council that
the 1990 figures had been updated. The Department should
have
explained why the estimated price of the project had
appeared to have
risen K25 million in less than two years and whether this
was
reasonable.KINHILL KRAMER PTY LTD GIVEN FAVOURABLE ASSESSMENT DESPITE ITS VAGUE
PROPOSAL[22.15] THE RECOMMENDATIONS OF POLICY SUBMISSION NO 33 OF 1992
The aspect of Policy Submission No. 33 of 1992 which made it
very
different to the previous one prepared by the Department of
Transport
was that it gave the National Executive Council a choice of
two
consortiums:Chapter 22
268
The Chinese consortium, which the Submission referred
to -
Page 299 of 397
-
as the “Tunson Engineering consortium”.
.QBThe “Kinhill Kramer consortium”, which was referred
to as a
consortium, even though the proposal had been lodged
by
Kinhill Kramer on its own.The recommendations of the Policy Submission were expressed
in the
following terms:“It is recommended that either consortium can be
selected. Tunson Engineering
consortium is proposing a better financial package
provided the source of
funding is confirmed. The Kinhill Kramer consortium has
advantage of
experience and quality product.It is also recommended that NEC direct Department of
Finance and Planning
and Department of Transport to carry out further
negotiations with the
approved consortium in consultation with the Department
of Attorney General.
Alternatively, it may be desirable to seek B.O.T or full
turnkey proposals for
design, construction and finance from all the companies
and consortiums who
registered interest’ [EXHIBIT 148, page 10][22.16] NEITHER CONSORTIUM DESERVED TO BE SELECTED
This was a very strange set of recommendations. The third
paragraph
seems to be an admission that all companies and consortiums
which had
expressed interest in the project had not been asked for
proposals. This
was, of course, quite true. -
Page 300 of 397
-
Chapter 22
269
In making this recommendation the Minister for Transport and
the
Department of Transport seem to have expressed a lack of
confidence in
their recommendation in the first paragraph that “either
consortium can be
selected”. The Ombudsman Commission considers that such a
lack of
confidence was warranted.In the opinion of the Ombudsman Commission, neither
consortium
deserved to be selected. The decision-making process that led
to the
National Executive Council being faced with this choice of
two proposals
was a shambles. There was insufficient information on which
the National
Executive Council could base an informed decision.Unfortunately, the Department of Transport was under pressure
from the
Minister to expedite the project. So, rather than
recommending to the
Minister that the project be put to tender in the normal and
lawful manner,
the Department inserted the vague recommendation that “it may
be
desirable” to seek more proposals.[2217] THE FAVOURABLE ASSESSMENT OF KINHILL KRAMER PTY LTD
Though the submission recommended that “either consortium can
be
selected”, this was not actually consistent with the
comparison of the two
proposals provided. On page 8, five criteria were identified
and the
proposals were ranked as follows: -
Page 301 of 397
-
Chapter 22
270
CRITERION KINHILL KRAMER TUNSON
Financier’s credibility excellent not clear
Financial package satisfactory to excellent
goodRelevant experience excellent confined to
China and not
clearExpected quality of excellent satisfactory
tunnelEmployment Papua New Guinea could be Chinese for
at least for unskilled labour
unskilled work[EXHIBIT 148, page 8]
Kinhill Kramer was ranked more favourably than the Chinese
consortium
on all but one of the criteria (the financial package). It is not
surprising
therefore that, though the final recommendation was that either
proposal
could be selected, the National Executive Council decided in favour
of
Kinhill Kramer.However, a dose examination of Kinhill Kramer’s ranking on four of
the -
Page 302 of 397
-
five criteria shows the whole decision-making process to be very
suspect
and verging on a farce.Chapter 22
271
FINANCIAL CRITERIA
[22.18] THE CRITERION OF “FINANCIER’S CREDIBILITY”
On this criterion, Kinhill Kramer was ranked “excellent”.
The Ombudsman
Commission finds this quite remarkable, because there was no
indication
given in the Kinhill Kramer proposal of who the financier
was going to be.The Ombudsman Commission is at a loss to see how any
reasonable
person could conclude from the Kinhill Kramer proposal that
their
financier’s credibility was “excellent”. Nobody – including
Kinhill Kramer –
knew where the finance was going to come from. The reason
for this was
explained earlier: after Kumagai Gumi dropped out of the
negotiations,
Kinhill Kramer did not have a consortium partner to do the
construction
work and so their source of finance was not known.Mr Kramer explained to the Commission that the documents
were drafted
in such a way that it was a matter for the consortium to
obtain the proper
finance within the parameters set in the proposal. We accept
that that was,
in fact, the situation. [EXHIBIT 253, paragraph 19] •Nevertheless the Ombudsman Commission concludes that it was
irresponsible of the Department of Transport to give the
company an
“excellent’ ranking on the issue of “financier’s
credibilityTM, when the -
Page 303 of 397
-
proposal did not name who the financier was going to be.
Chapter 22
272
[22.19] THE CRITERION OF “FINANCIAL PACKAGE’
On the issue of “financial package”, Kinhill Kramer was said
to be
“satisfactory to good”. But satisfactory to good, compared
to what? The
Policy Submission made the following comments:“From the cost point of view, Kinhill Kramer at K60m
would be a less attractive
consortium to Tunson Engineering at US$49383m.
From the point of view of financial package, Tunson
Engineering consortium
has proposed a better package.° [EXHIBIT 148, page 71It is apparent that the only benchmark against which the
Kinhill Kramer
financial package was being judged was the financial package
contained
in the contract agreement the Minister for Transport had
signed with
Tunson Engineering Co. Ltd on 15 October 1991 (see Chapter
14).We have already remarked on the atrocious quality of that
document. It
was so bad it could not be taken seriously. There was also
the problem
of whether that financial package truly represented the
Chinese
Consortium’s proposal. The Minister for Transport had been
negotiating
deals with at least three different Hong Kong-based
companies during
1991, as well as a couple of different agencies of the
Chinese -
Page 304 of 397
-
Government; so how could it be said that the package
referred to in the
Tunson contract was the real one?There was also a huge question-mark surrounding the bona
fides of the
Tunson company. The Department of Transport had still not
established
whether the company was genuine.Chapter 22
273
[22.20] THERE WAS NO GENUINE STANDARD AGAINST WHICH THE KINHILL
KRAMER PROPOSAL COULD BE JUDGEDIn these circumstances, it was very dangerous to use the
Tunson financial
package as a basis for comparison with the Kinhill Kramer
package. The
point is, there was no genuine standard against which the
Kinhill Kramer
financial package could be judged. Kinhill Kramer was
quoting an all-up
cost of K65 million, but there was no guarantee that that
figure was
realistic or that it represented value for money.[2 91] THE SECRETARY FOR TRANSPORTS COST ANALYSIS
When we suggested in our preliminary report that the
Department of
Transport had failed to check Kinhill Kramer’s price, the
Secretary for -
Page 305 of 397
-
Transport , Mr Amini, disagreed:
This statement is incorrect The Department did
check the price of 1065
million. The Department in accepting the cost was
guided by the World Bank
financed Port Moresby Road Needs Study which was
undertaken by Ow Arup
Consultants. The study estimated the cost of the
section of the project The
report was reviewed by Department of Transport,
Department of Works,
Department of Finance and Planning and the World
Bank and was accepted.’
[EXHIBIT 254, pare 191Mr Amini’s cost analysis can be summarised as follows:
Town to Boroko Drive K40 million
Boroko Drive to Airport K 5 million
Fly-overs K 5 million
Detailed design K 5 million
Cost increases K16 million
TOTAL COST K 71 MIWONChapter 22
274
With respect to the Secretary for Transport, we find his explanation
unsatisfactory. The analysis he provided was in the form of a
response
to the preliminary findings of the Ombudsman Commission. However,
there was no document in the Department of Transport files which
supported his analysis.It appears that the Secretary has only provided the Ombudsman
Commission with a retrospective justification of why, in his view,
the price
of K65 million was acceptable.He has been unable to convince us that any proper cost analysis of
the
project was undertaken before the Kinhill Kramer financial package
was
described in the Policy Submission as “satisfactory to good”. -
Page 306 of 397
-
Even if we accept that the analysis presented by Mr Amini was
undertaken
when the Kinhill Kramer proposal was being evaluated, it was, in our
opinion, a bad piece of administration to evaluate the cost of a
definite
proposal for a project by comparing it with (what could only have
been)
a rough estimate made in the course of a general study of the road
needs
of Port Moresby.The Ombudsman Commission maintains the view, expressed in the
preliminary report, that there was no genuine standard against which
the
Kinhill Kramer proposal could be judged and that the Department of
Transport failed to properly check Kinhill Kramer’s price.Chapter 22
275
[22.22] WAS THE PRICE QUOTED BY KINHILL KRAMER TOO HIGH?
In making the finding that there was no genuine
standard against which
the Kinhill Kramer financial package could be judged,
the Ombudsman
Commission is not saying that the price quoted by
Kinhill Kramer was
definitely too high.This point needs to be emphasised because, in his
response to our draft
report, the Executive Chairman of Kinhill Kramer Pty
Ltd was concerned
that the Ombudsman Commission had made a judgment on
this issue.
Mr Kramer stated:‘Repeatedly, your investigators show bias in
-
Page 307 of 397
-
their treatment of our February
1992 bid price – wrongly putting it in a
context of Tunson’s figure of K47114 –
odd. This was NOT the comparable figure.Was it deliberate malice that led your
investigators to omit the further K17M
– odd for overpasses? Any why do they fail to
disclose the ‘strings’ attached
to the Chinese bid?The relevance of these comments is that the
writer was repeatedly dismayed
upon reading your draft to note the repeated
and plainly malicious
characterisation of our bid as incapable of
comparison. There cannot always
be a convenient benchmark for the indolent
investigator – in this case, our bid
has to be judged on its own merits. If that
requires careful expert engineering
assessment of our bid’s component elements, so
be it.’ [EXHIBIT 253, para 11]Mr Kramer also provided copies of submissions made to
the Ellis
Commission of Inquiry concerning the price of the
project, to support his
claim that the price of K65 million was not excessive.
(A Commission of
Inquiry into the Spring Garden Road/Poreporena Freeway
project was
established on 30 August 1992; see Chapter 34.)Chapter 22
276
Counsel’s submissions
-
Page 308 of 397
-
Counsel for Kinhill Kramer, S.M. Littlemore, made the following
submissions during the course of the Inquiry:The Kinhill Kramer February bid was not excessive, in all the
circumstances.
It represents no more than 10% escalation of the 1990 estimate
(NB that was an
estimate and not a guaranteed maximum price); it is less than Mr
Clark would
have fixed it at; it is much more favourable than the Chinese Bid
– which was
highly qualified, open-ended, conditional upon the granting of
further mad
building contracts at, obviously, massive budgets, and was
plainly contrary to
the National Interest in that it would have imported coolie
labour; yet had been
Ministerially approved!It is a figure at which the mad would have been built – at a high
standard (Mr
Sharp agrees) and with the customary high quality of Kinhill
Kramer projects
(see Commission Document 0.181page 10).My clients are entirely confident that hindsight will prove the
State lost a
bargain when it cancelled this Contract.Nobody else has offered to build this mad at any price under
these conditions,
and nor will they in future.” [EXHIBIT 249B, Page 9]The Clark report
A report from J A Clark, of the Australian consulting firm Jackson
Clark
Pty Ltd, emphasised the considerable risks undertaken by the Kinhill
Kramer consortium as a result of the special nature of the design-
finance-
construct contract that was to be entered into:“I consider that the terms of the Contract impose risks and
obligations on the
Consortium that would usually be borne by a Principal to the -
Page 309 of 397
-
Contract I
believe that the terms of the Contract had the effect of making
the Contract
Amount a fixed price inclusive of any claims the Consortium may
make and
thus the Consortium was prudently required to make some judgment
as to the
risks of carrying out their obligations under the Contract and to
include what
they considered to be an appropriate monetary allowance in the
Amount they
agreed to perform those obligations.Chapter 22
277
In the usual form of Contract for mad works of this nature used
in Papua New
Guinea or elsewhere allowances for the costs of many of the
those risks would
not be included in the Contract Amount but would be the subject
of additional
payments by the Principal to the Contractor if and to the extent
those risks
emerged as actual events.” [EXHIBIT 249A, page 4]This report emphasised the substantial cost risks arising from the
unknown quality of the material accruing from the excavation of
Burns
Peak, the inability of the consortium to recover the costs of any
delays by
way of claims on the State, the uncertainty surrounding the extent
of
relocation of public utilities, the likely problem of land
acquisition and the
consortium’s obligation to arrange finance for the project within
the
maximum rate provided for in the contract of 9.5%.The report concluded:
-
Page 310 of 397
-
‘n my opinion and experience all of the above matters represent
substantial
risks which are likely to occur on a mad construction project in
Papua New
Guinea. In my experience significant costs would result from
their occurrence.
The question of what financial provision should be made for
those risks is a
matter for those who would be accepting the risks and their
assessment of them
together with their ability to overcome them as they arose.
Whatever provision
was allowed would be additional to costs which were taken from
the more
usual type of construction contract. The events giving rise to
such cost
allowance may not occur at all, occur in part, or occur in
excess of the
allowance but that is the risk a contractor accepts in such a
contract as this.In return the Principal has obtained the benefit of a fixed cost
for the project
without him being exposed to the cost of these substantial
risks.If the Contract Amount for the Poreporena Freeway is to be
compared against
the cost of other freeway projects it is important that the
comparison be made
with a project having a similar work content and similar risk to
the contractor.’
[EXHIBIT 249A page 8]Chapter 22
278
[2223] CONCLUSION AS TO THE PRICE OF THE PROJECT AND THE RANKING
-
Page 311 of 397
-
GIVEN TO THE KINHILL KRAMER FINANCIAL PACKAGE
We reiterate that we have nat concluded that the price of K65
million for
the Spring Garden Road/Poreporena Freeway project was
definitely too
high. Nor have we said that the State obtained a bad deal
when this
price was agreed to.But what we do say is this: if the State was getting value
for money or
as Kinhill Kramer asserted – “a bargain”, that situation had
only come
about by pure accident.During the course of this investigation, nothing could
convince the
Ombudsman Commission that the decision to award the project
to the
Kinhill Kramer consortium had been made in a competent,
rational,
methodical or professional manner.Many other companies had expressed interest in this project,
but they
were prevented from providing any competition for the Kinhill
Kramer
proposal by the arbitrary and mysterious short-listing
process that
occurred in 1990 and 1991 and by the Minister for Transport’s
decision to
invite only Kinhill Kramer to update its proposal, when the
National
Executive Council was on the verge of making its decision in
February
1992So, although the Kinhill Kramer financial package was
described in the
Policy Submission as “satisfactory to good”, it could well
have been one
of the most expensive options available to the Government,
since there
was no public tender.Chapter 22
279
-
Page 312 of 397
-
The Ombudsman Commission therefore concludes that, at the
time the
National Executive Council made its decision in favour of
Kinhill Kramer,
nobody could possibly have known how good the Knhill Kramer
financial
package was. It was entirely irresponsible for the
Department of Transport
to proffer the view that it was “satisfactory to good”.ENGINEERING CRITERIA
[22.24] THE CRITERIA OF “RELEVANT EXPERIENCE” AND “EXPECTED QUALITY
OF TUNNEL”On both of these criteria Kinhill Kramer was ranked
“excellent”. These
rankings reaffirmed the comparisons drawn earlier in the
Policy
Submission, where it was stated:‘From the point of view of experience, Kinhill Kramer
consortium offers
tunneling and construction expertise having the region’s
largest engineering
design capabilities.
Turman Engineering Consortium’s, and more specifically
the Second Surveying
and Designing Institute’s experience is confined to China
which still uses old
Russian methods of design.’ [EXHIBIT 148, page 7]The claim that Kinhill Kramer has “the region’s largest
engineering design
capabilities” is a direct quote from the letter to the
Department of
Transport from the then Kumagai Gumi-Kinhill Kramer
Consortium dated -
Page 313 of 397
-
25 June 1990. [EXHIBIT 16, page 1, para (iii) referred to in
Chapter 19]Chapter 22
280
In his response to the Ombudsman Commission’s preliminary
report the
Executive Chairman of Kinhill Kramer Pty Ltd maintained that
Kinhill Kramer
is the region’s largest engineering design firm. [EXHIBIT
253, para 20] We
make no comment on this claim. Our point is that the direct
quote from
one of the consortium’s own letters to the Department is not
the sort of
objective assessment that should have been contained in a
Policy
Submission of this nature. It must be comparatively assessed
independently.As to the claim that the Chinese consortium “still uses old
Russian
methods of design”, the Ombudsman Commission was unable to
find any
basis for this very prejudicial statement.The most alarming aspect of Kinhill Kramer’s “excellent”
ranking on
“relevant experience” and “expected quality of tunnel” is,
as pointed out
earlier, Kinhill Kramer had not decided on a contractor to
undertake the
construction phase of the project.[22.25] KINHILL KRAMER DID NOT HAVE A CONTRACTOR
-
Page 314 of 397
-
In Part 2 of their proposal Kinhill Kramer described their
own role as being
confined to project management, preliminary design, detail
design and
construction supervision:“Construction works including detailed tunnel design
shall be undertaken by
a Major contractor (yet to be named). The Contractor
shall also arrange the
financing of the project. The background of the
Contractor shall be provided
at a later stage.” [EXHIBIT 150]Chapter 22
281
This was reaffirmed in Part 3.6 of the submission:
The Major Contractor shall undertake all the construction
works for the project
including the construction of the tunnel through Burns
Peak.”
[EXHIBIT 1501In these circumstances, it was almost deceitful to suggest
that the Kinhill
Kramer consortium’s experience and the expected quality of
the tunnel
they would build were “excellent”. How could Kinhill Kramer
possibly be
given such a favourable assessment when it was not known
what
company was going to build the tunnel and the rest of the
freeway?WHO WAS RESPONSIBLE FOR THE IMPROPER ASSESSMENT OF KINHILL KRAMER?
-
Page 315 of 397
-
[22.26] SUMMARY OF THE DEPARTMENT OF TRANSPORTS ASSESSMENT OF
THE KINHILL KRAMER PROPOSALThe Kinhill Kramer proposal evaluated by the Department of
Transport was
given a very favourable assessment.On each of the criteria “financier’s credibility”, “relevant
experience” and
“expected quality of tunnel”, Kinhill Kramer was given an
“excellent”
ranking. This was despite the fact that nobody – including
Kinhill Kramer
Pty Ltd – knew who was going to build or finance the
freeway.We can only assume that a great deal of credit was being
given to Kinhill
Kramer on account of its past performance and experience in
project
supervision.Chapter 22
tw282
No proper checks had been done on whether Kinhill Kramer’s
quote of
K65 million plus interest represented value for money. And no
mention
was made of the fact that Kinhill Kramer’s price in 1990 was
only K40
million.There was no genuine standard against which the figure of K65
million
could be judged. The only other option offered to the
National Executive
Council was the proposal of Tunson Engineering Co. Ltd. But
there were -
Page 316 of 397
-
so many problems with it, it simply should not have been
taken seriously.The favourable assessment of the Knhill Kramer proposal was
therefore
quite unjustified. Not only that, it was irresponsible. It
was the Department
of Transport who made this assessment. However, the blame for
allowing
this situation to arise does not rest only with the
Department of Transport.(22-27]THE IMPORTANCE OF FOLLOWING CORRECT PROCEDURES
The problem of having to make a last-minute evaluation of a
very late
proposal from only one company would not have arisen if
proper
procedures had been followed by the Minister for Transport in
the first
place.
If the project had been put to public tender, all interested
parties would
have had an equal opportunity to lodge a proposal.A competitive bidding environment would have been created and
there
would have been ample time for a careful and methodical
assessment of
the available alternatives, by an experienced Supply and
Tenders Board –
not by the Minister for Transport or a self-appointed
“Ministerial
Committee” or a selected group of officers within one
Department.Chapter 22
283
Furthermore, if normal procedures had been followed, the rumour and
innuendo which have surrounded the National Executive Council’s
decision
to award the project to the Kinhill Kramer consortium would not have
flourished.* * * * * * * * * *
-
Page 317 of 397
-
Chapter 22
284
23. NATIONAL EXECUTIVE COUNCIL DECIDES TO AWARD
PROJECT TO KINHILL KRAMER CONSORTIUM:
24 FEBRUARY 1992[23.1] DECISION MADE ON MONDAY 24 FEBRUARY 1992
The National Executive Council made its decision on which
consortium
would be awarded the Spring Garden Road/Poreporena Freeway
project
on Monday 24 February 1992.NEC Decision No. 36/92 was recorded in the following terms:
On 24th February, 1992 Council:-
1, approved Kinhill Kramer consortium as the
successful tenderer -
Page 318 of 397
-
to finance the construction of the Spring Garden
Freeway; and2. directed the Departments of Transport, Attorney
General and
Finance and Planning to immediately carry out
further
negotiations with Kinhill Kramer with a view to
finalising all
contractual and financial arrangements within two
(2) months
as of the date of this decision.” [ITT 153)[232] CIRCUMSTANCES IN WHICH THE DECISION WAS MADE
The best thing that can be said about this decision is that
it was made
without a proper regard for normal procedures. But there are
many other
inferences that might be drawn from the circumstances in
which it was
made.Chapter 23
285
To recap, it must be borne in mind that on 17 February 1992 –
only seven days before the National Executive Council made its
decision – the
days before the National Executive Council made its decision –
the
Department of Transport knew nothing about the approved
proposal. It
was hastily put together on 18 or 19 February 1992 and the
Department
of Transport was instructed by the Minister for Transport to
quickly
evaluate it. The proposal was, by necessity, short on detail
and vague.
The company awarded the project did not, at that stage, have a
consortium partner to build the freeway and no finance had been
arranged. Nevertheless, the proposal was rated highly by the
Department
of Transport. -
Page 319 of 397
-
The proposal went to the National Executive Council without
being
evaluated by the Department of Works or the Department of
Finance and
Planning. Normal tender procedures were ignored.Despite the obvious shortcomings in the proposal and the fact
that there was no other against which it could properly be
compared and despite
was no other against which it could properly be compared and
despite
there being no evidence that anybody had properly checked
whether the
quoted price of K65 million was realistic, the National
Executive Council decided to approve it.
decided to approve it.L3] ALLEGATIONS OF BRIBERY AND CORRUPTION
L3] ALLEGATIONS OF BRIBERY AND CORRUPTIONThe Ombudsman Commission is not surprised that following
announcement of the decision, there were numerous allegations
of bribery and corruption. We do not propose to recite them
because they were not
and corruption. We do not propose to recite them because they
were not
supported by evidence.Chapter 23
286
However, we refrain from finding that there was no bribery or
corruption
involved in the decision-making process which led to the
National
Executive Council decision. Having considered all the
circumstances which
led to the decision and, in particular, the consistent
failure to follow normal
procedures, we cannot say that there was no corruption. -
Page 320 of 397
-
[23.4] CHALLENGES TO OPEN FINDING ON THE CORRUPTION ISSUE
When we stated in our preliminary report that we refrained
from finding
there was no bribery or corruption we were challenged by two
respondents.The Executive Chairman of Kinhill Kramer Pty Ltd. Mr Kramer,
stated:‘The draft report asserts that ‘many other inferences can
be drawn from the
circumstances in which (the decision) was made’.That is wrong.
It is trite to say that inferences can only be drawn from
proves facts.There is – as you acknowledge — NO EVIDENCE of any
bribery or corruption.The ‘environment of corruption” reference – is patently
borrowed from the
findings of the NSW LC.A.0 inquiry into the Metherell
allegations and, as
such, is superficial and unworthy. [EXHIBIT 253, paragraph
211The Chairman of the National Executive Council at the
relevant time. Prime
Minister Namallu stated:With due respect, I must beg to take issue with your
highly offensive words.-
To suggest that you “refrain from finding that there was
no bribery’, is
completely unnecessary.
In stating what you stated * you clearly intended to place
in the minds of the
readers that the Cabinet members have been corrupted, but
you can’t prove it!Chapter 23
-
Page 321 of 397
-
287
You next … create the environment “under which a
reasonable mind could
assume corruption’. We suggest this is defamatory. Your
allegations are
unbecoming and unfitting for a high constitutional office:The dangerous trend you now set whereby the National
Executive
Council decisions are exposed to adverse public comment
andThe consequent danger of exposing State Ministers to
ridicule and
unfounded, unsubstantiated scandalous comment.You, as Constitutional Office holders owe a duty to
conduct your affairs with
dignity, proper decorum and to suggest nothing or
insinuate nothing that is
not a fact or truth.We respectfully suggest you delete from your report, the
[paragraphs where
the Ombudsman Commission indicated that it refrained from
finding that there
was no bribery or corruption]. It adds nothing to your
general objectives,
suggests corruption and bribery and creates distress and
anxiety amongst all
former National Executive Council members.Questions of bribery and corruption should be taken up
specifically so that
individual leaders, if any, may be dealt with according to
law and not tried
and convicted by innuendo, insinuation and
suspicion.’ [EXHIBIT 256, page 2][23.5] THE DECISION-MAKING PROCESS MUST BE ABOVE SUSPICION
With respect to the two respondents who challenged our
preliminary
findings, the Ombudsman Commission states categorically that
it reserves -
Page 322 of 397
-
the right, in investigations of this nature, to form and
report an opinion on
the likelihood that corruption was involved in the decision-
making
processes of government.If, as in this case, we have found no proof of corruption, it
does not follow
that we will ignore the issue altogether.One of the central themes of this report is that the decision
– making
process must be above suspicion.Chapter 23
288
Decisions such as who is going to be awarded a multi-million
kina
contract to build a freeway and how much it is going to cost
should be
made fairly, openly and in accordance with law.When decisions are not made in this way, people become
suspicious,
allegations of corruption inevitably arise and reputations
suffer. That is the
price paid by all those involved in the making of these
decisions, and also
by those who benefit from them.Procedures are provided by law and they must be followed for
the benefit
and interests of all concerned.[23.61 MEEIMBORMENTIDELGOBERIEMON
In the opinion of the Ombudsman Commission, the environment
for
corruption was created by the way in which normal and
established
procedures were disregarded soon after the National Executive -
Page 323 of 397
-
Council
decided in January 1990 to go ahead with the project; in
particular by the
way in which the Minister for Transport, Mr Temo, took
control of the
decision-making process.Many of the ingredients of corruption were present, due to:
a flagrant disregard of normal tender procedures
selected companies being invited to lodge proposals
private negotiations involving the Minister for
Transport
being conducted in overseas locations without the
knowledge of his own Department or the National
Executive CouncilChapter 23
289
a very late proposal being invited from only
one
compa y, anda disregard of proper procedures for
presentation of
submissions to the National Executive Council.This is the sort of situation in which corruption can flourish.
Put simply, the National Executive Council decision to approve the
contractor for the Spring Garden Road/Poreporena Freeway project was
made in very unusual circumstances – not in the way we would expect
decisions involving large amounts of public money to be made.In the following chapters, the Ombudsman Commission records the
events
that took place after that decision was made. Many of the things
that
happened – though they did not prove that corruption was involved –
did
nothing to alleviate our concerns about the circumstances which led
to the
decision.* * * * * * * * * *
-
Page 324 of 397
-
Chapter 23
290
24. OVERVIEW OF EVENTS BETWEEN APPOINTMENT OF
KINHILL KRAMER CONSORTIUM AND SIGNING OF CONTRACT:
FEBRUARY – MAY 1992[24.1] THREE MONTH PERIOD UNDER REVIEW
The National Executive Council decided to award the project
to the Kinhill
Kramer consortium on 24 February 1992. Three months later, on
27 May
1992, the Governor-General signed a contract for the design,
finance and
construction of the Poreporena Freeway.Chapters 25 – 32 trace the events that occurred during that
period. It was
a hectic and turbulent time, especially in the second half of
April and early
May 1992 when the National Executive Council received
conflicting advice
on the course of action that should be taken.In this chapter we provide an overview of what happened,
before
recording the events in detail in the following chapters.[24.2] THE NATIONAL EXECUTIVE COUNCIL DECISION NO. 36/92 OF 24
FEBRUARY 1992There are two aspects of National Executive Council Decision
No. 36/92
that need to be noted:Chapter 24
-
Page 325 of 397
-
291
1. The failure to include a number of key Government
agencies
in the negotiating team.2. The imposition of a deadline for completion of
negotiations.[24.3] KEY GOVERNMENT AGENCIES. E G. DEPARTMENT OF WORKS, NOT
INCLUDED IN THE NATIONAL EXECUTIVE COUNCIL DECISIONThe National Executive Council directed that negotiations
with the Kinhill
Kramer consortium be carried out by the Department of
Transport, the
Department of Finance and Planning and the Department of
Attorney-
General. There was no mention of other key government
agencies such
as the Electricity Commission, the National Capital District
Commission and
the Department of Works.It appears that this was not an oversight. The Minister for
Transport’s
Policy Submission, which led to the National Executive
Council decision,
made no reference to any of these other agencies. [EXHIBIT
148, at page
10]It is regrettable that these key agencies were not included
in the National
Executive Council decision. The Department of Works, in
particular, is one
of the National Government’s key implementing agencies for
public works
projects and its administrative structures are geared to
negotiation of
contracts for road projects and the construction and
maintenance of
roads. It was necessary for the State’s negotiating team to
have access
to the experience of the Department of Works and its skilled
officers, so
that an informed position could be taken on the technical
engineering
aspects of the contract documents. It is also one of the
discrete functions
of the Department of Works to “design, plan, supervise, -
Page 326 of 397
-
execute and
Chapter 24
292
maintain Government works”. (See the Determination of the
Functions of
Departments made under the Public Services (Management) Act,
discussed in Chapter 40 of this report.)Though it transpired that the Department of Works was later
involved in
the negotiations, the Ombudsman Commission can see no good
reason
for that Department not being formally included in the
National Executive
Council decision.[24.4] DEADLINE IMPOSED BY THE NATIONAL EXECUTIVE COUNCIL,
The second significant aspect of the National Executive
Council decision
of 24 February 1992 is that there was a time limit imposed:
“all contractual
and financial arrangements” were to be finalised within two
months. Thus
24 April 1992 became regarded as the deadline for completion
of
negotiations.This was a disastrous decision, in the circumstances. The
meeting of the
deadline became an overwhelming pre-occupation of the
Department of
Transport; so much so, that insufficient attention was paid
to ensuring the
interests of the State were properly protected by the terms
of the contract.We believe it was inappropriate for the National Executive
Council to set
a deadline for conclusion of contractual negotiations in this
particular case.
In view of the complexity of the technical engineering
aspects of the
project and its vast budgetary implications the National
Executive Council
should have realised it would be dangerous to rush the
negotiations. If
there was a concern about getting the project started – but
we do not see
why there should have been – this could have been dealt with -
Page 327 of 397
-
by asking
the relevant Departments to report back to the National
Executive Council
at regular intervals on the status of the negotiations.Chapter 24
293
When we expressed these views in our preliminary report, the
Chairman
of the National Executive Council at the relevant time, Mr Namaliu,
responded as follows:‘You suggested the National Executive Council decision 3W92 was
inappropriate
and dangerous. That is a matter of opinion.Experience suggests that unless you give deadlines to
departments, you are not
likely to get any immediate responses. Evil minded people see
evil in
everything, we discharged our constitutional duties in good
faith, taking into
account the Government’s policies to create employment and to get
the work
done quickly.’ [EXHIBIT 256, page 3]Notwithstanding Mr. Namaliu’s views, the Ombudsman Commission sees
no good reason for the National Executive Council wanting to impose
a
strict limit on the negotiations.We appreciate that it is sometimes necessary to give deadlines to
departments, as an incentive to get policies implemented
efficiently. But
this was a very special project. It was not being implemented in the
normal manner. The legal issues created by the use of the turnkey
contract were quite involved. There were also complex engineering
issues
to address. None of the customary land in the vicinity of Burns Peak
had
been acquired. The budgetary and financial implications of a project
of this
magnitude were vast, and it should have been obvious that, because
normal budgetary procedures had not been followed, it would be
necessary for the State’s negotiating team to take special care to -
Page 328 of 397
-
ensure
that Papua New Guinea was getting a good deal and value for money
from the successful consortium.The Ombudsman Commission strongly maintains the view that it was
vital,
in this case, for the State’s negotiating team not to be put under
unnecessary pressure by the National Executive Council.Chapter 24
294
Unfortunately, the fact that a strict deadline was imposed
added to the
suspicion of corruption created by the unusual circumstances
leading to
the selection of the consortium to undertake the project.[24.5] CHRONOLOGY OF EVENTS
The following chronology highlights significant events in the
period
between the National Executive Council decision of 24
February 1992 and
the signing of the contract on 27 May 1992.An asterisk (“*”) is used to highlight meetings of the
National Executive
Council at which the Spring Garden Road/Poreporena Freeway
issue was
discussed.FEBRUARY 1992
*24 February National Executive Council Decision 36/92 to
award project
to Kinhill Kramer consortium.[EXHIBIT 153]MARCH 1992
2 March First meeting between Kinhill Kramer and the State,
represented by officers of Department of Transport
and
Department of Works. [EXHIBIT 155] -
Page 329 of 397
-
6 March Meeting between Kinhill Kramer and the State.
[EXHIBIT
157]Chapter 24
295
10 March Department of Works expresses serious concerns to
Department of Transport about the Kinhill Kramer proposal:“… Kinhill Kramer have simply pulled their estimates
out of the
air”. [EXHIBIT 158]13 March Steering committee meeting. [EXHIBIT 159]
13 March Secretary for Works writes to Secretary for Transport:
am very surprised that.. a very late submission dated
February 1992 by Kinhill Kramer which seemed to say
almost
the same terms and conditions in the Chinese proposal
is the
favourable one.Already there are complaints from other 100% national
owned
companies-.• [EXHIBIT 160118 March Secretary for Transport writes to World Bank seeking urgent
assistance in the form of a legal adviser and technical
expert.
(But there was no response.) [EXHIBIT 162]20 March Meeting between Kinhill Kramer and the State. [EXHIBIT
164]23 March Steering committee meeting. Department of Works
representatives indicated: -
Page 330 of 397
-
“…even at this late stage, something else should be
done. Let
Kinhill Kramer complete the design, Government pay
Kinhill
Kramer for the design, renegotiate with Kinhill Kramer
to design
to Department of Works standards and call tenders for
construction.• [EXHIBIT 166123 March Beca Worley write to Department of Works offering
consultant
assistance. [EXHIBIT 167]Chapter 24
296
APRIL 1992
3 April Meeting between Kinhill Kramer and the State.
Department
of Attorney-General and Department of Finance and
Planning
absent. [EXHIBIT 168]6 April Steering committee meeting. Department of Attorney-
General
and Department of Finance and Planning absent again.
[EXHIBIT 169]WEEK COMMENCING MONDAY 13 APRIL 1992
15 April Morning: steering committee meeting called by
Department
of Attorney-General and Department of Finance and
Planning
– concerned that they did not have a copy of Kinhill
Kramer’s
financial proposal. [EXHIBIT 175]15 April Afternoon: meeting between Kinhill Kramer and the
State,
1.00 pm, to discuss second draft of the contract
documents.
[EXHIBIT 176] -
Page 331 of 397
-
16 April Beca Gure commence review of contract documents.
[EXHIBIT 178]16 April Consortium agreement signed between Kinhill Kramer
Pty Ltd
and Curtain Bros (Old) Pty Ltd. [EXHIBIT 179]Chapter 24
297
WEEK COMMENCING MONDAY 20 APRIL 1992
21 April Maunsell Consultants commences review of draft contract.
[EXHIBIT 180]22 April Department of Transport files National Executive Council
Policy Submission No. 82/92, recommending execution of
draft contract. [EXHIBITS 181, 183]THURSDAY 23 APRIL 1992
23 April Results of Beca Gure review delivered to Department of
Works:‘In its present form the proposed contract is very
heavily i
weighted in favour of the consortium — the draft
documents as
reviewed are seriously flawed and should be totally
rewritten.’
POIDITT 184]23 April Department of Works advises Department of Transport:
11— at this time and date we do not believe that the
-
Page 332 of 397
-
State should
agree with the documents as they now
stand.’ [EXHIBIT IBS]23 April Preliminary review by Maunsell Consultants given to
Department of Works, advising that certain:1—fundamental requirements must be met without
which the
project cannot proceed in any proper
fashion.’ [EXHIBIT 187]Chapter 24
298
*23 April National Executive Council meeting: Departments ofi
Transport, Attorney-General and Finance and Planning
directed to finalise the contract for presentation to
National
Executive Council on Wednesday 29 April. [EXHIBIT 186]FRIDAY 24 APRIL 1992
24 April Secretary for Transport advises officer in charge of
negotiations that a number of Departments are not
supporting the signing of the draft contract and instructs
him
to ensure “everything is in order” before National
Executive
Council meeting on 29 April. [EXHIBIT 190]24 April Department of Works formally advises Department of
Attorney-General that if the draft contract is signed in
its -
Page 333 of 397
-
present form:
“…the State will be seriously disadvantaged”.
EXHIBITS 191,
192]MONDAY 27 APRIL 1992
27 April Secretary for Works writes to Chairman of Resource
Management Committee, to express:‘…deep concern about the way this project is
proceeding without
due protection for the interests of the State’.
[EXHIBITS 193,
196]Chapter 24
299
27 April Secretary for Transport advises Department of Works that
because of their delaying tactics, he was directing the
Kinhill
Kramer consortium to deal only with the Department of
Transport. [EXHIBITS 194, 195]27 April Second part of Beca Gure review delivered to Department of
Works, raising further concerns about draft contract:“…overall, this contract is not sufficiently defined
to identify the
full costs of the project to the Government of Papua
New
Guinea.’ [EXHIBIT 1961 -
Page 334 of 397
-
27 April Department of Transport arranges overnight review of
contract documents by Cardno & Davies. [EXHIBIT 201]TUESDAY 28 APRIL 1992
28 April Secretary for Works advises Secretary for Transport:
We are in favour of the project in principle but
continue to
advise that unsatisfactory aspects of the current
contract
documentation and the land issues, should be sorted
out Infos
a final agreement is signed.These objections are not raised to frustrate and delay
but to
provide proper protection of the State’s
interest.’ [EXHIBIT MO]28 April ElQom formally advises Department of Transport of serious
concerns about the draft contract:The Terms of Payments seem generously biased to the 11
contractor and progress payments are not linked to
work
performance.” [EXHHHT 2021Chapter 24
300
28 April Cardno & Davies review given to Department of Transport,
pointing out defects in the draft contract. [EXHIBIT 204]28 April Department of Works drafted letter to Prime Minister for
signature of Minister for Works, strongly objecting to
execution of the contract in its present form. [EXHIBIT
209] -
Page 335 of 397
-
WEDNESDAY 29 APRIL 1992
29 April Morning: Department of Finance and Planning prepares
analysis of alternative methods of financing the project,
emphasising disadvantages of turnkey financing. [EXHIBIT
199]29 April Morning: Secretary of Department of Attorney-General hand-
delivers letter to Office of Prime Minister, advising he
will not
issue a certificate of legal correctness for the draft
contract.
[EXHIBIT 211]*29 April Afternoon: National Executive Council meeting: Department
of Attorney-General given nine days in which to complete
the
certificate of legal correctness. [EXHIBIT 210]FRIDAY 1 MAY 1992
1 May Senior Department of Transport officer suggests that
Department of Works be re-involved in contract
negotiations.
[EXHIBITS 215, 216, 222]Chapter 24
301
1 May Acting Minister for Finance and Planning suggests that NEC
meeting be brought forward to 6 May. [EXHIBIT 217]MONDAY 4 MAY 1992
4 May Secretary for Transport advises Secretary of the Department
of Attorney-General against complete re-draft of the
contract.
[EXHIBIT 219]WEDNESDAY 6 MAY 1992
6 May Acting State Solicitor (Department of Attorney-General) gives
legal clearance for the contract, but draws attention of
National Executive Council to numerous serious defects in
the contract documents. [EXHIBIT 224]*6 May National Executive Council Meeting Decision No. 83/92:
-
Page 336 of 397
-
directed the Department of Transport and the
State Solicitor’s Office to Immediately confer
and verify” some of the defects in the draft
contract; andadvised the Governor-General to execute the
contract “upon finalization of … above”. [EXHIBIT
225]Chapter 24
302
THURSDAY 21 MAY 1992
21 May Acting State Solicitor advises Governor-General to
sign the
contract. [EXHIBITS 230, 231]WEDNESDAY 27 MAY 1992
27 May Certificate of Technical Correctness presented by
Secretary
for Transport. [EXHIBIT 232]27 May CONTRACT SIGNED
[24.6] RECORD OF EVENTS
The Ombudsman Commission records and comments on the events
of
the period from 24 February to 27 May 1992 in the following
way:Chapter 25 deals with the initial negotiations between
Kinhill Kramer and
the State, paying particular attention to the concerns raised
by the
Department of Works.Chapter 26 assesses the Department of Transport’s reaction to
the efforts
by the Department of Works to delay execution of the
contract.Chapter 27 documents the National Executive Council meeting
on 23 April
1992, at which it was decided to go ahead with execution of -
Page 337 of 397
-
the contract.
Chapter 24
303
Chapter 28 deals with developments between the National Executive
Council meetings on 23 April and 29 April 1992 and assesses the
action
taken by the four key Departments during that period.Chapter 29 documents the National Executive Council meeting on 29
April
1992, as a result of which the Department of Attorney-General was
directed to finalise the draft contract within nine days.Chapter 30 focuses on the legal clearance that emerged from the
Department of Attorney-General, just prior to the National Executive
meeting on 6 May 1992.Chapter 31 records the National Executive Council meeting on 6 May
1991, as a result of which the Department of Transport and the State
Solicitor’s Office were directed to verify certain defects in the
draft contract
prior to its execution by the Governor-General.Chapter 32 examines the events that occurred after the National
Executive
Council meeting on 6 May 1992, up to and including the execution of
the
contract on 27 May 1992.Chapter 33 provides an overview of the contract between the State,
Kinhill
Kramer Pty Ltd and Curtain Bros (Old) Pty Ltd.* * * * * * * * * *
Chapter 24
CONCERNS RAISED BY DEPARTMENT OF WORKS
ABOUT DRAFT CONTRACT: MARCH – APRIL 1992 -
Page 338 of 397
-
[25.1] SIEEMN6GOMMITMEAT GUSHED
Negotiations on behalf of the State were conducted by an
interdepartmental steering committee. In accordance with the
terms of
National Executive Council Decision No. 36192, it comprised
representatives
of three Departments:Transport
Attorney-General
Finance and Planning.Although the Department of Works was not included in the
National
Executive Council decision, officers of that Department were
nevertheless
involved in the initial meetings of the steering committee.There were also occasions on which officers of other
Departments and
governmental bodies were involved, such as the Department of
Lands and
Physical Planning, the Harbours Board, the Post and
Telecommunications
Corporation, the National Capital District Commission and
the Electricity
Commission.A draft contract was prepared by Kinhill Kramer Pty Ltd and
made available
to the steering committee for perusal.Chapter 25
305
The Department of Transport assumed control of the steering
committee,
which met on four occasions between 13 March and 15 April
1992.There were also four meetings between the steering committee
and the
Kinhill Kramer/Curtain Bros consortium, at which the terms of
the draft
agreement were negotiated. These meetings were held on 6
March, 20
March, 6 April and 15 April 1992. -
Page 339 of 397
-
The Ombudsman Commission interviewed a number of members of
the
steering committee in the course of this investigation. After
considering their
evidence, and the minutes of those meetings, we are satisfied
that there
was a considerable difference of opinion within the committee
as to the
acceptability of the terms and conditions put forward by the
Kinhill
Kramer/Curtain Bros consortium.CONCERNS ABOUT THE DRAFT CONTRACT
[252] THE VIEW THAT THE CONTRACT HEAVILY FAVOURED THE
CONSORTIUMSome members of the committee thought the terms were heavily
weighted
in favour of the consortium. These concerns were aired quite
early in the
negotiations.One of the burning issues was the price of K65 million. On 10
March 1992,
the Assistant Secretary (Roads and Bridges) in the Department
of Works,
Mr Bolt, wrote to the Secretary for Transport in the following
terms:Chapter 25
306
“It is difficult to avoid the conclusion that Kinhill
Kramer have simply pulled
their estimates out of the air and if we accept them
without question then
there is a real danger that the Government will be paying
far more for this
project than is necessary.”[Exhibit 1581One member of the committee testified that on a few occasions
the -
Page 340 of 397
-
representatives of the Department of Finance and Planning and
the
Department of Attorney-General deliberately failed to attend
meetings, as
a means of protesting against the course of the negotiations.As a result of these concerns the Department of Works engaged
two
consulting firms to separately review the terms of Kinhill
Kramer’s draft
contract. The consultants were:Beca Gure (PNG) Pty Ltd; and
Maunsell Consultants PNG.
[25.3] PART 1 OF THE BECA GURE REVIEW
Beca Gure was engaged by the Department of Works on 16 April
1992
and presented its review in two parts.The first part was made available on 23 April 1992 – the day
the Minister
for Transport advised the National Executive Council that the
contract
should be signed (see Chapters 26 and 27).Beca Gure provided a detailed commentary on two documents:
Chapter 25
307
the draft contract agreement between the State and the
Consortium; and -
Page 341 of 397
-
the draft “Particular Conditions of Contract for
Payment”.
[Exhibit 184]The commentary was stated to be “an aggregate of concurrent
reviews
carried out by Beca Gure (PNG) and Beca Worley International
(NZ) with
specialist legal advice from Rudd Watts and Stone in New
Zealand”.[25.4] SERIOUS RESERVATIONS EXPRESSED BY BECA GURE
Beca Gure presented a clause-by-clause analysis of the
documents and
expressed many serious reservations. Some of these were:The financing agreement between the consortium and its
financiers was not included in the list of contract
documents.
If this agreement were not integrated within the
documentation, the State would have no idea of the
terms on
which finance was being arranged.The scope of the works was not well defined.
The contract amount was fixed in United States dollars,
thus
exposing the State to the risk of currency
fluctuations.The contractors were entitled to import all plant and
equipment duty free, but there were no limits on its
use after
completion of the project.Chapter 25
308
The State only had three months in which to transfer
possession of the site to the consortium. This was
insufficient,
in view of the landowner issues that were likely to be
encountered and the problem of relocating squatters.The consortium was only required to use its “best
endeavours” to complete the project on time. There were
no -
Page 342 of 397
-
penalties for delayed completion or evaluation or award
of
extensions of time: “the State effectively has no control
over
progress”.There was inadequate provision for the State to monitor
the
progress of construction by a nominated representative
and
no provision for the State to inspect the works for
defects
prior to delivery.The terms of the contract relating to termination were
one-
sided: they gave the consortium innumerable grounds on
which to cancel the contract, but made no provision for
termination by the State.No provision was made for the costs and revenue that
would
be generated by disposal of the spoil from the cut.5.5] BECA GURE ADVISED THAT THE DRAFT CONTRACT WAS SERIOUSLY
FLAWED AND SHOULD BE TOTALLY REWRITTENIn addition to the commentary on particular terms of the draft
contract, Beca Gure advised as follows:
Beca Gure advised as follows:Chapter 25
309
‘We are of the opinion — that the
issues identified herein are of major significance to the State and
warrant urgent and careful consideration.In its present form the proposed
Contract is very heavily weighted in favour
of the Consortium with few, if any,
remedies open to the State in the event of
unsatisfactory performance. The
financial burden placed upon the State by the
various provisions of the Contract is
very considerable and is not balanced by
reciprocal obligations upon the
consortium. The General Conditions of
Contracts as represented by AS2124 -
Page 343 of 397
-
(1981) are largely inappropriate to lump sum
Turnkey contracts and presuppose
independent and impartial action by the
Superintendent, a situation not
inherent in the contractual arrangements
represented by the current
documentation.The requirements for exemption and/or
reimbursement of personal and corporate
taxation, customs duties and levies,
both within PNG and offshore, together with
the requirement for all payments to be
made in foreign currency, are unusual
and further increase the exposure of
the State during the ten year period covered
by the Agreement.It is in the opinion of ourselves and
associated specialist advisers that the draft documents as reviewed
are seriously flawed and should be totally rewritten.
In their present form the documents do
not provide the level of protection and
recourse for the State that would
normally be contained in contracts between
the State and contractors providing
goods and services.There are numerous and onerous
obligations placed upon the State and any
default exposes the State to
substantial additional costs, over and above the
Contract Amount of US$67.6 million.
There is a danger that claims against the
State for default may be translated
into pressures to make concessions to the
Consortium.We earnestly recommend that the Agreement is not signed until the
issues we
have identified have been resolved to
the full satisfaction of the State.the State may wish to consider
requesting competitive tenders for this project.
It is our experience that mad
construction costs are comparable internationally
and in Indonesia current costs for
dual two lane urban motorway, inclusive of
land costs, taxes, duties and levies
and the like are generally US$4 million/km
or US$33.6 million for 8.4 km. While
the Burns Peak excavation is an
extraordinary item it is difficult to -
Page 344 of 397
-
see why the costs for this project are some
USS34 million (or double) the cost of
similar projects elsewhere, and exclude
land costs and all taxes, duties and
the like’.[EXHIBIT 184, pages 2-3, emphasis added]
[25.6] PART 2 OF THE BECA CURE REVIEW : FINANCIAL RISKS
HIGHLIGHTEDThe second part of the review was given to the
Department of Works on27 April 1992, i.e. just two days before the
National Executive Councilmeeting on 29 April 1992 at which final approval
of the contract wasplanned to be given (see Chapter 29).
Chapter 25
310
It incorporated an analysis of financial risks, prepared by Deloitte
Rosg
Tohmatsu, Chartered Accountants, of Auckland New Zealand. This
highlighted a number of additional matters of concern. For example:The State was not protected against the financial failure of
members of the consortium. There were no performance
bonds or similar guarantees and no provision for the State
to take over the contractors’ plant and equipment in the event
of liquidation.The effect of six monthly interest periods would make the real
interest rate in the vicinity of 12%. -
Page 345 of 397
-
Interest charges could add a further US$51 million to the cost
of the project.Exchange rate fluctuations could add to the cost of the
project. A 10% change in the value of the US dollar by June
1995 could increase the contract price by another US$15
million.There was no provision for early re-payment by the State.
Deloitte Ross Tohmatsu concluded by stating:-
‘Overall, this contract is not sufficiently defined to identify
the full costs of
the project to the Government of Papua New Guinea — In terms of
negotiating
position, the State should ensure that all contingencies are
identified, quantified
and satisfactorily addressed prior to making any commitment to
such a
Contract.’ [EXHIBIT 196]Chapter 25
311
[25.71 THE MAUNSELL REVIEW : KINHILL KRAMER’S PRICE SHOULD NOT BE
ACCEPTEDA preliminary review of the draft contract by Maunsell
Consultants was
made available on 23 April 1992, the same day on which the
first part of
the Beca Gure review was given to the Department of Works.
[EXHIBIT
187]A more comprehensive review was delivered on 12 May 1992.
[EXHIBIT -
Page 346 of 397
-
228] This indicated the value of the project was probably
only K50 million
and pointed to the dangers of entering into turnkey
contracts. By the time
it arrived, however, it was too late to have any effect,
because the National
Executive Council had decided on 6 May 1992 to approve the
draft
contract and the price of K65 million.The preliminary review by Maunsells emphasised that the first
thing that
should be done was to engage Kinhill Kramer to complete a
conceptual
design for the project:“IC.K. should be engaged as soon as possible to complete a
conceptual design
for the Project. This should be paid for by the
Government, either on an agreed
Lump Sum or on a Time basis, with a budget limit. If and
when an agreement
is entered into this sum is deducted from the Contract Sum
payable.• [EXHIBIT
187, at page 3]Maunsells further advised it was necessary to establish a
reasonable
market price for the project. It was not satisfactory to
accept the price
quoted by the Kinhill Kramer/Curtain Bros consortium at face
value:Chapter 25
312
“Based on the conceptual design ._ a firm of Quantity
-
Page 347 of 397
-
Surveyors experienced
in the field of the types of construction work
contemplated should be engaged
by the Government to prepare a confidential budget
valuation of the total
Project, including the cost of all site investigation,
design, construction,
supervision, and all ancillary costs such as insurances
and sureties. This would
form a basis for comparison with the Consortium’s Payment
proposals.’
[EXHIBIT 187, at page 3][25.8] CREDIBILITY OF THE BECA GURE AND MAUNSELL REVIEWS
CHALLENGEDIn the course of his response to the Ombudsman Commission’s
preliminary report, the Executive Chairman of Kinhill Kramer
Pty Ltd, Mr F
M Kramer, CBE, challenged the credibility of the reviews
undertaken by
Beca Gure and Maunsells.First, Mr Kramer queried the source of some of the reviews:
“I find, with respect, this part of the report [dealing
with the Beca Gure and
Maunsell reviews] to be incredible. Throughout the report
you have constantly
stated that the State was not properly advised or indeed
received proper
independent advice in relation to the documentation and
other matters in
respect of the project. You then deal with 2 reports
obtained from Beca Gure
and Maunsells Consultants together with a report put
together by Deloitte Ross
Tohmatsu.In relation to both Beca Gure and Deloitte Ross Tohmatsu
it was interesting
to note that both reports were carried out by experts from
New Zealand. I fail
to see how any New Zealander could comment upon matters
relating to Papua
New Guinea. I find this part of the report offensive and
quite obviously
irrelevant to the matters in hand. In relation to the Beca
Gure report I would -
Page 348 of 397
-
refer you to the report of Jackson Clark Pty Limited and
more importantly the
submissions by Counsel in relation to the pricing of the
project.”[EXHIBIT 253, page 8, paragraph 23; note that the Jackson
Clark document and
counsel’s submissions to the Ellis Commission of Inquiry
are highlighted in
Chapter 22 of this report]Mr Kramer also challenged the independence of the reviews:
‘Quite obviously the engineering consultants are
competitors of Kinhill Kramer
Pty Limited and for that reason alone their independence
has to be questioned.’
[EXHIBIT 253, page 9, paragraph 23]Chapter 25
313
Mr Kramer then suggested that much of the advice contained
in the
reviews was ill-informed:‘In relation to the list where Beca Cure expressed many
serious reservations
I make no comment other than to say such comments are
obviously ill-
informed. for example, in respect of point 4 if your
investigations had made
proper enquiry they would have ascertained that the
Customs Department
would not allow the use of duty free plant and equipment
to be utilised on
any other projects. Should this happen duty is
immediately payable. This is
only one example of your investigators lack of partiality
and consideration of
the proper facts.1133CHIBIT 253, page 9, paragraph 231[25.9] RESPONSE TO MATTERS RAISED BY KINHILL KRAMER
-
Page 349 of 397
-
The Ombudsman Commission makes three points about the
matters
raised by Mr Kramer.1. Source of the reviews
As to the fact that two of the reviews emanated from New
Zealand,
we regard this as irrelevant to the question of their
credibility. The
draft contract was one that might have been executed in
any
country having a common law legal system similar to ours.
As
Papua New Guinea does not have an indigenous body of
contract
law, the commentaries on the draft contract did not
require a
detailed knowledge of Papua New Guinea.2. Reviews obtained
As to the reviews being obtained from Kinhill Kramer’s
competitors,
this is a fact. But the specialised nature of the advice
being sought
meant that whoever gave it was likely to be a competitor
of some
sort. The important thing was the substance of the
reviews, not their
WINCE).Chapter 25
314
3. Use of imported plant and equipment
We are very sceptical of the claim that the lack of restriction
on the
use of imported plant and equipment was not a problem because
the Bureau of Customs would not have allowed it to be used on
any other project. -
Page 350 of 397
-
If the duty-free exemption was supposed to be conditional on the
plant and equipment being used only on the Poreporena Freeway
project, it was very important for that to be expressly stated
in the
contract, for a number of reasons:(a) It would have avoided the possibility of disputes
arising
in the future. If the State executes a contract which
imposes no restrictions on the use of duty-free plant
and equipment, the party importing . it may have a
strong case when, say, three years later, the plant and
equipment is used on another project and duty is
sought to be imposed.(b) While the present policy of the Bureau of Customs
might be to impose duty in these circumstances, there
was no guarantee that that policy would have
remained in force for the next few years.(c) There is no guarantee that the Bureau of Customs can
monitor the use of all plant and equipment imported
duty-free.Chapter 25
315
(d) The lack of any restriction on its use left
open the
possibility of abuse: an item might be
imported duty
free, used for only a very short time on
the freeway
project and then sold at market price.Our understanding is that contracts conferring duty-
free status on
plant and equipment almost always include a term
imposing
restrictions on its use.For all of these reasons, we consider the concern
raised by Beca
Gure as to the duty-free provision in the draft
contract (and such a
provision was contained in the final contract) to
have been legitimate
and certainly not ill-informed. [EXHIBIT 231A,
Article 10.1(e)] -
Page 351 of 397
-
[25.10] WERE THE BECA GURE AND MAUNSELL REVIEWS CREDIBLE?
11
Having examined each of the reviews obtained by the
Department of ■
Works, the Ombudsman Commission does not find in them any
evidence
of “bias” against Kinhill Kramer. Each of them appears to
have been
competently and professionally compiled. We do not
necessarily endorse
all of the comments and recommendations they contained.
But there is no
doubt, in our opinion, they raised legitimate matters of
serious concern
about the terms of the draft contract.It was imperative, if the State’s interests were to be
adequately protected,
for the issues raised by the various reviews to be
comprehensively dealt
with in the course of the negotiations with the Kinhill
Kramer/Curtain Bros
consortium. But this did not happen. reChapter 25
316
THE PRICE OF THE PROJECT WAS NOT PROPERLY CHECKED
[25.11] DEPARTMENT OF TRANSPORT MADE NO PROPER ATTEMPT TO CHECK
THE PRICE OF THE PROJECTIn the opinion of the Ombudsman Commission, the advice of
Maunsells
and Delloite Ross Tohmatsu was eminently sensible. One of
the critical
flaws in the National Executive Council decision to award
the project to the
Kinhill Kramer consortium was that there was never any
proper attempt to
evaluate whether the price of K65 million quoted by Kinhill
Kramer was
realistic. Kinhill Kramer was awarded the project without -
Page 352 of 397
-
having to justify
its price (see Chapter 22).Until the contract was signed, it was not too late to
negotiate the price.
However, during the course of negotiations, no attempt was
made to get
an objective, independent valuation of the project. This was
just plain
financial irresponsibility. The Ombudsman Commission is very
concerned
that such an abuse of public money was made possible.When we made these findings in our preliminary report, the
Secretary for
Transport responded in the following terms:“The project cost was K65 million, however, the
Department negotiated the
project cost down from K65 million to K57 million by
changing the terms. The
difference of ICS million was classified as contingency
subject to the State
approval of the need to commit such funds. It may or may
not be used. The
Department of Finance and Planning was aware of this and
did not raise
objection. This is not defective administration.’
[EXHIBIT 254, para 191With due respect to Mr Amini, his assertion that the
Department of
Transport negotiated the price downwards by K8 million is
not supported
by the facts.Chapter 25
317
The “contract amount” actually contained in the contract
executed by the
State was US$67,619,500.00 plus interest. This was expressed
to be
inclusive of a general contingency sum of $5,201,500.00.
There was no -
Page 353 of 397
-
term in the contract which made liability to pay the
contingency sum
subject to “State approval”. That is, the contract amount
was a flat sum
and all payments due by the State to the Kinhill Kramer/
Curtain Bros
consortium were to be calculated in accordance with that
amount. [See
EXHIBIT 231A, Article 5.1 and EXHIBIT 231B, Article 2.1]Again, we are forced to conclude that the Department of
Transport – being
the Department in charge of the negotiations – was guilty of
gross
administrative incompetence and neglect.DEPARTMENT OF WORKS RAISES CONCERNS WITH DEPARTMENT OF TRANSPORT
AND STATE SOLICITOR[25.12] ACTION TAKEN BY DEPARTMENT OF WORKS FOLLOWING
CONSULTANTS’ ADVICE
The first part of the Beca Gure review and the advice of
Maunsells were
made available to the Department of Works on 23 April 1992.
On that day,
the Acting First Assistant Secretary (Technical Services),
Mr. D Gole, sent
a fax to the Secretary for Transport.Writing on behalf of the Secretary for Works, Mr Gole
stated:Chapter 25
318
We write to advise that at this time and date we do not believe
that the StEt(
should agree with the documents as they now stand.We have only yesterday received some of the documents to study
(e.g. concept
and specification and the consortium agreement and contract
agreement) and
note that there are a number of issues outstanding in the
drawings. Some of -
Page 354 of 397
-
the issues previously discussed have not yet being resolved.
We are currently studying the documents and continue to give full
cooperation
to resolve the outstanding issues in the near future, providing
full cooperation
is given by the consortium.’ [T BIT 1851The next day, 24 April 1992, Mr Gale, together with Mr M Sharp, the
First
Assistant Secretary (Operations) in the Department of Works, sent a
letter
by fax to the State Solicitor. This letter summarised the main
concerns
raised by Beca Gure and Maunsells:°It is the professional opinion of the officers of this
Department that =kw
these and related matters are adequately addressed then the State
will be
seriously disadvantaged should the agreement in its current form
be adopted.’
[a= 192, at page 1]The letter to the State Solicitor also raised a number of technical
matters:‘Consideration of the technical proposals has raised concern in
the following
cases.(I)Geometric Design Standards have not been strictly adhered to
Geometric Designs are therefore incorrect,Horizontal Alignments
Vertical Alignments
Cross-.Section
Grades
No spiral curves shownThere is inadequate Definition of Accesses to and from the
proposed
roadwork and the existing road network and properties.Inter-sectional treatments are not detailed and consequently
are not
approved by DOW, NCD. -
Page 355 of 397
-
Chapter 25
319
Plans are incorrect and incomplete and require changes
with respect to,Scales
libelling of features
Reference of Cross-Section TypesAt the time of signing the agreement, the land required
for the project will not
have been acquired. This is an undesirable, and possibly
illegal situation and
could threaten the progress of the works and leave the
State exposed to claims.”
[EXHIBIT 192, at page 3]The covering letter to the first part of the Beca Gure
review (which
recommended that the contract not be signed) was faxed to
the StateSolicitor’s Office on 24 April 1992. [EXHIBIT 191] A copy of
the letter
was also made available to the Department of Transport,
which received
it on 28 April 1992.[25.13] DID THE DEPARTMENT OF WORKS ACT RESPONSIBLY?
As we report in Chapter 26, the suggestion was made in some
quarters
that the Department of Works was acting irresponsibly in
raising these
concerns and protesting about the way in which the
negotiations were -
Page 356 of 397
-
proceeding.
In the opinion of the Ombudsman Commission, the Department
of Works
acted properly in obtaining the reviews from private
consultants. However,
once the results of the reviews were available, the
Department of Works
could have handled the matter more effectively and
professionally.The Department of Works’ letter of 24 April 1992 to the
State Solicitor
[EXHIBIT 192] did not indicate that “the professional
opinion” of the officers
of that Department was based on the reviews that had been
obtained from
private consultants. This letter should have clearly
conveyed that the viewsChapter 25
320
being expressed were not only those of the Department of Works’
officers.
Furthermore, although a copy of that letter was given to the
Department
of Transport, the Department of Works should have expressly stated
to
the Department of Transport that it had obtained the reviews from
private
consultants and given the Department of Transport copies of those
reviews
the moment they became available.We appreciate the difficult position that the Department of Works
was in.
However, if that Department had been willing to communicate more
openly and promptly with the Department of Transport, the relations
between those two departments may not have deteriorated to the
extent
that they did in this case.We also note that the letter of 24 April 1992 to the State Solicitor
was
signed by two senior officers of the Department of Works – not by -
Page 357 of 397
-
the
Secretary for Works. In a matter as important as this, this letter
should
have been signed by the Secretary for Works. Correspondence of this
nature must be signed by, or on behalf of, the departmental head
concerned. If it is not, the impression can easily be obtained that
senior
officers of a department are attempting to by-pass their
departmental
head.So, while the Department of Works acted responsibly in arranging the
reviews of the draft contract, it did not disseminate the results of
those
reviews in the correct manner.* * * * * * * * * *
Chapter 25
321
26. DEPARTMENT OF TRANSPORT RECOMMENDS SIGNING OF
CONTRACT AGAINST ADVICE OF OTHER DEPARTMENTS:
22 APRIL 1992[26.1] DEPARTMENT OF TRANSPORT STILL INTENT ON FINALISING THE
CONTRACTTo a large extent the efforts of the Department of Works
to get the
contract renegotiated were overtaken by other events.Though the Secretary for Transport advised against
awarding the contract
to Kinhill Kramer, he nevertheless saw it as his duty to -
Page 358 of 397
-
implement the
National Executive Council decision of 24 February 1992.
The National
Executive Council stipulated that the contract be signed
within two months,
which meant that 24 April 1992 was perceived as the
deadline. As the
deadline drew near, the Secretary instructed the officer
in charge of the
negotiations with the Kinhill Kramer/Curtain Bros
consortium, Mr Amoako,
to prepare a submission to the National Executive
Council, recommending
the action to be taken.[26.2] DEPARTMENT OF TRANSPORT PREPARES POUCY SUBMISSION
RECOMMENDING THAT THE CONTRACT BE SIGNEDConsequently, Policy Submission No. 82/92 was prepared by
Mr Amoako,
for the Minister’s signature. It was filed on Wednesday
22 April 1992,
together with five copies of a draft contract. [EXHIBIT
181]Chapter 26
322
The Policy Submission stated that the steering committee met with
the
consortium on a number of occasions and that a draft agreement
“substantially agreed to by all parties” had been prepared. The
features of
the contract were described in the following terms:The Consortium will Finance and construct a freeway from Port
Moresby Seaport to Port Moresby Airport.The mad will be 4 lanes all the way through.
The Burns Peak section will be an open cut 8% grade four lane.
There will be a minimum of 2 ‘flyovers* (overpasses) and a
-
Page 359 of 397
-
maximum
of tThe mad will be the first of its kind in the city and in the
country.The Consortium made up of Kinhill Kramer and Curtain Brothers
will
obtain loan to finance the projectUpon satisfactory completion of the project in 36 months the
Consortium
will hand over the project to the State.The State will then begin to pay off the principal of the
loan.The loan amount, drawn down will accrue an interest of 95%,
(This is
expected to be lower at time of signing Contract Agreement).
Interest
will be paid during construction.The total project cost is IC65 million, K5 million of which is
earmarked
for contingencies.There are other technical details of the project still to be
completed
but these should not stand in the way of the Contract
Agreement being
executed, and for works to commence. Understanding has been
reached
with the Consortium.”
[EXHIBIT 183, pages 1-2, emphasis added]The submission concluded by recommending that the National Executive
Council “directs Finance Minister to enter into Agreement by signing
the
Draft Contract with the Consortium.” [EXHIBIT 182, at page 3]Chapter 26
-
Page 360 of 397
-
323
[26.3] RESPONSE BY THE SECRETARY FOR TRANSPORT TO PRELIMINARY
FINDINGSIn our preliminary report, we recorded the view that it was
wrong of the
Department of Transport to recommend to the National
Executive Council,
through the Minister for Transport, that the Agreement be
signed at that
time. The Secretary for Transport, Mr Amini, responded as
follows:‘The submission did bring to the attention to NEC that
there were some
outstanding issues yet to be resolved, yet in Department’s
view they should
not stand in the way of the contract being executed
because the details in
question were to be provided during detailed design and
that was part of the
consortium’s work. Secondly, the Department was of the
view that the Legal
Correctness Certificate would be issued by the Department
of Attorney General
and, if they had concerns, they would be addressed at that
stage, still not too
late, and that is exactly what happened. We took this
approach because it
became clear that the attendances of the Department of
Attorney General
representative at the negotiating meetings were being
interfered with by
Department of Works officials, who wanted to delay the
project so that other
developer’s interests might be promoted. We raised this
concern and it was
repeated by Mr. Karl Stack in an NEC meeting. NEC cannot
be deceived by
this means. It should be remembered that the concerns were
all technical in
nature but the negotiation team’s commission was financial
and legal issues.
The technical issues were to be derived from detailed
design. There was risk
in this but that is a normal part of any turn-key project.
This was not defective
administration.’
[EXHIBIT 254, pars 201 -
Page 361 of 397
-
The Ombudsman Commission does not regard this as a
satisfactory
explanation. In this chapter of the report we explain why it
was premature
to recommend execution of the contract in April 1992.[26.4] WAS THE DEPARTMENT OF TRANSPORT AWARE OF THE CONCERNS
RAISED BY THE DEPARTMENT OF WORKS?Although the Policy Submission was prepared before the
Department of
Works officially conveyed its concerns on the draft contract,
the
Ombudsman Commission is satisfied that those concerns had
been
conveyed, unofficially, well before the submission was
prepared.Chapter 26
324
There had been a meeting on 3 April 1992 between the steering
committee and Kinhill Kramer. The minutes of that meeting
show that,
after the Kinhill Kramer representatives left, the following
discussion took
place:‘Assistant Secretary (Roads and Bridges) [in the Dept of
Works] expressed
serious concern that the committee will not be able to
adequately assess/change
the agreement documents and drawings by the deadline for
submission to NEC.First Assistant Secretary (POS) Um the Dept of Works]
stressed the importance
of identifying and clearly stating the shortcomings,
dangers and extra costs of
the final Agreement to the NEC. -
Page 362 of 397
-
Tony James (World Bank) joined the meeting and suggested
that the best way
to do this project is by regular procedures. He said that
the Government can
arrange much better loan terms than a commercial venture,
and the cost would
be significantly less. He also mentioned that the
interpretation of the word
‘Turnkey’ is situation dependent.Johnson Amoako mentioned that the DOT – DOW liaison
meetings are off,
and that meetings and communications will continue on a
more informal basis.’
[1•)011Bff 168, at page 4]It is clear that officers of the Department of Works were
conveying their
concerns to Mr Amoako informally.[26.5] CONCERNS ALSO RAISED BY DEPARTMENT OF ATTORNEY-GENERAL
AND DEPARTMENT OF FINANCE AND PLANNINGThe Department of Transport was also aware the Department of
Attorney-
General and Department of Finance and Planning were concerned
about
many aspects of the contract. On 15 April 1992, for example,
officers of
those departments called a special meeting of the steering
committee to
protest against the fact they had not yet seen Kinhill
Kramer’s financial
proposal. They had no knowledge of the proposed financing
agreement
between Kinhill Kramer and the Export Finance Insurance
Corporation.Chapter 26
325
-
Page 363 of 397
-
Mr (rung, Assistant State Solicitor, informed the meeting that the
Department of Attorney-General “required the financial proposal
before they
can go through the contract documents for their comments”. [EXHIBIT
175, at page 2]The minutes of the meeting also record the following statements made
by
Department of Finance and Planning officers:es. The Chairman informed the meeting that although the
financial proposal
was not available the committee should proceed to dear other
issues
where we have information. The committee has a deadline to
meet and
it should work towards meeting the deadline.6. DOFF provided the following comments:-
6.1 The financial package and scope of IC65 million to be
negotiated.6.2 RMC did not support the project.
6.3 The World Bank’s advise has changed and recommended
Government
financing.
6.4 Department of Works’ cost is IC40-50 million and Kinhill
Kramer’s cost
is IC65 million. The final figure should be established.6.5 Debt servicing gap needs to be reduced over the years. The
gap will
be increased if this project proceeds.6.6 Other Transport projects and overall capital works programme
will be
affected if the project proceeds. DCA also have a proposal
for a turnkey
project on Tokua Airport.” [EXHIBIT 175, at pages 2-3]These were important matters which should not have been just swept
aside by the Department of Transport and the Minister for Transport. -
Page 364 of 397
-
Chapter 26
326
[26.6] DID THE DEPARTMENT OF TRANSPORT ACT RESPONSIBLY IN
RECOMMENDING THAT THE DRAFT CONTRACT BE SIGNED?The meeting called by the Department of Attorney-General and
the
Department of Finance and Planning took place on Wednesday 15
April
1992 – just one week before the recommendation that the
contract be
signed. The concerns that had been raised were not addressed
in the
intervening period.The Department of Transport prepared the Policy Submission in
the
knowledge that the Department of Works, the Department of
Attorney7
General and the Department of Finance and Planning had
serious
reservations about the draft contract.For this reason, we find that it was irresponsible of the
Department of
Transport and the Minister for Transport to recommend to the
National
Executive Council, at that stage, that the contract be
signed.It was misleading to suggest that the draft contract had been
“substantially
agreed to”. The fact was, there was vehement opposition to it
by the
Department of Attorney-General, the Department of Finance and
Planning
and the Department of Works.It made no sense to concede that there were “other technical
details of the
project still to b.g completed”, but then to conclude that
“these should not -
Page 365 of 397
-
stand in the way of the Contract Agreement being executed”.
It was wrong
and not in the best interests of the State.It was naive to believe that, because an “understanding” had
been reached
with the consortium, the technical details could be sorted
out at some later
time.Chapter 26
327
The Ombudsman Commission appreciates that the National
Executive
Council had set a deadline and that, at the time this Policy
Submission
was prepared, it was fast approaching. But what is more
important:
achieving a deadline or protecting the interests of the State?The Ombudsman Commission has formed the view that the
Department
of Transport had no proper appreciation of the complexity of
the technical
and legal issues involved in a contract of this nature.[26.7]WHAT MOTIVATED THE DEPARTMENT OF TRANSPORT TO IGNORE THE
ADVICE OF THE DEPARTMENT OF WORKS?The Secretary for Transport believed that the Department of
Works was
attempting to “interfere” in what he regarded as a Department
of Transport
project.Relations between the two Departments had been frosty for some
time.
The situation did not improve when Mr Lohia Hitolo (until
1992, a senior
officer of the Department of Transport and in charge of the
Spring Garden
Road/Poreporena Freeway project) was appointed Secretary for
Works.In Chapter 18, we noted the tension created when Mr Hitolo, as
Secretary
for Works, briefed the Minister for Transport on the project –
without telling
the Secretary for Transport – just a few weeks before the
National -
Page 366 of 397
-
Executive Council decided to award the project to the Kinhill
Kramer
consortium.Chapter 26
Mr Arnini’s terse response to that incident was:
The matter of Spring Garden Road is the responsibility of the
Department of
Transport until such time as the consortium is selected and all
the detailed
contracting arrangements are completed. At the time of design and
construction, the Department of Works will be fully involved”.
[FJCHIBIT 149]It is evident that, because of the approach taken by the Department
of
Works during the steering committee meeting, the Secretary for
Transport
formed the view that the Department of Works was opposed to the
project. These views were expressed in an internal Department of
Transport memo to Mr Amoako on 24 April 1992:‘As discussed yesterday (23 April), it was revealed that a number
of
Departments is reluctant to give a full support to this
Submission because they
feel strongly that some important technical issues have not been
seriously
addressed by Kinhill Kramer Consortium and unless they are
attended to, they
are of the view that the submission should be deferred. In
particular, is the
Wog
Department in what we have been directed to do by National
Executive
Council.The General Manager of Elcom also verbally told me yesterday that
he is
writing to us to express his views that we should seriously study
the technical
aspects of the project and seek an independent Consultant to -
Page 367 of 397
-
assist us because
he fears that the Kinhill Kramer Consortium has not addressed
these thoroughly
and there may be flaws in their submission to the Government
through the
Department.If these organizations are expressing their doubts on this
project, we should
at least try to listen to them and reassess our approach to it.It could be that these organizations may have been approached by
Department
of Works personnel who have been opposing this project to get off
the ground.
This assumption is based on what you have told me yesterday. This
could be
wrong but quiet investigation could reveal this one way or
another.It is quite clear that a number of organizations has vested
interest in this project
and, unless these issues are addressed, these organizations could
stifle the
project thus discredit the Department and embarrass the
Government altogether.
This must not happen at all cost! You are, therefore, directed to
ensure that
everything is in order before the submission is submitted to
National Executive
Council on 29 April.” [EXHIBIT 190, emphasis added]Chapter 26
329
The Secretary for Transport expressed the same views when, on
27 April
1992, he replied to the Department of Works’ advice that the
contract with
Kinhill Kramer should not be signed:‘Having tried to frustrate the deliberation of the
Committee, it is not surprising -
Page 368 of 397
-
to us to receive such a letter at the last day and put the
blame on the
Consortium for lack of cooperation, when the Consortium
had given the
Committee full cooperation by meeting demands placed on
thene.[EXHIBIT
194]On the same day, 27 April 1992, the Secretary for Transport
directed the
Kinhill Kramer/Curtain Bros consortium to deal only with the
Department
of Transport. [EXHIBIT 195][26.8] NO JUSTIFICATION FOR DEPARTMENT OF TRANSPORT IGNORING THE
CONCERNS OF OTHER DEPARTMENTSThe Secretary for Transport thought that the Department of
Works was
motivated more by a desire to embarrass the Department of
Transport,
than genuine concern for the interests of the State.But even if this were, in fact, the case, the Ombudsman
Commission can
see no justification for the Department of Transport ignoring
the issues that
had been raised. Concerns were being expressed, not only by
the
Department of Works, but also by the Department of Attorney-
General and
the Department of Finance and Planning.These issues were fundamental to the contract and required
urgent
attention. They were never properly addressed during the
negotiations with
the Kinhill Kramer/Curtain Bros consortium.Chapter 26
-
Page 369 of 397
-
330
In an internal memo to the Secretary for Transport on 28
April 1992, Mr
Amoako advised he had given the comments of a consultant
engaged by
the Department of Works to the consortium and discussed them
in his
office:To my knowledge they did include all the outstanding
issues at that point in
time.”
[EXHIBIT 201, page 2, para 4]This is nonsense. It is clear from reading the contract
actually executed on
27 May 1992, that the vast bulk of the concerns raised in the
Beca Gure
and the Maunsell reviews were not incorporated in the final
contract.The Department of Transport had ignored the advice and the
concerns of
three key Departments, namely, the Department of Attorney-
General, the
Department of Finance and Planning and the Department of
Works.[26.9] SUMMARY OF THE DEPARTMENT OF TRANSPORTS ACTIONS
In the opinion of the Ombudsman Commission the Department of
Transport made serious errors in the negotiations with the
Kinhill
Kramer/Curtain Bros consortium.The Department was not prepared to listen to the advice of
other
Departments. The pleas for caution by the Department of
Attorney-
General, the Department of Finance and Planning and the
Department of -
Page 370 of 397
-
Works were consistently brushed aside as the Department of
Transport
pushed ahead in its determined, but careless, pursuit of the
National
Executive Council’s deadline.Chapter 26
[Paragraph unreadable in the original]
An information paper could have been file for the National
Executive
Council’s consideration, explaining the ……… for not meeting the
deadline and asking for an extension of time in order to
to attend to certain important issues.Instead of doing this, the Department of Transport pretended that
theconcerns raised by the other Departments were not legitimate and
recommended that the contract be signed.This was wrong and defective administration.
* * * * * * * * * *
-
Page 371 of 397
-
Chapter 26
NATIONAL EXECUTIVE COUNCIL DECIDES THAT CONTRACT
MUST BE FINALISED 23 APRIL 19927 I POLICY SUBMISSION TO NATIONAL EXECUTIVE COUNCIL HAD
IGNORED CONCERNS OF KEY DEPARTMENTSAs we reported in Chapter 26, the attempts by the
Department of Works
to have the terms of Kinhill Kramer’s draft contract
renegotiated were
thwarted by the Department of Transport.The Policy Submission of 22 April 1992 not only ignored
the serious
concerns raised by the Department of Works, it also failed
to mention the
concerns of the Department of Attorney-General and the
Department of
Finance and Planning.The Policy Submission recommended that the contract be
signed and was
considered by the National Executive Council at its
meeting on Thursday
23 April 1992.[27.2] NATIONAL EXECUTIVE COUNCIL DECIDES TO POSTPONE APPROVAL
OF CONTRACTRather than approving the draft contract, the National
Executive Council -
Page 372 of 397
-
decided to defer formal consideration of the matter until
its next meeting,
on Wednesday 29 April 1992.Chapter 27
333
However, the National Executive Council made it clear that
negotiations
were to be concluded by that date.The Departments of Transport, Attorney-General and Finance and
Planning
were given a formal direction in the following terms:“to finalise contracts on the Spring Garden Freeway with
Kinhill Kramer and
Curtain Bros for presentation to the NEC on 29th April 1992”.
[EXHIBIT 186]As this new deadline was only six days away, the Departments which
were
opposing execution of the contract, as it then stood, had to act
quickly if
they were to achieve their objective.The next chapter of the report focuses on the events that occurred
in the
lead-up to the National Executive Council meeting of 29 April 1992.* * * * * * * * * *
-
Page 373 of 397
-
Chapter 27
334
28. ACTION TAKEN BY FOUR KEY DEPARTMENTS PRIOR TO
THE NATIONAL EXECUTIVE COUNCIL MEETING ON
29 APRIL 1992[28.1] THE POSITION OF THE FOUR KEY DEPARTMENTS: TRANSPORT.
WORKS. ATTORNEY-GENERAL AND FINANCE AND PLANNINGOn 23 April 1992 the National Executive Council directed that
the contract
between the State and the Kinhill Kramer/Curtain Bros
consortium be
finalised by 29 April 1992. This decision put the Department
of Works, the
Department of Attorney-General and the Department of Finance
and
Planning in a difficult position.These Departments were opposed to the contract being signed,
in its
existing form. They wanted more time to negotiate. The
Department of
Finance and Planning also wanted to examine the financing
agreement
between Kinhill Kramer and the Export Finance and Insurance
Corporation,
which had not been made available.Only the Department of Transport was interested in seeing
that the new
deadline was met. -
Page 374 of 397
-
This chapter of the report assesses the action taken by these
four key
departments in the lead-up to the meeting of the National
Executive
Council on Wednesday 29 April 1992.Chapter 28
335
THE DEPARTMENT OF WORKS
[28.2] CONCERNS RAISED WITH RESOURCE MANAGEMENT COMMITTEE
With the meeting of 29 April 1992 only a couple of days away,
the
Secretary for Works, Mr Hitolo, tried a different way of
airing his
Department’s concerns.On 27 April 1992, he wrote to the Chairman of the Resource
Management
Committee (the Secretary of the Department of Prime Minister,
Mr Brown
Bai CBE) in the following terms:I write to advise the Committee of my Department’s deep
concern abut the
way this project is proceeding without due consideration
for the protection of
the best interests of the State, and urge that the
Committee advise the National Executive Council mg to agree
to the signing of the proposed contracts until the
documents have been amended accordingly and made good? [EXHIBIT 193]
Executive Council mg to agree to the signing of the
proposed contracts until the documents have been amended
accordingly and made good? [EXHIBIT 193]
documents have been amended accordingly and made good?
[EXHIBIT 193] -
Page 375 of 397
-
The other official action taken by the Department of Works
during this
period was the drafting of a letter for the Minister for
Works, the Hon.
Lukas Waka MP. The letter was directed to the Prime Minister.
It stated:-‘My Prime Minister, as I have stated above I would be
failing you if I did not
draw my serious concerns to your attention. I fully
support the project and
appreciate the need for rapid implementation. I would
however strongly
recommend that the current contract should not be signed
until adequate time
has been given to review and amend the documents and in
particular the main
agreement between the State and the Consortium- This would
ensure that the
State’s interests are protected and that the land related
matters could also be addressed’. [EXHIBIT 209, at page 2]
addressed’. [EXHIBIT 209, at page 2]Chapter 28
336
THE DEPARTMENT OF TRANSPORT
[28.3] APPROACH REMAINED THE SAME
During the lead-up to the meeting on 29 April 1992 the
Department of
Transport maintained. the approach it had taken since the
National
Executive Council decided in favour of Kinhill Kramer: it had
an overriding
duty to comply with the direction from the National Executive
Council to
finalise the contract. -
Page 376 of 397
-
The officer in charge of the negotiations, Mr Amoako, advised
the
Secretary for Transport on 28 April 1992 that all the
amendments
suggested by other members of the steering committee had been
incorporated in the draft contract. [EXHIBIT 201, at page 1]Mr Amoako also advised that, apart from the Department of
Works and
the Electricity Commission, no other Department or
governmental body
had expressed their objections in writing to the Department
of Transport
or the steering committee.The Ombudsman Commission accepts that the latter advice was
correct:
though the concerns were widespread amongst the membership of
the
steering committee, only the Department of Works and the
Electricity
Commission had formally put them in writing.However, Mr Amoako’s advice that all the suggested amendments
had
been incorporated in the draft contract was wrong and
misleading.Chapter 28
337
[28.4] ELCOM RAISES CONCERNS WITH DEPARTMENT OF TRANSPORT
On 28 April 1992, the General Manager of the Electricity
Commission, Mr
P K Amini, wrote to the Secretary for Transport, expressing
concerns
about the draft contract. The Electricity Commission had an
interest in the
project, because its transmission lines would be affected by
the route of
the freeway.These concerns mirrored those raised by the Department of
Works;
particularly about the conflict of interest created by having
Kinhill Kramer
act, on the one hand, as project manager on behalf of the -
Page 377 of 397
-
consortium,
and, on the other hand, as superintendent of the project on
behalf of the
State.The Electricity Commission letter was received in the
Department of
Transport on 29 April 1992, but there appears to have been no
response
to it. [EXHIBIT 202][28-5] DEPARTMENT OF TRANSPORT AWARE OF WIDESPREAD CONCERN
ABOUTRIEDRAELCONIBACIThe Department of Attorney-General and the Department of
Finance and
Planning did not formalise their concerns in the same manner
as the
Department of Works and the Electricity Commission. However,
the
Department of Transport was well aware that these other
departments
were also very concerned about the terms of the draft
contract.
Unfortunately, the Department of Transport attributed this to
the efforts of
the Department of Works to embarrass the Department of
Transport and
did not take them seriously (see Chapter 26).Chapter 28
Nevertheless, the Department of Transport decided to get a
“second
opinion”.[28.6] DEPARTMENT OF TRANSPORT ARRANGES OVERNIGHT REVIEW OF
DRAFT CONTRACTOn the afternoon of Monday 27 April 1992 – just two days
before the
contract was due to be approved by the National Executive
Council – the
Department of Transport asked the consulting firm Cardno &
Davies (PNG)
Pty Ltd to review some aspects of the draft contract.
[EXHIBIT 201, at
page 2] -
Page 378 of 397
-
Cardno & Davies reported back to the Department of Transport
the
following day, 28 April 1992. Given the very short period of
time, the
analysis was, understandably, not as comprehensive as that
given to the
Department of Works by Beca Gure and Maunsells (see Chapter
26).
Nevertheless a number of matters of concern were raised.[28.7] THE CARDNO & DAVIES REVIEW
Cardno & Davies suggested, for example:
The scope of the project had to be defined in more
detail.Specific provision had to be made for delays in land
acquisition.Chapter 28
It was necessary to identify and list all codes and
standards
for each item of structural work.The specifications for bridges did not meet the normal
requirements of earthquake engineering for bridges in
Papua
New Guinea.The role of the superintendent had to be defined and
clarified
to minimize confusion. [EXHIBIT 204]On Wednesday 29 April 1992, the Secretary for Transport
instructed Mr
Amoako to incorporate the issues raised by the Cardno &
Davies review
and take them up with the parties concerned. This was a very
strange
instruction. It was given on the very day the National
Executive Council
was due to approve the contract. Surely it was too late for a
major revision
of the contract. -
Page 379 of 397
-
[28.8] THE CARDNO & DAVIES REVIEW WAS TOO LATE TO HAVE ANY
EFFECTIt is not surprising that none of the concerns raised by
Cardno & Davies
were addressed in the final contract. In fact nothing was
really achieved
by this whole exercise.It was simply a belated and rather half-hearted attempt by
the Department
of Transport to get confirmation that the contract was in
order.■
Chapter 28
340
But clearly the contract was not in order. This was the third
independent
review of the contract. In each review, there were serious
matters of
concern raised. They were not minor matters that could be
negotiated
later. They were issues which went to the heart of the
contract, such as
who would be the superintendent of the project and who would
protect the
State’s interest during the construction phase.[28.9] DEPARTMENT OF TRANSPORT MADE NO PROPER ATTEMPT TO HAVE
THE CONTRACT REVIEWEDWe recorded these views in our preliminary report and
emphasised that
the Department of Transport had not made a proper attempt to
have the
contract reviewed. The Secretary for Transport responded in
the following
terms:This statement lie. that the Department of Transport made
-
Page 380 of 397
-
no proper attempt
to have the contract reviewed] is totally incorrect. The
negotiating team were
doing precisely that. The consultant’s work was only a
supplement. Remember
the draft document had been reviewed clause-by-clause,
paragraph-by-
paragraph and page-by-page prior to that. This was the
role of the Committee.
This is not defective administration. There was no need to
ask NEC to defer
because the issues raised by the Consultant were adopted
before the submission
to NEC. The Consultant review was in contrast to that
pursued by the
Department of Works. Clearly, the Department of Works was
on the wrong
path. The person in charge was not a qualified Highway
Engineer but an
architect, who had recently taken the Highway Engineering
job as Acting First
Assistant Secretary.” [EXI-HBIT 254, pars 22]The Ombudsman Commission does not accept Mr Amini’s
explanation.
Three key departments were expressing serious concerns about
the draft
contract in the course of the negotiations. In these
circumstances, it was
incumbent on the Department of Transport to arrange its own,
independent review before recommending the contract be
executed.Chapter 28
341
When the Department did receive the results of the review by
Cardno &
Davies, it should have realised that it was dangerous to
proceed with the
existing draft contractThe Ombudsman Commission reiterates the finding made in
Chapter 26:
it was irresponsible of the Department of Transport to pursue -
Page 381 of 397
-
execution of
the contract when so many doubts, from so many different
quarters, were
being expressed. It was irrelevant that only the Department
of Works and
the Electricity Commission had put their concerns in writing.
All the
concerns were genuine and deserved close consideration.Though it may have been embarrassing for the Department and
the
Minister for Transport to postpone execution of the contract
on the eve of
its approval, common sense should have prevailed: the
National Executive
Council should have been advised that it would be safer to
re-negotiate
the contract properly in the interests of the State.THE DEPARTMENT OF ATTORNEY-GENERAL
pa 10] ACTION NOT TAKEN UNTIL ONE DAY BEFORE THE NATIONAL
EXECUTIVE COUNCIL MEETINGOn Tuesday 28 April 1992 – the day before the contract was
due to be
approved – the Secretary of the Department of Attorney-
General, Mr P
Paliau ISO, sent a letter by fax to the Secretary for Works.
He said he
agreed the draft contract did not adequately protect the
interests of the
State and advised he would not be issuing a legal clearance
for the
contract. [EXHIBIT 205]Chapter 28
342
Mr Paliau also asked the Secretary for Works to brief the
Minister for
Works and get the Minister to write a letter to the Prime
Minister,
recommending execution of the contract be delayed. -
Page 382 of 397
-
[28.11] SECRETARY OF THE DEPARTMENT OF ATTORNEY-GENERAL ADVISES
PRIME MINISTER THAT LEGAL CLEARANCE WOULD NOT BE ISSUEDOn the following day, Wednesday 29 April 1992, Secretary
Paliau wrote to
the Chairman of the National Executive Council, Prime
Minister Namaliu.
He advised he had perused the contract documents and
concluded as
follows:‘la) this project did not comply with the rules and
procedure for Tender
under the Public Finances (Management) Act;(b) the execution and performance of the Agreement
and the Contract
Documents in L(b) – (f) above at this stage will
mean that the Contract
amount of K65,000,000.00 authorized by the Loans
Overseas (Borrowing)
Act and also the Loans Overseas (Borrowing) (No.
2) Act, will be
exceeded, hence Section 209 of the Constitution
will be breached.(c) the Agreement in 1 (a) above and the Contract
Documents in 1(b) – (f)
above do not protect or appear to protect the
best interest of the State;(d) the execution of this Agreement and the Contract
Documents therewith
be delayed until they are adequately and
satisfactorily finalised to
protect the best interests of the State, the
Consortium, the Project
Manager and possibly the Export Finance Insurance
Corporation of
Australia.Accordingly, I decline to issue a Letter of Legal
Clearance on the Agreement’
[EXHIBIT 211]This letter was hand-delivered to the Prime Minister’s
office on the morning
of Wednesday 29 April 1992 by Secretary Paliau. -
Page 383 of 397
-
Chapter 28
343
[28.12] DEPARTMENT OF ATTORNEY-GENERAL ACTED PROPERLY BUT ADVICE
SHQULD HAVE BEEN GIVEN SOONERIn view of the widespread concern expressed about the draft
contract, the
Ombudsman Commission considers the decision by the Secretary
of the
Department of Attorney-General to write the letter to the
Prime Minister on
29 April 1992 to have been responsible and entirely proper.It is unfortunate, however, that it was not written sooner,
as this was the
first occasion on which the Department of Attorney-General
had formally
put in writing the defects perceived in the draft contract.So, while we praise Secretary Paliau for writing the letter
of 29 April 1992
to the Prime Minister, we must also criticise his Department
for not taking
action sooner. It was not sufficient for his officers to
simply raise their
concerns in the steering committee. This was a case which
called for a
thorough briefing to the Attorney-General in writing.[28.13] ATTORNEY-GENERAL SHOULD HAVE BEEN ADVISED
At the relevant time the Attorney-General was the Hon
Bernard Narokobi,
LLB MP. By virtue of Section 156(2) of the Constitution and
Sections 3 and
4 of the Attorney-General Act 1989, he was also the
Principal Legal Adviser
to the National Executive.The Department of Attorney-General should have advised him
very early
in the course of negotiations that there were serious -
Page 384 of 397
-
defects in the draft
contract provided by Kinhill Kramer.Chapter 28
344
The Attorney-General should have also been formally advised
that the
Public Finances (Management) Act and other legislation would
be
breached if the National Executive Council proceeded with
the planned
course of action.[28.14] RESPONSE OF THE DEPARTMENT OF ATTORNEY GENERAL
We accept that the Department of Attorney-General
representatives on the
steering committee had raised a number of concerns during
the
committee’s meetings. Specifically, we accept what the
Acting State
Solicitor, Mr Z Gelu, said in his response to our
preliminary findings:This project was arranged through the turn key concept.
The concept by
passes all procedures and requirements under the Public
Finance &
Management Act. I may say here that Messrs. hung and
Singin raised these
concern during their consultative meeting. The Contract
was drafted by Kinhill
Kramer Pty Ltd and Curtain Brothers (Qld). The Contract
was pushed through
NEC by the Department of Transport.” [EXHIBIT 26.2, parr
41However, by raising concerns in the committee meetings, the
Department
of Attorney General had only gone part of the way to
protecting the -
Page 385 of 397
-
State’s interests.
When this was put to Secretary Paliau in the form of a
preliminary finding,
he responded as follows:“Like any project of such nature of any matters that
require legal assistance in
terms of advise or drafting of agreements, I normally
delegate such matters to
the State Solicitor to handle consistent with his Duty
Statements. The State
Solicitor will only come back to me if the matters
require my personal attention.Chapter 28
345
Furthermore, client Departments are at liberty to
instruct the State Solicitor
directly and I am always informed about such instructions
by the State Solicitor.
Again apart from such information the State Solicitor
deals with the matter
directly with the client Department unless the matter
requires my personal
attention…As to the findings in Chapter 28, — the matter only came
to my personal
attention at that particular time and I attended to it
there and then on 29 April
1992.The findings — on myself failing to advise the Attorney-
General on serious
defects in the draft contract and the breaching of the
requirements of the Public -
Page 386 of 397
-
Finances (Management) Act and other Legislation if the
NEC proceeded with
the course of action if proposed is ill founded.At that period of time when the matter was being
entertained by the NEC, the
Hon. Bernard Narokobi, the Attorney-General was not
available. In fact he was
out of speedy and effective communication and he was
unable to fulfil the
duties of Office of the Attorney-General.By virtue of Section 5 of the Attorney-Generals Act, I as
the Departmental
head became the Attorney-General and the Principal Legal
Adviser to the
National Executive Council. Therefore I see no reason why
I should advise
the Attorney-General or advise myself for that
matter.” [EXHIBIT 258][28.15] POOR COMMUNICATION WITHIN THE DEPARTMENT OF ATTORNEY
GENERALThe Secretary’s defence is that the project had been
delegated to the
State Solicitor and the matter only came to the Secretary’s
personal
attention shortly before the meeting of the National
Executive Council on
29 April 1992. He also says the reason the Attorney General
was not
advised was that he (the Secretary) was actually the
Attorney-General on
29 April 1992.With respect to Secretary Paliau, he has not actually
addressed our
criticisms. If we accept that the matter was not brought to
his attention
until very late in the negotiations, this does not rebut our
findings – it
reinforces them. -
Page 387 of 397
-
Chapter 28
Our criticism is directed at the Department of Attorney
General, as a
whole, and the State Solicitor’s Office in particular, for
not formally briefing
Attorney-General Narokobi early in the negotiating period.
The fact that the
Secretary of the Department was also not fully briefed
underscores the
overall lack of affirmative action taken by officers of his
Department. It also
reflects poorly on the lines of communication within the
Department.We therefore conclude that the Department of Attorney-
General was remiss
in its duty to promptly advise the National Executive
Council, via the
Attorney-General, of all of the legal problems associated
with immediate
execution of the contract.THE DEPARTMENT OF FINANCE AND PLANNING
[28.16] CONCERNS RAISED DURING STEERING COMMITTEE MEETINGS
The Department of Finance and Planning had little
involvement in the
decision to award the contract to Kinhill Kramer. The
Department was
concerned, as early as June 1990, about the funding of the
project.
[EXHIBIT 10B] However, the shortlisting and evaluation of
proposals – even
when it was based on financial criteria – took place without
consulting the
Department of Finance and Planning.The Department of Finance and Planning only became involved
when the
steering committee was established to negotiate with the
Kinhill Kramer
consortium.Chapter 28
-
Page 388 of 397
-
347
Like the Department of Attorney-General and the Department of Works,
the
Department of Finance and Planning had serious reservations about
the
way the negotiations were proceeding. On 15 April 1992,
representatives
of the Department of Finance and Planning called a special meeting
of the 11
steering committee to protest that they had not seen Kinhill
Kramer’s
financing agreement. [EXHIBIT 175]This, in itself, was a matter of concern: nobody knew the terms on
which
the consortium was obtaining finance for the project. In fact, these
terms
were never made available to the State. On 27 May 1992, when the
freeway contract was signed, the agreement with the Export Finance
Insurance Corporation was not executed. iAnd the agreement remained
un-
executed, even when the contract between the State, Kinhill Kramer
Pty
Ltd and Curtain Bros (Old) Pty Ltd was terminated on 27 August 1992
(see Chapter 34).
The officers of the Department of Finance and Planning suggested
that the
Kinhill Kramer financial package be renegotiated and that
alternative
sources of funding be investigated. But this was never done.If it had been done, implementation of the project would no doubt
have
been delayed. But there were obvious alternatives to Kinhill
Kramer’s
turnkey proposal: concessional financing from sources such as the
World
Bank or the Asian Development Bank, which is generally cheaper than
finance obtained through institutions such as the Export Finance and
Insurance Corporation of Australia.Unfortunately, the Department of Finance and Planning did not
undertake
a detailed analysis of the alternative methods of financing the
Poreporena
Freeway project until the eve of the National Executive Council
meeting on
29 April 1992.Chapter 28
-
Page 389 of 397
-
[28.17] FINANCIAL ANALYSIS OF ALTERNATIVE FUNDING
The First Assistant Secretary (Loans and Revenue) in the
Department of
Finance and Planning, Mr Kahona, testified to the
Ombudsman
Commission that, on 27 or 28 April 1992, he was
instructed by the Acting
Secretary of the Department, Mr Mulina, to prepare a
comparison of the
different methods of financing.The EFIC interest rate was estimated to be 9.5% , which
transpired to be
the interest rate in the final contract. This was
compared with the
prevailing interest rates for World Bank (IBRD) and Asian
Development
Bank Loans of 7.72% and 6.58% respectively. An analysis
of the “grant
element’ and the “effective rate of interest’ for each
loan regime was then
carried out, which took account of the period of the loan
repayments, the
grace period and the commitment fees.[28.18] EFIC FINANCING SHOWN TO BE EXPENSIVE
The Department of Finance and Planning analysis was
summarised in the
following terms:‘Grant Element (GE) and Effective Rate of Interest
(ERI) ComparisonLender Current Grant Effective
Interest (%)Element (%) Rate of
Interest (%)EFIC 9.50 13 9.7
IBRD 7.72 13.8 7.9 -
Page 390 of 397
-
ADB 6.58 23.3 6.7
Chapter 28
349
It is obvious from the above table that the grant
element of the EFIC option
is very low at 1.3% compared to IBRD and ADB options at
13.8% and 23.3%
respectively. The grant element measures the degree of
concessionality of a
loan in comparison to a direct grant. So, the higher the
grant elements the
higher the degree of concessionality.The effective rate of interest on the EFIC proposal is
high at 9.7% as compared
to either IBRD or ADB at 7.9% and 6.7% respectively.comparison to financing the proposed project through
World Bank or ADB
financing. It is also understood that the World Bank has
indicated that they
maybe able to fund the project at a lower total project
estimated cost of around
US$45 million”
[EXHIBIT 199, at page 2, emphasis added]In the same report, it was estimated that, if the Kinhill
Kramer financingproposal was adopted, the total cost to the State over the
life of the loanwould exceed K90 million.
-
Page 391 of 397
-
[28.19] REPORT GIVEN TO THE ACTING MINISTER FOR FINANCE AND
PLANNINGThis report was presented to Acting Secretary Mulina on the
morning of29 April 1992, ie the day on which the National Executive
Council was due
to approve the contract.Soon after this the report was given to the Acting Minister
for Finance and
Planning, Hon. Karl Stack, MP. He faxed a copy of the report
to theSecretary for Transport on the following day, 30 April 1992.
[EXHIBIT 213]Chapter 28
350
[28.20] DID THE DEPARTMENT OF FINANCE AND PLANNING ACT SOON
ENOUGH?The Department of Finance and Planning report of 29 April
1992 was
straightforward:Kinhill Kramer’s turnkey financing was expensive.
The project might be able to be implemented for K20
million
i than what Kinhill Kramer had quoted. -
Page 392 of 397
-
The total project cost of the project over a
thirteen year
period was in excess of K90 million.This report was of critical importance to the whole project
and the
Ombudsman Commission is amazed that it was not prepared much
sooner.It seems that by the time they met on the afternoon of 29
April 1992, a
majority of the members of the National Executive Council
had made up
their minds to approve the Kinhill Kramer/Curtain Bros
contract.Perhaps, if the Department of Finance and Planning report
had been
available sooner, it may have had some impact.It is a matter of concern to the Ombudsman Commission that,
though the
Department of Finance and Planning had serious reservations
about this
project quite early in the contract negotiations, nothing
tangible was done
until the last minute. Like the Department of Attorney-
General, the
Department of Finance and Planning failed to give its advice
promptly –
when it would have had a much greater chance of being
accepted.Chapter 28
351
[28.21] CONCERNS HAD TO BE RAISED AT A HIGH LEVEL
We accept that the Department’s concerns were raised at the
steering
committee meetings. The Secretary for Finance stated to the
Ombudsman
Commission that, though his Department failed to follow up
these matters
in writing, they expected the Department of Transport and
the Knhill
Kramer/Curtain Bros consortium to respond to the requests at
subsequent
meetings. [EXHIBIT 255]In the opinion of the Ombudsman Commission this is simply
-
Page 393 of 397
-
not good
enough. The Department of Finance and Planning should have
raised its
concerns at a much higher level: the Secretary for Finance
should have
thoroughly briefed the Minister for Finance in writing. And
this should have
been done very early in the negotiating period.
Alternatively, the Secretary
for Finance could have raised the matter formally in writing
with the
Secretary for Transport.[28.22] ALTERNATIVE FUNDING SOURCES SHOULD HAVE BEEN THOROUGH Y
EXPLOREDThe Ombudsman Commission is also concerned that the
Department of
Finance and Planning was not more enterprising in
investigating the
possibility of concessional funding for the project, through
the Office of
International Development Assistance (01DA).Chapter 28
352
[28.23] RESPONSE BY THE DEPARTMENT OF FINANCE AND PLANNING TO
THE OMBUDSMAN COMMISSION’S ALLEGATIONSThe Ombudsman Commission put the above findings to the
Secretary for
Finance, Mr G Aopi MBE, in our preliminary report. He
responded as
follows:The report correctly states that DFP was not involved in
the project (Le.
contract negotiations) until after the NEC Decision in
February 1992. Prior to
this, all discussions were undertaken by the Department
of Transport. -
Page 394 of 397
-
However, our comments on the project were consistent –
the project was
expensive and that alternatives should be pursued. In
addition, from a planning
perspective, while this project was in the Transport
development plans in terms
of priorities, consideration should have been given to
developing the rural
infrastructure which is in dire need of improvement.In view of DOT not providing the information
requested„ we could not provide
a detailed brief for the Minister for Finance and
Planning, NEC and RMC.
Chapter 28 of the report supports this. However, it is
unfair on the part of the
Commission … to be critical of the Department’s action
when other parts of the
report state that information requested by the
Department from DOT was never
received.I would like to place once again on record that we did
not receive any formal
offer of financial assistance from the Consortium for
financing of the Freeway.
We were also not in a position to realistically and
accurately advise the Minister
for Finance and Planning on the implications of
financing the project either
through concessional sources or those proposed by the
Consortium. The
financial analysis _ was done just before NEC met on the
29th April. This
analysis was done on the basis of terms and conditions
prevailing at that time
and on information obtained through informal
discussions.If the Department had been provided with a formal offer
of finance for
financing of the project, we would have provided a
detailed analysis for the
Minister’s consideration and other interested parties
well in advance. The
Minister was however, verbally briefed on several
occasions of the Department’s
position on the project…— The procurement of goods and services by Government
agencies is dearly
set out in the Public Finances (Management) Act, and
senior government
officials should be aware and understand these and other -
Page 395 of 397
-
administrative
procedures.The Department of Transport also, during various
discussions, knew the
Department’s position together with those of the State
Solicitor, and these
should have been reflected in various submissions to the
National Executive
Council. The Department may have been deliberately left
out in a lot of the
discussions because of its strong views against this
project.Chapter 28
353
As for finding alternative sources of funds, there are
certain laid-down
procedures which must be followed to secure concessional
funds. Projects
should be submitted through the normal budgetary process
and evaluated prior
to negotiating the financial package. Obviously the
process is too slow and
cumbersome for some people, hence the turnkey
proposal.’ [EXHIBIT 255][28.24] UNSATISFACTORY EXPLANATION BY DEPARTMENT OF FINANCE AND
PLANNINGThe reasons advanced by Mr Aopi for his Department’s failure
to provide
a prompt analysis of the cost of the project are not
convincing.We appreciate the Department was not in a position to carry
out a precise
analysis, because of the unavailability of the exact terms
of the EFIC
financing package. But there was nothing to stop the
Department -
Page 396 of 397
-
estimating the cost of the EFIC finance – which is what, in
fact, was done
on the eve of the National Executive Council meeting of 29
April 1992.The estimate could have been based on the terms of the
financing
package proposed by Kinhill Kramer Pty Ltd in February 1992
and
considered by the National Executive Council (see Chapter
22, Exhibit
151). And this financial analysis could, and should, have
been done as
soon as the National Executive Council decision was
announced.It is not a good excuse for the Department of Finance and
Planning to say
it did nothing because it never received a formal financing
proposal. We
do not believe any Department of the State is entitled to
sit back and
make no comment on a major financial commitment by the State
because
it was not formally approached for advice or not given all
the information
it wanted.Chapter 28
[28.25] CONCLUSION AS TO CONDUCT OF DEPARTMENT OF FINANC AN D
PLANNINGThe Ombudsman Commission concludes that the Department
of Finance
and Planning was remiss in its duty to ensure that
prompt advice was
given to the National Executive Council, via the
Minister for Finance, on the
financial implications of the Kinhill Kramer turnkey
proposal.* * * * * * * * * *
-
Page 397 of 397
-
Chapter 28