Report of an Investigation into the Spring Garden Road Poreporena Freeway Project (Part 1)

Mentions of people and company names in this document

The information these results are derived from was last updated in June 2022

Name References in this document Mentions in other documents

It is not suggested or implied that simply because a person, company or other entity is mentioned in the documents in the database that they have broken the law or otherwise acted improperly. Read our full disclaimer

  • About

    Part 1 of the Ombudsman Commission Report of an Investigation into the government's Spring Garden Road Poreporena Freeway Project.

Document content

  • OMBUDSMAN COMMISSION

    OF

    PAPUA NEW GUINEA

    REPORT OF AN

    INVESTIGATION INTO

    THE SPRING GARDEN ROAD

    POREPORENA FREEWAY PROJECT

    MEMBERS

    OF THE

    OMBUDSMAN COMMISION

    Charles Maino Ango Wangatau Jim Ridges
    Chief Ombudsman Acting Ombudsman Acting Ombudsman

    18 December 1992

  • Page 2 of 397

  • OMBUDSMAN COMMISSION

    OF

    PAPUA NEW GUINEA

    REPORT OF AN INVESTIGATION
    INTO THE SPRING GARDEN ROAD
    POREPORENA FREEWAY PROJECT

    PART I: NATURE AND PURPOSE OF THE INVESTIGATION

    1. INTRODUCTION 2

    2. BACKGROUND OF THE FREEWAY PROPOSAL 9

    3. STRUCTURE OF THE REPORT 14

    PART H: RECORD OF EVENTS AND FINDINGS OF THE
    OMBUDSMAN COMMISSION

    4. DECISION TO PUBLICLY INVITE 18
    EXPRESSIONS OF INTEREST: MAY 1990

    5. ADVERTISEMENT INVITING 23
    EXPRESSIONS OF INTEREST: JUNE 1990

    6. RESPONSES TO THE ADVERTISEMENT: JULY 1990 35

    7. SIGNIFICANT INTERDEPARTMENTAL 49
    MEETING: 31 JULY 1990

    8. PROGRESS DURING SECOND 54
    HALF OF 1990
    9. PREPARATION OF SHORTLIST: 73
    FEBRUARY 1991

    10. TERMS OF REFERENCE FOR THE 94
    PROJECT: EARLY 1991

    11. THE MINISTERIAL COMMITTEE MEETING 103
    OF 18 JULY 1991

  • Page 3 of 397

  • 12. THE RELATIONSHIP BETWEEN THE CHINESE 120
    CONSORTIUM AND THE MINISTER FOR TRANSPORT

    13. FURTHER CHANGE IN COMPOSITION OF
    THE CHINESE CONSORTIUM: SEPTEMBER 1991 155

    14. MINISTER FOR TRANSPORT SIGNS CONTRACT 162
    FOR CONSTRUCTION OF FREEWAY: OCTOBER 1991

    15. ROLE OF THE WORLD BANK IN THE
    SPRING GARDEN ROAD/POREPORENA 178
    FREEWAY PROJECT

    16. FATE OF THE POLICY SUBMISSION FAVOURING 185
    THE CHINESE CONSORTIUM: DECEMBER 1991

    17. CONCERNS ABOUT CREDENTIALS OF TUNSON
    ENGINEERING CO LTD: 196
    DECEMBER 1991 – JANUARY 1992

    18. MINISTER FOR TRANSPORT EXPEDITES
    PREPARATION OF NEW POLICY 707
    SUBMISSION: FEBRUARY 1992

    19. HISTORY OF THE PROPOSAL BY 217
    KINHILL KRAMER PTY LTD

    20. RESOURCE MANAGEMENT
    COMMITTEE RECOMMENDS RE-TENDERING 238
    OF PROJECT: 20 FEBRUARY 1992

    2L THE MINISTER FOR TRANSPORTS 241
    POLICY SUBMISSION OF FEBRUARY 1992

    22. FAVOURABLE ASSESSMENT OF
    THE KINHILL KRAMER PROPOSAL

    23. NATIONAL EXECUTIVE COUNCIL DECIDES TO
    AWARD PROJECT TO KINHILL KRAMER 284
    CONSORTIUM: 24 FEBRUARY 1992

  • Page 4 of 397

  • 24. OVERVIEW OF EVENTS BETWEEN APPOINTMENT
    OF KINHILL KRAMER CONSORTIUM AND 290
    SIGNING OF CONTRACT: FEBRUARY – MAY 1992

    25. CONCERNS RAISED BY DEPARTMENT OF WORKS
    ABOUT DRAFT CONTRACT: 304
    MARCH – APRIL 1992

    26. DEPARTMENT OF TRANSPORT RECOMMENDS SIGNING
    OF CONTRACT AGAINST ADVICE OF OTHER 321
    DEPARTMENTS: 22 APRIL 1992

    27. NATIONAL EXECUTIVE COUNCIL DECIDES THAT 332
    CONTRACT MUST BE FINALISED: 23 APRIL 1992

    28. ACTION TAKEN BY FOUR KEY DEPARTMENTS
    PRIOR TO THE NATIONAL EXECUTIVE COUNCIL 334
    MEETING ON 29 APRIL 1992

    29. NATIONAL EXECUTIVE COUNCIL REJECTS ADVICE
    OF DEPARTMENT OF ATTORNEY-GENERAL: 29 APRIL 1992 355

    30. ACTING STATE SOLICITOR GIVES LEGAL CLEARANCE 358
    DESPITE DEFECTS IN CONTRACT: 6 MAY 1992

    31. NATIONAL EXECUTIVE COUNCIL APPROVES 367
    EXECUTION OF CONTRACT: 6 MAY 1992

    32. EVENTS LEADING UP TO EXECUTION OF 375
    THE CONTRACT: 6 – 27 MAY 1992

    33. THE CONTRACT OF 27 MAY 1992 395

    34. EVENTS AFTER 27 MAY TERMINATION
    OF CONTRACT AND APPOINTMENT OF A 400
    COMMISSION OF INQUIRY

    PART III: LAWS RELEVANT TO PUBLIC WORKS CONTRACTS

  • Page 5 of 397

  • 35. THE PUBLIC TENDER REQUIREMENTS OF 406
    THE PUBLIC FINANCES (MANAGEMENT) ACT

    36. THE PUBLIC WORKS COMMITTEE ACT AND THE
    ROLE OF THE PARLIAMENT IN MONITORING 424
    PUBLIC WORKS PROJECTS

    37. CONTROL OF OVERSEAS 39
    BORROWING BY THE STATE

    38. LAWS GOVERNING FOREIGN INVESTMENT 446

    39. LIMITS ON THE POWERS OF MINISTERS 451

    40. FUNCTIONS OF THE DEPARTMENT OF 460
    TRANSPORT AND THE DEPARTMENT OF WORKS

    PART IV; FINDINGS UNDER SECTION 219(1) OF THE
    CONSTITUTION AND SECTION 22(1) OF THE
    ORGANIC LAW ON THE OMBUDS • COMMISSION

    41. FINDINGS AS TO THE CONDUCT OF THE 468
    FORMER MINISTER FOR TRANSPORT

    42. FINDINGS AS TO THE CONDUCT OF THE
    DEPARTMENT OF TRANSPORT AND 480
    THE SECRETARY FOR TRANSPORT

    43. FINDINGS AS TO THE CONDUCT OF THE
    DEPARTMENT OF WORKS AND THE 497
    SECRETARY FOR WORKS

    44. FINDINGS AS TO THE CONDUCT OF THE
    DEPARTMENT OF ATTORNEY-GENERAL, THE 501
    SECRETARY OF THE DEPARTMENT AND THE
    ACTING STATE SOLICITOR

    45. FINDINGS AS TO THE CONDUCT OF THE
    DEPARTMENT OF FINANCE AND PLANNING 506

  • Page 6 of 397

  • AND THE SECRETARY FOR FINANCE

    46. FINDINGS AS TO THE CONDUCT OF THE 512
    NATIONAL EXECUTIVE COUNCIL

    PART V; RECOMMENDATIONS OF THE OMBUDSMAN COMMISSION

    47. RECOMMENDATIONS CONCERNING LAWS RELEVANT 518
    TO PUBLIC WORKS PROJECTS

    48. RECOMMENDATIONS AS TO THE EXERCISE 529
    OF POWERS BY MINISTERS

    49. RECOMMENDATIONS CONCERNING THE POWERS 534
    AND DUTIES OF DEPARTMENTAL HEADS

    50. RECOMMENDATIONS CONCERNING PROCEDURES 536
    OF THE NATIONAL EXECUTIVE COUNCIL

    5L RECOMMENDATIONS TO THE DEPARTMENT 544
    OF TRANSPORT

    52. RECOMMENDATIONS TO THE DEPARTMENT 548
    OF ATTORNEY-GENERAL

    53. RECOMMENDATIONS TO THE DEPARTMENT 550
    OF FINANCE AND PLANNING

    54. RECOMMENDATIONS TO THE MINISTER FOR
    TRADE AND INDUSTRY AND THE INVESTMENT 554
    PROMOTION AUTHORITY

    55. RECOMMENDED DISCIPLINARY PROCEEDINGS 557

    56. RECOMMENDATIONS CONCERNING THE FUTURE OF THE 561
    SPRING GARDEN ROAD/POREPORENA FREEWAY PROJECT

    PART VI SUMMING UP

    57. SUMMING UP 566

  • Page 7 of 397

  • LIST OF EXHIBITS 571

    i

    PART I 1
    NATURE AND PURPOSE OF THE INVESTIGATION

    2

    1. INTRODUCTION

    (1.1] THE OMBUDSMAN COMMISSION’S DECISION TO CONDUCT AN
    INVESTIGATION

    On 27 May 1992 the Governor-General, Sir Wiwa Korowi, signed a
    contract
    on behalf of the Independent State of Papua New Guinea for the
    design,
    finance and construction of a freeway in the city of Port
    Moresby. The
    Governor-General was acting on the advice of the National
    Executive
    Council, which a few weeks earlier had given final approval
    for the signing
    of the contract.

  • Page 8 of 397

  • The Ombudsman Commission received information from a number of
    different sources suggesting that normal procedures had not
    been
    followed. It was also alleged there were irregularities in the
    contract
    negotiations and that the terms of the contract were heavily
    weighted
    against the interests of the State.

    After making preliminary inquiries, it appeared that the
    project had neither
    been put to tender nor considered by the Parliament. As it was
    the
    Commission’s understanding that public works projects of this
    magnitude
    (the contract committed the State to a minimum payment of US
    $67 million
    plus interest) were subject to these procedures, the
    Commission decided
    in May 1992 that it would conduct an investigation, on its own
    initiative, into
    the circumstances leading to and surrounding the decision of
    the National

    Chapter 1

    3
    Executive Council to advise the Governor-General to sign
    the contract for
    the design, finance and construction of the freeway.

    [1.2] JURISDICTION

    The Commission conducted its investigation under the
    Organic Law on the
    Ombudsman Commission. Section 13 authorises it to
    investigate, on its
    own initiative, any “conduct” on the part of any
    “governmental body” or any
    of its officers. The Commission can thus investigate the
    conduct of any
    arm, department, agency or instrumentality of the National
    Government,
    including the National Executive Council (Schedule 1.2(1)
    of the
    Constitution).

    The Commission can investigate the policy of the National

  • Page 9 of 397

  • Government or
    a Minister, to the extent that the policy is contrary to
    law or to the National
    Goals and Directive Principles, the Basic Rights or the
    Basic Social
    Obligations or any Act of the Parliament (Section 219(3) of
    the
    Constitution).

    The Ombudsman Commission is not authorised to conduct an
    investigation
    into the conduct of private citizens and companies.
    Nevertheless, in the
    course of reporting its findings and opinions on the
    conduct of
    governmental bodies, it is sometimes necessary to comment
    on the
    conduct of others who may not be within the jurisdiction of
    the
    Ombudsman Commission. That has happened in this report: we
    have
    occasionally made comments on the conduct of private
    companies, as part
    of the formation of an opinion on the conduct of various
    governmental
    bodies.

    Chapter 1

    4

    [1.3] THE PURPOSE OF THIS INVESTIGATION

    The purpose of this investigation was not to report on whether
    the city of
    Port Moresby needs a freeway. That could have formed a part of
    the
    investigation, because Section 219(3) of the Constitution
    allows the
    Ombudsman Commission to inquire into National Government
    policies
    which are contrary to the National Goals and Directive
    Principles.

    The second of our National Goals is for all our citizens to
    have an equal
    opportunity to participate in, and benefit from, the

  • Page 10 of 397

  • development of our
    country’. Directive Principles 2(3) and 2(4) require that
    every effort be
    made to achieve an equitable distribution of the benefits from
    development
    and an equalisation of services throughout the various parts
    of the country.

    It is arguable whether these objectives were advanced by the
    decision of
    the National Executive Council to commit a large amount of
    public money
    to the building of a freeway in the nation’s capital;
    especially as it is widely
    recognised that the rural infrastructure of our country is
    seriously under-
    developed.

    Nevertheless, the Ombudsman Commission decided, in its
    deliberate
    judgment, not to make that policy decision of the National
    Executive
    Council the subject of this investigation. We were concerned,
    instead, with
    the decision-making process which attempted to implement that
    policy.

    In accordance with Section 219(1) (a) of the Constitution the
    purpose of the
    investigation was:

    to determine whether any of the “conduct” under
    investigation
    was “wrong”; and

    Chapter 1

    5

    to determine whether there were “defects in any law
    or

    administrative practice.

    [1.4] WHAT IS ‘WRONG’ CONDUCT?

  • Page 11 of 397

  • Section 219(2) of the Constitution states that conduct is
    “wrong” if, for

    example, it is:

    “(a) contary to law; or

    (b) unreasonable, unjust/oppressive or improperly
    discriminatory, whether
    or not it is in accordance with law or practices or

    (c) based wholly or partly on improper motives,
    irrelevant grounds or
    irrelevant considerations; or

    (d) based wholly or partly on a mistake of law or of
    fact or

    (e) conduct for which reasons should be given but were
    not,

    whether or not the act was supposed to be done in the
    exercise of deliberate
    judgement within the meaning of Section 62 (decisions in
    ‘deliberate judgement’).”

    However, Section 219(2) of the Constitution also provides
    that the

    Ombudsman Commission is not constrained in its determination
    of whether

    conduct is “wrong”, by the examples listed above. The
    Ombudsman

    Commission has a wide discretion to exercise in making this
    determination.

    In exercising its discretion the Commission is guided, in
    particular, by the

    National Goals and Directive Principles and the Basic Rights
    and the Basic

    Social Obligations, as permitted by Sections 25 and 63 of
    the Constitution.

  • Page 12 of 397

  • Chapter 1

    6

    (1.51 RELEVANCE OF THE LEADERSHIP CODE
    The Ombudsman Commission of Papua New Guinea is entrusted with
    the
    task of administering two Organic Laws:

    the Organic Law on the Ombudsman Commission; and

    the Organic Law on the Duties and Responsibilities of
    Leadership.

    The provisions of the Organic Law on the Duties and
    Responsibilities of
    Leadership, together with those in Division 111.2 of the
    Constitution,
    comprise the Leadership Code.

    We emphasise that this report has not been prepared for the
    purpose of
    recording alleged breaches of the Leaddership Code. The
    procedure for
    dealing with such matters is prescribed by the Organic Law on
    the Duties
    and Responsibilities of Leadership. This report has Int been
    prepared
    under that Organic Law.

    This is a report prepared in accordance with the Organic Law on
    the
    Qmbudsman Commission. Our primary function in this
    investigation has
    been to investigate and report on wrong conduct and defective
    laws and
    administrative practices and to make recommendations
    accordingly.

    In discharging that function the Ombudsman Commission has not
    formed
    any judgment on whether any of the persons involved have

  • Page 13 of 397

  • breached the
    Leadership Code.

    Chapter 1

    7

    METHOD OF INQUIRY

    The Commission obtained documents and other evidence from a number
    of different sources and used its powers under Section 18 of the
    Organic
    Law on the Ombudsman Commission to summon persons to attend before
    the Commission and give evidence under oath and produce documents
    in their possession or control. Most persons summoned to attend were
    co-
    operative. However it was, on occasions, necessary to warn some
    persons
    of their obligation to comply fully with the terms of the summons
    served
    on them.

    We take this opportunity to point out that it is not sufficient for
    a person
    who has been required to produce all documents pertaining to a
    certain
    subject matter to attend the Commission and produce only some, or
    even
    most, of the documents required. Failure to comply fully with an
    Ombudsman Commission summons is a serious criminal offence under
    Section 30 of the Organic Law on the Ombudsman Commission, the
    penalty for which is a K500.00 fine or three months imprisonment for
    each
    offence (see The State v Allan Ebu Marai, National Court decision,
    O.P. 1
    of 1991, 12.2.92).

    A number of the documents obtained by the Ombudsman Commission
    under summons would in the ordinary course of events be regarded as
    confidential in nature,e.g. those providing evidence of the
    proceedings of
    the National Executive Council. However, the effect of Section 19(1)
    of the
    Organic Law on the Ombudsman Commission is that the Ombudsman
    Commission can only be denied access to such documents when the
    Prime Minister, after consultation with the Chief Ombudsman,
    certifies that
    their production is likely to:

  • Page 14 of 397

  • Chapter 1

    “(a) prejudice the security, defence or international
    relations of Papua New
    Guinea (including Papua New Guinea’s relations with the
    Government
    of any other country or with any international
    organization) or the
    investigation or detection of offences; or

    (b) involve the disclosure of proceedings, deliberations or
    decisions of the
    National Executive Council which the “‘time Minister
    certifies relate
    to matters of a secret or confidential nature,
    disclosure of which would
    be contrary to the public interest.”

    In the present case, no certificate under Section 19(1) was issued
    in
    respect of any documents which the Commission sought access to and
    so the Commission was able to require the production of those
    documents.

    The investigation was conducted in private, as required by Section
    17(2)
    of the Organic Law on the Ombudsman Commission.

    * * * * * * * * * *

  • Page 15 of 397

  • Chapter 1

    2. BACKGROUND OF THE FREEWAY PROPOSAL

    [2.1] PORT MORESBY’S TRAFFIC PROBLEMS

    It has been recognised for many years that the peculiar
    geography of the
    city of Port Moresby has given rise to a serious traffic
    problem. Other than
    following the long and winding “back road” through Baruni, or
    the
    inconvenient route along Scratchley Road through Kila Kila,
    only the Sir
    Hubert Murray Highway can carry traffic between downtown Port
    Moresby
    and the other major traffic-generating parts of the city at
    Gerehu, Waigani,
    Hohola, Boroko and Jacksons Airport.

    The Highway, however, is not a high quality road and it is
    often congested.
    Breakdowns and accidents on some sections, particularly Three
    Mile Hill,
    can cause huge traffic jams.

    2.2] THE UNCONNECTED SECTIONS OF THE SPRING GARDEN ROAD
    NETWORK

    Construction of an alternative route, between the suburbs of
    Hohola and
    Konedobu, has long been regarded as the solution to the
    problem.
    Various proposals have been put forward over the last thirty
    years and

  • Page 16 of 397

  • most have favoured a road passing through the saddle of Burns
    Peak
    linking two presently unconnected sections of “Spring Garden
    Road”.
    These two unconnected sections are shown on the map at the end
    of this
    chapter. They are:

    Chapter 2

    10

    from Champion Parade Konedobu to a point close to the
    Department of Transport headquarters in Konedobu: see
    map, points “B” to “C”; and

    from Burns Peak Road Hohola to Wards Road Hohola: see
    map, points “D” to “E”.

    There are also other unconnected sections of the Spring Garden Road
    network which have, at various times, been earmarked for
    construction or
    redevelopment. These are:

    from Wards Road Hohola to a point near the Hohola
    Demonstration School: see map, points “E” to “F”; and

    from Hekakora Street Hohola to Boroko Drive: see map,
    points “G” to “I”.

    More recently, it has been proposed that the Spring Garden Road
    network
    be extended at “both ends”, to form one arterial road linking the
    seaport
    at downtown Port Moresby with Jacksons Airport: see map, points “A”
    to
    ‘. Under this proposal, the extended sections of the Spring Garden
    Road
    network would have been:

    from Stanley Parade in downtown Port Moresby, along
    Champion Parade, to Spring Garden Road, Konedobu: see
    map points “A” to “B”; and

    from the intersection of Spring Garden Road and Boroko
    Drive, Gordons, via Geauta Road, across the Sir Hubert
    Murray Highway at Erima to Jacksons Airport: see map,
    points “in to “K’. via “J”.

    Chapter 2

    11

  • Page 17 of 397

  • [2.3] DECISIONS OF THE NATIONAL EXECUTIVE COUNCIL DURING THE
    1980s

    In the 1980s, the Spring Garden Road issue was addressed by
    the
    National Executive Council on a number of occasions. In
    dealing with
    National Executive Council submissions and decisions in this
    report, we
    have paid special reference to the “Submissions Handbook for
    National
    Executive Council and National Parliament”. [EXHIBIT 1]

    In 1984, the National Executive Council directed the then
    Department of
    Transport and Civil Aviation to arrange a feasibility study on
    the “Burns
    Peak Road” and to ensure that funding was available under the
    National
    Road Improvement Programme for 1985-88. [EXHIBIT 2]

    In 1988, requests for assistance were made to the GoVernment
    of Japan
    for possible funding under grant aid and soft loan
    arrangements for a
    number of projects, including the Burns Peak tunnel. [EXHIBIT
    3]

    Also in 1988, Barclay Bros (PNG) Pty Ltd put a proposal to the
    National
    Government which included an open-cut road through Burns Peak,
    linking
    the Konedobu and Hohola sections of Spring Garden Road, at an
    estimated cost of K11 million. It was proposed that the
    project take place
    in conjunction with the redevelopment of Port Moresby’s port
    facilities. The
    Barclay Bros proposal was discussed by a committee which
    recommended
    that the project be tendered. This proposal also failed to
    come to fruition.
    [EXHIBITS 4 & 4A]

    In 1989, the Departments of Transport, Foreign Affairs and
    Finance and
    Planning were directed by NEC Decision No. 76/89 to approach
    the
    Government of Denmark for aid funding on this and other
    transport
    projects. [EXHIBIT 5]

    Chapter 2

  • Page 18 of 397

  • 12

    [2.4] THE NATIONAL EXECUTIVE COUNCIL DECISION OF 25 JANUARY
    1990

    It was against this background that the National
    Executive Council
    reconsidered the matter at its meeting on 25 January
    1990, following a
    Policy Submission by the Minister for Transport, Mr
    Anthony Temo.
    [EXHIBIT 6]

    In Decision No.14/90, the National Executive Council:

    directed the Department of Transport,
    Department of Works and
    Department of Finance and Planning to
    formulate detail plans for the
    construction of Burns Peak Road;

    2. directed that the plan should include the
    re-evaluation of the Barclay
    proposals and any other Turn-Key’
    proposals available;

    3. approved the engaging of Ove Amp and
    Partners (Pacific) Pty Ltd, to
    undertake the Port Moresby Road Needs
    Study (Arterial Roads);

    4. advised the Governor-General to enter into
    agreement on behalf of the
    State with Ove Amp and Partners (Pacific)
    Pty Ltd” [EXHIBIT 6A]

    * * * * * * * * * *

  • Page 19 of 397

  • Chapter 2

    MAP: THE SPRING GARDEN
    ROAD NETWORK AND THE ROUTE OF

    THE PROPOSED POREPORENA FREEWAY

    Points marked:

    A Stanley Parade/
    Champion Parade
    B Champion
    Parade,Spring Garden Road
    C End of Spring.
    Garden Road Konedobu
    D Spring Garden
    Road/Burns Peak Road
    E Spring Garden
    Road/Wards Road
    F Spring Garden Road
    (Near Hohola Demonstration School)
    G Spring Garden
    Road/Hekakora Street
    H Spring Garden
    Road/Waigani Drive
    I Spring Garden
    Road/Boroko Drive/Geauta Road (Courts’ Roundabout)
    Geauta Road/
    Kookaburra Street/Sir Hubert Murray Highway
    K Jackson
    International Airport

  • Page 20 of 397

  • • Burns Peak

    Chapter 2

    14

    3. STRUCTURE OF THE REPORT

    [3.1] FOCUS OF INVESTIGATION

    On 6 May 1992 the National Executive Council decided to advise
    the
    Governor-General to enter into a contract with Kinhill Kramer
    Pty Ltd and
    Curtain Bros (Old) Pty Ltd for the design, finance and
    construction of the
    Poreporena Freeway. That decision was a crucial one. However,
    in
    conducting this investigation, the Ombudsman Commission was
    not only
    interested in the circumstances immediately surrounding that
    particular
    decision. Our wider concern was to determine whether the whole
    decision-
    making process which occurred after the National Executive
    Council
    decision of 25 January 1990 was carried out lawfully in
    accordance with
    sound administrative practices.

    The Ombudsman Commission therefore considered all the events
    that
    occurred after 25 January 1990, which culminated in the
    signing of the
    contract on 27 May 1992. After examining the evidence obtained
    in the
    course of the investigation, the Commission made a number of
    findings.

    These are set out in Part II of the report, which contains a
    chronological
    account of the events which led to the signing of the
    contract. Each of
    Chapters 4 to 33 highlight a significant incident or decision
    which formed
    the chain of events up to 27 May 1992.

  • Page 21 of 397

  • Chapter 3

    15

    2] ALL PERSONS ADVERSELY COMMENTED ON HAVE BEEN GIVEN A

    RIGHT TO BE HEARD

    During the course of documenting these findings, the
    Ombudsman

    Commission found it necessary to be critical of the conduct
    of some

    individuals and governmental bodies. All of these persons
    and, in the case

    of governmental bodies, their representatives, were given an
    opportunity

    to be heard prior to the completion of this report, in
    accordance with the

    duties imposed on the Ombudsman Commission under Section
    17(4) of

    the Organic Law on the Ombudsman Commission.

    Section 17(4) states:

    “Nothing in this Law compels the Commission to hold any
    hearing and no
    person is entitled as of right to be heard by the
    Commission except that –

    (a) where a report of the Commission may affect a State
    Service, provincial
    government body or statutory body, the Commission
    shall provide

  • Page 22 of 397

  • reasonable opportunity for the Permanent Head of
    that service or the
    statutory head of that body, as the case may be, to
    comment on the
    subject of the investigation; and

    (b) the Commission shall not make any comment in its
    report that is adverse
    to or derogatory of any person without –

    (i) providing him with reasonable opportunity of
    being heard; and

    (ii) fairly setting out his defence in its report”

    3.3] RELEVANT IAM

    One of the main concerns of the Ombudsman Commission at the

    commencement of the investigation was the allegation – which
    came from

    many sources – that proper financial and contractual
    procedures had been

    bypassed.

    Chapter 3

    16

    Part II( of the report accordingly gives an account of
    some of the important
    laws regulating public works contracts in Papua New
    Guinea.

    [3.4] PART IV SUMMARISES AND FORMALISES ADVERSE FINDINGS

  • Page 23 of 397

  • Part IV of the report summarises the adverse findings
    made against
    individuals and governmental bodies in Part II. These
    findings are based
    on Section 219 of the Constitution and Section 22 of
    the Organic Law on
    the Ombudsman Commission, which prescribe the type of
    conduct which
    is “wrong” or otherwise requires criticism by the
    Ombudsman Commission.

    [3.5] RECOMMENDATIONS OF THE OMBUDSMAN COMMISSION

    Part V of the report contains a number of important
    recommendations
    arising from our investigation. In particular, we make
    suggestions as to the
    manner in which public works projects such as the
    Spring Garden Road
    (also known as the Poreporena Freeway) project should
    be handled in
    future.

    [3.6] SUMMING UP

    Part VI sums up the investigation and the findings of
    the Ombudsman
    Commission.

    * * * * * * * * * *

    Chapter 3

    17

    PART II

    RECORD OF EVENTS
    AND FINDINGS OF THE OMBUDSMAN COMMISSION

    18

  • Page 24 of 397

  • 4. DECISION TO PUBLICLY INVITE EXPRESSIONS OF INTEREST:
    MAY 1990

    [4.1] THE INTERDEPARTMENTAL MEETING OF 22 MAY 1990

    After the National Executive Council decided in January 1990
    that detailed
    plans ‘tor the construction of Burns Peak Road” be drawn up,
    very little
    happened until May 1990, when the Minister for Transport, Mr
    Anthony
    Temo, convened an interdepartmental meeting. The meeting was
    held on
    22 May 1990 and was chaired by Mr Temo. The subject was ‘the
    Burns
    Peak Road Development’. [EXHIBIT 8]

    Representatives from various departments and the Harbours
    Board were
    present, as well as a consultant employed by Ove Arup and
    Partners, the
    firm engaged to conduct the Port Moresby Road Needs Study.
    This study
    later concluded that construction of a link through Burns Peak
    would have
    a beneficial effect on the Port Moresby economy and that
    traffic flow on
    the Three Mile Hill section of the Sir Hubert Murray Highway
    would
    consequently be reduced by almost 50%.

    [42] ISSUES UNDER CONSIDERATION

    During this meeting, two crucial issues were addressed:

    Chapter 4

    19

    1. The method of construction of the Bums Peak link

    Once it had been decided that the route for the new road
    would pass through Burns Peak, the next thing to decide was
    the best way of getting through. Should a tunnel be
    constructed or would it be better to make a “cut” through the
    mountain?

  • Page 25 of 397

  • 2. The method of financing the project

    The other crucial issue discussed at the meeting was the
    method of financing the project. One proposal, closely linked
    with the tunnel option, was that part of Spring Garden Road
    would become a tollway.

    This later became transformed into the Build-Operate-Transfer
    (BOT) concept. Under this method of financing, it was
    envisaged that the Government would engage a contractor
    to build and operate the road as a tollway, holding the ‘title’
    to it for, say, twenty years, until the contractor made a
    reasonable return on its investment, and then returning the
    road to the State. el

    The Minister for Transport favoured this option, though he
    was also willing to consider other options, provided they
    involved no financial cost to the Government.

    Chapter 4

    20

    [4.3] NO FIRM POUCY DECISIONS MADE

    No firm decisions were made on either the method of
    construction or the
    method of financing the project at the meeting of 22 May 1990.
    The most
    important outcome was that the Minister for Transport directed
    the
    Department of Transport to advertise the project so that
    interested parties
    could express their interest.

    The Minister also announced that he intended to direct the
    Department of
    Works to commence detailed design of the project immediately
    and to
    complete the design within six months. This was confirmed in
    writing the
    following day, 23 May 1990, in a letter to the Acting
    Secretary of the
    Department of Works, Mr G Morea. [EXHIBIT 9]

  • Page 26 of 397

  • [4.4] MINISTER FOR TRANSPORT EXCEEDED HIS POWERS

    It should be noted that the Minister for Transport had no
    power to give this
    direction to the Department of Works.

    Section 148 of the Constitution states that Ministers only
    have such titles,
    portfolios and responsibilities as are given to them, from
    time to time, by
    the Prime Minister. During 1990, Mr Temo had no responsibility
    for the
    Department of Works and therefore it was wrong of him to
    direct the
    Department to finish the design within six months. We are not
    suggesting
    there was anything improper about getting the design phase
    underway;
    but if the Minister for Transport wanted to expedite the
    project, he should
    have gone about it the right way, by liaising with the
    Minister for Works,
    Secretary for Works and Secretary for Transport.

    Chapter 4

    21

    When we made this finding in our preliminary report, Mr Temo
    responded
    as follows:

    ‘The direction to Secretary for Works was a result of a
    suppose to be ministerial
    committee meeting. When the respective ministers did not
    turn up their
    respective secretaries or their nominees turned up.
    The Department of Works representative suggested the
    idea that it would take
    up to 6 months to have the Geo-Technical report ready
    and he wanted the
    decision to be relayed officially as a result of this
    meeting.
    This letter was drafted by my staff relaying the
    decision of the meeting.
    I was also acting as Chairman of ministerial committee
    on infrastructure_
    [10331BIT 257, page 1]

  • Page 27 of 397

  • Mr Temo’s response does not address the thrust of our
    criticism. His
    direction to the Department of Works was unlawful and wrong,
    in that it
    was contrary to Section 148 of the Constitution.

    .5] MINISTERS DO NOT HAVE THE POWER TO DIRECT DEPARTMENTS IN 1
    THEIR DAY-TO-DAY ACT1VMES

    There is an important aspect of Sectior 148 of the
    Constitution that muss
    be emphasised here: though Section 148 gives Ministers
    “political.
    responsibility for particular Departments, it does not give
    them any power
    to direct or control a Department in its day-to-day
    activities.

    A Minister is not the boss of a Department – the Head of the
    Department
    is the boss. The Ministers job – in conjunction with the
    National Executive
    Council – is to set the Department’s policy on important
    issues. It is not his
    job to give directions to the Departmental Head or to
    Departmental officers
    on day-to-day matters. The only exception is where a Minister
    is specifically
    empowered by an Act of Parliament to give directions or make
    certain
    decisions. 1

    Chapter 4

    22

    This important constitutional principle was explained
    by the Supreme Court
    in Supreme Court Reference No. 1 of 1982: Re Bouraga
    [1982] PNGLR
    178. We discuss it further in Chapter 39 of this
    report.

    So, even if Mr Temo had had political responsibility

  • Page 28 of 397

  • for the Department of
    Works, it still would have been wrong for him to direct
    the Secretary for
    Works to complete the design within six months. He
    could only request
    that that be done and ensure that there were sufficient
    funds available for
    that purpose.

    [4.6] IGNORANCE OF SECTION 148 OF THE CONSTITUTION: A MAJOR
    PROBLEM
    There is a lot of misunderstanding of Section 148 of
    the Constitution in the
    Public Service, and some Ministers appear to know
    little about it.

    The Ombudsman Commission often finds that Ministers
    believe that, simply
    because they are Ministers, they have the right to give
    directions to anyone
    in “theirs Department, or even, as shown in the present
    case, in a
    Department for which they have no responsibility. This
    is wrong. It is
    unconstitutional and it leads to chaos.

    Unfortunately, there were many occasions during the
    life of the Spring
    Garden Road/Poreporena Freeway project when the
    Minister for Transport
    exceeded his powers as a Minister. This was the first
    of them.

    * * * * * * * * * *

    Chapter 4

    23

    5. ADVERTISEMENT INVITING EXPRESSIONS OF INTEREST:
    JUNE 1990

    [5.1] ADVERTISEMENT PUBLISHED IN POST COURIER AND NATIONAL
    GAZEnE
    Advertisements inviting expressions of interests in the “Burns
    Peak/Spring

  • Page 29 of 397

  • Garden Road Link” were published in the Post Courier on 20 and
    22 June
    1990 and the National Gazette on 28 June 1990. [EXHIBITS 12 &
    18]

    There are three points that should be noted about the
    advertisement. They
    concern:

    the scope of the project;

    co-ordination of the project; and

    financing of the project.

    I. THE SCOPE OF THE PROJECT

    [5.2] TERMS OF THE ADVERTISEMENT

    The advertisement stated that the National Executive Council
    had decided
    that “the section of Spring Garden Road in the National
    Capital District
    between Waigani Drive and Kaevaga/Konedobu … is to be
    constructed as
    soon as possible”.

    Chapter 5

    24
    This statement was a little misleading.

    What precisely had the National Executive Council decided?

    What the National Executive Council had, in fact, decided by
    Decision No.
    14/90 was that “plans for the construction of Burns Peak Road”
    be
    formulated.

    This was a very vague decision. The only road in Port Moresby
    that is
    called “Burns Peak Road” is the dirt track running from Spring
    Garden
    Road, near Walnut Place, Hohola to the top of Burns Peak where
    the
    telecommunications transmitters are located.

    Despite the vagueness of Decision No. 14/90 it was assumed by
    everyone
    concerned that the National Executive Council was actually
    referring to

  • Page 30 of 397

  • Spring Garden Road. However, this interpretation still caused
    problems,
    because the National Executive Council did not specify (and
    has never at
    any stage specified) the particular parts of Spring Garden
    Road it wanted
    constructed and/or upgraded.

    [5.3] WHAT WAS MEANT BY ‘THE BURNS PEAK ROAD” OR “SPRING GARDEN
    ROAD”?

    This was not just a small side issue – it concerned the scope
    of the whole
    project. Did the National Executive Council want the upgraded
    road to
    begin at the junction of Stanley Esplanade and Cuthbertson
    Street in
    downtown Port Moresby or was the network to begin at the
    junction of
    Champion Parade and Spring Garden Road in Konedobu? Was the
    road
    to go through Burns Peak to Wards Road? Or one stage further,
    to
    Waigani Drive? Or to the end of Spring Garden Road at Boroko
    Drive? Or
    further still, to the Sir Hubert Murray Highway, at Erima? Or
    was the road
    required to go all the way to Jacksons Airport?

    Chapter 5

    25

    Any of these options could conceivably have been brought
    within the
    terms of the decision that “plans for the construction of the
    Burns Peak
    Road” be formulated.

    The Policy Submission which had generated the decision did not
    shed any
    light on this issue. It simply made reference to the scope of
    the project in
    general terms such as:

    The purpose of the Submission is to request the National
    Executive Council
    to direct Department of Works, Department of Transport and
    Department of

  • Page 31 of 397

  • Finance and Planning to adopt special procurement
    procedures to undertake the construction of Burns Peak Road
    (Spring Garden Road). The measures could
    construction of Burns Peak Road (Spring Garden Road). The
    measures could
    include turnkey arrangements.-
    Construction of the BUMS Peak will involve considerable
    financial commitment’ [EXHIBIT 6, page 1]
    [EXHIBIT 6, page 1]

    5.4] THE DEPARTMENT OF TRANSPORTS INTERPRETATION OF THE
    5.4] THE DEPARTMENT OF TRANSPORTS INTERPRETATION OF THE
    NATIONAL EXECUTIVE COUNCIL DECISION

    The Secretary for Transport, Mr B K Amini CBE, interpreted the
    decision
    as applying only to the section of Spring Garden Road between
    Konedobu
    and Waigani Drive. This is evident from a letter dated 7 June
    1990 he
    wrote to the Secretary for Works, Mr A Temu. Mr Amini
    described the
    scope of the project in the following terms:

    ‘I wish to restate that the scope has not change except the
    grade and the
    elimination of the design of the tunnel option. Basically
    the scope of works am-
    am-

    8% grade
    4 lanes (2 lanes in each direction)
    80 km/ph
    Establishment of a highway link between Rohola (Junction of
    Waigani Drive
    and Spring Garden Road East) and Konedobu (Junction of
    Champion Parade
    and Spring Garden Road West) by improving and extending
    Spring Garden
    Road over Burns Peak, Intersecting and crossing Wards
    Road.’
    [EXHIBIT 10, page 1]

    Chapter 5

  • Page 32 of 397

  • 26

    [5.5] CHANGE OF SCOPE WITHOUT EXPLANATION

    The Secretary for Transport’s interpretation of the National
    Executive
    Council decision was reflected in the advertisements inviting
    expressions
    of interest. But that interpretation did not remain constant.

    Two years after the advertisement was published, the State had
    entered
    into a contract for construction of a freeway all the way from
    downtown
    Port Moresby to Jacksons Airport. This was a considerable
    expansion in
    the original scope of the project. [EXHIBITS 231 A, 231 B,
    232]

    [5.6] WHO MADE THE DECISION TO EXPAND THE SCOPE OF THE PROJECT?

    In the course of this investigation, the Ombudsman Commission
    was never
    able to identify when the decision was made to alter the scope
    of the
    project. Nor can we say who made it. It seems to have “just
    happened’
    that way.

    Mr Amini’s explanation

    When we raised this matter in our preliminary report, the
    Secretary for
    Transport, Mr Amini, responded in the following terms:

    For every major project undertaken by the Department of
    Transport, there is
    a feasiblity study that defines the scope in general terms.
    The outcome of the
    feasibility study is a three-part report – a summary
    containing the main findings

  • Page 33 of 397

  • and recommendations, – a main report containing the main
    issues and – technical
    appendices or working papers. These serve as working papers
    on each project,
    including this one and there is minimum of paperwork. After
    these reports,
    follows the detailed design that pins down the last
    centimetre of the project’s
    scope – where it starts and where it ends. It should be
    noted that, for this
    project, the detailed design had not been done as it was
    part of the turn-key –
    the consortium was going to do that as part of the
    contract.

    Chapter 5

    27

    The project feasibility report prepared by the
    consultants, Ove Arup of Australia
    – entitled ‘Spring Garden Road Economic Assessment’ –
    contained the detailed
    scope of the project and it is a reference point and not a
    file. The scope was
    extended to connect the new DCA road from the airport
    (note this is normal to
    extend the scope – Department of Works almost invariably
    extend every project
    they implement). The end of the DCA project was known
    because it had been
    designed and that is where we were to end this project.
    The DCA project was
    two-lane and wisely we decided to widen it to four to
    conform with the
    Freeway. Both the start and the end of the project were
    clearly known. The
    Department followed its set procedures and this cannot be
    construed as
    defective administration.” [EXEUBIT 254, pages 2-3]

    Unsatisfactory explanation

  • Page 34 of 397

  • In our view, Mr Amini has not given a satisfactory explanation of
    his
    Department’s failure to make a careful and reasoned and properly
    documented decision as to the scope of the Spring Garden
    Road/Poreporena Freeway project.

    His reference to the ‘Spring Garden Road Economic Assessment’ report
    by Arup Australia is, with respect, misleading. Mr Amini suggests
    that the
    scope of the project was determined in accordance with that report.
    Even
    if that were true, we would still expect to find evidence that at
    some stage
    the Department of Transport had made a formal decision to adopt the
    recommendations of the report.

    However, the Arup report entitled ‘Spring Garden Road Economic
    Assessment’ did not provide any basis for the decision to extend the
    scope of the project to Jacksons Airport along the route envisaged
    in the
    contract with the Kinhill Kramer/Curtain Bros consortium.

    Despite Mr Amini’s claim that the start and end of the project were
    clearly
    known, the ‘Spring Garden Road Economic Assessment Report’ only
    contemplated a four-lane road from downtown Port Moresby to the
    intersection of Spring Garden Road and Waigani Drive (see Chapter 2

    Chapter 5

    28
    map, points “A” to “H”), plus other associated works. The Spring
    Garden
    Road project, according to that report, did not include the
    upgrading of
    Spring Garden Road from Waigani Drive to Boroko Drive (see map, “H”
    to
    “I”). The project also did not include a four-lane arterial road
    from the
    intersection of Spring Garden Road and Boroko Drive to Jacksons
    Airport,
    via Geauta Road, which was the route envisaged in the contract
    entered
    into with the Kinhill Kramer/Curtain Bros consortium (see map,
    points “I”
    to “K”). [EXHIBIT 9A, page 10, para 5.12; EXHIBIT 233, Part Z
    Description of Concept]

    In Arup’s Study Report, which was separate from the Spring Garden

  • Page 35 of 397

  • Road
    Economic Assessment Report, it was recommended that, in addition to
    the
    Spring Garden Road project, many other road construction and
    improvement projects should be undertaken in the city of Port
    Moresby.
    These included widening the section of Spring Garden Road between
    Waigani Drive and Boroko Drive to four lanes (see map, “H” to “I”).
    However, the Study Report did not recommend the widening or
    upgrading
    of Geauta Road, from Boroko Drive to the Sir Hubert Murray Highway
    (see
    map, “I” to “J”). The Study Report, in fact, recommended that the
    most
    direct route between downtown Port Moresby and Jacksons Airport
    should
    be via Sir John Guise Drive, which was proposed to be extended as a
    two-lane arterial road. [EXHIBIT 69A, para 7.0, table 1]

    Thus, neither the Spring Garden Road Economic Assessment Report nor
    the Study Report recommended a four lane arterial road along the
    route
    contained in the contract executed with the Kinhill Kramer/Curtain
    Bros
    consortium.

    Mr Hitola’s explanation

    When our criticism of the Department of Transport’s failure to
    specify the
    scope of the project was conveyed to the Secretary for Works, Mr
    Hitolo

    Chapter 5

    29
    (who was responsible for this project for a considerable time in the
    Department of Transport) he offered a different explanation.

    Mr Hitolo said that because the project was to be implemented using
    Build-Operate-Transfer financing, it was up to the private sector to
    determine the financial viability of the project before proposing
    the scope
    to the Government for approval. Mr Hitolo also said that a careful
    and
    reasoned and properly documented decision about the scope of the
    project required a feasibility study costing between K200,000.00 and
    K400,000.00, which had not been budgeted for.
    [EXHIBIT 265, page 2]

    Explanation rejected

    We find Mr Hitolo’s explanation unconvincing. Even if we accept

  • Page 36 of 397

  • that, in the
    case of a Build-Operate-Transfer project, the scope is determined by
    the
    developer, the fact is that no Build-Operate-Transfer proposal was
    ever
    lodged for the Spring Garden Road/Poreporena Freeway project. All of
    the
    proposals involved turnkey financing.

    This meant that inevitably – at some stage – the Government would be
    paying for the freeway. It was therefore necessary for the
    Government to
    know exactly where it wanted the freeway to go and how long the
    freeway
    would be.

    No proper comparison of competing proposals could be made unless
    everyone concerned knew the beginning and end points of the freeway
    and its route.

    It was the Department of Transport’s responsibility to make a
    careful and
    reasoned decision on this basic issue. However, it failed to do
    this.

    Chapter 5

    30

    [5.71 CHANGE OF FUNDAMENTAL DESIGN ALSO WITHOUT EXPLANATION

    We make a similar observation on the decision about the
    tunnel/cut option.
    Mr Amini’s letter to the Secretary for Works of 7 June 1990
    makes mention
    of the fact that the tunnel option had been eliminated.
    [EXHIBIT 10, third
    paragraph] But, at an interdepartmental meeting on 31 July
    1990, it was
    decided that a geotechnical investigation was required, before
    a final
    decision could be made (see Chapter 7).

    Throughout 1991, when negotiations were taking place with
    likely
    contractors, it was assumed the project would include a
    tunnel. When the
    National Executive Council made Decision No. 36/92 in favour
    of IGnhill
    Kramer Pty Ltd in February 1992, one of the key criteria (and
    one on
    which Knhill Kramer was rated “excellent”) was the “expected

  • Page 37 of 397

  • quality of
    tunnel”. But when the contract was signed, on 27 May 1992,
    there was
    no mention of a tunnel.

    MrAminarasmnrA

    In our preliminary report, we were critical of the Department
    of Transport
    for the haphazard manner in which the tunnel/cut issue was
    addressed.
    The Secretary for Transport, Mr Amini, replied that the
    geotechnical
    investigation undertaken by Coffey Partners International (see
    Chapter 8)
    was meant to give a conclusive answer; but he said it turned
    out to be
    inconclusive. As to the eventual decision to opt for the cut,
    rather than the
    tunnel, Mr Amini said it was made by the Department of Works.
    [EXHIBIT
    254, page 3]

    Chapter 5

    31

    Mr Hitolo’s response

    Mr Hitolo’s explanation of the confusion over the tunnel/cut issue
    was that
    it was an investment decision, to be made by the consortium selected
    to
    undertake the project. [EXHIBIT 254, page 2]

    Neither response was satisfactory

    Having considered the responses of Messrs Amini and Hitolo, we
    conclude
    that neither offered a satisfactory explanation for the Department
    of
    Transport’s failure to make a careful, reasoned and properly
    documented
    decision on the tunnel/cut issue.

    Mr Hitolo’s claim that it was an “investment decision” could only
    possibly
    make sense if the project were based on Build-Operate-Transfer
    financing.

  • Page 38 of 397

  • But, as pointed out earlier, no such proposal was ever put to the
    Department of Transport. The Government of Papua New Guinea was
    always going to pay for this project and therefore it should have
    decided
    whether a tunnel or a cut through Burns Peak was preferable.

    We accept Mr Amini’s description of the geotechnical report as
    inconclusive. But that report was made available in May 1991 – the
    Department of Transport had ample time after that to make a
    determination
    on this basic technical issue. Though the Department of Works was
    eventually consulted, this should have been done on a formal and
    methodical basis – not by means of casual conversation between
    officers
    of the two Departments.

    We simply do not regard it as an acceptable administrative practice
    for the
    Department of Transport to have prepared a Policy Submission which
    assumed the project would include a tunnel and then – without any
    record

    Chapter 5

    32
    of consultation or any record of any different decision – to
    allow a situation
    to develop in which the project included a cut through Burns
    Peak, rather
    than the tunnel.

    [5.8] ADMINISTRATIVE INCOMPETENCE BY THE DEPARTMENT OF
    TRANSPORT

    It is stating the obvious to say that decisions concerning
    Papua New
    Guinea’s transport infrastructure should not be made as they
    were in the
    case of the Spring Garden Road/Poreporena Freeway project.

    Decisions such as the length of a freeway and its fundamental
    design
    should not be made haphazardly. These decisions involve the
    expenditure
    of large amounts of public money. They must be made carefully
    and
    methodically and they must be properly documented. If
    Government
    departments make important policy decisions haphazardly, it is
    virtually
    impossible to keep a check on the expenditure of public money.
    And it

  • Page 39 of 397

  • creates an environment ripe for corruption.

    When an investigatory agency such as the Ombudsman Commission
    does
    a check on a decision-making process which led to the
    commitment of
    millions of kina of public money, it should be able to find
    evidence of a
    series of reasoned and methodical steps and the careful
    evaluation of
    alternatives. But the evidence we have gathered shows the
    exact
    opposite: it was as if decisions – like the route of the
    freeway – were falling
    out of the sky.

    The Ombudsman Commission has concluded that this situation
    arose
    because of the administrative incompetence of the Department
    of
    Transport.

    Chapter 5

    33

    IL CO-ORDINATION OF THE PROJECT

    [5.9] EXPRESSIONS OF INTEREST CO-ORDINATED BY DEPARTMENT OF
    WORKS

    Despite the Minister for Transport’s direction at the
    meeting of 22 May
    1990 that the project be advertised by the Department of
    Transport, the
    advertisements were actually organised by, and the
    responses had to be
    made to, the Department of Works.

    Apparently, this turnaround occurred because the First
    Assistant Secretary
    (Planning and Research) in the Department of Transport, Mr
    Amoako, •
    asked the Department of Works for assistance in drafting
    the
    advertisement. The Principal Engineer (Roads), Mr
    Newberry, prepared a
    draft which was forwarded to the Department of Transport

  • Page 40 of 397

  • for review and
    issue. However, Mr Amoako returned the document to Mr
    Newberry,
    advised him that it was satisfactory and requested that it
    be published by
    the Department of Works. [EXHIBIT 51, page 2 and EXHIBIT
    52, page 2]

    [5.10] A SIGNIFICANT LACK OF CO-ORDINATION

    Though there was nothing improper in what was done by Mr
    Amoako, this
    incident is significant because it typified what was, and
    continued to be,
    a confusing state of affairs regarding the implementation
    of the whole
    project: there was a great deal of confusion as to the
    respective roles of
    the Department of Transport and the Department of Works,
    which we
    consider was ultimately detrimental to the overall
    interests of the State.

    Chapter 5

    34

    III. FINANCING OF THE PROJECT

    [5.11] TERMS OF THE ADVERTISEMENT

    The advertisement of June 1990 alluded to the issue of
    financing the
    project, in the following terms:

    “The work may be financed by a combination of
    any or all of the following:

    a toll on the new road link
    commercial leases on reclaimed

  • Page 41 of 397

  • land
    grant funding by external agencies

    Other means of funding will be considered but
    it is not intended that the
    Government will contribute to any major
    extent.”

    [EXHIBITS 12 & 18]

    The advertisement did not stipulate that the
    successful contractor would
    have to itself finance the project.

    This is significant, because, as the Commission was to
    discover in the
    course of the investigation, there were a number of
    interested parties that
    were later summarily rejected because of the
    inadequacy of their financing
    proposals.

    We consider this to have been quite unfair, because,
    though the
    advertisement stated that the Government would
    probably not finance the
    project, it did not stipulate that any company which
    failed to submit a
    “financial package” would be automatically excluded
    from consideration.

    * * * * * * * * * *

    Chapter 5

    35

    RESPONSES TO THE ADVERTISEMENT: JULY 1990

  • Page 42 of 397

  • 6.1] RESPONSES SENT TO DIFFERENT PLACES

    The Ombudsman Commission discovered that some of the
    expressions of
    interest were sent to the Department of Works, whereas others
    went to the Department of Transport.
    Department of Transport.

    [6.2] EXPRESSIONS OF INTEREST SENT TO THE DEPARTMENT OF WORKS

    We have been able to confirm, by examining the files of the
    Department
    of Works, that ten expressions of interest were registered
    with it, on or before 31 July 1990, as required by the
    advertisement:
    before 31 July 1990, as required by the advertisement:

    Coecon Pty Ltd [EXHIBITS 13, 21]

    Barclay Bros (PNG) Pty Ltd [EXHIBIT 14]

    Connell Wagner (Old) Pty Ltd [EXHIBIT 17]

    Willing and Partners Pty Ltd [EXHIBIT 20]

    Robert Laurie Company Pty Ltd [EXHIBIT 20AA]

    Maunsell Consultants PNG/Hornibrook
    Constructions Pty Ltd [EXHIBIT 22]

    Chapter 6

    36

    Curtain Bros (PNG) Pty Ltd [EXHIBIT 23]

    LKN Construction Pte Ltd [EXHIBIT 25]

    Cardno & Davies PNG Pty Ltd [EXHIBIT 26]

    Juara Ltd [EXHIBIT 29]

    (A number of documents we obtained referred to an expression
    of interest
    being received from Frame Harvey West (e.g. EXHIBITS 24, 38,
    50, 148).
    However, we could find no evidence of this. The consulting
    firm of Frame
    Harvey West & Maso later joined with Periquan International
    Resources
    and submitted a proposal to the Minister for Transport in July

  • Page 43 of 397

  • 1991, but
    it appears not to have formally expressed any interest before
    that.)

    [6.3] EXPRESSIONS OF INTEREST SENT TO THE DEPARTMENT OF
    TRANSPORT

    Despite the clear statement in the advertisement that
    expressions of
    interest be registered with the Department of Works, five
    groups wrote to
    the Department of Transport. These were:

    Executive Decisions Inc Pty Ltd [EXHIBIT 1 OA]

    Kumagai Gumi Co Ltd/Kinhill Kramer Pty Ltd
    [EXHIBITS 15, 16]

    Pan Asia Management Consultants Center [EXHIBIT 27]

    Chapter 6

    37

    Ove Arup & Partners (Pacific) Pty Ltd [EXHIBIT
    21A]

    Sabina Ltd/Peter Chen & Partners Pty Ltd
    [EXHIBIT 35]

    [6.4] MOST EXPRESSIONS OF INTEREST HELD BY DEPARTMENT OF WORKS

    The Department of Works was made aware of all but one of
    these
    expressions of interest (from the Singapore-based
    Executive Decisions Inc
    Pty Ltd) when the Department of Transport faxed copies to
    them on 1 and
    2 August 1990. [EXHIBITS 34, 35] Mil

    In light of the above, we are satisfied that as at 2
    August 1990, the II
    Department of Works had at least fourteen expressions of
    interest in its
    possession and that they were held by the Principal
    Engineer (Roads), Mr IN
    E Newberry, who was the Department of Works co-ordinator
    of the project.

  • Page 44 of 397

  • IR
    [6.5] NO ACKNOWLEDGEMENT OF THE EXPRESSIONS OF INTEREST

    During the first week of August 1990, Mr Newberry
    prepared a summary
    of the expressions of interest and delivered it to the
    Department of
    Transport. No attempt was made at this stage to rank them
    in any way.
    We are not critical of this, because the advertisement
    had not called for
    firm proposals – all that was required were expressions
    of interest.

    We consider, however, that the Department of Works should
    have at least
    sent an acknowledgment to each of the interested groups,
    indicating when
    a more detailed information package would be available,
    which could be
    used to formulate firm proposals for the project.

    Chapter 6

    38

    When we expressed this opinion in our preliminary report, the
    Department
    of Works advised that, in fact, several of the expressions of
    interest were
    acknowledged. We were referred to letters sent to Connell Wagner and
    Ove Arup and Partners Pacific and to a telephone call made to the
    Robert
    Laurie Company. [EXHIBIT 261, page 1]

    We accept that acknowledgements were given to each of these
    companies
    in the manner described. [EXHIBITS 17A, 19A AND 20AA]

    However, acknowledgements were not given to the other twelve
    interested
    parties. In his response to the Ombudsman Commission, the Secretary
    for Works, Mr Hitolo, gave an explanation for this:

    ‘It seems that the major reason that E0Is were not acknowledged
    was the rush
    that things were done in. This meant that a proper terms of

  • Page 45 of 397

  • reference (TOR)
    was not sent out, so most EOI’s came in, not so much as
    expressions of interest,
    but as queries about the project. Concurrently, Mr Newberry was
    singlehandedly writing a further TOR (which would have involved a
    full team
    of !specialists for a project of this scope and magnitude) and
    handling all of
    the other National Road Design Projects. For a period Mr Newberry
    was (or
    very nearly was) the only Road Engineer in the Roads & Bridges
    Branch, where
    the work load is more than 10 engineers ems could handle. He
    probably ran out of
    time to perform everything. This staff shortage still plagues the
    branch…

    One further complication was that Department of Transport
    contacted some of
    the parties independently, asking for different information and
    receiving their
    expressions of interest. These were then passed on to Department
    of Works two
    weeks after the dosing of expressions of interest.

    These factors all contributed to the overlooking of the
    acknowledgement of
    most of the Expressions of Interest. There is no indication that
    the failure to
    acknowledge them was purposeful.’ [EXHIBIT 263, page 1]

    While we appreciate the difficulties faced by any Department
    suffering
    from shortages of staff or other resources, the Ombudsman Commission
    remains critical of the Department of Works for not sending
    acknowledgements to all the companies which had expressed interest
    in
    the project. It was a simple administrative task to perform. It was
    wrong
    of the Department of Works not to carry it out.

    Chapter 6

    39

    [6.6] BREAKDOWN IN COMMUNICATION BETWEEN DEPARTMENT OF WORKS
    AND DEPARTMENT OF TRANSPORT

    We noted earlier that despite the Minister for Transport’s
    direction that the project be handled by his Department, the

  • Page 46 of 397

  • advertisements calling for
    project be handled by his Department, the advertisements
    calling for
    expressions of interest were actually organised by the
    Department of
    Works.

    This was very surprising because it is clear that the Minister
    for Transport, Mr Temo, and the Secretary for Transport, Mr
    Amini, both genuinely
    Mr Temo, and the Secretary for Transport, Mr Amini, both
    genuinely
    believed that the project “belonged” to the Department of
    Transport.

    The Ombudsman Commission formed this view after interviewing
    both Mr
    Temo and Mr Amini in the course of the investigation. It was
    also apparent
    from correspondence between the Minister and the Secretary for
    Transport, that the project was regarded as belonging to the
    Department
    of Transport. We refer, for example, to a letter from Mr Amini
    to Mr Temo
    on 28 June 1990 in which, only a few days after publication of
    the
    advertisement, Mr Amini gave Mr Temo an update on the
    expressions of
    interest for his “advice and directive”. [EXHIBIT 1 9]

    [6.7] DEPARTMENT OF TRANSPORT SUDDENLY INVITES DETAILED
    PROPOSALS

    The closing date given by the advertisements for registration
    of
    expressions of interest was 31 July 1990. The Ombudsman
    Commission
    was surprised to find that before that date, the Department of
    Transport
    decided – without consulting the Department of Works -to
    contact a
    selected group of companies and invite detailed proposals for
    the project.

    Chapter 6

    40

    [6.8] ONLY A SELECT GROUP OF COMPANIES WERE INVITED TO SUBMIT
    PROPOSALS IN JULY 1990

  • Page 47 of 397

  • This surprising turn of events occurred around the period
    17-20 July 1990.
    A pro-forma letter headed “HEARING FOR DEVELOPMENT OF THE
    SPRING GARDEN ROAD” was drafted within the Department of
    Transport
    [EXHIBIT 20A]. It was apparently meant to be sent to all the
    companies
    which had lodged expressions of interest. We infer this from
    the “List of
    Interested Companies” attached to the pro-forma letter in the
    Department
    of Transport file. [EXHIBIT 20A, page 3]

    However, the Ombudsman Commission is not satisfied that the
    letter was
    in fact sent to all of those companies. There is no evidence
    on file
    verifying the postage or facsimile transmission of the letter
    to all of the
    companies that had lodged expressions of interest.

    Furthermore, the list in the Department of Transport file
    excludes four
    groups that had registered interest with the Department of
    Works:

    Curtain Bros (PNG) Pty Ltd;

    Cardno & Davies (PNG) Pty Ltd;

    Maunsell Consultants/Hornibrook
    Constructions Pty Ltd; and

    Juara Ltd.

    Chapter 6

    41

    [6.9] WHY WERE SOME COMPANIES DROPPED FROM THE UST?
    [6.9] WHY WERE SOME COMPANIES DROPPED FROM THE UST?

    Perhaps the reason for these companies not being on the
    Department of
    Transport’s list was that their expressions of interest were
    received later
    than the others (the four referred to above were received by
    the
    Department of Works during the period 27 July 1990 to 1

  • Page 48 of 397

  • August 1990).
    But other than the expression of interest from Maunsell/
    Hornibrook (which
    was one day late) all were received within the period
    specified in the
    advertisement.

    There was therefore no justification for these companies
    being dropped
    from the list and deprived the opportunity to submit a formal
    proposal.

    During the course of the Commission’s investigation,
    representatives of
    both Cardno & Davies and the Maunsell/Hornibrook consortium
    were
    questioned and they confirmed that they had never received
    any formal
    acknowledgement of their expressions of interest, or been
    invited to submit
    a formal proposal.

    It is surprising that these particular companies were omitted
    from the short- list, even though they all have permanent
    bases in Papua New Guinea and
    list, even though they all have permanent bases in Papua New
    Guinea and
    their expressions of interest were among the most detailed of
    those
    received by the Department of Works.

    Indeed, it is ironic that the company which provided the
    least amount of
    information in its expression of interest – Curtain Bros
    (PNG) Pty Ltd – was ultimately selected to be closely
    involved in construction of the freeway.
    ultimately selected to be closely involved in construction of
    the freeway.
    [EXHIBIT 23]

    Chapter 6

    42

    [6.1 0] RESPONSE BY THE SECRETARY FOR TRANSPORT

    When we made these findings in our preliminary report, the

  • Page 49 of 397

  • Secretary for
    Transport, Mr Amini, responded in the following terms:

    ‘The Department did not receive any complaint from any
    developer. I will urge
    the Ombudsman Commission to be cautious in promoting any
    particular
    developer. If it was unreasonable, at least one or two of
    the developers would
    have made suggestions as they always do. No developer was
    ever stopped or
    prevented from submitting a proposal. They were actively
    encouraged. In any
    case, the submission date was extended twice to
    accommodate late bids. This
    is not defective administration.’ [EXHIBIT 254, page 31

    The Ombudsman Commission does not regard Mr Amini’s response
    as
    satisfactory. His assertion that no developer was ever
    prevented from
    submitting a proposal is not borne out by the facts.

    We are not suggesting the Department rejected or refused to
    accept any
    proposal. What the Department did wrong was to invite
    proposals from
    only a select group of companies, thus excluding a number of
    companies
    from consideration.

    [6.11] OTHER MATTERS OF CONCERN

    The Ombudsman Commission is not only concerned about the
    Department
    of Transport letter being sent to only a select group of
    companies. What
    is also disconcerting is the timing of the letter and the
    demands placed
    upon the companies chosen to receive it.

    The Ombudsman Commission has been able to confirm that the
    letter
    inviting proposals was sent, during the second half of July
    1990, to at least
    five of the companies and consortiums referred to on the

  • Page 50 of 397

  • Department of
    Transport list:

    Chapter 6

    43

    Coecon Pty Ltd [EXHIBIT 20B]

    Willing and Partners Pty Ltd [EXHIBIT 22A]

    Ove Arup & Partners Pacific Pty Ltd [EXHIBIT 28]

    Sabina Ltd/Peter Chen & Partners Pty Ltd [EXHIBIT 30]

    Kumagai Gumi Co Ltd/Kinhill Kramer Pty Ltd. [EXHIBIT
    31]

    [6.12] THE DEPARTMENT’S REQUIREMENTS COULD NOT BE MET

    Unreasonable and unrealistic demands were imposed by the
    Department
    of Transport. The letter stated:

    “Dear Sir

    HEARING FOR DEVELOPMENT OF THE SPRING GARDEN ROAD
    This is to inform you of the fact that the Steering
    Committee administering
    the above-mentioned project will be meeting to consider
    your proposals and
    you are advised to send the details to this Department
    before the 25/7/90.

    The following planning information is required from you to
    assist the
    Government in selecting the developer.

  • Page 51 of 397

  • I. Technical Feasibility Report

    2. Preliminary Design or Plans.

    3. Financial Viability for a Toll System.
    4. Details of Financial Arrangements.

    5. Involvement of Landowners in the Development

    Chapter 6

    44

    Since the Government is anxious to complete this project
    by September next
    year in preparation for the South Pacific Games, it is
    important that you state
    very clearly whether you can achieve this time frame.

    Yours faithfully
    [Signed]
    BRIAN K AMINI CBE
    Secretary’. [EXHIBIT 20A]

    The Ombudsman Commission is at a loss to see how the
    Department of
    Transport could reasonably have expected these requirements
    to be met
    within one week. The only specifications available to the
    companies were
    those in the June 1990 advertisements. How could they be
    expected to
    submit meaningful technical feasibility reports, preliminary
    designs and
    financial arrangements, as well as give a proper assessment
    of the financial
    viability of a toll system and the involvement of landowners,
    in the space
    of a few days?

  • Page 52 of 397

  • As one consultant explained to the Ombudsman Commission, a
    detailed
    feasibility study of the type being sought by the Department
    of Transport
    would cost thousands of kina and it would take considerably
    longer to do
    than the few days suggested in the letter.

    In sending this letter, the Department of Transport gave the
    impression it
    had no idea at all of what was involved in a project of this
    magnitude.

    [6.13] MR HETOLO’S EXPLANATION

    In his response to our preliminary report, the former head of
    the Policy
    Secretariat in the Department of Transport, Mr Hitolo, made
    these
    comments:

    Chapter 6

    45

    ‘The unreasonable and unrealistic demands were placed on
    the plight&
    developers because the department was under pressure to
    meet the September
    1991 Games as mentioned in the letter. This letter was
    sent to a selected few
    which was a normal practice and usually is called
    selective tendering. As long
    as three or more proposals are tendered a selection can be
    convened. The
    whole purpose was for interested and so-called reputable
    companies to propose
    a plan of execution of the tasks mentioned in the letter
    and propose an
    alternative if they cannot meet the deadline of September
    Games stated in the

  • Page 53 of 397

  • letter. It was not mandatory to include all those that
    showed interest because
    some of the companies saw me personally or phoned to find
    out whether
    funding was available and when it was explained otherwise
    they indicated
    disinterest as most of them are not financiers. They only
    offer their engineering expertise and were unable to
    finance such a big project.•
    expertise and were unable to finance such a big project.•
    [EXHIBIT 265, page 3]

    Mr Hitolo’s explanation that representatives of some companies
    had seen
    him personally or telephoned to find out whether funding was
    available is
    not considered satisfactory. There were no file notes kept of
    the occasions
    on which these companies signalled their loss of interest in
    the project. We
    are also unimpressed by the suggestion that, provided at least
    three
    proposals were received, a proper selection could be made.

    The private and undocumented “selective tendering” evident in
    the limited
    dispatch of the letters of July 1990 is very, very dangerous,
    because it can
    easily lead to corruption. It is vitally important that the
    public tendering
    procedures in the Public Finances (Management) Act are
    strictly adhered
    to, especially in projects which involve millions of kina of
    public money (see
    Chapter 35).

    6.14] LETTERS WERE SENT LATE

    The unreasonableness of the demands contained in the letters
    of July 1990
    was exacerbated by the fact that the letters were sent late.

  • Page 54 of 397

  • Chapter 6

    46

    Of the five companies we verified as receiving the letter,
    only one received
    it before the deadline for submission of proposals. [See the
    reference in
    each of EXHIBITS 28, 30 and 31 to the letter having arrived
    late and the
    date-received stamp of 26 July 1990 on EXHIBIT 22k]

    An example of the confusion caused by the Department of
    Transport

    Coecon Pty Ltd received its letter by facsimile transmission
    at 9.32 am on
    20 July 1990, but the company was obviously (and
    understandably)
    confused as to what was required of it. At 2.25 pm on the
    same day, the
    General Manager, Mr P J Neville, sent a facsimile message to
    the Principal
    Engineer (Roads), Mr Newberry, at the Department of Works:

    ‘Please advise us of present stage of development for
    Burns Peak. For instance:
    any technical reports such as preliminary design plans
    etc.’ [EXHIBIT 711

    There is a handwritten note at the foot of that document
    (though it is not
    clear who its author is, it was probably made by an officer
    of the
    Department of Works) that typifies the general state of
    confusion:

    ‘The information requested of Department of Works by
    Coecon is what is
    requested of Coecon by Department of Transport. We seem to
    be going around
    in circles? [EXHIBIT nj

  • Page 55 of 397

  • [6.15] ADMINISTRATIVE INCOMPETENCE BY THE DEPARTMENT OF
    TRANSPORT

    To sum up, the Ombudsman Commission is of the view that the
    conduct
    of the Department of Transport in dispatching the pro-forma
    letter dated
    17 July 1990, advising companies that they had to send
    details of their
    proposals by 25 July 1990, was unfair, unrealistic and
    incompetent
    administratively for the following reasons:

    Chapter 6

    47

    (a) the letter was sent to only a select group of
    companies and,
    furthermore, excluded the two PNG-based companies
    which
    had submitted detailed expressions of interest;

    (b) the Department of Transport failed to advise the
    Department
    of Works (which was co-ordinating the expressions
    of interest)
    that it was sending the letter;

    (c) the letter placed unrealistic demands on the
    companies,
    which made it impractical for them to respond by
    the
    deadline;

    (d) the deadline for submission of proposals was on a
    date It
    before the closing date given in the
    advertisements for
    registration of expressions of interest; and

    (e) the letter was sent late, which resulted in most
    of the
    companies not receiving it until after the
    deadline set for
    submission of proposals.

  • Page 56 of 397

  • [6.16] SOME COMPANIES WERE NEVER GIVEN ANOTHER OPPORTUNITY TO
    SUBMIT PROPOSALS

    The conduct of the Department of Transport during July 1990
    cannot be
    dismissed as a mere administrative hiccup. It would have
    been possible
    to *forgive” the Department for its unfairness and
    incompetence if, at some
    later time, a proper opportunity to submit detailed
    proposals was given to
    a companies which had expressed genuine interest in the
    project. But this
    never happened.

    f’hRpter 6

    48

    As we show later in the report, a number of companies
    were never
    considered or even contacted by the Department of
    Transport again. This
    was a disgraceful state of affairs.

    When this sort of thing goes on, how can honest and
    responsible
    companies have confidence in the Department of
    Transport, or any other
    Department for that matter? How can anybody have
    confidence in the
    integrity of government in Papua New Guinea? The
    selective picking-
    and-choosing of companies to submit proposals must be
    avoided at all
    costs, since it is unfair and not in the best interests
    of the State and such
    practices breed corruption.

    [6.17] LITTLE RESPONSE TO THE REQUEST FOR PROPOSALS

    The Department of Transport’s attempt, in July 1990, to
    get the “selected”
    companies to submit proposals, was so badly
    implemented, that hardly
    any of those companies responded. This meant that in
    1991, the

  • Page 57 of 397

  • shortlisting process had to begin again.

    But as we show in Chapter 9, the shortlisting process
    in 1991 was also
    carried out in an arbitrary, unfair and unsatisfactory
    way.

    * * * * * * * * * *

    Chapter 6

    49

    SIGNIFICANT INTERDEPARTMENTAL MEETING:
    31 JULY 1990

    7.1] ORIGINAL PURPOSE OF MEETING

    An interdepartmental meeting, involving representatives of
    the Departments
    of Transport, Works, Finance and Planning and Attorney-
    General, was held
    on 31 July 1990. It was jointly chaired by the Secretary
    for Transport, Mr
    Amini, and the Secretary for Works, Mr Temu.

    It was originally intended that the meeting would consider
    proposals invited
    by the Department of Transport’s letters of 17-20 July
    1990. [See the
    minute from the Director of the Department of Transport’s
    Policy
    Secretariat, Mr Hitolo, to Mr Amini dated 27 July 1990 at
    paragraph 2 and
    the handwritten notes which refer to the “selection
    criteria”: EXHIBIT 24.]

  • Page 58 of 397

  • However, because the letters were sent late, the companies
    could not
    respond in time. Rather than being a forum for assessment
    of proposals
    the meeting therefore focused on other important issues
    concerning the
    project.

    2] ISSUES DISCUSSED AT THE MEETING OF 31 JULY 1990

    The minutes of the meeting record discussion of the
    following issues:

    Chapter 7

    50

    The name of the project – the Secretary for Transport
    favoured the name “Spring Garden Road (Burns Peak) Link”.

    Funding of the project – Mr Hitolo advised that the World
    Bank had been approached.

    The Port Moresby Roads Needs Study – the First Assistant
    Secretary of the Department of Transport’s Planning and
    Research Division, Mr Parakei, advised that the Burns Peak
    project was part of the Study.

    Engineering details – the Department of Works’ Principal
    Engineer (Roads), Mr Newberry, addressed the tunnel/cut
    option, particularly the problems associated with disposal of
    the cut.

    Landowner issues – Mr Hitolo advised that preliminary
    discussions had been held with landowners, some of whom
    were claiming lump sum payments prior to commencement
    of the project.

    Scope of the project – some consideration was given to
    upgrading other sections of the Spring Garden Road network,
    particularly Wards Road to Waigani Drive.

  • Page 59 of 397

  • Target date for completion – it was generally agreed the
    project could not be completed by the original target of
    September 1991, coinciding with the South Pacific Games.
    [EXHIBIT 33]

    Chapter 7

    51

    [7.3] FUTURE ACTION
    [7.3] FUTURE ACTION

    As to the next action to be taken, two things were decided:

    1. The National Executive Council was to be informed that the
    project
    could not be completed for the South Pacific Games.

    2. Further geological investigations would have to be
    undertaken, so
    that a decision could be made on the tunnel/cut option.
    [EXHIBIT
    33, paragraph 5 and EXHIBIT 51, page 4, para 3]

    [7.4] PROPOSALS WERE NOT CONSIDERED AT MEETING ON 31 JULY 1990
    [7.4] PROPOSALS WERE NOT CONSIDERED AT MEETING ON 31 JULY 1990
    MAIAITLOILEBIEIEIIING
    We note there is a reference to this meeting of 31 July 1990
    in the Policy Submission presented to the National Executive
    Council in February 1992,
    Submission presented to the National Executive Council in
    February 1992,
    which led to the decision to award the project to Kinhill
    Kramer Pty Ltd
    (see Chapter 21).

    It was suggested in the Policy Submission that the various
    expressions of interest and proposals had been presented at
    the meeting of 31 July 1990.
    interest and proposals had been presented at the meeting of 31
    July 1990.

    However, it is quite dear, from the minutes of the meeting and
    other
    documents considered by the Ombudsman Commission, that the
    proposals were Dot presented at that meeting. There were no
    proposals,
    as at 31 July 1990, that could be considered.

  • Page 60 of 397

  • Moreover there was never, in the life of the Spring Garden
    Road/Poreporena Freeway project, any interdepartmental meeting
    at which
    all the proposals were considered. Neither was there a meeting
    within the

    Chapter 7

    52

    Department of Transport at which all the proposals were
    considered. There
    was not even a meeting at which all the expressions of
    interest were
    considered.

    The Department of Transport’s failure to methodically consider
    all options
    available to the Government was one of the worst aspects of
    the decision-
    making process that led to the National Executive Council
    decision in
    favour of IGnhill Kramer Pty Ltd in February 1992.

    It was very unfair of the Department of Transport to
    arbitrarily reject
    expressions of interest from other companies that had put
    considerable
    time and effort into responding to the June 1990
    advertisement.

    [7.51 SECRETARY FOR TRANSPORT CLAIMS THAT ALL OPTIONS WERE
    CONSIDERED

    When we put these allegations to the Secretary for Transport,
    he claimed
    that all options were considered:

    “As I have said, all options were considered, including the
    Barclay proposals.
    Mr Lohia Hitolo with his immense breath of experience and
    qualifications, did
    the assessment. Although he did not use the preferred
    approach, nevertheless,
    the approach he used has been used quite often by the

  • Page 61 of 397

  • Department of Works
    Design Branch. In addition, an NEC sub-committee reviewed
    his assessment
    This is not defective administration.”[EXHIBIT 254, page 4]

    [7.6] MR HITOLO CONCEDES THAT SOME COMPANIES WERE REJECTED ON
    THE BASIS OF THEIR EXPRESSION OF INTEREST

    In contrast to Mr Amini’s response, the former head of the
    Department of
    Transport Policy Secretariat, Mr Hitolo, conceded some
    companies had ngt
    been seriously considered. The reason, he said, was that their
    expressions

    Chapter 7

    53
    of interest did not state that they were willing to
    finance the project.
    [EXHIBIT 265, page 3, para 5]

    .7] FAILURE TO CONSIDER ALL OPTIONS
    In our view, Mr Hitolo’s response is testimony to the
    lack of effective
    communication which pervaded the whole project.

    As we pointed out in Chapter 5, the June 1990
    advertisement did rat state
    that the successful contractor had to itself finance the
    project. Nor had
    such a requirement been imposed by the National Executive
    Council.

    It was therefore unfair and wrong of the Department of
    Transport to
    summarily reject companies, simply because they had not
    indicated an
    ability to provide finance.

    In the opinion of the Ombudsman Commission, by failing to
    convene a
    meeting at which all expressions of interest could be
    formally considered,
    the Department of Transport failed to consider all of the

  • Page 62 of 397

  • options available
    to the Government. This was wrong and defective
    administration.

    * * * * * * * * * *

    Chapter 7

    54

    8. PROGRESS DURING SECOND HALF OF 1990

    [8.1] A PERIOD OF INACTION 1

    The period between the meeting of 31 July 1990 and the
    beginning of
    1991 was significant in three respects:

    1. There was little action taken to follow-up the
    expressions of
    interest.

    2. The geotechnical survey was initiated by the
    Department of
    Works, but not completed.

    3. A draft information paper was prepared for the
    National
    Executive Council, but not presented.

    LACK OF ACTION FOLLOWING INVITATION FOR EXPRESSIONS OF INTEREST

    [8.2] DEPARTMENT OF WORKS GUILTY OF DEFECTIVE ADMINISTRATION

    Other than the unsuccessful attempt by the Department of
    Transport in
    July 1990 to obtain firm proposals from some companies, no
    further action

  • Page 63 of 397

  • was taken by either the Department of Transport or the
    Department of
    Works during the second half of 1990 to follow-up the
    expressions of
    interest.

    Chapter 8

    55

    It is apparent that Mr Newberry, of the Department of Works,
    drafted a
    letter of acknowledgment around the end of October 1990, which
    was
    intended to be sent to all companies which had expressed
    interest.
    [EXHIBIT 50]. But this was not done. The letter was drafted
    very late and
    shows incompetence by the Department of Works. In a minute to
    the
    Secretary of the Department of Works, Mr Temu, on 11 January
    1991, Mr
    Newberry conceded “an acknowledgement should have been sent’,
    and
    added “… but I wished to advise them what was happening or
    going to
    happen. There was/is considerable confusion over the
    acceptability of a
    tunnel proposal.” [EXHIBIT 51, page 5, paragraph 3]

    In our view, this was not an acceptable reason for not sending
    the
    acknowledgments. A number of companies had invested time and
    expense in formulating their expressions of interest and the
    very least they deserved was an acknowledgment. Mr Newberry’s
    draft letter of 31
    deserved was an acknowledgment. Mr Newberry’s draft letter of
    31
    October 1990 correctly and succinctly stated the position as
    at that date
    and we can see no good reason for it not being dispatched,
    although it
    was very late.

    Since the Department of Works was at that time co-ordinating
    the
    expressions of interest, it should be held responsible for
    this bad
    administrative error.

    THE GEOTECHNICAL INVESTIGATION
    THE GEOTECHNICAL INVESTIGATION

  • Page 64 of 397

  • [8.3] PROS AND CONS OF TUNNEL AND CUT
    [8.3] PROS AND CONS OF TUNNEL AND CUT

    The most important outcome of the interdepartmental meeting of
    31 July
    1990 had been the decision to conduct a comprehensive
    geotechnical
    investigation of the Burns Peak Saddle.

    Chapter 8

    56

    The rationale for this decision was explained in a minute
    from Mr Newberry
    to the Secretary for Works on 11 January 1991:

    ‘Confusion was increased by the letter/fax sent by DOT to
    some of the
    registrants on 20 July. The DOW/DOT meeting on 31 July did
    clarify some of
    the issues.
    Since that time Works has proceeded on the basis that no
    requests can be made
    for detailed proposals until the additional geotechnical
    investigation provides
    data sufficient to allow a developer to make a reasoned
    choice between a tunnel
    and a cut.

    The concept of the project if a tunnel is chosen is
    entirely different from that
    if a cut is to be constructed. A tunnel provides very
    little material for filling
    or for use in other parts of the construction. If any
    reclamation is to be carried
    out it would have to be from imported materiaL The road
    pavement and fill
    materials would also have to be imported. The tunnel also
    has a continuing
    high operation and maintenance cost. The tunnel option
    also carries a higher
    risk of damage, closure or operational loss as a result of
    an accident or
    vandalism particularly with only a single two lane tunnel
    for the initial period.
    The presently proposed tunnel cross section may be
    inadequate for safe use by

  • Page 65 of 397

  • trucks carrying containers. Trucks with dangerous
    materials would not be
    allowed to use the tunnel but would have to use an
    alternate route.

    It has been claimed that the tunnel would allow a grade of
    only 3% for the
    road connection. This is possible but would require a
    tunnel of much greater
    length and cost than that presently proposed. The present
    proposal has grades
    of over 8% on the western approach road.

    The cut provides considerable, possibly excessive,
    material for use in the
    construction of the project and connecting roads
    embankments and pavements
    and also for port and other reclamation. The cut would
    provide an immediate
    four lane road connection. The provision of four-lanes
    reduces the risk of
    accident, damage and operational loss. However the risk of
    loss from collapse
    of part of the cut wall still exists with the level of
    risk increasing as the cut
    slopes are steepened and the volume and cost of the cut
    decrease. There is
    however increased opportunity for early financial return
    from port and harbour
    reclamation works which may reduce the financial risks in
    the project.

    The developer has a difficult choice to make between the
    tunnel and cut options
    and the government also has to make an assessment of the
    risks it is prepared
    to take and the charges (eg. toll) it is prepared to allow
    the developer to make
    for provision of facilities.’ (Emphasis added) [EXHIBIT
    511

    [8.4] WHY WAS A FURTHER GEOTECHNICAL INVESTIGATION NECESSARY?

    A preliminary study in 1977 by consultants Dames and Moore
    had found
    it was geologically feasible to build a tunnel, but the
    Department of Works

  • Page 66 of 397

  • Chapter 8

    57

    obviously felt that a more detailed investigation should be
    carried out. This
    point was explained in a press statement drafted by Mr
    Newberry on 18
    January 1991 (which apparently was not released):

    The last time a detailed investigation was made of the
    underground conditions
    along the Spring Garden Road Link from Hohola to Konedobu
    was in 1977.
    Then holes were drilled in the rock and samples of the
    rock taken for
    examination. These holes were generally along the line of
    a proposed deep cut
    It was then decided that the sides of the cut may fall
    down unless flatter side slopes were used so a tunnel was
    proposed. However tunnels are expensive as
    slopes were used so a tunnel was proposed. However tunnels
    are expensive as
    the rock in the tunnel roof must be supported so that it
    does not fall into the tunnel Ventilation also becomes
    important as air can only enter and leave at
    tunnel Ventilation also becomes important as air can only
    enter and leave at
    the ends of the tunnel and fans may be necessary.

    Since 1977 there have been other geological investigations
    around Port Moresby
    and it is now believed that the underground rock
    conditions may be more
    complicated than was thought in 1977. It is now considered
    too risky to decide
    on building either a tunnel or a rock cut without further
    investigation of the
    underground conditions. This is particularly important
    since the estimated cost of the rock cut for a 4-lane mad
    is about 1(20 million, 2-lane tunnel would cost about 1(20
    million and a 4-lane tunnel would cost about IC40 million with about
    another KS million for improvements to Champion Parade, Wards Road,
    Waigani
    of the rock cut for a 4-lane mad is about 1(20 million, 2-
    lane tunnel would cost about 1(20 million and a 4-lane
    tunnel would cost about IC40 million with about another KS
    million for improvements to Champion Parade, Wards Road, Waigani
    about 1(20 million and a 4-lane tunnel would cost about
    IC40 million with about another KS million for
    improvements to Champion Parade, Wards Road, Waigani
    another KS million for improvements to Champion Parade,

  • Page 67 of 397

  • Wards Road, Waigani
    Drive and the existing sections of Spring Garden
    Road.’ [EXHIBIT 52A]

    [8.5] CO-ORDIANATION OF THE GEOTECHNICAL INVESTIGATION
    [8.5] CO-ORDIANATION OF THE GEOTECHNICAL INVESTIGATION

    The geotechnical investigation was co-ordinated by Mr
    Newberry and also
    involved the Senior Engineering Geologist from the Geological
    Survey of
    PNG in the Department of Minerals and Energy. It was decided
    the project
    would be offered to a private consultant, so the first step
    was to formulate
    terms of reference for the project. This was done during
    August 1990 by
    Mr Newberry. [EXHIBIT 51, page 4]

    [8.6] THE PROCEDURE USED TO SELECT THE CONTRACTOR
    [8.6] THE PROCEDURE USED TO SELECT THE CONTRACTOR

    Terms of Reference

    The terms of reference was sent to the Department of
    Transport for
    ratification during August 1990. The Secretary for Transport
    replied that

    Chapter 8

    58
    his Department agreed with the course of action proposed by the
    Department of Works.
    [EXHIBIT 42A]

    Invitations, accompanied by a document entitled “Sub Surface
    Exploration
    and Assessment for Spring Garden Road Link between Hohola and
    Konedobu Via Burns Peak Saddle: Terms of Reference for Consultants
    Brief’, were sent in September 1990 to the following companies:

  • Page 68 of 397

  • Engineering Geology Ltd, of Lae.

    Coffey Partners International Pty Ltd, of Australia.

    Cardno & Davies Pty Ltd, of Port Moresby.

    Kinhill Kramer Pty Ltd, of Port Moresby

    Maunsell Consultants PNG Pty Ltd, of Port Moresby.

    Ove Arup & Partners Pacific Pty Ltd, of Port Moresby.

    Snowy Mountains Engineering Corporation, of Australia.

    Hollingsworth, Dames & Moore (PNG) Pty Ltd, of Port
    Moresby. [EXHIBITS 44A, 44B1

    Failure to publicly invite tenders

    We note that there was no public advertisement inviting tenders for
    the
    geotechnical project. Nor was a “certificate of inexpediency” –
    which could
    have authorised the selective tendering procedure – issued under
    Section

    Chapter 8

    59
    40(3)(b) of the Public Finances (Management) Act. This meant that,
    though the matter was ultimately referred to a Supply and Tenders
    Board,
    there had been a breach of the Public Finances (Management) Act.

    Section 40(1) of the Act requires that tenders be publicly invited
    for the
    supply of works and services expected to cost more than the
    prescribed
    amount (which at the relevant time was K5,000.00). The public tender
    procedures of the Public Finances (Management) Act are discussed in
    detail in Chapter 35 of this report.

    We are satisfied that none of the exceptions to the general rule
    imposed
    by Section 40(1) applied in the case of the geotechnical project.

    The Department of Works therefore acted wrongly, by engaging in the
    process of selective tendering without obtaining a certificate of
    inexpediency in accordance with the Public Finances (Management)
    Act.

    Evaluation of proposals

  • Page 69 of 397

  • The closing date for submission of proposals was 25 October 1990
    and,
    according to Mr Newberry’s minute to the Secretary for Works of
    January
    1991, this was when the task of evaluating the proposals began.
    [EXHIBIT
    51, page 4] However, because of ambiguity in the wording of the
    terms
    of reference, due to the incompetence of the Department of Works, it
    was
    necessary to obtain supplementary proposals from a number of
    respondents. This delayed the selection process by at least a month.
    [EXHIBITS 48A, 50A, 50B]

    Submission to Design Priorities Committee and Tender Board

    On 5 December 1990, Mr Newberry presented a detailed submission to
    the Design Priorities Committee and Tender Board, recommending the

    Chapter 8

    60
    contract for the geotechnical investigation be awarded to
    Coffey Partners
    International of Sydney, Australia, at a cost of K184,000.00.
    [EXHIBIT 500].
    The recommendation was endorsed by the Board at its meeting on
    11
    December 1990. [EXHIBIT 50F] Coffey Partners International was
    subsequently advised it had won the contract and arrangements
    were
    made to commence the seismic field work during January 1991
    [EXHIBITS
    50G, 51A]

    [8-7] GEOTECHNICAL INVESTIGATION DURING JANUARY – MAY 1991
    The investigation took approximately four months to complete.
    A “Burns
    Peak Geotechnical Steering Committee” was established to
    monitor the
    project and progress reports were provided during the course
    of the
    investigation [EXHIBITS 55A, 64A, 66A, 79A, 80A, 84A]. The
    final report
    was presented to the Department of Works at the end of May
    1991.
    [EXHIBITS 87A, 87B]

    It was recommended that “the deep open cut option through
    Burns Peak
    Saddle will involve greater financial uncertainty than the

  • Page 70 of 397

  • tunnelling option”.
    [EXHIBIT 87B, page 29, paragraph 8]

    The time it took to organise the geotechnical investigation
    was a cause of
    frustration to some people, including the Minister for
    Transport, Mr Temo.
    On the EM TV news bulletin of 8 January 1991 he was reported
    to be
    highly critical of the Department of Works and apparently
    blamed the
    Department for delaying the project. This prompted a detailed
    response
    from the Secretary for Works, Mr Temu, which was forwarded to
    the
    Secretary for Transport in a letter dated 11 January 1991
    [EXHIBIT 52]

    Chapter 8

    61

    .8] THE GEOTECHNICAL INVESTIGATION CAUSED A DELAY OF NINE
    MONTHS

    In retrospect, it can be seen that the decision to undertake the
    geotechnical investigation delayed the planned commencement of
    the
    project by about nine months. After the interdepartmental
    meeting on 31
    July 1990:

    It took five weeks for the terms of reference for the
    consultancy brief to be finalised and invitations for
    proposals
    to be dispatched.

    The consultants were given six weeks to lodge their
    proposals.

    Six weeks were spent on clarifying and evaluating the
    proposals.

    The recommendation favouring Coffey Partners International
    was before the Design Priorities Committee and Tenders
    Board for about a week before a decision was made and
    announced.

    It took Coffey Partners International about five weeks to
    mobilise its equipment and personnel and commence the

  • Page 71 of 397

  • seismic field work.

    The actual investigation, including laboratory testing of
    core
    samples, took four months to complete (from late January
    1991 to late May 1991).

    Chapter 8

    11

    62

    [8.9] FINDINGS IN RELATION TO THE GEOTECHNICAL INVESTIGATION

    1. The need for the investigation

    We do not question the need for the investigation.
    Irrespective of whether
    a tunnel or a cut is built through Burns Peak, safety
    considerations
    obviously must be paramount.

    2. IMaltinSIII .cgAngthatthQinvgggigatcKLI8MINKMEM:Y.
    investigation
    However, we are critical of the Department of Works for the
    delay in
    making the decision that a geotechnical investigation was
    necessary.

    The decision to go ahead with the Spring Garden Road project
    was
    conveyed to the Department of Works in late January 1990. The
    Department of Works, amongst others, was directed to
    “formulate detailed
    plans for the construction of the Burns Peak Road”. [EXHIBIT
    61■] We
    have already noted the impreciseness of that decision and
    criticised the
    National Executive Council for not being more explicit in its
    requirements.
    However that does not excuse the Department of Works for its
    failure to
    expeditiously implement the decision.

    Nor is it an excuse to say that the Department of Works was
    waiting for
    an indication from the Department of Transport as to the route
    of the road.
    The geotechnical investigation was a matter that was clearly
    within the
    jurisdiction of the Department of Works.

  • Page 72 of 397

  • When we raised these matters in our preliminary report, the
    Secretary for
    Works responded in the following terms:

    Chapter 8

    63

    ‘What caused the delay in deciding to perform the Geotechnical
    Investigation?
    Initially it was not projected to perform a further Geotechnical
    Investigation.
    However, Department of Transport wanted to jump in and build the
    project
    without any significant planning, while Works was pushing for as
    much
    planning and advise from specialists as possible. Several times
    Mr Newberry
    (then Principal Engineer Roads) met with the Geological Survey
    Section of
    DME to discuss the project. Of specific concern was the “ICold
    Fault’ which
    was known to run right through the ‘saddle’. It appears that the
    requirement
    for further investigation was not seriously considered until
    advised accordingly
    by a Senior Engineering Geologist at an inter-departmental
    working group on
    19 July 1990 [see Exhibit 51]—This seems to be the conception of
    the requirement
    for further geotechnical investigation to give a degree of
    confidence to any
    decision regarding ‘Open Cut” or ‘Tunnel”‘ [OCKIBIT 263, page 1]

    Having considered this response, the Ombudsman Commission retains
    the
    view that the Department of Works should have, by itself, raised the
    issue
    of the need for a geotechnical investigation sooner than it did,
    since it is
    the appropriate Department responsible for such matters in the
    interests
    of the State.

    The excavation of the Burns Peak Saddle was clearly going to be a
    complex engineering task. It was up to the Department of Works to

  • Page 73 of 397

  • find
    out whether any further geotechnical investigation was necessary as
    soon
    as possible and take follow-up action. The need for this should have
    been
    raised at least as early as the interdepartmental meeting on 22 May
    1990
    (see Chapter 4).
    N

    The Ombudsman Commission considers that the six month delay in
    making the decision to undertake the geotechnical investigation was
    unjustifiable. Furthermore, in the absence of a certificate of
    inexpediency,
    invitations to submit tenders for this work should have been
    publicly
    advertised – not selectively issued.

    Once the decision was made, on 31 July 1990, to undertake the
    investigation, there were some further delays but – with the
    exception of
    the failure to publicly invite tenders – the Department of Works
    handled the
    matter well from then on.

    Chapter 8

    64

    We note that various proposals were carefully and
    methodically evaluated.
    The proposal made by Coffey Partners International was
    detailed and well
    presented [EXHIBIT 48A]. There was a sharp contrast between
    the quality
    of that document and some of the atrocious documents [eg
    EXHIBIT 115]
    that were later to be paraded as serious proposals for
    construction of the
    freeway.

    Indeed, the professional way in which the geotechnical
    investigation
    proposals were evaluated was in stark contrast to the events
    which later
    led to the execution of the contract for the design, finance
    and
    construction of the Poreporena Freeway.

  • Page 74 of 397

  • THE MINISTER FOR TRANSPORTS DRAFT POLICY SUBMISSION OF AUGUST 1990

    [8.10] DECISION TO ADVISE NATIONAL EXECUTIVE COUNCIL OF PROGRESS

    Besides the decision to undertake the geotechnical
    investigation, the other
    important outcome of the interdepartmental meeting of 31 July
    1990 was
    the decision to advise the National Executive Council of
    progress on the
    project, in particular to clarify the fact that it would be
    impossible to finish
    the Burns Peak link in time for the South Pacific Games in
    September
    1991. To this end, a document headed “Policy Submission For
    Members
    of the National Executive Council” was drafted within the
    Department of
    Transport in August 1990. [EXHIBIT 36]

    Chapter 8

    65
    1

    8.11] CONTENT OF THE DRAFT POLICY SUBMISSION

    This document gave an update of the status of the project
    as at August

    1990, and referred to the decision to undertake a further
    geotechnical

    investigation of the Burns Peak Saddle. The bulk of the
    document,

    however, was devoted to explaining the need for public
    participation in the

    planning process and the preparation of an environmental
    impact

  • Page 75 of 397

  • statement.

    The document concluded as follows:

    It is recommended that the Spring Garden Road
    project scope includes
    the commencement point (Cuthbertson and
    Stanley Esp. Junction) at the
    Port Moresby main overseas wharf and
    termination at the Jackson’s
    AirPort-

    2. It is recommended that an Environmental
    Impact Statement be made
    of the whole route using the N.S.W. manuals
    including soil erosion
    guide for the assessment.

    3. It is recommended that the upgrading to the
    Waigani Road and any
    other spot improvements along the main
    arterial network be done as
    a matter of urgency in preparation for the
    South Pacific Games in 1991.

    4. It is recommended that the savings be
    immediately identified in the
    current capital works and studies votes in
    order to implement these
    projects.

    5. It is recommended that the Council note that
    advice of the experts for
    delay in the opening of the Burns Peak link
    and approve the new scope
    to be implemented in three stages.

    6. It is recommended that this project be
    developed through involvement
    of the private sector and the landowners
    using toll for financing.”

  • Page 76 of 397

  • .12] WIDE CIRCULATION OF THE DRAFT POLICY SUBMISSION

    This document was widely circulated and comments were
    received from

    a number of Government departments. [EXHIBITS 39, 40, 41,
    42, 43, 44,

    48]

    Chapter 8

    66

    Some departments expressed serious reservations about its
    recommendations. The Secretary for Finance, Mr Morea Vele,
    for example,
    was particularly concerned about the economic viability and
    the security
    risk of the tunnel/toll road proposal. [EXHIBIT 42]

    The Secretary of the Department of Environment and
    Conservation, Mr
    Barney Rongap, pointed out that Papua New Guinea had its own
    environmental impact legislation – the Environmental Planning
    Act (Chapter
    No. 370) – and therefore it was inappropriate to rely on the
    New South
    Wales model for this purpose.

    The draft policy submission was also sharply criticised
    within the
    Department of Transport itself. [EXHIBITS 46, 47] The First
    Assistant
    Secretary (Land Transport Division), Mr M Ume, went so far as
    to say:

    ‘It is very difficult to follow what the Submission is
    about and perhaps if it is
    on Burns Peak then more discussion should be on Burns Peak
    Road itself.*

  • Page 77 of 397

  • [8.13] RE-DRAFTING OF THE JULY 1990 DOCUMENT

    In January 1991, after receiving the views and comments from
    various
    departments, the Department of Transport redrafted the
    National Executive
    Council submission. This time, the document was entitled
    “Information
    Paper For Members of the NEC: Burns Peak Link of Spring
    Garden Road”.
    [EXHIBIT 54]

    This document also emphasised the need for an environmental
    impact
    statement. But it was different to the earlier document in a
    significant
    respect: whereas the July 1990 document contained very little
    discussion
    of the method of financing the project, the January 1991
    document was
    dogmatic in its assertion that “this project will be
    constructed under Build,
    Operate and Take-over (BOT) system”. [EXHIBIT 54, page 5,
    para 2.12]

    Chapter 8

    67

    [8.14] POUCY SUBMISSION AND INFORMATION PAPER NOT PRESENTED TO
    NATIONAL EXECUTIVE COUNCIL

    The Ombudsman Commission was surprised to discover that,
    despite the
    time and effort put into the drafting and redrafting of the
    National Executive
    Council submission and the wide circulation of the first
    draft, neither the
    first nor the second draft submission was actually filed with
    the National
    Executive Council.

    That is, despite the fact that draft submissions had been
    circulated for
    more than six months, the National Executive Council was not
    fully
    informed – as it should have been – of progress on the
    project and the
    reasons for delay in its commencement.

  • Page 78 of 397

  • We note that the Department of Transport complied with the
    normal
    administrative requirement to give status reports to the
    Secretary of the
    Department of Prime Minister and National Executive Council.
    [EXHIBITS 6C, 25A, 63A, 77A, 87C & 124A]

    However, the Ombudsman Commission considers that, because of
    the
    magnitude of the project, the Minister for Transport had an
    administrative
    obligation to ensure the National Executive Council was fully
    and formally
    advised of the important developments that were taking place.
    In our view,
    this duty was not discharged.

    [8.15] MINISTER FOR TRANSPORT FAILED TO PROPERLY ADVISE NATIONAL,
    EXECUTIVE COUNCIL OF PROGRESS

    There were some aspects of the August 1990 document which
    should
    have been brought to the attention of the National Executive
    Council as a

    Chapter 8

    68
    matter of priority, particularly the recommendation that the
    scope of the
    project be expanded. But this important policy matter was
    very poorly
    documented and was eventually put before the National
    Executive Council,
    in February 1992, without explanation or justification. The
    scope of the
    project, being essentially important, should have been
    explained and
    defined in detail for the benefit of the members of the
    National Executive
    Council.

    The August 1990 document was widely circulated for views and
    comments.
    The failure to present it reveals a lack of regard for proper
    administrative
    procedures by the Minister for Transport, Mr Temo. He did not
    appreciate
    the importance of keeping his colleagues, at the National
    Executive Council
    level, fully informed of progress of the project and
    explaining significant

  • Page 79 of 397

  • changes in policy.

    [8.16] THE NEED TO KEEP THE NATIONAL EXECUT1VE_COUNCIL FULLY
    INFORMED

    There is a lesson to be learned here by all departments and
    ministries: if
    delays are experienced in the implementation of Government
    policies, the
    National Executive Council must be advised of the delay and
    the reasons
    for it.

    Often there are justifiable reasons for projects not being
    implemented as
    soon as originally planned. But if the National Executive
    Council is not
    advised why there has been a delay, it will naturally be
    assumed that there
    are no good reasons for further delay. The National Executive
    Council will
    become frustrated and impatient and the environment will be
    ripe for the
    making of rash and ill-considered decisions in the end.

    Chapter 8

    69

    All of these things happened in the case of the Spring Garden
    Road/Poreporena Freeway project.

    3.17] SCOPE OF THE PROJECT

    The first recommendation of the August 1990 “Policy
    Submission” was that
    the scope of the project should be expanded, so as to create a
    direct link,
    via Spring Garden Road, between downtown Port Moresby and
    Jacksons
    Airport. [EXHIBIT 36, page 5, para 11.1]

    However, there was no discussion or analysis – in fact, hardly
    a mention –
    of this crucial policy decision in the text of the Submission.

    As we emphasised in Chapter 5, the Ombudsman Commission found
    ft
    extraordinary that in the course of this investigation we were
    not able to

  • Page 80 of 397

  • pinpoint when the decision was made to expand the scope of the
    project,
    from the original proposal to link the two unconnected
    sections of Spring
    Garden Road between Konedobu and Hohola.

    The way in which this recommendation was added to the document

    giving the appearance that it was an afterthought – simply
    adds to the
    mystery surrounding that decision.

    18] THE BUILD-OPERATE-TRANSFER CONCEPT

    Another feature of the January 1991 draft “Information Paper’
    is that it is
    the first Department of Transport document which referred to
    the Build-
    Operate-Transfer method of financing the project.

    Chapter 8

    70

    However, just as the August 1990 document failed to explain
    or discuss
    the pros and cons of expanding the scope of the project, the
    January
    1991 document failed to weigh the pros and cons of different
    methods of
    financing the project. [EXHIBIT 54, page 5, paragraphs 2.12 –
    2.13]

    These failures clearly indicate lack of consultation
    resulting in the poor
    drafting of the documents for the National Executive Council.

    [8.19] DEFICIENT POUCY MAKING BY THE DEPARTMENT AND MINISTRY OF
    TRANSPORT

    The fact that both the August 1990 Policy Submission and the
    1991
    Information Paper documents were only in draft form and never
    actually
    filed with the National Executive Council means that the
    Ombudsman
    Commission cannot be overly critical of their contents.

    But, in the absence of evidence to the contrary, these
    documents support

  • Page 81 of 397

  • our conclusion that important policy decisions such as the
    length of the
    freeway and the method of financing were being made by the
    Department
    and Ministry of Transport without proper analysis or
    documentation.

    SUMMARY OF DEVELOPMENTS DURING 1990

    [8.20] PROGRESS DURING 1990

    Progress on the project during 1990 can be summarised as
    follows:

    Chapter 8

    71

    In late January 1990 the National Executive Council directed
    the Department of Transport, the Department of Works and
    the Department of Finance & Planning to formulate detailed
    plans for the project.

    Nothing was done until 22 May 1990, when the Minister for
    Transport chaired an interdepartmental meeting and directed
    that design of the project be finalised within six months and
    expressions of interest be publicly invited.

    An advertisement inviting expressions of interest was
    published in June 1990 by the Department of Works.

    Around 17 – 20 July 1990, the Department of Transport invited
    a select group of companies to lodge proposals for the
    project, but this exercise was incompetently handled, hence
    there was little response.

    On 31 July 1990, it was decided that the Department of
    Works would arrange a further geotechnical investigation of
    the Burns Peak Saddle.

    A draft policy submission, intended to provide an update on
    progress, was circulated for comment during August and
    September 1990. The submission was subsequently revised
    but never presented to the National Executive Council.

    The first version of the submission proposed that the scope
    of the project be considerably expanded, but there was no
    documented discussion or analysis of this proposal.

  • Page 82 of 397

  • Chapter 8

    72

    On 11 December 1990, the contract for the
    geotechnical
    investigation was awarded to Coffey
    Partners International Pty
    Ltd of Australia after invitations were
    sent to selected
    companies by the Department of Works.

    [8.21] STATUS OF THE SPRING GARDEN ROAD PROJECT AT THE END OF
    1990

    By the end of 1990:

    The National Executive Council had not
    been fully and
    formally advised of the delay in
    commencement of the project
    or the apparent proposal to expand its
    scope.

    The geotechnical investigation had not
    begun, so no decision
    had been made on the tunnel/cut option.

    No decision had been made on the exact
    route or length of
    the road.

    No decision had been made on the method
    of financing the
    project.

    * * * * * * * * * *

    Chapter 8

    73

    9. PREPARATION OF SHORTLIST: FEBRUARY 1991

  • Page 83 of 397

  • 9. PREPARATION OF SHORTLIST: FEBRUARY 1991

    [9.1] FIFTEEN GROUPS HAD EXPRESSED INTEREST
    [9.1] FIFTEEN GROUPS HAD EXPRESSED INTEREST

    The advertisements in June 1990 inviting expressions of
    interest in the
    “Burns Peak/Spring Garden Road Link” had attracted fifteen
    interested
    parties. In July 1990, the Department of Transport made an
    abortive
    attempt to get some of them to submit firm proposals.

    It was later decided that the Department of Works would
    organise a
    detailed geotechnical investigation of Burns Peak, so a firm
    decision could
    be made on the tunnel/cut option. This investigation began in
    January
    1991 and continued until May 1991. While that investigation
    was still in
    progress, a shortlist of prospective developers was prepared.

    In this chapter we record our findings as to the preparation
    of the shortlist.
    .

    MINISTER FOR TRANSPORT PREPARES SHORTLIST
    MINISTER FOR TRANSPORT PREPARES SHORTLIST

    [9.2] WHEN WAS THE SHORTLIST PREPARED AND WHO PREPARED IT?
    [9.2] WHEN WAS THE SHORTLIST PREPARED AND WHO PREPARED IT?

    The Ombudsman Commission has concluded that the shortlist was
    prepared in February 1991 by the Minister for Transport, Mr
    Anthony
    Temo.

    Chapter 9

    74

    On 27 February 1991, Mr Temo wrote to the Secretary of the
    Department
    of Transport in the following terms:

  • Page 84 of 397

  • “My Dear Secretary

    A total of 15 (Fifteen) companies have shown or
    registered expressions
    of interest to design and construct the Burns Peak
    Road..

    This is under Turnkey arrangement meaning financing
    will be done
    by them.

    The following Companies have been selected for short
    list-

    1. Outlet Year Limited

    2. Sietco

    3. Barclay Bros and Maunsell Joint

    4. Curtain Bros

    5. L.K.N. Construction

    6. Kumagai Gumi

    7. Sabina Group Consortium

    Please inform them respectively by way of fax and
    organise a bid walk
    in 3 weeks from 27/2/91.” [EXHIBIT 631

    [9.3] A LATE ADDITION TO THE SHORTLIST

    On 28 March 1991, the Minister for Transport wrote another
    letter to the
    Secretary for Transport:

    ‘My dear Secretary

    I refer to my letter dated 27 February, 1991 in which I
    short listed a number of
    companies for the Burns Peak Project.

  • Page 85 of 397

  • Chapter 9

    75

    I now wish to include the following on the short list-

    Tasman Pacific International

    Please inform the Company accordingly” [F3CIBB1T 69]

    [9.4] THE MINISTER PREPARED THE SHORTLIST WITHOUT ADVICE OR
    CONSULTATION

    In his response to our preliminary report Mr Temo
    emphatically denied
    that he had prepared the shortlist. He said the letter to the
    Secretary for
    Transport of 27 February 1991 was simply a list of companies
    which had
    sent written expressions of interest to his office. He said
    his staff in the
    Ministry did not understand the term “shortlist”:

    ‘The various expressions of interest in the Burns Peak
    Road project by different
    companies was sent by way of letter or verbal to 3
    different place:

    (a) Department of Works
    (b) Department of Transport
    (c) Chairman of Ministerial Committee and Minister for
    Transport.

    Some companies about 15 contacted my office. About half of
    them verbally and
    the other half by way of letter or fax.

    It was the Department of Transport in consultation with
    Department of Works
    that prepared the short list not me or my office.

  • Page 86 of 397

  • Department of Works and the Department of Transport did
    their short list and
    Chairman of the Ministerial Committee did their own short
    list”
    [EXHIBIT 257, page 1]

    With due respect to Mr Temo, the Ombudsman Commission cannot
    accept
    what he says about the preparation of the shortlist. The
    terms of his letter
    to the Secretary for Transport on 27 February 1991 were quite
    clear: he
    advised that seven companies “have been selected for
    shortlist”. There is
    no evidence the companies on the Minister’s list had written
    directly to him,
    rather than the Department of Transport.

    Chapter 9

    76

    The Ombudsman Commission is satisfied that neither the
    Department of
    Transport nor the Department of Works had any involvement in
    the
    preparation of the shortlist. The Minister prepared the
    shortlist without
    consulting either Department.

    [a5] MINISTERS SHOULD NOT BE INVOLVED IN IMPLEMENTATION MATTERS

    The Minister for Transport’s preparation of the shortlist in
    February 1991
    was defective administration in a number of respects.

    First, there was no need for a shortlist to be prepared. The
    interested
    parties had only submitted expressions of interest in the
    project and had
    not been given the opportunity to submit firm proposals, so
    preparation
    of a shortlist was premature.

    Even if it had been an appropriate time to prepare a
    shortlist, this job
    should have been done by officers of the Department of

  • Page 87 of 397

  • Transport and/or
    the Department of Works. It is not the function of a Minister
    to prepare a
    shortlist for a public works project.

    Too often in Papua New Guinea, Ministers make unilateral
    decisions without
    calling on their qualified and experienced Departmental
    officers for advice.
    This is very bad. If Ministers cut themselves off from their
    Departments –
    by always giving directions, rather than asking for advice –
    it is inevitable
    they won’t always have the best information before them on
    which to make
    decisions.

    It was very naive of the Minister for Transport to believe he
    had the
    necessary technical knowledge to prepare a shortlist of
    developers without
    the advice of his Department.

    Chapter 9

    77 O

    Whenever a Minister makes an important decision in this way,
    it inevitably
    leads to suspicion about his motives. People start to ask
    questions. Why
    were some companies selected for the shortlist and others left
    out? Did
    some companies make the shortlist because the people running
    them
    were friends or wantoks of the Minister? Was anyone bribed? Et
    cetera.

    The only way the People can have confidence in their
    Government
    departments and Ministers is if normal, established procedures
    are
    followed.

    The decision-making process must be above suspicion.

    [9.6] SOME COMPANIES WERE SHORTLISTED WITHOUT JUSTIFICATION

    The Ombudsman Commission makes the following findings in
    relation to
    the eight groups shortlisted by the Minister for Transport:

  • Page 88 of 397

  • 1. Outlet Year Ltd
    This Hong Kong-based company had not lodged an expression of
    interest.
    It first became interested in the project in February 1991,
    when the Minister
    for Transport travelled to Taiwan and Hong Kong and was
    entertained by
    the company’s officers and its associates (see Chapter 12).

    As a result of the Minister’s visit, the company’s Managing
    Director, Mr
    Leung Keung, wrote a letter dated 12 February 1991 to Prime
    Minister
    Namaliu. Outlet Year Ltd offered to “design and build Southern
    Highlands
    Kikori Road and Burns Peak Road in Port Moresby’ and “invest
    up to US
    dollars 5 billion in Papua New Guinea.” [EXHIBIT 57]

    Chapter 9

    78

    On 13 February 1991, Outlet Year Ltd wrote similar letters addressed
    to:
    “Hon. Anthony Temo, Minister for Transport or Hon. Ted Diro, Deputy
    Prime Minister, Acting Transport Minister”. [EXHIBITS 59 & 60]

    Soon after that, on 19 February 1992, Mr Diro wrote to the Secretary
    for
    Transport, advising that he had received advice from Mr Temo that
    Outlet
    Year Ltd be “included in the pre-qualification for all tenders in
    Erave-Kikori
    and Burns Peak roads in Port Moresby”. Mr Diro directed the
    Secretary
    to take “necessary actions” in relation to the “pre-qualification”
    of Outlet
    Year Ltd. [EXHIBIT 61]

    The Ombudsman Commission was to discover in the course of this
    investigation that the Minister for Transport’s trip to Hong Kong,
    where he
    held discussions with Outlet Year Ltd, was paid for by associates of
    that
    company. This is wrong.

    The shortlisting of this particular company was therefore improper.

    It should also be noted that the Deputy Prime Minister does not have
    power to give directions to a Departmental Head, unless such a power

  • Page 89 of 397

  • is
    expressly given by an Act of the Parliament or some other law. The
    office
    of Deputy Prime Minister is created by Section 2 of the Prime
    Minister Act
    (Chapter No. 27 of the Revised Laws). However it does not carry with
    it
    any greater power of direction and control than those held by other
    Ministers. The purpose of the office of Deputy Prime Minister is to
    enable
    a Minister to step into the shoes of the Prime Minister whenever the
    Prime
    Minister is unable to perform the duties of his office or any of the
    other
    situations in Section 143 of the Constitution exist.

    Chapter 9

    79

    That is, the person holding the office of Deputy Prime Minister
    is not the
    “second-in-charge” of the Ministry and does not have any powers
    of
    direction and control by virtue of holding that office. His
    powers and
    responsibilities are at all times constrained in accordance with
    Section 148
    of the Constitution (see Chapter 39).

    2. Sietco
    The company known as Sietco (PNG) Pty Ltd is a PNG off-shoot of a
    government agency in the People’s Republic of China, known as the
    “China Sichuan Corporation for International Techno-Economic Co-
    operation”. Neither of these groups had lodged an expression of
    interest.

    Sietco is interested in road construction projects in the
    Southern Highlands
    Province and, during 1991, the company had a very close business
    connection with the Minister for Transport, Mr Temo. In fact,
    just a few
    weeks before directing that Sietco be included on the shortlist,
    the
    Minister’s family company, Outskirts Construction Pty Ltd, had
    entered into
    a “partnership agreement” with Sietco, whereby the two companies
    agreed
    to jointly invest in Papua New Guinea and set up a “partnership
    enterprise”

  • Page 90 of 397

  • to undertake “construction and maintenance of roads and some
    other civil
    engineering projects as contractor or sub – contractor’. This
    agreement
    was signed by the Minister, on behalf of Outskirts Construction
    Pty Ltd.
    [EXHIBIT 55B]

    The closeness of the relationship between the Minister and Sietco
    is further
    demonstrated by the fact that only five days before including the
    company
    on the shortlist, the Minister had visited China and signed an
    agreement
    with Sietco’s Chinese parent company, which was intended to
    clarify the
    partnership contract signed just a couple of weeks before in
    Papua New
    Guinea. [EXHIBITS 62k 62B]

    Chapter 9

    80

    When the Minister was interviewed by the Ombudsman Commission, he
    was asked whether he thought it improper a company he was so
    closely
    involved with, was asked by him to lodge a proposal for
    construction of
    the freeway. He did not deny his close relationship with Sietco
    but stressed
    that, as soon as the company had expressed an interest, he had
    instructed
    that it not be further considered because it might not look
    right.

    But, if that is the case, why did the Minister put the company on
    the
    shortlist?

    The Ombudsman Commission cannot accept Mr Temo’s explanation and
    is forced to conclude that his decision to shortlist this company
    was
    improper.

    3. Barclay Bros and Maunsell Joint
    Both of these groups had lodged expressions of interest -but not
    as joint
    venturers. Maunsell Consultants were linked with Barclay Bros in
    1988
    (see Chapter 2), but had actually lodged a joint expression of
    interest with

  • Page 91 of 397

  • Baulderstone Hornibrook in response to the June 1990
    advertisement.

    The Minister’s decision to link Maunsell with Barclay Brothers
    therefore did
    not make sense.

    4. Curtain Bros
    This company – though it ultimately became closely involved with
    the
    consortium selected to undertake the project – had submitted the
    expression of interest with the least amount of detail.

    Chapter 9

    81 ■

    While it is an established construction company, with experience
    in Papua
    New Guinea, we query its inclusion at the expense of other
    companies
    which had expressed their interest in the project in a more
    active and
    detailed manner.

    5. LKN Construction
    This Singapore-based company, represented by LKN (PNG) Pty Ltd,
    had
    lodged a two page expression of interest in July 1990.

    6. Kumagai Gumi
    This Japanese company had lodged a joint expression of interest
    with
    Kinhill Kramer Pty Ltd in 1990. The company had shown interest
    in the
    project for some time.

    7. Sabina Group Consortium
    Peter Chen and Partners, of Brisbane Australia, had lodged an
    expression
    of interest on behalf of the Sabina Group Consortium, in July
    1990. A
    brochure, giving details of the consortium’s previous
    activities, was
    enclosed, but otherwise no details concerning the Spring Garden
    Road
    project were provided.

    8.. TagitaL.PagifiCalea

  • Page 92 of 397

  • This PNG company is essentially a K2.00 shelf company, which
    operates
    a small consultancy business in Port Moresby. It was added to
    the
    shortlist one month late. At the relevant time, its 100%
    shareholder was
    Mr Sam Pepena.

    The Ombudsman Commission also became aware that the Deputy Clerk
    of the National Parliament, Mr Ano Pala, had a close association
    with the
    company.

    Chapter 9

    82

    Tasman Pacific International has few assets and no employees.
    It has no
    experience in road construction or design. It had not lodged
    an
    expression of interest.

    The company later joined with the Australian company Cooks
    Mitchell
    Peacock Stewart Pty Ltd to lodge a formal proposal for the
    project.

    However, in March 1991, there was little justification for
    Tasman Pacific
    International being on the shortlist at the expense of other
    established
    PNG companies.

    [9-7] PREPARATION OF THE SHORTLIST WAS IRRESPONSIBLE AND
    QUESTIONABLE

    Three of the groups on the shortlist had not submitted an
    expression of
    interest. Of these, the Ombudsman Commission discovered that
    the
    Minister for Transport, Mr Temo, had direct negotiations with
    two of them
    (Outlet Year and Sietco) outside Papua New Guinea, just a
    couple of
    weeks before he gave the shortlist to the Secretary for
    Transport. The
    other one – a Port Moresby shelf company with no experience in
    road
    construction or design, Tasman Pacific International – was
    added to the

  • Page 93 of 397

  • shortlist one month later.

    Question-marks also surround the decision to put companies
    such as
    Curtain Bros and Sabina on the shortlist, because their
    expressions of
    interest were flimsy compared with the carefully documented
    expressions
    of interest submitted in July 1990 by established PNG
    consulting firms
    such as Cardno & Davies and Maunsell Consultants.

    Chapter 9

    83

    In the opinion of the Ombudsman Commission the most favourable
    view
    that can be taken of the Minister for Transport’s shortlist is
    that it was
    unfair and arbitrary. But unfortunately the way in which it was
    prepared
    leaves room for suspicion that the Minister for Transport was
    compromised.
    Whether this was, in fact, the case, the Ombudsman Commission
    cannot
    say, because we found no hard evidence of bribery.

    However, the evidence shows that, if the Minister was not
    compromised,
    he was at least naive and irresponsible in believing that he
    alone – and not the officers of the Department of Transport or
    the Department of Works –
    the officers of the Department of Transport or the Department
    of Works –
    had the necessary technical expertise to decide which companies
    were
    to be shortlisted.

    VENTS AFTER PREPARATION OF SHORTLIST

    ).8] WHAT ACTION WAS TAKEN FOLLOWING PREPARATION OF THE
    MINISTER’S SHORTLIST?

    Shortly after preparation of the shortlist, a standard letter
    was drafted
    within the Department of Transport, over the signature of the

  • Page 94 of 397

  • Secretary for
    Transport, Mr Amini.

    Copies of this letter – dated 8 March 1991 – were apparently
    intended to
    be dispatched to each of the shortlisted companies, explaining
    the
    information to be contained in their proposals.

    Chapter 9

    84

    The letter read, in part:

    Your company has been short-listed for the above-
    mentioned project and you
    are hereby requested to send K40.00 … for cost of
    reproducing the Terms of
    Reference and preliminary “Economic’ and “Financial
    Assessment’ reports plus
    air mail to your address if you do not have an
    Office here in Port Moresby —

    Your proposal should contain the following
    information:-

    Financial Plan

    1.1 Traffic Forecasts

    Traffic throughout estimates and
    anticipated growth of Pori
    Moresby with your estimate of timing for
    maximum capacity,

    1.2 Design, construction and other
    associated costs for suggested
    alternative schemes must be on a fixed
    prize [sic] basis.

    These conceptual designs should
    estimated Bills of Quantifies
    for our guide only.
    The estimate of total project cost must
    include the engineering

  • Page 95 of 397

  • elements of the work as well as costs
    payable to Government,
    including a land premium for area
    occupied if and when needed,
    An estimate cost of setting up the
    project company for this
    project and training the operatives
    prior to opening _11
    [EXHIBIT 64, page 1]

    The letter concluded by stating:

    It must be pointed out very clearly that all
    financing will be your
    responsibility.” [EXHIBIT 64, page 3]

    [9.9] MISSING DOCUMENTS

    There are some perplexing things to note about the
    standard letter drafted
    by the Department of Transport. In particular, there are
    no copies of it on
    any Department of Transport files that the Ombudsman
    Commission
    inspected: there is simply no Departmental record that
    these letters were
    sent, or even that they were drafted.

    Chapter 9

    85

    We only became aware of their existence when the former Minister for
    Transport, Mr Temo, was summoned to appear before the Commission
    and produce relevant documents. Mr Temo had fourteen copies of the
    letter in his possession, addressed to the following companies:

    1. Barclay Bros (PNG) Pty Ltd 1
    2. Cardno & Davies PNG Pty Ltd
    3. Coecon Pty Ltd

  • Page 96 of 397

  • 4. Connell Wagner (Old) Pty Ltd
    5. Curtain Bros (PNG) Pty Ltd
    6. Frame, Harvey and West
    7. Juara Ltd
    8. Kumagai Gumi/Kinhill Kramer
    9. LKN (PNG) Pty Ltd – •
    10. Maunsell Consultants PNG
    11. Ove Arup & Partners Pacific Pty Ltd ■
    12. Robert Laurie Pty Ltd
    13. Sabina Group Consortium
    14. Sietco (PNG) Pty Ltd
    [EXHIBITS 64, 64B – 64N] •

    I

    We also became aware that a copy of the same letter – dated 28 March
    1991 – was sent to Tasman Pacific International, the company that
    was a
    late addition to the Minister’s shortlist. There was also no copy of
    this
    letter in the Department of Transport’s files. [EXHIBIT 68B]

    Chapter 9

    86

    [9.10] FURTHER MYSTERY SURROUNDING THE LETTERS OF MARCH 1991

    Each of the letters dated 8 March 1991 began by stating:
    “Your company
    has been short-listed for the above-mentioned project” (but
    the letters in
    fact had no title). This was very strange. The Minister had
    short-listed
    seven companies for the project on 27 February 1991. Why were
    fourteen
    companies being advised by a letter dated 8 March 1991 that
    they had
    been short-listed? This simply did not make sense.

    Upon discovering the existence of the fourteen letters dated
    8 March
    1991, each of which bore the signature of the Secretary for
    Transport, the
    Ombudsman Commission conducted interviews with

  • Page 97 of 397

  • representatives of
    four Port Moresby-based companies, among the list of
    fourteen:

    Barclay Bros (PNG) Pty Ltd

    Maunsell Consultants PNG

    Cardno & Davies (PNG) Pty Ltd

    Frame Harvey and West.

    Some companies did not receive the Secretary’s letter

    Each of the persons interviewed had knowledge of the Spring
    Garden
    Road project and their company’s interest in it. They each
    stated that they
    had never seen the letter of 8 March 1991 before. Not only
    that, they had
    never received acknowledgment of their company’s expression
    of interest
    in the project, let alone been advised that their company had
    been short-
    listed.

    Chapter 9

    87

    9.11] OTHER COMPANIES DID RECEIVE THE LETTER

    Some companies did receive a copy of the letter of 8 March
    1991. A
    representative of LKN Construction (PNG) Pty Ltd, for
    example, was able
    to confirm, by checking the company’s files, that the letter
    had been
    received. [EXHIBITS 66B, 70]

    It is also likely that Sabina Ltd, of Brisbane Australia,
    received a copy of
    the letter. [See the letter from Sabina to Mr Amini of 8
    April 1991, which
    refers to a letter dated 18 March 1991: EXHIBIT 71]

    9.12] THE SECRETARY FOR TRANSPORTS EXPLANATION

  • Page 98 of 397

  • Mr Amini’s explanation of the confusion over the letters of
    March 1991 was
    as follows:

    ‘Normally for a common letter meant for more than one
    addressee, the original
    is signed and then photocopied for the different
    addressees to be typed on. In
    so doing, the clerks were missing out mating additional
    copies for files. In the
    end, only one copy was left for filing. This practice was
    discovered and
    corrected. As far as I am aware, all those short-listed
    were sent an invitation.
    Some were by facsimile. To suggest that such a simple
    mistake could not occur
    is just being unrealistic. This is not defective
    administration.’ [EXHIBIT 254,
    para 71

    (9.13] DEPARTMENT OF TRANSPORT GUILTY OF DEFECTIVE ADMINISTRATION

    We accept Mr Amini’s point that simple mistakes can occur in
    any
    organisation. But we find it difficult to understand why the
    Department of
    Transport files contain no record at all of the existence of
    these letters.
    And why were fourteen letters drafted, when only seven
    companies had
    been shortlisted? Why did some companies not receive the
    letter? Why is
    there no record of the existence of the Tasman Pacific
    International letter
    in the Department’s files?

    Chapter 9

    88

    If no proper records are maintained, especially in projects
    such as this,
    how can the decision-making process be properly put in place
    and
    justified?

  • Page 99 of 397

  • One of the themes of this report is that unequal treatment
    was given to
    companies which had expressed interest in the project. Some
    were treated
    very favourably, whereas others did not even have their
    expressions of
    interest acknowledged.

    There are too many unanswered questions surrounding the
    letters of
    March 1991 to dismiss the above matters as a minor
    administrative bungle.
    We are surprised that the Minister for Transport had copies
    of the letters
    and not the Department of Transport – though they were signed
    by the
    Secretary for Transport.

    We can only conclude that the Department of Transport’s
    failure to retain
    any record of these letters and the failure to ensure that
    all the letters
    were sent was a serious case of defective administration,
    which had the
    effect of denying a number of companies the opportunity of
    making a bid
    for the project.

    [9.14] THE STATE OF THE SHORTLIST IN MARCH 1991

    In light of the above evidence, the situation with the
    Minister’s shortlist, as
    at March 1991, can be summarised as follows:

    In February 1991 the Minister short-listed seven
    companies,
    two of which had not lodged expressions of interest,
    without
    the advice of his Department.

    Chapter 9

    89

    One month later, the Minister added another company to
    the
    shortlist, even though it also had not lodged an
    expression
    of interest. This company had no experience in road
    design

  • Page 100 of 397

  • or construction. It was advised in writing it had been
    shortlisted, but there is no copy of the letter in the
    Department’s files.

    In the meantime, standard letters advising fourteen
    companies they had been short-listed, were signed by
    the
    Secretary for Transport.

    However, there is no record of the existence of these
    letters
    in the Department’s files.

    At least four of the fourteen letters were not
    received.

    At least one of the companies on the Minister’s
    shortlist –
    Barclay Bros (PNG) Pty Ltd – did not receive the
    letter.

    This was all quite bizarre. However, even stranger things
    were to
    happen in the months ahead. •

    [9.15] THE FATE OF THE SHORTLISTED COMPANIES

    As at the end of March 1991, the Minister had shortlisted
    eight
    consortiums for the project. However, when the Ministerial
    Committee on
    Spring Garden Road met on 18 July 1991, it had a shortlist of
    five:

    Chapter 9

    90

    Topbay Investment Limited & China Ample
    Development Ltd, the Second Surveying & Designing
    Institute, Ministry of Railways, People’s Republic of
    China, together with Moore’s Investment Group.

    Kumagai Gumi-Kinhill Kramer consortium.

    Periquan’s International Resources Pty Ltd and Pty Ltd
    Asia Management Consultants Centre.

    Tasman Pacific International and Crooks Mitchell
    Peacock Stewart Pty Limited.

  • Page 101 of 397

  • McConnell Dowell.

    Only two of these were on the original shortlist of eight.
    So, what
    happened to the six groups that disappeared from the list?
    And
    where did the three new ones come from?

    [9.16] THE COMPANIES WHICH LEFT THE SHORTLIST

    The Ombudsman Commission makes the following observations
    in
    relation to the six companies which disappeared from the
    shortlist:

    1. Outlet Year Ltd – in June 1991 it was “substituted” by
    Topbay
    Investment Ltd, another Hong Kong-based company (see
    Chapter 12).

    Chapter 9

    91
    III

    2. Sietco (PNG) Pty Ltd – there is no evidence that
    this U
    company was advised it was on the shortlist. In
    fact, there
    is no evidence on the Department of Transport
    files of any
    correspondence from or to this company.

    III
    3. Barclay Bros (PNG) Pty Ltd/Maunsell Consultants
    PNG Pty
    Ltd – neither of these companies were advised
    they had la
    been shortlisted.

    FE
    4. Curtain Bros – there is no evidence that either
    Curtain Bros
    (PNG) Pty Ltd or Curtain Bros (Old) Pty Ltd were
    advised II
    they had been shortlisted.
    5. LKN Construction – on 8 April 1991 LKN (PNG) Pty
    Ltd wrote II

  • Page 102 of 397

  • to the Department of Transport and advised that
    it was
    withdrawing its expression of interest. [EXHIBIT
    70]

    6. Sabina Group Consortium – this group was
    definitely aware
    it had been shortlisted, but was unable to meet
    the deadline
    for submission of proposals. [EXHIBITS 76, 82,
    83]

    [9.17] THE THREE NEW GROUPS “ADDED ” TO THE SHORTLIST

    The Ombudsman Commission makes the following
    observations in
    relation to the three groups included in the July
    1991 shortlist, but
    not in the March 1991 shortlist:

    1. Topbay Investment Ltd – this company replaced
    Outlet Year
    Ltd, but essentially the same group of Asian
    businessmen
    was involved (see Chapter 12).

    Chapter 9

    92

    2. Periquan’s International Resources Pty Ltd – this
    company
    joined with the Port Moresby consulting firm, Frame
    Harvey
    West & Maso, and submitted a late proposal. But no
    formal
    expression of interest had been lodged before this.

    3. McConnell Dowell – this Brisbane-based company only
    heard
    about the project in April 1991. On the basis of a
    half-page
    fax to the Department of Transport and two telephone
    conversations with the Director of the Policy
    Secretariat, Mr
    Hitolo, a letter was dispatched to the company,
    advising it
    had been shortlisted. [EXHIBITS 74, 75, 77]

  • Page 103 of 397

  • SUMMARY OF PREPARATION OF SHORTLIST

    [9.18] UNEQUAL TREATMENT WAS GIVEN TO COMPANIES WHICH HAD
    EXPRESSED INTEREST IN THE PROJECT

    There was a great disparity in the treatment given to the
    various
    companies that had expressed interest in the Spring Garden
    Road project
    since July 1990:

    Some companies were shortlisted, even though they had
    not
    lodged an expression of interest (e.g. Outlet Year Ltd,
    Topbay Investment Ltd, Tasman Pacific International and
    McConnell Dowell) whereas others which had lodged
    detailed expressions of interest in July 1990 were
    excluded
    and never received acknowledgement of their interest
    (e.g.
    Cardno & Davies and Maunsell Consultants).

    Chapter 9

    93

    Some shortlisted companies were allowed extensions of
    time
    to submit proposals [see EXHIBITS 67, 72, 76, 78, 79,
    81,
    83, 93, 94] whereas others (e.g. Barclay Bros) were
    not even
    advised they had been shortlisted.

    The result of this arbitrary and unsatisfactory process was that, by
    July
    1991, a shortlist of five had been prepared for the consideration of
    the
    Ministerial Committee on Spring Garden Road.

    * * * * * * * * * *

  • Page 104 of 397

  • Chapter 9

    94

    10. TERMS OF REFERENCE FOR THE PROJECT: EARLY 1991

    [10.1] PURPOSE OF THE TERMS OF REFERENCE

    In early 1991, a document was drafted within the Department
    of Transport,
    entitled ‘Terms of Reference-Spring Garden Road”. The purpose
    of this
    document was to describe the requirements of the Department
    of
    Transport and assist potential developers in the formulation
    of proposals.
    [EXHIBIT 55]

    In the Ombudsman Commission’s view, the document was
    seriously
    flawed and very confusing. It failed to specify the scope of
    the project
    and its technical parameters. The timing of the document’s
    release, its
    limited circulation and. its stipulation concerning Build-
    Operate-Transfer
    financing are also matters for concern.

    [10.2] THE SCOPE OF THE PROJECT

    We reported in Chapter 5 that, despite extensive
    investigations, we were
    never able to pinpoint who made the decision to extend the
    scope of the
    Spring Garden Road/Poreporena Freeway project from the
    original plan to
    link Konedobu, through Burns Peak, with Hohola.

  • Page 105 of 397

  • Nor could we determine when the decision was made that a
    freeway
    should be built all the way from downtown Port Moresby to
    Jacksons
    Airport.

    Chapter 10

    95

    The problem of defining the scope of the project was
    exacerbated by the
    Terms of Reference document. Whereas the advertisements
    published by
    the Department of Works in June 1990 had specified
    (arbitrarily) that the
    new road would link Konedobu and Waigani Drive, the
    Department of
    Transport’s Terms of Reference simply spoke in vague terms
    such as “the
    Spring Garden Road Link near the Burns Peak”.

    [10.3] WHAT DOES THE “SPRING GARDEN ROAD UNK” MEAN?

    This term can mean at least three things:

    a link between Champion Parade Konedobu and Wards
    Road Hohola; or

    a link between Champion Parade Konedobu and Waigani
    Drive; or

    a link between Champion Parade Konedobu and Boroko
    Drive. [See the map at the end of Chapter 2]

    All of the above alternatives would “link” various
    unconnected sections of
    Spring Garden Road, which runs from Champion Parade Konedobu
    to
    Boroko Drive, Gordons.

    The Terms of Reference document was seriously deficient in
    its failure to
    specify exactly what was required of prospective developers.
    The
    qualifying words which appear in the document – “near the
    Bums Peak” –
    suggest the scope of the project was intended only to be the
    link between
    Champion Parade and Wards Road.

  • Page 106 of 397

  • Chapter 10

    96

    But if that was the case, why did the State eventually enter
    into a contract
    for the construction of a freeway going all the way from
    downtown Port
    Moresby to Jacksons Airport?

    [10.4] THE TERMS OF REFERENCE DEFIED COMMON SENSE

    It seems common sense that when the Government commissions
    the
    building of a road, one of the first things to decide is
    where the road is
    going to go and how long it should be. How can a company
    lodging a
    proposal to build a road estimate the total project cost
    (inclusive of design
    and construction) when it doesn’t know where the road is
    supposed to
    go or how long it is supposed to be?

    In his response to our preliminary report, the Secretary for
    Works, Mr
    Hitolo, who was responsible for the project for a
    considerable time in the
    Department of Transport, stated that the scope of the project
    was
    deliberately not specified in the Terms of Reference
    document, because
    this was to be a Build-Operate-Transfer project:

    “Government’s role is purely to create the business
    atmosphere conducive to
    the private company to become interested in investing on a
    scale and scope it
    believes it can get a profitable return.” [EXHIBIT 265,
    page 3]

    Mr Hitolo said it would have been premature to specify the
    scope of the
    project in the Terms of Reference. He also suggested that the
    Ombudsman Commission did not understand the Build-Operate-
    Transfer

  • Page 107 of 397

  • concept.

    By contrast, when the Secretary for Transport, Mr Amini,
    responded to our
    preliminary report, he maintained that the detailed scope of
    the project
    was contained in the Terms of Reference document. However,
    when
    asked to point to the section of the document which specified
    the scope,
    Mr Amini was unable to do so. [EXHIBIT 254, page 4]

    Chapter 10

    97

    Quite dearly, the Terms of Reference did nol specify the
    scope of the
    Spring Garden Road project. It did not state where the road
    was
    supposed to begin and end. We reject Mr Amini’s claim that it
    did. We
    also reject Mr Hitolo’s claim that it was unnecessary for the
    scope of the
    project to be specified.

    The Ombudsman Commission concludes that the Terms of
    Reference
    document was vague and confusing, especially because of its
    failure to
    specify what was required of prospective developers.

    The inadequacy of the document is borne out by the fact that,
    despite its
    insistence that proposals be based on Build-Operate-Transfer
    financing,
    no such proposal was ever lodged with the Department of
    Transport.

    [10.5] THE TERMS OF REFERENCE ALSO FAILED TO SPECIFY THE
    TECHNICAL PARAMETERS OF THE PROJECT

    Another serious defect in the Terms of Reference document was
    its failure
    to specify the fundamental technical parameters of the

  • Page 108 of 397

  • project. This point
    was made by the World Bank Mission which visited Port Moresby
    in
    September 1991 to monitor the Spring Garden Road project:

    Mu technical parameters are left =claw as to whether Papua
    New Guinea
    was seeking a two or four lane road, one or two tube
    tunnels, and whether the road surface would be of
    compacted gravel or asphalt concrete, and whether an open
    cut or tunnel was desired.’
    road surface would be of compacted gravel or asphalt
    concrete, and whether an open cut or tunnel was desired.’
    open cut or tunnel was desired.’
    [EXHIBIT 111, at page 1 and see generally Chapter 15J

    [10.6] TIMING OF THE RELEASE OF THE TERMS OF REFERENCE

    The Terms of Reference document was first released in March
    1991. This
    was before the results of the geotechnical investigation
    undertaken by

    Chapter 10

    98
    Coffey Partners International was completed. However, the
    interdepartmental meeting on 31 July 1990 had decided that
    firm
    proposals would not be called for, until after that
    investigation was
    complete (see Chapter 7).

    The Ombudsman Commission therefore seriously questions the
    timing of
    the release of the document

    0.7] LAVED CIRCULATION OF THE TERMS OF REFERENCE

    An even more serious concern is the fact that the Terms of
    Reference
    document was only circulated to a limited number of
    developers. It was
    only those companies shortlisted by the Minister for
    Transport, Mr Temo,
    in February/March 1991, that were eligible to receive a

  • Page 109 of 397

  • copy.

    We have already commented on the unsatisfactory and
    arbitrary way in
    which that shortlist was prepared (see Chapter 9). It would
    have been far
    better to publicly advertise the availability of the Terms
    of Reference,
    rather than selectively offer it to only a few companies.

    Whenever investment opportunities are offered to companies
    “selected” by
    a Minister, there are bound to be suspicions of corruption.
    The best way
    to avoid this is to give all interested companies an equal
    opportunity to
    submit proposals through public advertisements.

    .8] BUILD-OPERATE-TRANSFER FINANCING

    A feature of the Terms of Reference document. is that it
    dictated that the
    project be undertaken using the Build-Operate-Transfer (BOT)
    method of
    financing.

    Chapter 10

    99

    The Ombudsman Commission has been unable to establish how or, even,
    when this important policy decision was made, because the Terms of
    Reference document is undated and the Department of Transport files
    did
    not disclose this information. It was certainly never the stated
    policy of the
    National Executive Council that the project be financed in this way.

    In the absence of such a policy directive, the Ombudsman Commission
    expected to find some evidence that, before stipulating the project
    would
    be financed in this way, the Department of Transport had carefully
    and
    methodically considered all the policy options available and
    formally made
    a decision to invite proposals on the basis of Build-Operate-
    Transfer
    financing. However, our examination of their files revealed that
    Build-
    Operate-Transfer financing was addressed only in the following
    documents:

  • Page 110 of 397

  • the Information Paper that was supposed to be presented to
    the National Executive Council, but which never was (see the
    final part of Chapter 8); and

    the Terms of Reference document. [Exhibits 36 & 55]

    Neither document could satisfy us that the decision concerning
    Build-
    Operate-Transfer financing for the Spring Garden Road project had
    been
    made carefully or competently.

    In our preliminary report we suggested that the Department of
    Transport
    had failed to make a careful, reasoned and properly documented
    decision
    on financing the Spring Garden Road project. The Secretary for
    Transport,
    Mr Amini, responded by stating:

    Chapter 10

    100

    ‘The concept of BOT was debated at length at our Executive
    Meetings. It was
    introduced by Mr Hitolo. I do not encourage new concepts which
    are not fully
    assessed for implications and impacts to be put before the NEC.’
    [EXHIBIT 254, page 31

    However, when Mr Amini was pressed on this issue, the only evidence
    he
    could provide was the minutes of a Department of Transport Executive
    Staff Meeting on 14 September 1990. The minutes stated:

    “Director (Policy Secretariat) said he will prepare a submission
    to NEC for
    discussion when considering plans for the project on the BOT
    system. HOT
    stands for Build, Operate and Takeover.

    The system simply means that the company awarded the contact will
    build the
    mad (project) and operate it in a bid to recover costs and

  • Page 111 of 397

  • expenses. Then hands
    the mad back to National Government.” [EXHIBIT 45A, page 4]

    Mr Amini also provided copies of two papers presented at a Transport
    Sector Seminar held in Port Moresby in 1991, which addressed the
    issue
    of Build-Operate-Transfer financing. One of them was prepared by Mr
    Hitolo, then Director of the Policy Secretariat in the Department of
    Transport, entitled “Spring Garden Road BOT Concept’. Mr Hitolo
    stated:

    ‘The main reason to get Spring Garden Road to be proposed for
    financing
    through private sector was the fact that the Government’s
    intention for this
    project to attract aid was not successful despite its good
    economic justifications.
    Hence the Government, decided to get private funding by directing
    the
    Department of Transport to assess the turn-key concept as the
    basis for
    implementing the project. This simply meant that a particular
    company be
    selected on a competitive basis and get it to arrange a private
    loan on behalf
    of the Government. As the general policy and understanding was to
    use the
    private sector for the total financing, construction and
    operation so that
    efficiency in the private sector may be tapped in the provision
    of infrastructure
    services.

    In actual fact the BOT (Build, Operate and Transfer) or the
    alternative BOO
    (Build, Own and Operate) systems were implied in the above-
    mentioned policy.
    Hence the concept of BOT system came into consideration followed
    by an
    invitation for interests in this sort of scheme. Unfortunately,
    the concept was
    not very well known in this country and therefore the responses
    were not
    satisfactory.’ [EXHIBIT MA, page 303]

    Chapter 10

  • Page 112 of 397

  • 101

    The Ombudsman Commission does not dispute Mr Hitolo’s
    expertise. Nor
    do we take issue with the Build-Operate-Transfer concept, as
    such. As an
    innovative method of financing it deserved to be closely and
    widely
    considered.

    What we are critical of is the Department of Transport’s
    failure to carefully consider all the financing options
    available and its failure to formulate a
    consider all the financing options available and its failure
    to formulate a
    policy and advise the Minister for Transport to table it
    before the National
    Executive Council so that a formal Cabinet policy decision
    could be made
    on this important issue.

    10.9] SUMMARY OF THE TERMS OF REFERENCE: INCOMPETENT
    ADMINISTRATION BY THE DEPARTMENT OF TRANSPORT

    There were many unsatisfactory aspects of the Terms of
    Reference
    document prepared by the Department of Transport in early
    1991:

    As a document which was supposed to indicate to developers
    what
    was required in their proposals, it was very vague. It did
    not
    mention where the road would go, or how long it would be.

    It also failed to specify basic engineering aspects of the
    project.

    It was prematurely released.

    It dictated that the proposals incorporate Build-Operate-
    Transfer
    financing, however no formal decision in favour of this
    method of
    financing had been made by the Department of Transport, the
    Minister for Transport or the National Executive Council

    Chapter 10

    102

  • Page 113 of 397

  • It was made available – unfairly – to only a selected group of
    companies.
    In the opinion of the Ombudsman Commission the preparation and
    distribution of this important – but defective – document was
    another
    example of incompetent administration by the Department of
    Transport.

    * * * * * * * * *

    Chapter 10

    11. THE MINISTERIAL COMMITTEE MEETING
    OF 18 JULY 1991

    [11.1] PERSONS PRESENT AT THE MEETING

    The Minister for Transport Mr Anthony Temo convened a meeting
    of “the
    Ministerial Committee on Spring Garden Road” in his
    Parliamentary office
    on 18 July 1991. Present at the meeting were:

    Mr Temo, MP;

    the Minister for Lands and Physical Planning, Sir Hugo
    Berghuser MP;

  • Page 114 of 397

  • the Minister for Works, Lukas Waka OBE, MP;

    the Parliamentary Secretary for Finance and Planning,
    Thomas
    Negints MP;

    the Head of the Policy Secretariat in the Department of
    Transport, Lohia Hitolo; and

    the First Assistant Secretary (Planning & Research) in
    the
    Department of Transport, Henry Paraket.

    Chapter 11

    104
    [11.2] WHAT WAS THE PURPOSE OF THE MINISTERIAL COMMITTEE
    MEETING?

    The purpose of the meeting was to select a developer to
    undertake the
    Spring Garden Road project. As a result of the arbitrary and
    unsatisfactory
    shortlisting process between February and July 1991
    (considered in
    Chapter 9) five consortiums were to be considered.

    THE MINISTERIAL COMMITTEE ON SPRING GARDEN ROAD

    [11.3] STATUS OF THE MINISTERIAL COMMITTEE

    Before we address the deliberations of the Ministerial
    Committee, there is
    one important point to note: in the course of its
    investigation the
    Ombudsman Commission was unable to find any document showing
    how
    or when this Committee was established or who its members
    were.

    The Secretary to the National Executive Council testified
    there was no
    record of the establishment of such a committee and the
    Secretary for
    Transport said his Department had also tried in vain to find
    some record
    of the Committee’s existence.

  • Page 115 of 397

  • When we put the issue to Mr Temo, he was adamant that the
    Committee
    had been duly authorised by the National Executive Council to
    report back
    to it on the preferred method of implementing the project. He
    could not,
    however, provide any details of the Committee’s
    establishment.

    Chapter 11

    105

    Mr Temo stated:

    “My mind is quite clear that there was a NEC
    decision which authorised the
    Minister for Transport to be Chairman of the
    Ministerial Committee on
    infrastructure. Also the same Ministerial Committee
    used NEC decision to
    bypass normal tender procedures to construct Enga
    Highway Stage 2 or 3. If
    NEC did not make this decision), Porgera mine would
    not have started
    production on time because normal department tender
    procedures normally
    takes a very long time even the normal political
    will does not work.

    One should understand that if there was no such
    Ministerial Committee
    established why was NEC recognising and expecting
    Ministerial Committees
    recommendations?

    Therefore obviously I acted with some lawful
    authority even if we are unable
    to get the records. See letter from NEC Secretary
    dated 19 November 1992′
    [EXHIBIT 257 para 2]

  • Page 116 of 397

  • When we questioned Sir Hugo Berghuser on this point, he
    stated that the

    Committee had been established at his initiative. But Sir
    Hugo, also, could

    not point to any formal record of its existence.

    [11.4] THE MINISTERIAL COMMITTEE ACTED WITHOUT AUTHORITY

    The Ombudsman Commission concludes that the “Ministerial
    Committee

    on Spring Garden Road” was never formally established by
    the National

    Executive Council and had no authority to make decisions
    binding or

    purporting to bind the National Executive Council.

    At this juncture, we note that Section 149(4) of the
    Constitution provides:

    ‘Except where the contrary intention appears,
    nothing in this
    Constitution prevents the powers, functions, duties
    or responsibilities
    of ti e [National Executive Council] from being
    exercised, as determined
    by t, through a Minister.”

  • Page 117 of 397

  • Thus, the Constitution does allow the powers of the
    National Executive

    Council to be delegated to Ministers.

    Chapter 11

    106

    But this does not mean that any group of Ministers can
    appoint
    themselves to “committees” of the National Executive Council
    and clothe
    that “committee” with powers or status.

    A Ministerial Committee – even one which only intends to make
    recommendations to the National Executive Council – must have
    its powers
    and responsibilities properly delegated and controlled by the
    National
    Executive Council under Section 149(4) of the Constitution
    before it makes
    any decisions or holds itself out as having any powers or
    responsibilities.

    This did not occur in relation to “the Ministerial Committee
    on Spring
    Garden Road”. It therefore had no lawful status or power or
    authority.

    [11.5] WHAT DOCUMENTS WERE CONSIDERED AT THE “MINISTERIAL
    COMMITTEE” MEETING?

    The Head of the Policy Secretariat in the Department of

  • Page 118 of 397

  • Transport, Mr
    Hitolo, brought the following documents to the meeting on 18
    July 1991,
    for the consideration of the Ministerial Committee:

    the proposals of the five shortlisted consortiums; and

    a document dated 17 July 1991 entitled “Financing the
    Construction of the Spring Garden Freeway”.

    Chapter 11

    107

    LOSS OF DOCUMENTS

    [11.6] MOST OF THE FIVE PROPOSALS HAVE BEEN LOST

    It has been very difficult for the Ombudsman Commission to
    ascertain
    exactly which proposals the Ministerial Committee had before
    it. By the
    time we conducted our investigation, most of the proposals
    had been lost.

    The investigation was also hampered by the fact that the
    meeting is poorly
    documented in the files of the Department of Transport. In
    fact, the only
    evidence of the meeting taking place is a letter from the
    Minister for
    Transport to the Secretary for Transport asking him to attend
    the meeting
    and a one-page memorandum of the decisions made at the
    meeting.
    [EXHIBITS 97,102]

    [11.7] HOW WERE THE PROPOSALS LOST?

    Mr Hitolo testified that at the end of the meeting he had
    left all five
    proposals in the Minister for Transport’s office at the
    request of Sir Hugo
    Berghuser, who said that he wanted to study them further
    before making
    a decision.

  • Page 119 of 397

  • When Sir Hugo was questioned on this point, he agreed the
    proposals
    had been left, at his request, in the office. But he said he
    only asked that
    copies be made for him. He was dissatisfied with the
    proposals before
    the Committee and he said as much to the other members of the
    Ministerial Committee. ‘When I left the office, the proposals
    were still there
    and I have never seen them since’, Sir Hugo said.

    Chapter 11

    108

    Correspondence between Mr Hitolo (who became Secretary for
    Works in
    early 1992) and Mr Amini in March 1992 confirmed that this
    incident took
    place [EXHIBIT 160, final paragraph]. But the Ombudsman
    Commission
    has not been able to trace the whereabouts of the proposals
    left in the
    Minister’s office.

    The Ombudsman Commission concluded that the proposals were
    lost by
    the Minister for Transport, Mr Temo.

    When we made this allegation in our preliminary report, Mr
    Temo claimed
    that, in fact, the proposals had been lost by Sir Hugo
    Berghuser.
    However, even if this were, in fact, the case, Mr Temo was
    the Minister of
    the State entrusted with custody of these important and
    confidential
    documents. It was his responsibility to take adequate steps
    to ensure the
    documents were in safe hands.

    [11.8] THE DEPARTMENT OF TRANSPORT FAILED TO KEEP COPIES OF THE
    PROPOSALS

    Surprisingly, the Department of Transport had not kept copies
    of the
    proposals, except the one made by the Chinese consortium –
    which was
    the group selected by the Ministerial Committee to undertake
    the project.

  • Page 120 of 397

  • This meant, therefore, that most of the proposals had been
    lostTM.

    This particular administrative mistake was to have far-
    reaching
    consequences several months later, when pressure was put on
    the
    Department to expedite the project and the Department had
    second-
    thoughts about supporting the Chinese proposal (see Chapter
    18).

    Chapter 11

    109

    It meant that when the Department was required to prepare a
    National
    Executive Council Policy Submission in February 1992,
    recommending a
    consortium to undertake the project, it only had one proposal
    in its
    possession.

    [11.9] DEPARTMENTAL RECORDS SHOULD NOT BE GIVEN TO MINISTERS

    As a general rule the Ombudsman Commission believes that
    official
    Government records and files should not be left in the
    possession of
    Ministers. An official Government file is the property of the
    State – it does
    not belong to a Minister. A Minister has the right to be
    fully and objectively
    briefed by his or her Departmental Head. But he does not have
    the right
    to keep possession of official files.

    If this principle of sound public administration had been
    followed in the
    present case, the proposals probably would not have been
    lost.

    EVALUATION OF PROPOSALS

    [11.10]la
    SPRING GARDEN FREEWAY

  • Page 121 of 397

  • This document was the focus of discussion ac the Ministerial
    Committee
    meeting of 18 July 1991. It is dated 17 July 1991, i.e. one
    day before the
    Ministerial Committee meeting. were in fact two versions of
    it:

    Chapter 11

    110

    One version was addressed to “the Members of the
    Resource Management Committee”. It was drafted as a
    submission by the Department of Transport and shows the
    submitter as “B K Amini CBE Secretary”; however, it was
    unsigned. [EXHIBIT 100]

    The other version of the document was drafted as a Policy
    Submission to the National Executive Council by the Minister
    for Transport; it was signed by Mr Temo. [IXHIBIT 99]

    Although there are some minor variations, both versions of the
    document
    are essentially the same:

    They outline the background of the Spring Garden Road
    project.

    The scope of the project is described as being from
    downtown Port Moresby to Jacksons Airport.

    The five short-listed proposals are evaluated, according to
    ten criteria.

    The conclusion is reached that the Second Surveying and
    Designing Institute of the Peoples’ Republic of China (which
    lodged a proposal in conjunction with Topbay Investment
    of Hong Kong) be “appointed” to commence negotiations
    with the Department of Transport for the development of the
    Spring Garden Road.

    Chapter 11

    111

    [11.11] THE METHOD USED TO EVALUATE THE SHORTLISTED PROPOSALS

  • Page 122 of 397

  • The “Financing the Construction of the Spring Garden
    Freeway” document
    evaluated the five proposals according to ten criteria:

    1. Interpretation of the Terms of Reference.
    2. Logical Phasing of Tasks in the Methodology.
    3. Environment Impact Statement.
    4. Financier’s Credibility.
    5. Main Contractor’s Relevant Experience.
    6. Local Partner Participation.
    7. Proposed Equity Distribution.
    8. Personnel Proposed in General.
    9. Team’s Experience in B.O.T. System.
    10. Funding Proposal for the Project.

    The proposals were given a rating of “Excellent”, “Very
    Good”, “Good”,
    “Fair” or “Satisfactory” on each criteria.

    The proposals were then given an overall ranking, as
    follows:

    1st: Topbay Investment Ltd/Second Surveying & Designing
    Institute, People’s Republic of China.

    2nd: Periquan’s International Resources.

    3rd: Kumagai Gumi/Kinhill Kramer.

    4th: Tasman Pacific International.

    5th: McConnell Dowell.

    Chapter 11

    112

    In light of these rankings, the document concluded that the
    project be
    awarded to the Chinese consortium.

    (11.12] FURTHER UNSATISFACTORY ADMINISTRATION BY THE DEPARTMENT
    OF TRANSPORT

    We have noted elsewhere in this report that the standard of
    documentation of important policy decisions by the
    Department of
    Transport was extremely poor. We made that finding in
    relation to a
    number of issues, e.g. the decision to extend the freeway to
    Jacksons

  • Page 123 of 397

  • Airport, the tunnel/cut issue and the Build-Operate-Transfer
    method of
    financing (see Chapters 5 & 10).

    We make a similar finding in relation to the evaluation of
    the five proposals
    shortlisted for consideration by the Ministerial Committee.
    The
    Ombudsman Commission considers that a much more detailed and
    methodical comparison of the alternative proposals was
    required than the
    one page table attached as an appendix to the “Financing the
    Construction of the Spring Garden Freeway” document.

    The subjective rankings on the basis of the ten selected
    criteria were
    vague and meaningless.

    This situation occurred because the Department of Transport
    did not have
    any established procedures for evaluating proposals for
    construction of
    roads or other transport infrastructure. The Department of
    Transport, on
    the instructions of the Minister for Transport, had wrongly
    assumed
    responsibility for a task that should have been carried out
    by a Supply
    and Tenders Board, in accordance with the Public Finances
    (Management)
    AM

    Chapter 11

    113

    [11.13] OTHER DEPARTMENTS NOT INVOLVED IN THE RANKING OF
    PROPOSALS

    A feature of the decision-making process which led to the
    selection of the
    consortium to build the Spring Garden Road/Poreporena
    Freeway, is the
    flagrant disregard of normal tender procedures (see Chapter
    35).

    If the project had been properly put to public tender in the
    first place, the
    Ministerial Committee would not have had to deliberate on
    the matter and
    the Department of Transport would not have been required to
    rank the
    proposals shortlisted by the Minister.

  • Page 124 of 397

  • Though these mistakes were made, the maladministration would
    not have
    been so serious, if the Minister for Transport and the
    Department of
    Transport had been willing to consult other Departments when
    ranking
    the shortlisted proposals. However, no consultation took
    place.

    We are particularly concerned that the Department of Works
    was not
    consulted. This Department has far more experience in
    selection of
    contractors to undertake road projects than the Department
    of Transport.

    It was also wrong for the Department of Transport not to
    consult the
    Department of Finance and Planning. There is no evidence
    that any proper
    checks were made by the Department of Transport on criteria
    such as
    “Financier’s Credibility” and “Funding Proposal for the
    Project”. We note the
    Chinese proposal was rated “excellent” on both these
    criteria. Yet six
    months later the Department of Transport found it necessary
    to seriously
    question the bona fides of the proponents (see Chapter 15).

    Chapter 11

    114

    [11.14] DID THE PROJECT “BELONG” TO THE DEPARTMENT OF TRANSPORT?

    We have no doubt many mistakes were made because the
    Minister for
    Transport and the Secretary for Transport believed that the
    Spring Garden
    Road/Poreporena Freeway project was “a Department of
    Transport project”
    – not “a Department of Works project”.

    However, the terms of National Executive Council Decision
    No. 14/90 were
    that “the Department of Transport, the Department of Works
    and the
    Department of Finance and Planning formulate detail plans

  • Page 125 of 397

  • for the
    construction of Burns Peak Road”. [EXHIBIT 6A]

    We could therefore see no justification for the Minister for
    Transport or the
    Department of Transport shutting out these two other
    departments from
    the decision-making process.

    Though it was within the policy prerogative of the
    Department of Transport
    to determine where the freeway would go, whether there would
    be a
    tunnel or cut through Burns Peak and whether the project
    would be
    undertaken using Build-Operate-Transfer financing, it was
    wrong for the
    Minister for Transport and the Department of Transport to
    exclude the
    other key Departments from the decision on who was going to
    design,
    finance and build the freeway.

    [11.15] THE FORMAL RECORD OF THE MINISTERIAL COMMITTEE’S DECISION

    In his oral testimony to the Ombudsman Commission, Sir Hugo
    Berghuser
    stated that the Ministerial Committee meeting lasted not
    much longer than
    30 minutes and that the discussion had been confined to the
    contents
    the “Financing the Construction of the Spring Garden
    Freeway” document.

    Chapter 11

    115

    No minutes of the meeting were kept and the only record
    of the
    Committee’s decision is a document, under Ministry of
    Transport
    letterhead, that was signed by Mr Temo, Mr Waka and Mr
    Negints. It
    stated:

    ‘On the 18th day of July 1991, the Ministerial
    Committee On The Spring Garden

  • Page 126 of 397

  • Road Development met at the Transport Minister’s
    office in the National
    Parliament House and authorized and approved the
    following recommendation:

    That the Chairman of this Committee seek
    National Executive Council
    (NEC) endorsement for the appointment of
    The Second Surveying and
    Designing Institute, Ministry of Railways
    of Peoples Republic China to
    commence negotiation for the development
    of the Spring Garden Road.

    2. That the Chairman of the Committee seek
    National Executive Council
    endorsement to authorize the Attorney-
    General’s Department and the
    Department of Finance and Planning to
    negotiate and execute the
    principle terms and conditions of the
    contract emerging from their
    proposals.

    3. That the Chairman of this Committee seek
    National Executive Council
    endorsement to negotiate and use B.O.T. or
    turnkey as the basis of
    funding the Spring Garden Road
    Development.

    4. That the Chairman of the Ministerial
    Committee seek National
    Executive Council endorsement in order to
    authorize Department of
    Finance and Planning to negotiate and
    execute the Franchise agreement
    and any other necessary and desirable
    documents relating thereto on
    behalf of the State? [EXHIBIT 102]

    Sir Hugo testified that this document was not signed at
    the meeting of 18
    July 1991 and we accept that that was in fact the case.

    [11.16] WHAT HAPPENED AFTER THE MEETING?

  • Page 127 of 397

  • The document recording the decisions of the Ministerial
    Committee
    appears to have been signed a day or two after the
    meeting took place.

    Chapter 11

    116

    Sir Hugo stated that, though he had seen this document, he
    had
    deliberately not signed it because he did not agree with its
    contents. He
    was very suspicious about the negotiations that had already
    taken place
    with the Chinese. In fact, Sir Hugo alleged that he had been
    invited to a
    Chinese restaurant in Port Moresby, and asked to sign the
    document in
    the presence of other members of the Ministerial Committee
    and
    representatives of the Chinese consortium. He said that he
    refused to sign
    the document and walked out of the restaurant.

    The Ombudsman Commission has been unable to obtain any
    corroborating evidence of this particular incident. However,
    we share Sir
    Hugo’s concern about the propriety of the decision to favour
    the Chinese
    consortium.

    WAS THERE AN OBJECTIVE EVALUATION?

    [11.17] HAD THERE BEEN A GENUINE ATTEMPT TO EVALUATE THE
    ALTERNATIVES?

    On the face of it, the selection of the Chinese consortium
    was yet another
    example of the type of haphazard and careless decision

  • Page 128 of 397

  • making that had
    come to characterise the Ministry and Department of
    Transport’s handling
    of the Spring Garden Road/Poreporena Freeway project. But
    our
    investigations revealed that there was more to the selection
    of the Chinese
    than just slipshod administration.

    Chapter 11

    117
    [11.18] THE DECISION HAD ALREADY BEEN MADE

    In the opinion of the Ombudsman Commission, the Ministerial
    Committee
    meeting of 18 July 1991 was really just a rubber-stamping
    exercise for a
    decision already made by the Minister for Transport, Mr
    Temo, to award
    the project to the Chinese consortium.

    Both versions of the “Financing the Construction of the
    Spring Garden
    Freeway” document actually referred to “the Ministerial
    Committee’s
    decision to appoint the SSDI to commence negotiations …for
    the
    development of the Spring Garden Road”. But the document was
    dated
    17 July 1991 – one day before the Ministerial Committee made
    that
    decision!

    The Ombudsman Commission discovered that, in fact, the
    Minister for
    Transport had formed a close association with members of the
    Chinese
    consortium well before the meeting. He had entertained a
    delegation from
    the consortium, in Port Moresby, only one week before the
    Committee’s
    decision to favour them (see Chapter 12). 1

    In light of that evidence, the Ombudsman Commission was
    forced to
    conclude that the deliberations of the Ministerial Committee
    were not a
    genuine attempt to objectively evaluate the five short-
    listed proposals.

  • Page 129 of 397

  • [11.19] MR TEMO’S RESPONSE

    When we suggested in our preliminary report that Mr Temo had
    improperly arranged the selection of the Chinese consortium,
    he
    responded in the following terms:

    Chapter 11

    118

    “Most of the companies that showed or expressed interest either did
    not
    understand the terms of reference of the project or did not bother
    to re-check
    with the Committee or Departments of Transport or Works.

    As you can see in NEC decision or purpose of the NEC submission No.
    14/90
    it was the wish of the NEC to speed up the project. That is why the
    NEC
    submission’s purpose was to bypass normal tender procedures in order
    to speed
    up the project to be completed in time for the SP Games. Also there
    was a
    criticism against me in NEC or Parliament every time there was a
    traffic
    problem along Sir Hubert Murray Highway even by public what are you
    doing
    Mr Chairman or Mr Minister for Transport.

    While I was being pressured by the public NEC and Parliament I had
    to
    negotiate with any of these companies that showed interest as a
    Chairman of
    Committees I was left to look like a fool if I did not report back
    to NEC with
    a positive report I would have failed my duty and I was scared I
    could loose
    my job.

    No companies complained because it was a new concept proposed by
    Barclay
    Bros. before my time. I had to carry on from that initiative. It has
    been a very

  • Page 130 of 397

  • tough job trying to get the best companies to do the job.

    Some companies responded again when it was convenient to them. We
    had to
    follow them because PNG does not have the resources in monetary and
    manpower.

    The companies that came up with fancy proposals and sort of got in
    touch with
    my office or the Secretary’s office kept getting our attention.

    At least I was given a responsibility to present to NEC. I did not
    discriminate
    other companies against that showed interest It was a mere who comes
    first
    with the best proposal for PNG.

    I have a feeling that the Chinese companies were not consortium but
    they were
    selling their information from one company to another.

    The Department was very uncooperative to me or NEC.

    I, Mr Temo was not hiding any transactions from the Department. I
    always
    notified of the progress that is why I have them all information. I
    therefore
    regardless whether I had meeting or not prior to not really relevant
    in the
    situation of this new confused situation as there was no better
    proposals and
    interest shown other than that of the Chinese.

    All the time the Department was aware I did not organise any secret
    de–11c an
    my mine was dear all the time.” [EXHIBIT 257, page 2]

    Chapter 11

    119

    [11.20] CONCLUSION AS TO THE DELIBERATIONS OF THE MINISTERIAL
    COMMITTEE

  • Page 131 of 397

  • With due respect to Mr Temo, he has not satisfactorily
    answered our
    criticism of the way in which the Chinese consortium
    was favoured by the
    Ministerial Committee. We conclude that he convened the
    meeting of the
    Ministerial Committee for the purpose of facilitating
    the Chinese consortium
    selected by himself to undertake the project.

    The closeness of the relationship between Mr Temo and
    the Chinese
    consortium is explored further in the next chapter.

    * * * * * * * * * *

    Chapter 11

    120

    12. THE RELATIONSHIP BETWEEN THE CHINESE
    CONSORTIUM AND THE MINISTER FOR TRANSPORT

  • Page 132 of 397

  • [12.1] A MATTER OF CONCERN

    The manner in which the Chinese consortium was chosen by the
    Ministerial Committee was a matter of concern to the
    Ombudsman
    Commission.

    We therefore wanted to find out who was actually behind the
    proposal of
    the “Second Surveying and Designing Institute, Ministry of
    Railways,
    People’s Republic of China”. We were also interested to know
    whether the
    Minister for Transport had any particular association with
    those negotiating
    on behalf of the Chinese.

    WHO WAS IN THE CHINESE CONSORTIUM?

    [12.2] KEY PARTIES IN THE PROPOSAL INVOLVING THE SECOND SURVEYING
    AND DESIGNING INSTITUTE

    Mr Leo Moore of Taiwan

    Our investigations revealed that a key person was Mr Leo
    Moore, a citizen
    of the Republic of China (Taiwan). Mr Moore is a businessman,
    with
    interests in the Taiwanese fishing industry, who had made a
    number of
    visits to Papua New Guinea during 1991 and 1992.

    Chapter 12

    121

    Mr Moore was called to give evidence under oath on several occasions
    in
    the course of this investigation. We formed the view that he was a
    co-
    operative and reliable witness. His evidence shed considerable light
    on
    the events leading to the selection of the Chinese consortium.

    Outlet Year Ltd and Mr Leung Keung of Hong Kong

    Mr Moore stated that he had first become interested in Papua New
    Guinea
    in September 1990, after a meeting in Taiwan with another

  • Page 133 of 397

  • businessman,
    Mr Leung Keuno (hereafter referred to as Mr Leung).. Mr Leung is the
    head of a Hong Kong-based company known as Outlet Year Ltd, which
    was supposedly considering making large investments in Papua New
    Guinea. The meeting between Mr Moore and Mr Leung was arranged by
    Mr To Ken Chung (Mr Moore’s godfather and Mr Leung’s close friend)
    and Mr Stephen Zohr (one of Mr Moore’s business advisers).

    At that meeting it was agreed that an invitation would be extended
    to a
    group of government officials from Papua New Guinea to come to
    Taiwan
    to discuss business opportunities in Papua New Guinea.

    Business relationship between Outlet Year Ltd and the SSDI

    Mr Moore explained that Outlet Year Ltd had business connections
    with
    a number of government authorities in the Peoples’ Republic of China
    (ie
    mainland China); one of them being the Second Surveying and
    Designing
    Institute (SSDI).

    The SSDI is a civil engineering agency involved in design and
    construction
    of railways and highways. Mr Moore supplied the Ombudsman
    Commission with a brochure describing its activities. [EXHIBIT 102A]

    Cnapter 12

    122

    Mr Moore explained that, as a result of overtures made by Mr
    Leung, the
    SSDI had contacted Mr Moore on 27 January 1991. In a one page
    facsimile transmission, a representative of the SSDI
    indicated that they
    were a very strong and influential government company in
    China and that
    they were keen to go into business with Mr Leung and Mr Moore
    for the
    purpose of building a freeway in Port Moresby, which they had
    been
    informed about by Mr Leung. [EXHIBIT 53]

    OVERSEAS TRIP PAID FOR BY CHINESE CONSORTIUM

    [12.3] VISIT TO TAIWAN AND HONG KONG BY PAPUA NEW GUINEA

  • Page 134 of 397

  • PARLIAMENTARIANS IN FEBRUARY 1991: A MATTER OF CONCERN

    Mr Moore testified that on 6 February 1991 he purchased four
    return
    tickets from Port Moresby to Hong Kong, which were later
    picked up at
    the Cathay Pacific office in Port Moresby.

    After being invited to Taiwan and Hong Kong, a “delegation”
    from Papua
    New Guinea arrived in Taipei on 8 February 1991. The
    delegation
    comprised:

    the Minister for Transport, Mr Anthony Temo;

    the Member for Gulf Province, Mr Aaron Noaio;

    the Member for Sohe Open, Mr David Beu; and

    Chapter 12

    a member of the Official Personal Staff of the
    Minister for
    Fisheries & Marine Resources (who at that time was the
    Deputy Prime Minister Mr Akoka Doi) Mr Chris Maravis.

    The Ombudsman Commission interviewed Mr David Beu in
    connection
    with this trip and the evidence he gave corroborated that
    given by Mr
    Moore.

    [12.4] STATUS OF THE PNG DELEGATION

    Before we address the events that transpired during and after
    the trip,
    there is one important matter to emphasise: the Papua New
    Guinea
    “delegation” had no official status. Although the members of
    the group
    were, in a sense, representing the Government of Papua New
    Guinea, the
    delegation was privately sponsored. All the expenses,
    including airfares,
    accommodation and meals, were paid for either by Mr Leo Moore
    or
    Outlet Year Ltd.

  • Page 135 of 397

  • [12.5] PRIVATELY SPONSORED OVERSEAS TRIPS CAN BE UNLAWFUL

    It is important for all leaders of Papua New Guinea who
    contemplate
    privately sponsored trips to bear in mind that it is a
    requirement of the
    Leadership Code that permission from the Ombudsman Commission
    be
    obtained before accepting the benefits of such a trip.

    This is a principle of Papua New Guinea law that should also
    be
    considered by any person or company thinking about offering
    such a trip
    to a leader.

    Chapter 12

    124

    [12.6] THE MINISTER ALLOWED HIMSELF TO BE ENTERTAINED BY ONE OF
    THE COMPANIES BIDDING FOR THE PROJECT AT THE SAME TIME HE
    WAS PREPARING THE SHORTLIST

    The Ombudsman Commission is concerned that the Minister for
    Transport,
    Mr Temo, made his trip to Taiwan and Hong Kong and involved
    himself
    in negotiations for the Spring Garden Road/Poreporena Freeway
    project
    at the same time be was preparing the shortlist of
    prospective developers
    (see Chapter 9).

    The Ombudsman Commission emphasised earlier in this report
    that
    Ministers should not be preparing shortlists for public works
    projects. In
    this case, the Minister for Transport was not only preparing
    the shortlist,
    he was, at the same time, allowing himself to be wined and
    dined
    overseas, at the expense of one of the companies interested
    in getting the
    contract for construction of the freeway.

    When this sort of thing happens, it is very difficult to
    conclude that the
    decision-making process was legitimate, fair and proper.

    It is also difficult to say there was no bribery or
    corruption.

  • Page 136 of 397

  • [127] THE MINISTER FOR TRANSPORTS DEFENCE

    When we suggested in our preliminary report that it was wrong
    of Mr
    Temo to make an overseas trip, paid for by one of the
    companies bidding
    for the project, at the same time he was preparing a
    shortlist of
    prospective developers, he denied any impropriety. He said he
    did not
    realise it was a privately sponsored trip until after he
    accepted the
    invitation to go to Hong Kong:

    Chapter 12

    125

    “The trip to Taiwan and Hong Kong was organised by a Chris
    Maravis in Mr
    Akoka Dors office. Mr Doi was the Deputy Prime Minister so I took
    it that
    I was going on an official trip. later I realised that it was a
    PAP fishing trip
    paid by Mr Leo Moore and some fishing people.

    While in Taiwan and Hong Kong as I was not Minister for Fisheries
    so I was
    asked about Transport Projects and I said we have a 10 year plan
    that need to
    be completed. However, we did not have finance and manpower it
    was paid
    by Mr Leo Moore not short listed company.

    I did not prepare the final short list.

    While in Hong Kong I told the company representative to let the
    Prime
    Minister, Minister for Finance and the other senior ministers
    know of their
    investment proposal in PNG.

    According to me I did not hide anything and I told them, if you
    want to invest
    for the trip and accommodation while in Taiwan and Hong Kong. I
    did this
    after learning that it was a PAP fishing trip. Therefore, I

  • Page 137 of 397

  • notified the
    Ombudsman in writing about who was paying for the trip and
    accommodation
    while in Taiwan and Hong Kong. I did this after learning it was a
    PAP fishing
    trip.” [F.XHIBIT 257, page 3]

    The Ombudsman Commission, with respect, does not consider Mr Temo’s
    explanation to be satisfactory. We find it difficult to believe that
    a Minister

    of the State would legitimately travel overseas without knowing what
    the
    purpose of the trip was.

    As to the claim that he advised the Ombudsman Commission of the trip
    and who was paying for it, we refer to a letter dated 28 March 1991
    received by the Commission from Mr Temo:

    Mr Temo stated:

    ‘Thank you for your very helpful Leadership Manual received
    today. I note
    that I must declare to the Commission every time I leave for
    overseas be it
    official or unofficiaL

    I therefore wish to inform the Commission that from the 22
    February, 1991 until
    4 March, I was on an official visit paid for by M.T.L
    Organisation. This trip
    was approved by the National Government to lead a delegation to
    Taiwan.’
    [EXHIBIT 68B]

    Chapter 12

    126
    [12.8] POOR ADMINISTRATION BY THE MINISTER FOR TRANSPORT

    One thing is certain: irrespective of whether Ministers and
    other
    Government officials breach the Leadership Code when they

  • Page 138 of 397

  • accept
    benefits such as free travel, free accommodation and gifts
    from foreign
    enterprises, it is a very bad administrative practice.

    It undermines the integrity of the decision-making processes
    of
    Government. It creates the impression that to get Government
    approval for
    a project in Papua New Guinea, it is necessary to be on
    friendly terms
    with the right Minister. It attracts the wrong sort of
    foreign investors to
    Papua New Guinea. It creates a bad image of Papua New Guinea.

    If this sort of administrative practice continues, instead of
    honest and
    genuine investors coming to our country, we will be overrun
    by fly-by-
    night operators, only too willing to bypass normal procedures
    in the quest
    for easy money for themselves and not for the People of Papua
    New
    Guinea. Papua New Guinea has had enough of them already.

    Since it is not in the best interests of the People of Papua
    New Guinea
    and our country, such practices must be stopped at all costs.

    [12.9] WHAT HAPPENED DURING THE TRIP TO TAIWAN AND HONG KONG?

    Mr Moore testified that Messrs Temo, Noaio, Beu and Maravis
    spent three
    days in Taipei, followed by four days in Hong Kong.

    Three days in Taipei

    In Taipei, the members of the PNG “delegation” were
    entertained by Mr
    Moore.

    Chapter 12

    127
    Mr Moore testified that during this visit there was a lot
    of talk about road
    projects, particularly “the 8.8 km road in Port Moresby”,
    as well as other
    investment opportunities in Papua New Guinea. The Papua
    New Guinea
    people described their country as a good place to invest –
    particularly in

  • Page 139 of 397

  • mining, oil, fishery and forestry projects – but they said
    the road network
    was not very good and that is why Papua New Guinea is a
    poor country.

    Mr Moore told the Minister for Transport he would like to
    come to Papua
    New Guinea and see the country for himself.
    Four days in Hong Kong

    After spending three days in Taiwan the group from Papua
    New Guinea
    travelled to Hong Kong, leaving Mr Moore behind. Mr Moore
    stated that
    throughout their stay in Hong Kong, the group from Papua
    New Guinea
    was looked after by Mr Leung of Outlet Year Ltd. He said
    that, as it was
    Chinese New Year, much of the time was taken up in social
    activities and
    the group from Papua New Guinea was housed at the Sheraton
    Hotel.

    It was during this visit to Hong Kong that Mr Temo, in his
    capacity as
    Minister for Transport, signed a quite extraordinary
    document: a
    “memorandum of agreement” for the construction of the
    Southern
    Highlands-Kikori Road. [EXHIBIT 58]

    [12.10] THE MEMORANDUM OF AGREEMENT FOR THE CONSTRUCTION OF
    THE SOUTHERN HIGHLANDS – GULF ROAD

    The Minister for Transport, Mr Temo, signed this agreement
    in Hong Kong
    on 12 February 1991, on behalf of “the Ministry of
    Transport, National
    Government of Papua New Guinea”. The other signatory was
    Mr Leung
    Keung, who entered into the agreement on behalf of Outlet
    Year Ltd of

    Chapter 12

    128

    Hong Kong. The document was witnessed by Mr Aaron Noaio, the
    Member for Gulf Province and Mr To Ken Chung (Mr Leo Moore’s
    godfather).

  • Page 140 of 397

  • Terms of the agreement for the construction of the Southern
    Highlands
    Gulf Road

    The terms of this agreement, which appeared under the letterhead of
    Outlet Year Ltd, were as follows:

    ‘MEMORANDUM OF AGREEMENT

    ‘KNOW ALL MEN BY THESE PRESENTS:

    This Memorandum of Agreement is entered into and executed this
    12th day of
    February, 1991, by and between:

    Ministry of Transport, National Government of Papua New Guinea
    with
    principal offices of P.O. Box 457 Konedobu, National Capital
    District, Papua
    New Guinea represented by Hon. Anthony Temo, Minister for
    Transport
    (hereinafter referred to as NPG).

    and

    Outlet Year Limited, a duly registered Hong Kong Corporation
    with principal
    offices at No. 20, HOK Yuen Street, Block FL 3/F Hunghom,
    Kowloon, Hong
    Kong, herein represented by Mr Leung Keung, Managing Director
    (hereinafter
    referred to as HK).

    1NITNESSETH:

    WHEREAS, the National Government of Papua New Guinea has fully
    authorized NPG to implement an Infrastructure Development Plan

    WHEREAS, NPG is willing to undertake this job per engineering
    details and
    specifications, contained in the NPG’s Cost Study (Gulf-Southern
    Highlands
    Province – ERAVE to KEREMA [sic]).

    WHEREAS, NPG has found the credentials of HICG to be financially
    qualified
    and technically capable to execute this project in a manner
    consistent with the
    technical standards set forth by engineering standards.

  • Page 141 of 397

  • WHEREAS, HEW has offered to undertake construction of this
    project.

    NOW, THEREFORE, for and in consideration of the above premises
    and of the
    mutual covenants heretofor set forth, the parties have agreed,
    as they hereby
    agree, on the following terms and conditions:

    Chapter 12

    129

    1. PROJECT

    NAME Southern Highlands Kikori Road

    LOCATION From ERAVE to KIKORI

    SPECIFICATION AND INSPECTION
    Per Cost Study (Gulf-Southern
    Highlands Province – ERAVE to KEREMA)

    DURATIONFrom May 1st, 1991 to May 1st, 1993.
    BONUS AND PENALTY.

    2. CONTRACT PRICE : HKG shall submit within 60 days after
    signing of this Memorandum a price, to
    be forwarded to and acceptable to PNG.

    3. PAYMENT Payment plan to be negotiated between
    PNG and HKG on an equitable and
    acceptable basis to both parties

    4. PERFORMANCE Upon signing of Contract by both parties
    BOND MG shall provide to PNG a
    Performance Bond in the form of cash,
    bank guarantee or other form of
    guarantee acceptable to PNG, for an
    amount not less than 10% of the Contract
    value, to warrant the performance of
    EKG’s obligation under the Contract
    (Gulf-Southern Highland Province –
    ERAVE TO KEREMA). This

  • Page 142 of 397

  • Performance Bond shall be returned
    HKG without interest, when HKG shall
    have fulfilled its obligations under the
    Contract.

    5. FORCE MAJEURE HKG is not responsible for delay or non-
    performance of its contractual obligation
    to construct, caused by war, blockade,
    revolution, insurrection, civil commotion,
    riots, mobilization, strikes, Act of God,
    plague, or other epidemic, fire, flood,
    action or acts of government or public
    enemy.

    Chapter 12

    130

    6_ CANCELLATION & : PNG may cancel the Contract, and
    ALTERATION OF confiscate the Performance Bond,
    if
    CONTRACT IIKG is unable to deliver in
    accordance
    with the stipulated time schedule
    or
    breath of Contract.

    Postponement or alteration of the
    Contract if required, should be
    agreed
    by both parties in writing.

    IN WITNESS WHEREOF, the parties hereto have hereunto
    affixed their
    signatures at Hong Kong this 12th day of February
    1991.

    MINISTRY OF TRANSPORT

    [signed]

  • Page 143 of 397

  • HON. ANTHONY TEMO
    MINISTER FOR TRANSPORT

    WITNESS: MEMBER OF PARLIAMENT

    [signed]

    HON. AARON NOAIO
    MP For Gulf Province

    For and on behalf of

    OUTLET YEAR LIMITED

    [signed]

    Authorized Signature

    LEUNG KEUNG
    MANAGING DIRECTOR

    WITNESS:

    [signed]
    TO KEN CHUNG” [EXHIBIT 58]

    [12.11] THE AGREEMENT OF 12 FEBRUARY 1991 DID NOT MAKE SENSE

    Any person with a basic knowledge of contracts and the
    English language
    would realise that this document is very poorly drafted. The
    grammar is
    atrocious and, in places, the document just does not make
    sense. For

    Chapter 12

    131
    instanLe though the subject of the agreement is described
    in Clause 1 as
    “Southern Highlands Kikori Road from Erave to Kikori”,
    there are three sai
    other references in the document to the “Erave to Kerema”
    Cost Study or
    Contract.

  • Page 144 of 397

  • 1111

    The Ombudsman Commission is left wondering whether the
    parties to this
    agreement actually knew what they were agreeing to. In
    view of this, it is
    very doubtful whether the agreement could have ever been
    regarded as
    valid or enforceable.

    But that does not, in our view, excuse the Minister for
    Transport for his
    actions in signing this agreement.

    [12.12] THE PROPRIETY OF THE MINISTER FOR TRANSPORTS ACTIONS

    In the opinion of the Ombudsman Commission, it is very
    embarrassing for
    our country when persons holding official positions sign
    documents as
    amateurish as the agreement for the construction of the
    Southern
    Highlands-Kikori Road. It is terrible administration for
    any office-holder,
    particularly a Minister of the State, to unilaterally
    decide to enter into such
    agreements.

    The Ombudsman Commission believes that whenever any
    Minister goes
    overseas to engage in negotiations on behalf of Papua New
    Guinea, he
    should be accompanied by at least one senior Departmental
    adviser. If
    that had happened in this case, we have no doubt the
    Minister for
    Transport would have been advised not to sign the
    agreement for the
    construction of the Southern Highlands-Guff Road.

    Having said that, the Ombudsman Commission still finds it
    remarkable
    that, during the course of being entertained by foreign
    businessmen, and

    Chapter 12

    132

    while outside Papua New Guinea, the Minister for Transport

  • Page 145 of 397

  • would have
    signed an agreement for the carrying out of an extremely
    important
    national road project without the advice or knowledge of the
    Department
    of Transport or the Government he was supposed to be
    representing.

    This sort of thing simply should not happen. It raises
    questions of legal
    authority and breeds the atmosphere and environment ripe for
    bribery
    and corruption.

    [12.13j COULD THE MINISTER’S ACTIONS BE JUSTIFIED?

    During the course of this investigation, the Ombudsman
    Commission
    questioned the former Minister for Transport on his actions.
    He agreed he

    had been to Hong Kong and signed the Memorandum of
    Agreement. In
    his view, however, he had done nothing improper. His
    explanation was

    that it was not intended to be a binding document:

    “While in Hong Kong I signed a couple of pages
    documents as memorandum
    of understanding. This a Chinese Government policy that
    before they leave
    to go out of R.O. China it is a mandatory that they
    must have some form of
    agreement of some sort so they be allowed to leave
    their country. They had
    no choice but to show their Government information why
    they were leaving
    for PNG. I was authorised by NEC to negotiate on Burns
    Peak Road.

    Therefore, I had some authority to negotiate not make a
    decision. The
    Department was made known as usual.”
    [EXHIBIT 257, pages 3-4]

  • Page 146 of 397

  • In the opinion of the Ombudsman Commission, that is not a
    satisfactory
    explanation.

    A Minister should not sign any document which purports to
    bind himself
    or his Department or the Government of Papua New Guinea to
    any course
    of action unless he has been expressly and lawfully
    authorised to do so.
    L

    Chapter 12

    133

    There is no evidence, as Mr Temo claims, that he was
    authorised by the

    National Executive Council to conduct any negotiations.
    Nor is there any

    evidence he advised the Department of Transport what he
    was doing.

    The Secretary for Transport’s evidence was to the
    contrary. 11

    The Minister for Transport had no authorisation to conduct
    negotiations 11

    concerning the Southern Highlands-Gulf Road or the Spring
    Garden

    Road/Poreporena Freeway project. He had no right to sign
    this

  • Page 147 of 397

  • document He signed it without the advice or knowledge of
    his

    Department or the National Executive Council. tt was very
    wrong of him to

    sign it.

    [12.14] OTHER EVIDENCE OF OUTLET YEAR LTD’S INTEREST IN PAPUA NEW

    GUINEA

    a

    Mr Leo Moore’s oral evidence of Outlet Year Ltd’s interest
    in Papua New

    Guinea is corroborated by three documents that the
    Ombudsman

    111
    Commission has obtained:

    a
    (i) A letter from Outlet Year Ltd. dated 12 February
    1991, to the then

    Prime Minister. Mr Rabbie Namaliu. The letter states:

    ‘Your Excellency:

  • Page 148 of 397

  • A delegation from your Government headed by
    Hon. Anthony Temo,
    Minister for Transport, approached our Company
    seeking funds and
    technical assistance to develop – an
    infrastructure Development Plan –
    in your country Papua New Guinea. We are
    interested to invest up to
    US Dollars 5 billion in Papua N. G.

    As per our meetings, [with Mr Terns)] we wish
    to design and build
    Southern Highlands ICikori Road and Burns Peak
    Road in Port Moresby.
    We shall build these roads under a Turnkey
    arrangement, which means
    we shall supply manpower as well as financing.
    111

    Should your Government endorse this idea,
    please send me an
    invitation so our delegation consisting of the
    undersigned and Mr
    Steven Zohr and Mr Leo Moore, could assist your
    Country in the
    nearest future.

    Chapter 12

    1111

    134

    We are taking this as a matter of urgency and priority,
    and hope to
    meet you personally.

    Respectfully yours,
    [signed]
    LEUNG ICEUNG
    MANAGING DIRECTOR”

  • Page 149 of 397

  • This letter was marked:

    “c.c. His Excl. Ted Biro [sic], Deputy Prime Minister
    His Excl. Sir Michael T. Samare, [sic], Foreign Minister
    His Excl. Hon. Paul Bora [sic], Finance Minister
    His Excl. Hon Anthony Temo, Minister for Transport’.
    [EXHIBIT 57]

    (ii) A letter from Outlet Year Ltd dated 13 February 1991 to Mr
    Temo
    (also addressed to Deputy Prime Minister Mr Ted Diro, who was
    described as the Acting Transport Minister).

    This letter was headed “Application for pre-qualification of
    Southern
    Highlands Kikori Road’ and states:

    “We wish to design and construct Southern Highlands/
    Kikori Road in
    Port Moresby [sic] under a Turnkey arrangements which
    means we will
    supply manpower and finance’. [EXHIBIT 59]

    (iii) Another letter from Outlet Year Ltd dated 13 February 1991 to
    Mr
    Temo (also addressed to Mr Diro).

    This letter was headed “Application for Pre-qualification of
    Bums
    Peak Road” and states:

    ‘We wish to design and construct Burns Peak Road in Port
    Moresby
    under a Turnkey arrangements which means we will supply
    manpower
    and finance”. [EXHIBIT 60]

    Chapter 12

  • Page 150 of 397

  • 135

    [1215] THE TRIP TO TAIWAN AND HONG KONG WAS A VERY BAD PIECE OF
    ADMINISTRATION

    The three letters from Outlet Year Ltd were written at the
    time of the
    Minister for Transport’s visit to Hong Kong. When the
    letters are
    considered, together with the signing of the “Memorandum
    of Agreement”
    for the Southern Highlands-Gulf road, they show that, by
    shortlisting Outlet
    Year Ltd, the Minister had given that company favoured
    treatment.

    It would not be unreasonable for any person knowing these
    facts to
    wonder whether the Minister’s actions were a result of his
    trip to Hong
    Kong and Taiwan.

    The Minister had compromised his own impartiality by
    allowing his airfares
    and accommodation to be paid by foreign enterprises at a
    crucial time in
    the decision-making process.

    By taking it upon himself to become actively involved in
    the selection of a
    contractor for the Spring Garden Road/Poreporena Freeway
    project the
    Minister had a duty, as a matter of administration, to be
    totally impartial in
    his evaluation of the competing proposals. Not only that,
    he had to be
    seen to be totally impartial and objective.

    The Minister for Transport failed, in our view, to fulfil
    this basic
    administrative duty. The trip to Taiwan and Hong Kong and
    the signing a
    of the agreement on 12 February 1991 was a very bad piece
    of
    administration.

  • Page 151 of 397

  • Chapter 12

    [12.16] THE FINANCIAL STATUS OF OUTLET YEAR LTD136

    The three Outlet Year Ltd letters referred to
    earlier give the impression
    that the company is large and influential, with
    huge financial resources at
    its disposal. Mr Leo Moore’s evidence, however,
    suggests that this was far
    from being the case.

    Mr Moore testified that Outlet Year Ltd was quite
    a small company which
    simply did not have the sort of money to invest in
    Papua New Guinea it
    made out it had. He said this had first been
    brought to his attention in a
    facsimile message received on 27 March 1991 from a
    business adviser, Mr
    Stephen Zohr. [EXHIBIT 68]

    Mr Zohr was concerned about the uncertain
    financial background of Outlet
    Year Ltd and advised Mr Moore to be cautious in
    making any decisions
    about investing in Papua New Guinea.

    [12.17] OUTLET YEAR LTD HAD NO EXPERTISE IN ROAD PROJECTS
    AND NO
    EXPERIENCE IN PAPUA NEW GUINEA

    Mr Moore further testified that Mr Leung, of
    Outlet Year Ltd, had realised,
    soon after he wrote those letters, that his
    company would find it very
    difficult to raise the finances necessary to
    undertake projects such as
    Spring Garden Road and the Southern Highlands-Gulf
    Road. Mr Moore
    stated that the Minister for Transport, in all of
    his negotiations, had insisted
    on a 10% performance bond being given to the
    Government of Papua

  • Page 152 of 397

  • New Guinea.

    Nevertheless, Outlet Year Ltd continued to be
    involved in the negotiations,
    at least until July 1991. And it was not until
    September 1991 that the
    company formally dropped out of the negotiations
    (see Chapter 13).

    Chapter 12

    137

    The Ombudsman Commission was unable to question Mr Leung in
    the
    course of this investigation. However, on the basis of
    evidence available,
    we are satisfied that Outlet Year Ltd was quite a small
    company with no
    expertise in road construction or design and no prior
    experience in Papua
    New Guinea.

    THE MINISTER FO9 TRANSPORT AND MR LEO MOORE

    [12.18] MR LEO MOORE’S FIRST VISIT TO PAPUA NEW GUINEA

    Mr Moore first came to Papua New Guinea in May 1991. He was
    accompanied by his wife, Ida Moore, and Mr Leung of Outlet
    Year Ltd.
    They were met at Jacksons Airport by the four men who formed
    the
    delegation to Taiwan and Hong Kong in February 1991. Mr
    Moore said
    that on the second day of their visit, they had a meeting
    with the Minister
    for Transport to discuss the Spring Garden Road project. The
    cost was
    estimated to be US$50 million.

    The Minister wanted the Outlet Year consortium to build the
    road first and
    to pay them 5 to 10 years later. But Mr Leung was not very
    interested.
    In fact, he went home early, while Mr and Mrs Moore stayed
    behind for
    another week. During this time, the Minister introduced Mr
    Moore to the
    then Deputy Prime Minister and Minister for Fisheries and
    Marine

  • Page 153 of 397

  • Resources, Mr Akoka Doi, and various other investment
    projects were
    discussed.

    Chapter 12

    138

    [12.19] MINISTER FOR TRANSPORT APPEALS FOR LOAN FUNDS ON BEHALF
    OF PAPUA NEW GUINEA

    Before he returned to Hong Kong, Mr Moore was handed a
    letter from the
    Minister, under Ministry of Transport letterhead, in
    which he asked Mr
    Moore to arrange a loan to develop Papua New Guinea’s
    “ten year
    development plan”. The Ombudsman Commission obtained a
    copy of this
    letter. It is dated 24 May 1991 and reads as follows:

    “Mr Leo Moore,

    Papua New Guinea is a Country, full of all Natural
    Resources renewable and
    non renewable.

    At this stage Papua New Guinea requires Financial
    assistance badly.

    Our Economy will pick up in 1993 onwards.

    Until then Papua New Guinea requires at least US$50
    million dollars in
    infrastructure development in the next five (5)
    years from 1992 or sooner the
    better.

    Should you require my department’s ten (10) year
    development plan I will bring
    it with me.

    By this letter I am appealing on behalf of PNG
    Government that you arrange
    for a loan in kind or cash to develop and implement
    our ten (10) year

  • Page 154 of 397

  • development plan.

    Should you arrange for same, please try to make the
    loan finance cheaper than
    Asian Development bank and World Bank.

    I thank you and your group in advance, with kind
    regards.

    [Signed)
    ANTHONY TEMO
    Minister for Transport” [EXHIBIT 871

    The purpose of this letter was to enable Mr Moore to go
    back to Taiwan
    with some proof he had negotiations with a Minister of
    the State in Papua
    New Guinea.

    chapter 12

    139 II

    [12.20] MR MOORE RETURNS TO TAIWAN AND NEGOTIATES DIRECTLY WITH
    THE SSDI

    Mr Moore testified that, on his return to Taiwan in May
    1991, he contacted
    Mr Leung in Hong Kong and told him that, despite Mr Leung’s
    reservations, he was still very keen to see the Port Moresby
    road project
    go ahead, with the assistance of the SSDI.

    Mr Moore then started (with Mr Leung’s knowledge) to
    negotiate directly
    with Mr Lee Chong Chan, who was the link-man between the
    SSDI and
    the Government in Bejing. These negotiations resulted in the
    Bejing
    Government approving a visit to Port Moresby by
    representatives of the
    SSDI in July 1991.

    [12.21] ANOTHER VISIT TO HONG KONG BY THE MINISTER FOR TRANSPORT

  • Page 155 of 397

  • Prior to the visit to Port Moresby by the SSDI observation
    group, the
    Minister for Transport made another unofficial trip to Hong
    Kong, at Mr
    Leo Moore’s expense.

    This visit took place between 7 and 14 June 1991. The
    Minister was
    accompanied by his wife, whose airfare was paid for by Mr
    Leo Moore;
    the Minister for Transport had his own airfare on this
    occasion. The
    Minister and his wife again stayed at the Sheraton Hotel and
    all their
    expenses in Hong Kong, including meals and accommodation,
    were paid
    for by Mr Leo Moore.

    Chapter 12

    140

    [12.22] MINISTER FOR TRANSPORT HOLDS PRIVATE DISCUSSIONS WITH
    TOPBAY INVESTMENT LTD IN HONG KONG

    During this visit to Hong Kong, the Minister for Transport
    met with Mr Leo
    Moore and six representatives of a Hong Kong-based company
    called
    Topbay Investment Ltd.

    Mr Moore testified they had discussed the Spring Garden Road
    project for
    almost two days. Mr Moore arranged the meeting himself. By
    this stage,
    he had formed the view that Outlet Year Ltd may not have the
    ability to
    undertake the Spring Garden Road project. He had had
    previous business
    dealings with Topbay Investment Ltd and saw them as a good
    substitute
    for Outlet Year Ltd.

    The Ombudsman Commission asked Mr Moore whether Topbay
    Investment Ltd had any experience in road construction or
    design: they
    did not. The company had never done any business in Papua
    New
    Guinea and none of the company’s principals had ever been to

  • Page 156 of 397

  • Papua
    New Guinea.

    [12.23] EVIDENCE OF THE MINISTER FOR TRANSPORT’S PRIVATE
    DISCUSSIONS IN HONG KONG

    In the course of this investigation the Ombudsman Commission
    obtained
    from Mr Temo, a copy of a letter from Topbay Investment Ltd
    addressed
    to the Secretary for Transport, dated 14 June 1991. The
    letter reads:

    Chapter 12

    141

    “My Dear Secretary,

    Re: Burns Peak Freeway

    Please enclose our proposal as requested.

    We would like to show our interest to support
    funding this Freeway project
    subject to all details of construction plan will be
    released to us as soon as
    possible.

    Funding [illegible] US$50,000,000.00 (US Dollars,
    Fifty Million) will be available
    on receipt of our acceptance notification from PNG
    Government.

    Final terms and condition to be discussed on
    acceptances of our proposaL

    Note: The Company has changed from Outlet Year
    Company to Topbay
    Investment Ltd.
    Thank you and we are waiting your favourable reply.

    Yours sincerely,
    [Signed]
    W.C. Dave Kwok
    Group General Manager”
    [EXHIBIT 89]

  • Page 157 of 397

  • The date of this letter coincides with the date of the
    Minister’s visit to
    Hong Kong, which the Commission has confirmed by checking
    the
    Minister’s passport.

    We are satisfied, therefore, that the evidence given by Mr
    Leo Moore as
    to the Minister’s visit to Hong Kong between 7 and 14 June
    1991 is true
    and correct.

    [1224] WRONG CONDUCT BY THE MINISTER FOR TRANSPORT

    We have emphasised how important it is for Ministers of
    the State not to
    go on privately sponsored overseas trips, especially when
    they are
    provided by foreign enterprises which may expect to reap
    rewards by
    showing hospitality to a Minister.

    Chapter 12

    111

    142

    In our preliminary report, we suggested it was wrong for Mr
    Temo to
    make this second trip to Hong Kong. His response was as
    follows:

    “I met the expenses for my second trip to Hong Kong,my
    wife’s expenses were
    paid for by Mrs L Moore and were on a family business
    trip.
    While there I may have talked to somebody about Burns

  • Page 158 of 397

  • Peak as a total 10 year
    plan. However, the trip was for my private co. business
    and I have also advised
    the Ombudsman Commission about that trip.” [EXHIBIT 257,
    page 4]

    Mr Temo’s excuse that he was on a family business trip is
    not considered
    acceptable. As the Minister who had assumed primary
    responsibility for
    the Spring Garden Road/Poreporena Freeway project, he
    compromised
    his impartiality by accepting the benefits associated with
    this trip from an
    associate of one of the companies bidding for the project.
    There is also
    no evidence that the Department of Transport knew anything
    about the
    trip or the negotiations the Minister had with Topbay
    Investment Ltd.

    In the circumstances, it was wrong of Mr Temo to conduct
    these
    negotiations. It was another very bad piece of
    administration.

    CHINESE CONSORTIUM VISITS PORT MORESBY

    [12.25] SSDI VISITS PORT MORESBY IN JULY 1991

    An observation group from the Second Surveying & Designing
    Institute
    visited Port Moresby from 6 to 10 July 1991 – just a week
    before the
    Ministerial Committee decided to favour their proposal. The
    group, which
    consisted of about seven engineers, was led by Mr Sun Young
    Hse, who
    described himself as the “Executive Director on behalf of
    the Observation
    Group of the Second Surveying and Designing Institute
    Ministry of
    Railways”. [EXHIBITS 95, 96, 102B].

  • Page 159 of 397

  • Chapter 12

    143

    Mr Moore, his wife Ida Moore, Mr Leung and Mr Leung’s son
    also
    travelled to Port Moresby for the occasion. Mr Moore said
    that his group
    and the SSDI group were met at the Port Moresby Travelodge
    Hotel by
    the Minister and they spent considerable time inspecting the
    route of the
    Spring Garden Road/Poreporena Freeway project.

    12.26] CONFUSING ASPECTS OF THE OBSERVATION GROUP’S VISIT

    The Ombudsman Commission wonders why Mr Leung of Outlet Year
    Ltd
    would have made this trip to Port Moresby, in view of Mr
    Moore’s
    evidence that Mr Leung had already realised his company
    didn’t have the
    financial capability to undertake the project. There are also
    other aspects
    of the SSDI’s visit that the Ombudsman Commission finds very
    confusing:

    Evidence obtained by the Commission suggests that
    another
    agreement was signed by the Minister for Transport
    during
    the visit of the Chinese consortium. However, no such
    agreement appears in the files of the Department of
    Transport.

    We are also confused by the fact that two different
    proposals
    for the design, finance and construction of the freeway
    appear to have been submitted around this time on
    behalf
    of the Chinese consortium.

    Chapter 12

  • Page 160 of 397

  • 144

    [12.27] WERE ANY AGREEMENTS SIGNED DURING THE VISIT BY THE
    CHINESE CONSORTIUM?

    Mr Leo Moore testified that during the July 1991 visit by
    the Chinese
    consortium, the Minister for Transport signed a document,
    about two or
    three pages in length, which summarised the financial
    terms on which the
    Government of PNG would engage the consortium.

    The document was also signed by Mr Zhu Chuanhua, a member
    of the
    SSDI observation group. [A copy of a business card in the
    name of this
    person is located in the Department of Transport’s files:
    EXHIBIT 102B]

    According to Mr Moore, the signing of this agreement took
    place at the
    Port Moresby Travelodge Hotel.

    Mr Moore described this document as a “pre-agreement”. The
    Ombudsman Commission has tried unsuccessfully to obtain a
    copy of it.
    The document is not in the Department of Transport’s
    files. But, there is
    a reference to it in a letter to the Minister for
    Transport from the China
    Huashi Enterprises Corporation dated 6 September 1991.

    This letter reads:

    Your Excellency,

    Attached please find a CERTIFICATE issued by Bank of
    China Chengdu
    Branch, which we hope will provide you with a brief
    description of our firm’s
    financial status. We, China Huashi Enterprises Corp,
    (CHECO) joint with the
    Second Surveying & Designing Institute, Ministry

  • Page 161 of 397

  • Railways are very willing
    and fully capable to undertake the surveying,
    designing and construction of the
    proposed Spring Garden Road Link project

    In order to release current traffic congestion as
    soon as possible based on
    suggestion made by observation group of the Second
    Surveying & Designing
    Institute, Ministry of Railways, the proposed road
    will be constructed in
    following stages.

    Chapter 12

    145

    1. completion of engineering survey, design
    and geological work of above
    road project;

    construction of the first of a twin tunnel
    through the Burns Peak;

    3. construction of the missing sections (i.e.
    nonexisting sections) along the
    proposed route from Moresby Harbour in
    Konedobu to Jackson Airport;

    4. construction of the second of the twin
    tunnel and upgrading the
    existing road to 4-lane highway.

    If you agree the above-mentioned arrangement in
    principle, we intend to sign
    a main contract of contracting the Spring Garden
    Road Link project with you
    based on the Pre-agreement signed by you and Mr
    Zhu Chuanhua in P.N.G.
    And then to sign execution sub-project contract
    stage by stage, and provide you
    Bank Guarantee according to the stipulization of
    sub-project contract

    Please do not hesitate to contact us should you
    desire more information about

  • Page 162 of 397

  • our firm or clarification of the points in this
    letter.

    With best regards.

    Yours sincerely,

    Liu Shouning Mau Shesheng
    Deputy General Manager Second Surveying
    & Des-
    China Huashi Enterprises Corp. igning
    Institute, Ministry
    of
    Railways.” [11XIIIBTY 106]

    [12.28] WHAT IS THE CHINA HUASHI ENTERPRISES CORPORATION?

    Mr Leo Moore stated that this was another agency of the
    Peoples’

    Republic of China – a Government company closely linked
    with the SSDI.

    In Mr Moore’s view it was not unusual that the letter
    of 6 September 1991

    had come from it, rather than the SSDI, because the
    SSDI is not itself

    authorised to enter into contracts outside China. Only
    a company such as

    the China Huashi Enterprises Corporation can do this,
    he said.

    Chapter 12

    146

  • Page 163 of 397

  • [12.29] THE MINISTER HAD SIGNED A PRE-AGREEMENT

    The letter of 6 September 1991 confirms Mr Moore’s evidence
    as to the
    signing of some form of “pre-agreement” by the Minister for
    Transport
    during the visit of the SSDI in July 1991.

    When we made this finding in our preliminary report, it was
    not disputed
    by Mr Temo.

    In the opinion of the Ombudsman Commission it was wrong of
    Mr Temo
    to sign any “pre-agreement’. He had no authorisation from
    the National
    Executive Council to conduct negotiations, let alone sign an
    agreement.
    Even the so-called Ministerial Committee on Spring Garden
    Road had not
    authorised its signing. The Minister signed the agreement
    without the
    knowledge or advice of his Department.

    CONFUSION CAUSED BY LODGMENT OF DIFFERENT PROPOSALS

    [12.30] WHAT PROPOSALS WERE ACTUALLY SUBMITTED TO THE
    DEPARTMENT OF TRANSPORT DURING THE COURSE OF THE SSDI’S
    VISIT TO PORT MORESBY?

    As we noted in Chapter 11, it has been impossible to
    precisely ascertain
    which proposals were considered by the Ministerial Committee
    when it
    decided that the project be awarded to the Chinese
    consortium. Most of
    the proposals were lost after they were left in the Minister
    for Transport’s
    office, and the Department of Transport did not keep copies
    of them.

    Chapter 12

    147

    The confusion was made worse by our discovery of two
    different
    proposals on behalf of the Chinese consortium.

  • Page 164 of 397

  • Of course, it must be appreciated that whenever the term
    “Chinese
    consortium” is used in this report there is bound to be some
    confusion.
    This cannot be avoided because the composition of the
    consortium kept
    changing.

    Even with the benefit of hindsight it has been very
    difficult to ascertain
    which companies comprised the consortium at different times.
    Nevertheless, it is appropriate to always refer to the loose
    grouping of
    companies and individuals as ‘the Chinese consortium”
    because, despite
    frequent changes in its composition, it usually had some
    common
    elements, viz the SSDI and Mr Leo Moore.

    [12.31] THE PROPOSAL BY OUTLET YEAR LTD AND THE SSDI

    The files of the Department of Transport show a joint
    proposal being
    made by Outlet Year Ltd and the SSDI. The proposal was
    submitted
    under cover of a letter on SSDI letterhead addressed to the
    Secretary for
    Transport.

    This letter is undated. Also, there is no date-received
    stamp on it, which
    makes it doubly difficult to determine when it was
    submitted. [EXHIBIT 95]

    In the course of his interrogation by the Ombudsman
    Commission, Mr Leo
    Moore indicated that this letter had been typed on 8 or 9
    July 1991 at the
    Port Moresby Travelodge Hotel. It is poorly written and
    difficult to
    understand. It reads:

    Chapter 12

    148

    “Dear Sir,

    OBSERVATION REPORT (Draft)

  • Page 165 of 397

  • ON A PROPOSED FREEWAY PROJECT FROM PORT
    MORESBY TO JACKSON’S AIRPORT IN PNG

    It is really a pleasure to send you the Observation Report
    (Draft) on a proposed
    freeway project from Port Moresby to Jackson’s Airport in PNG.
    After having
    received your invitation letter and scrutinizing all relevant
    documents available,
    we, the Second Surveying and Designing Institute, Ministry of
    Railways P.ILC,
    immediately sent a observation group to your beautiful Country,
    (4 Senior
    Engineers and a Senior economist), together with Mr Leung Keung
    (Managing
    Director of Outlet Year Limited) and his partly. From July 6,
    arriving day, to
    July 10, we have made a on-the-spot investigation to the
    proposed freeway
    project. The Observation Report (draft) is attached to the
    Financial Proposal.

    The total project including the tunnel could cost almost US$50
    million are
    included. We believe it is unwise at this stage because the
    traffic lights can
    function just as effectively, but off cause it is negotiable.

    Hence, your government gives the approval of the construction
    of this project
    at a total cost of US$50 million which will become a loan to
    the Government
    in principle with the following Principal terms and conditions.

    Borrow: The Independent State of PNG on behalf of the
    Spring Garden Toll Road Corporation.
    Lender, The Bank of China and our Corporation
    Maturity: 10 years
    Grace Period: 3 years (including construction period)
    Amount: US$50 million (approx K million)
    Interest Rate: Nil
    Commitment Fee: Nil
    Management Fee: Nil
    Performance Bond 10% to be issue by the Bank of China.

    We hope all these reports and conditions for the funding are
    acceptable for
    your requirement.

    With Best Regards.
    Yours faithfully
    [Signed]
    MOORE’S INVESTMENT GROUP
    Sun Young HSE (Executive Director)

  • Page 166 of 397

  • On Behalf of
    Observation Group of
    The Second Surveying and Designing
    Institute
    Ministry of Railways.” [palIBIT 95]

    This undated letter was accompanied by an “Observation Report’. It
    states:

    Chapter 12

    149

    “This proposal has been prepared in response to an
    invitation from the
    Department of Transport to Outlet Year Ltd to submit
    a proposal for the
    development of the Spring Garden Road through BOT
    system…Outlet Year Ltd
    in joint partnership with the Ministry of Railways of
    People’s Republic of
    China will assume full responsibility to the
    Department of Transport for the
    successfully completion of the required services from
    planning, design,
    financing and implementation.” [EXHIBIT 951

    Curiously, most of this twenty-eight page “observation
    report’ was almost
    exactly the same (i.e. word-for-word) as another document
    the
    Ombudsman Commission obtained during the investigation.
    This other
    document is entitled “Spring Garden Road through BOT
    System Technical
    Proposal Submitted by Topbay Investment Limited Kowloon
    Hong Kong
    June 1991”. [EXHIBIT 91]

    [12,32] THE PROPOSAL BY TOPBAY INVESTMENT LTD

  • Page 167 of 397

  • The “Technical Proposal” in the name of Topbay Investment
    Ltd is not in
    the files of the Department of Transport. The Ombudsman
    Commission
    was not aware of its existence until it was produced under
    summons by
    Mr Temo. Although the greater part of this document
    [EXHIBIT 91] is
    exactly the same as the “Observation Report’ submitted by
    Outlet Year Ltd
    [EXHIBIT 95] there are significant differences between the
    two documents.

    [12.33] DIFFERENCES BETWEEN TOPBAY PROPOSAL AND THE OUTLET YEAR
    PROPOSAL
    11

    The most obvious difference is in the identity of the
    proponents. Whereas
    the “Observation Report” in the possession of the
    Department of Transport
    refers to Outlet Year Ltd and the SSDI, the document we
    obtained from
    the Minister for Transport states, in the corresponding
    paragraphs:

    Chapter 12

    150

    “This proposal has been prepared in response to an
    invitation from the
    Department of Transport to Topbay Investmented [sic] to
    submit a proposal for
    the development of the Spring Garden Road through the
    BOT system… Topbay
    Investmented [sic] in joint partnership with the
    Ministry of Foreign Economic
    Relations and Trade of the People’s Republic of China
    will assume full
    responsibility to the Department of Transport for the
    successfully completion
    of the required services from planning, design,
    financing and implementation.”
    [EXHIBIT 91]

  • Page 168 of 397

  • It will be observed that not only is there a different Hong
    Kong -based
    company referred to here, there is also a different agency
    of the Chinese
    Government: the Ministry of Foreign Economic Relations and
    Trade, rather
    than the Ministry of Railways. And at another point in the
    Topbay
    Investment Ltd document, there is a reference to yet another
    mysterious
    entity called the “China Guangzhou International Economic
    and Technical
    Co-operation Company”. [EXHIBIT 91, third last page]

    The “Financial Proposals” included in the two documents are
    also different.
    [Compare EXHIBIT 95, folios 96-101 with the last 3 pages of
    EXHIBIT 91.]

    However, the Topbay and Outlet Year proposals do have some
    things in
    common. They are equally vague and poorly drafted and they
    both
    contain bald assumptions about involvement of Motu-Koita
    landowners in
    the project. They both assume (alarmingly) that as part of
    the deal, the
    Chinese consortium will be awarded contracts for other major
    road
    projects in Papua New Guinea.

    [12.34] THE MYSTERY SURROUNDING THE TWO DIFFERENT PROPOSALS ON
    BEHALF OF THE CHINESE CONSORTIUM IS A MATTER OF SERIOUS
    CONCERN

    Although the bulk of the two proposals was exactly the same,
    they were
    in fact two separate documents. The Ombudsman Commission is
    mystified
    and seriously concerned by the fact that only one of the
    proposals was
    in the possession of the Department of Transport.

    Chapter 12

  • Page 169 of 397

  • 151

    It is also a mystery why the Topbay Investment Ltd Technical
    Proposal
    was linked with a Ministry of the Chinese Government different to
    the one
    which had consistently been referred to in earlier documentation.

    Even after closely examining the files of the Department of
    Transport and
    questioning two of the key persons in the negotiations at length
    (i.e. the
    Minister for Transport and Mr Leo Moore) it is impossible for us to
    say
    exactly what negotiations had taken place, when they took place and
    with
    whom.

    The mystery surrounding these two proposals is a small indication of
    how
    unprofessionally the whole negotiating process was being handled. tt
    was
    nothing short of a farce.

    The sad thing is that a group of well-intentioned foreign
    businessmen and
    representatives of the Government of the People’s Republic of China,
    were
    being given false expectations by a Minister of the State.

    The Minister was acting without the advice of his Department and had
    assumed far too much control over a decision-making process that
    should
    have been carried out objectively and fairly by other bodies using
    the
    normal and lawful procedures under the Public Finances (Man -gement)
    Act and other laws regulating public works projects (see Part Ill of
    this
    report).

    Chapter 12

    152

  • Page 170 of 397

  • [12.35] WHAT IMPRESSION WAS GIVEN TO THE CHINESE CONSORTIUM BY
    THE END OF THEIR VISIT IN JULY 1991?

    The Ombudsman Commission has no doubt that the observation
    group
    of the SSDI left Port Moresby at the end of their visit in
    July 1991 with the
    firm belief that, subject to confirmation of financing
    arrangements such as
    the 10% performance bond, they had “won” the contract for
    the Spring
    Garden Road/Poreporena Freeway project.

    This is evident from the undated letter to the Secretary for
    Transport which
    the SSDI delivered just before its departure. It stated:

    “Hence, your government gives the approval of the
    construction of this project
    at a total cost of US$50 million…”. [EXHIBIT 95, page
    1]

    The letter to the Minister for Transport from the China
    Huashi Enterprises
    Corporation of 6 September 1991 was in similar terms:

    “If you agree the above-mentioned arrangement in
    principle, we intend to sign
    a main contract of contracting the Spring Garden Road
    Link project with you
    based on the Pre-Agreement signed by you and Mr Zhu
    Chuanhua in PNG.”.
    [EXHIBIT 106, page 2]

    The Ombudsman Commission questioned Mr Leo Moore as to his
    view of
    the situation at the end of the observation group’s visit.
    He testified that
    the group appreciated the Minister’s decision had to be
    ratified by the
    National Executive Council. But they understood this to be
    only a formality.
    The Minister had told them he foresaw no problems. As long
    as they
    could arrange for a bank guarantee of the performance bond,
    the final
    contract would be signed.

  • Page 171 of 397

  • Chapter 12

    153

    IMPROPER RELATIONSHIP BETWEEN THE MINISTER AND THE CHINESE
    CONSORTIUM

    [12.36] SUMMARY OF THE RELATIONSHIP BETWEEN THE MINISTER FOR
    TRANSPORT AND THE CHINESE CONSORTIUM PRIOR TO THE
    MINISTERIAL COMMITTEE MEETING OF 18 JULY 1991

    In light of the evidence outlined above, the Ombudsman
    Commission is
    satisfied that, prior to the meeting of the Ministerial
    Committee on 18 July
    1991, the Minister for Transport had formed a very close
    association with
    members of the Chinese consortium.

    In particular we draw attention to the following
    unsatisfactory aspects of
    that relationship:

    1. The Minister had twice been on all-expenses-paid
    overseas trips to
    personally negotiate deals concerning the Spring Garden
    Road/Poreporena Freeway project and other national road
    projects.
    Both trips were paid for by one of the key persons
    involved in the
    bid by the Chinese consortium.

    2. On the first of these trips, the Minister signed a
    contract for
    construction of the Southern Highlands-Kikori Road with
    a company
    that was part of the Chinese consortium. He did this
    without
    authorisation and without the advice or knowledge of the
    Department of Transport.

    3. The first trip took place at the same time the Minister
    himself was
    preparing the shortlist for the Spring Garden Road/

  • Page 172 of 397

  • Poreporena
    Freeway project.

    Chapter 12

    154

    4. The Minister invited representatives of the Chinese
    consortium to
    Port Moresby on two separate occasions before the Ministerial
    Committee (which he chaired) made its decision on which
    consortium to favour. On both occasions the Minister engaged
    in
    detailed negotiations concerning the Spring Garden
    Road/Poreporena Freeway project, as well as other national
    road
    projects.

    5. On the second visit to Port Moresby by the Chinese
    consortium, the
    Minister signed a “pre-agreement” and gave the clear
    impression
    that, subject to finance, they had won the contract for the
    Spring
    Garden Road/Poreporena Freeway project.

    6. Furthermore, the Minister had formed a personal friendship
    with one
    of the key persons involved in the Chinese bid, Mr Leo Moore.
    This
    friendship was strengthened in the second half of 1991: the
    Minister had another visit to Hong Kong paid for by Mr Moore
    and
    the Minister went into business with Mr Moore.

    By forming this association with the Chinese consortium and entering
    into
    private negotiations without consulting the Department of Transport
    before
    the Ministerial Committee met on 18 July 1991 and before the matter
    was
    considered by the National Executive Council, the Minister for
    Transport,
    Mr Temo, had transformed the decision-making process for the Spring
    Garden Road/Poreporena Freeway project into a sham.

    * * * * * * * * * *

    Chapter 12

  • Page 173 of 397

  • 155

    13. FURTHER CHANGE IN COMPOSITION OF THE
    CHINESE CONSORTIUM: SEPTEMBER 1991

    [13.1] THE NEGOTIATING PATTERN IN THE FIRST HALF OF 1991

    During the first half of 1991 the Minister for Transport
    had been negotiating
    with a number of different companies and individuals, in
    relation to the
    Spring Garden Road/Poreporena Freeway project. In
    particular, the
    Minister had been negotiating with:

    Mr Leo Moore;

    the Second Surveying and Designing Institute,
    represented
    by Mr Sun Young Hse; and

    Outlet Year Ltd, represented by Mr Leung
    Keung.

    [13.2] WHO ELSE FORMED ‘THE CHINESE CONSORTIUM’?

    However, these were not the only parties that formed,
    what the
    Ombudsman Commission has termed in this report, “the
    Chinese
    consortium”. The following parties were also, at
    different times, involved:

    Topbay Investment Ltd: a Hong Kong-based
    company. The
    proposal endorsed by the Ministerial
    Committee on Spring
    Garden Road was actually in the name of this

  • Page 174 of 397

  • company.
    [EXHIBIT 99, at page 13]. However, the
    company had never
    conducted business in PNG and the principals
    of the
    company had never been to PNG.

    Chapter 13

    156

    China Guangzhou International Economic and Technical
    Cooperation Company and Ministry of Foreign Economic
    Relations and Trade of the Peoples’ Republic of China:
    referred to as joint partners in the Technical Proposal of
    Topbay Investment Ltd. [EXHIBIT 91] Their role in the
    negotiations is a complete mystery.

    China Ample Development Lid: also linked with Topbay
    Investment Ltd and the SSDI in the summary of proposals
    contained in the draft NEC Submission of July 1991. [EXHIBIT
    99, at page 13, discussed in Chapter 8] However, the name
    does not appear in any other documents in the records of
    the Department of Transport obtained by the for the purposes
    of this investigation. Its role in the negotiations is also a
    complete mystery.

    Moore’s Investment Group: a name used in two letters written
    by Mr Sun of the SSDI. It appears to be a name of
    convenience only, used to describe the consortium, of which
    the SSDI was an integral part.
    [EXHIBITS 95, 110]

    China Huashi Enterprises Corporation: from the evidence of
    Mr Moore, this Chinese Government company is closely linked
    with the SSDI. It was apparently intended that it would
    formally enter into the contract for the Spring Garden project
    Road/Poreporena Freeway with the PNG Government.

    Chapter 13

    157

  • Page 175 of 397

  • [13.3] THE ROLE OF MR LEO MOORE

    Mr Leo Moore’s role in the negotiations was not well defined,
    but it is clear
    he had an active and vested interest in everything that was
    happening in
    relation to the project.

    The Ombudsman Commission does not suggest there was anything
    illegal
    or improper in Mr Moore’s involvement. He was, however, at
    all times, an
    important link between the Minister for Transport and the
    other parties
    involved.

    [13.4] ANOTHER HONG KONG COMPANY JOINS THE CONSORTIUM

    During September 1991 there was a significant change in the
    negotiating
    pattern: another Hong Kong-based company was appointed to act
    on
    behalf of the SSDI. This company was called Tunson
    Engineering Co Ltd.

    News of this change of plan was conveyed to Mr Temo in a
    letter from the
    SSDI dated 28 September 1991. The letter reads as follows:

    ‘Dear Mr. Temo:

    Our second surveying & designing Institute, ministry of
    Railways Prc. Now
    has pass the burns peak project to our contractor in Hong
    Kong under the
    name of Tnnson Engineering Co. Ltd, 1-3/F, 21-23 Han Wong
    Road, Kowloon
    City, Kowloon Hong Kong. Who has the experience of
    contracting the Mordem
    constructions both in peoples republic of China as well as
    Hong Kong.

  • Page 176 of 397

  • Chapter 13

    158

    It would be much appreciated if your department will change
    your record
    Accordingly.

    Yours faithfully

    [Signed]
    MOORS INVESTMENT GROUP
    SUN YOUNG HSE (EXECUTIVE DIRECTOR)
    ON BEHALF OF OBSERVATION GROUP OF THE
    SECOND SURVEYING AND DESIGNING
    INSTITUTE, MINISTRY OF RAILWAYS [sic]. [EXHIBIT 110]

    The Minister for Transport made a handwritten note at the bottom of
    the
    letter, dated 10.10.91.

    “SECRETARY

    PLEASE TAKE NOTE OF ABOVE CHANGE AS I HAVE NO OBJECTION AS
    LONG AS THEY ARE MEETING OUR CRITERIA.
    ALSO PREPARE THE FINAL SUBMISSION TO CABINET. WORK CLOSELY
    WITH FINANCE DEPARTMENT.
    THANK YOU
    A. TEMO”. [EXHIBIT 110]

    In his response to the Ombudsman Commission’s preliminary report, Mr
    Temo also claimed that he had asked the Secretary for Transport to
    do
    a company search on all the companies that put in a bid:

  • Page 177 of 397

  • even instructed the Secretary to send someone to Hong Kong
    to find out in
    case we mislead the NEC.” [EXHIBIT 257, page 4]

    We have been unable to find any evidence to corroborate this claim.

    Chapter 13

    159

    [13.5] SIGNIFICANCE OF CHANGE IN COMPOSITION OF THE CONSORTIUM

    Tunson Engineering Co Ltd was at least the third Hong
    Kong-based
    company to join the Chinese consortium in less than six
    months. In the
    opinion of the Ombudsman Commission, the fact there had
    been yet
    another change in the composition of the consortium should
    have been
    a matter of great concern, both to the Minister for
    Transport and the
    Department of Transport.

    During the course of this investigation, the Ombudsman
    Commission found
    it impossible to identify the precise legal relationships
    between the various
    parties that, at different times, constituted the Chinese
    consortium. We are
    left to wonder how confusing it must have been at the
    time, with
    companies such as Outlet Year Ltd, China Ample Development
    Ltd and
    Topbay Investment Ltd, as well as “Moore’s Investment
    Group”, all being
    linked with the proposal of the SSDI and various other

  • Page 178 of 397

  • agencies of the
    Chinese Government.

    The addition of Tunson Engineering Co Ltd to the
    consortium in
    September 1991 could only have added to the utter
    confusion that any
    reasonably cautious administrator would have experienced
    at that time.

    [13.6] THE CONFUSION CAUSED BY A FURTHER CHANGE IN THE
    CONSORTIUM SHOULD HAVE LED TO A HALT IN NEGOTIATIONS

    There were some obvious questions to ask about the arrival
    of Tujison
    Engineering Co Ltd:

    Why was the change in composition of the
    consortium
    necessary?

    Chapter 13

    160

    Were the companies previously in the consortium
    disreputable?

    Did they have financial problems?

    If so, what guarantee was there that the same problems
    wouldn’t be encountered with this new company?

    Who was behind Tunson Engineering Co Ltd?

    Was it a reputable company?

    How long had it been established?

    Did it have any experience operating in PNG?

    Had any of its principals been to PNG?

    What was the company’s asset base?

  • Page 179 of 397

  • Did the company have experience in civil engineering
    projects?

    Was it registered with the National Investment and
    Development Authority (NIDA)?

    It later transpired that the Department of Transport did begin to
    ask some
    of these questions (see Chapter 15). The Minister’s reaction,
    however, was
    not the same as the Department’s.

    Chapter 13

    161

    [13.7] THE MINISTER’S LACK OF CONCERN WAS IRRESPONSIBLE

    The Ombudsman Commission considers that the Minister
    for Transport’s
    direction to the Secretary of the Department of
    Transport on 10 October
    1991 to “take note of the change” and the Minister’s
    comment that he had
    “no objection as long as they are meeting our criteria”
    was an ill-
    considered, inadequate and reckless response to the
    addition of Tunson
    Engineering Co Ltd to the Chinese consortium.

    The Minister for Transport showed a total disregard for
    all the normal and
    proper legal and administrative procedures regulating
    public works projects
    in Papua New Guinea.

    The Minister should have been deeply concerned about
    this development.
    But he was not concerned. Far from it. As we show in
    the next chapter of
    this report, only a few days after advising the
    Secretary for Transport about
    Tunson Engineering Co Ltd, the Minister signed a
    contract with that
    company for construction of the freeway.

    * * * * * * * * * *

  • Page 180 of 397

  • Chapter 13

    162

    14. MINISTER FOR TRANSPORT SIGNS CONTRACT FOR
    CONSTRUCTION OF FREEWAY: OCTOBER 1991

    [14.1] NEGOTIATIONS WITH TUNSON ENGINEERING CO LTD

    During October 1991, the Managing Director of Tunson
    Engineering Co
    Ltd, Mr Siu Chu Yen, visited Port Moresby and had
    negotiations with the
    Minister for Transport, concerning the Spring Garden Road/
    Poreporena
    Freeway project.

    Mr Siu was accompanied by four other Hong Kong businessmen,
    as well
    as Mr Leo Moore.

    Mr Moore testified that the Tunson group visited Port Moresby
    for one
    week and stayed at the Port Moresby Travelodge Hotel. He came
    on the
    same flight as the Tunson group and returned with them to
    Hong Kong
    in mid-October 1991.

    The Ombudsman Commission is satisfied that the negotiations
    between the
    Minister for Transport and Tunson Engineering Co. Ltd
    occurred without
    the knowledge of the Secretary for Transport, Mr Amini.

    [142] RESULT OF NEGOTIATIONS

    The result of the negotiations was that, on 15 October 1991,
    the Minister
    for Transport, purporting to act on behalf of the Department

  • Page 181 of 397

  • of Transport,

    Chapter 14

    163

    signed a contract for the construction of the Spring Garden
    Road/Poreporena Freeway. The contract was entered into with
    Tunson
    Engineering Co. Ltd. of Kowloon Hong Kong. [EXHIBIT 115

    THE CONTRACT OF 15 OCTOBER 1991

    [14.3] TERMS OF THE CONTRACT

    The contract dated 15 October 1991 is nine pages in length
    and is entitled:

    ‘CONTRACT AGREEMENT ■
    The agreement for the construction of (Burnspeak-Spring
    Garden Road) (from
    Port Moresby to Jackson Airport [sic].’

    The document states, amongst other things:

    To change the traffic condition from Port Moresby to
    Jackson airport, design
    the construction of the Spring Garden Road Link project
    from Port Moresby to
    jacksons Airport in PNG.

    From June 1991, we have invited by the Ministry of
    Transport of PNG to realize
    the work and make the agreement as following item.

    A. This agreement will be signed between the
    Transportation of PNG as
    Party A and Tunson Engineering Co., Ltd. as Party.

    B. Project Description:

  • Page 182 of 397

  • Bl(a) The proposed mad link will start from Moresby
    Harbour in Konedobu,
    along the existing Spring Garden Road crossed the Bums
    Peak saddle (by
    tunnel) and intersects with Wards, Waigani, Boroko Roads,
    and then along the
    Geauta Drive Road intersects with Hubert Murray Highway,
    finally to Jackson
    airport total length 8.8 km.

    B1(b) Based on the economic Assessment for Spring Garden
    Road on Port
    Moresby Road needs study and requirements pointed out by
    the Department
    of Transportation. The main technical standards are as
    follows:

    Chapter 14

    164

    Length of new mad : 4.6 kilometer
    Length of existing mad: 3.5 kilometer
    Number of Lanes : 4
    Width of each Lanes : 35m
    Medium 2m
    Width of each pedestrian
    (earth surface) (for : 3.5 m
    each side, not including
    tunnel)
    Width of Subgrade 23m
    Pavement Bituminous Concret
    Including Traffic Sign Board.’
    [EXHIBIT 115]

    [14.4] A POORLY DRAFTED AND BARELY INTELLIGIBLE DOCUMENT

    This is quite a remarkable document. It purports to be a
    contract for
    construction of the Spring Garden Road/Poreporena Freeway
    project. But

  • Page 183 of 397

  • it is so vague and poorly drafted, it is difficult to
    believe it was prepared
    by anyone with legal qualifications or, indeed, anyone
    reasonably fluent in
    the English language.

    Mr Moore testified the contract had been drafted and typed
    in a rush, and
    was not finished until the early hours of one morning at
    the Port Moresby
    Travelodge Hotel. This is evident from the quality of the
    document.

    It is riddled with bizarre and barely intelligible terms.
    For example, Clause
    E quotes a total construction cost of US$49,383,000.00.
    Clause F then
    states:

    Not including:

    F(1) Unexpected (nn-limited) cost etc.

    F(2) The cost for land acquisition and removal of
    existing structures,
    houses, electrical power cables, underground
    pipes and cable etc.

    Chapter 14

    165 1

    F(3) Party A shall be responsible for the net profit,
    import materials
    machinery and daily equipment taxes that can be
    omitted.

    F(4) Changing price for the requirements the money or
    other unexpect
    cost.
    From above F(1) and F(4) mentioned about the price
    will be
    written in details in construction agreement.

  • Page 184 of 397

  • F(5) The construction of channel, drainage, manhole,
    traffic lights and
    all E & M services works.’
    [EXHIBIT 115, page 4]

    It is stating the obvious to say that many of these
    provisions – which
    presumably represent additions to the “total construction
    cost” – simply defy
    comprehension.

    [14.5] THE MINISTER FOR TRANSPORT AGREED TO AWARD OTHER ROAD
    CONTRACTS TO TUNSON

    An alarming part of the Contract is Clause G, which relates
    to ‘Terms of
    Payment”. Its states:

    “G(1) Party A must pay in U.S. dollars and it must make
    promise from bank
    guarantee of (The Bank of Papua New Guinea).

    G(2) Payment to be paid with 10th years including
    construction period. Any
    default over 10th years % (percent) will be charge per
    year.

    G(3) In the meantime, Part A and Part B intend to sign
    other contract.

    G(4) If Party B sign more than one contract with Part A
    (Transportation
    Department of Papua New Guinea Government), the
    aforesaid item of
    G(2) must be voided and payment will according to the
    following
    payment terms, details as shown on G(7), (8), (9).

  • Page 185 of 397

  • Chapter 14

    166

    G(5) Party B is agree [sic] to sign one more contract for
    45 kilometer [sic]
    of Roadway with Party A (Minis’ try of Transport) Than
    the payment
    must be according to the Original Contract.

    G(6) Furthermore, Party B also intend to sign the another
    contract of
    construction for 147 kilometer length mad link will
    start from Bereina
    to Lae and Malalna to Erave with Party A after their
    future site
    investigation and other preparation works [sic].•
    [EXHIBIT 115, page 4]

    It is apparent from these terms that, in the course of
    negotiating
    construction of the Spring Garden Road/Poreporena Freeway,
    the Minister
    for Transport was also negotiating other road projects,
    including a road
    between Erave, Southern Highlands Province, and Malalaua,
    Gulf Province.

    The Department of Transport was not aware the Minister was
    conducting
    negotiations for the Erave-Malalaua road. Nor is there
    evidence the
    Minister was authorised by the National Executive Council to
    do so.

    [14.6] THE SCOPE OF THE PROJECT IN THE CONTRACT OF 15 OCTOBER
    1991

    The scope of the project is very poorly defined in the
    contract with Tunson
    Engineering Co Ltd.

    Clause B(1)(a), for example, describes the route of the
    proposed road link
    in very general terms and describes the total length as 8.8
    kilometres.

    Clause B1(b) then states the length of new road will be 4.6
    kilometres, and
    the existing road 3.5 kilometres, ie a total of only 8.1
    kilometres: 700

  • Page 186 of 397

  • metres of road has disappeared in the space of one paragraph.

    Chapter 14

    167

    Clause B1 (b) further states that there will be one
    tunnel, four bridges,

    sixteen cross road drainages and four junctions, but does
    not specify

    where any of them will be.

    These are only a few of the many defects in this woefully
    inadequate

    document The Ombudsman Commission is at a loss to find
    any good

    reason why a Minister of the State would have signed it.

    [14.7] COULD THE MINISTER’S ACTIONS BE JUSTIFIED?

    We emphasised in Chapter 12 that, in the opinion of the
    Ombudsman
    Commission, it is very wrong for any Minister of the
    State to sign contracts

    on behalf of his Department or the Government without
    express

    authorisation.

    In this case, the Minister for Transport repeated the
    mistake he made eight

  • Page 187 of 397

  • months earlier in Hong Kong: he signed a contract for a
    mufti-million kina

    transport project of national significance, without the
    authorisation of the

    National Executive Council and without the knowledge or
    advice of his

    Department This was unlawful and wrong, and was not in
    the best

    interests of the Government and the State.

    [14.8] WAS THE CONTRACT MERELY A *MEMORANDUM OF

    UNDERSTANDING’?

    The only conceivable way the signing of the contract with
    Tunson

    Engineering Co Ltd could be acceptable is if it were
    regarded as merely

    a record of an “understanding” reached between Mr Temo
    and the

    Managing Director of that company. This was the view
    taken by the

    Department of Transport, when it discovered the signing
    of the agreement.

    Chapter 14

    168

    In his response to our preliminary report, Mr Temo also claimed the

  • Page 188 of 397

  • contract was only meant to be a memorandum of understanding:

    The Secretary for Transport or in his absence there was always
    someone to
    give me advice in fact we had a morning briefing every week on
    Burns Peak
    and other matters.

    The contract was a documentation of some sort required by Chinese
    Government
    before they leave out of China.

    Because it was mentioned that they did not have office in PNG so
    they required
    a form and reason paper to show their Government so they could
    come again
    to PNG many times. This was very important to them as a
    requirement.’
    [EXHIBIT 257, page 41

    The Ombudsman Commission regards this as a very charitable
    assessment
    of the Minister for Transport’s actions, which were wrong and
    unacceptable.

    The document of 15 October 1991 is entitled “Contract Agreement”.
    Though it is poorly drafted and barely intelligible, it gives the
    appearance –
    at first glance – of being intended to be a binding agreement. It
    has a
    number of specific terms and sets a “total construction cost” of
    US$49,383,000.00. The document has been signed and witnessed in a
    way
    contracts are normally executed.

    The Ombudsman Commission therefore cannot accept that the “Contract
    Agreement” of 15 October 1991 was only intended to be a memorandum
    of understanding.

    Nor do we accept Mr Temo’s spurious claim that it was necessary to
    sign
    the contract, so that members of the consortium based in the
    People’s
    Republic of China would be allowed to leave their country. If there
    were

  • Page 189 of 397

  • such a requirement, then the only proper way to comply with it was
    to

    Chapter 14

    169
    formally advise and liaise with the Chinese Embassy in Port
    Moresby.
    However, there is no suggestion that that was done.111

    [14.9] THE DANGERS OF ENTERING INTO UNAUTHORISED AGREEMENTS
    WITH FOREIGNERS

    We do appreciate that, in his own mind, the Minister for
    Transport might
    have believed that the contract with Tunson Engineering Co
    Ltd was not
    enforceable without National Executive Council approval. But
    that does not,
    in our view, provide an excuse for his actions.

    When foreign enterprises enter into written agreements with
    Ministers, they
    expect those agreements to be honoured. If the agreements
    are not
    honoured, the time and money of the foreign enterprises can
    be wasted.
    This gives Papua New Guinea a bad name and the investment
    climate
    becomes uncertain, if not bad. Our image abroad is very
    important

    Foreigners who are not familiar with our laws and our
    Constitution won’t
    always understand that the Minister they were dealing with
    had no authority
    to sign the agreement entered into. Nor do they always know
    that an
    agreement will require the approval of the National
    Executive Council or
    a Supply and Tenders Board or the Public Works Committee.
    This is
    especially the case with businessmen from Asia, where
    accepted methods
    of doing business are often different from those applying in
    Papua New
    Guinea.

    In addition to the embarrassment that these *specie’
    agreements with

  • Page 190 of 397

  • Ministers can cause for the whole Nation when not honoured,
    such
    agreements create an environment for sweetheart deals,
    bribery and
    corruption. It is just plain common sense that Ministers –
    and any other
    persons holding official positions – must not sign these
    documents.

    Chapter 14

    170

    In the opinion of the Ombudsman Commission it was grossly
    irresponsible
    of the Minister for Transport to sign the Contract Agreement
    with Tunson
    Engineering Co Ltd on 15 October 1991.

    [14.10] REACTION OF THE DEPARTMENT OF TRANSPORT TO THE SIGNING OF
    THE CONTRACT WITH TUNSON ENGINEERING CO LTD

    The Department of Transport became aware of the contract
    with Tunson
    soon after it was signed. Not surprisingly, the news that
    the Minister had
    signed a contract for the building of the freeway without
    National Executive
    Council approval caused alarm and bewilderment within the
    Department.

    [14.11] MR HITOLO ADVISES MR AMINI ABOUT THE CONTRACT OF 15
    OCTOBER 1991

    In a minute to Secretary Amini dated 17 October 1991, the
    Director of the
    Policy Secretariat, Mr Hitolo stated:

    ‘… Now I am at a loss, as to how to proceed on this
    project because your verbal
    instruction which is consistent with the World Bank
    advice seem to be in direct

  • Page 191 of 397

  • conflict with this signed contract agreement.

    I do not know the legality of it but it seems our
    procurement procedures are
    being short-circuited by the use of the delegated powers
    of the NEC in his
    capacity as the Chairman of the Special Ministerial
    Committee on Spring
    Garden Road. Even so, I think there are other legal
    aspects like registration
    of the company in PNG and also the professional
    requirement to practice as
    Engineers in PNG needs to be completed…

    I am trying to get this circulated to the Members of the
    Steering Committee
    so that we are able to get proper advice as to how to
    proceed, because it seems
    our Minister is determined to pursue the project with
    the Chinese. In other
    words, the policy from him is loud and clear as I
    interpreted it, but let us make
    it our business to get the best and the most cost
    effective solution for Papua
    New Guinea.’ [EXHIBITS 117,1181

    Chapter 14

    171

    [14.12] SECRETARY FOR TRANSPORT ADVISES MINISTER TO EXERCISE
    CAUTION

    Shortly after receiving Mr Hitolo’s advice, Secretary Amini
    wrote to the
    Minister in the following terms:

    “My Dear Minister

    I have just browse through an agreement on the Bums Peak
    project (attached)
    which you have signed with the proposed developers.

  • Page 192 of 397

  • It comes across to me that it may not be accepted as a
    legal binding document
    for the following reasons:-

    As Chairman of the Ministerial Committee, you made
    recommendation for the construction contract to be
    awarded to
    The Second Surveying and Designing Institute,
    Ministry of
    Railways of China’ but the agreement sign is with
    Tunson
    Engineering Co. Ltd, Hong Kong a completely new
    company;

    2. It is my understanding that such agreements are
    between the
    State and the developers, in which case the
    Finance Minister
    or the Governor General is the one that has the
    delegated
    powers to sign;

    3. Some of the conditions and terms are not in the
    best interest
    of the State. Our Attorney General Department
    should review
    the document;

    I am inclined to suggest that perhaps it wads meant to be
    a Memorandum of
    Understanding, in which case you are right to sign but it
    should be made clear
    that it is so, and that it has no legal binding on the
    State.

    On these basis, I would advise you strongly that you do
    not pursue the
    document as an agreement.

    In this regard, I would suggest that you write to the
    developers and advise
    them of this position. I have attached a draft letter for
    your perusal.

    In the meantime, I will seek legal advice from the
    Attorney General Department
    to assist you in dealing with this situation.

  • Page 193 of 397

  • ale; tiar 14

    172

    I am available to discuss this further with you at your
    convenience.

    Yours sincerely
    [Signed]
    BIC AMINI, CBE
    Secretary’ [EXHIBIT 122 ]

    [14.13] PROPRIETY OF THE SECRETARY’S ACTIONS

    Like Mr Hitolo’s letter to Mr Amini, Mr Amini’s letter to
    the Minister made

    a number of pertinent points about the propriety of the
    Minister’s signing

    of the contract with Tunson. It is, in our view, quite
    proper and necessary

    for the Secretary of a Department to bring such matters to
    the attention

    of his or her Minister.

    Mr Amini deserves praise, at this point, for his prompt
    action in advising

    the Minister to write to Tunson and tell them not to rely on

  • Page 194 of 397

  • the contract as

    a binding agreement.

    There was one very important matter, however, which Mr Amini
    neglected

    to mention: the signing of the contract was in direct
    conflict with the advice

    of the World Bank. This had been brought to Mr Amini’s
    attention by Mr

    Hitolo and Mr Amini should have spelt it out in clear and
    unambiguous

    terms to the Minister.

    Only a couple of weeks before the Minister signed the
    contract with

    Tunson Engineering Co Ltd, the World Bank had strongly
    advised that the

    Spring Garden Road/Poreporena Freeway project be re-
    tendered. This

    development is documented in Chapter 15.

    Chapter 14

    173

    MINISTER CONTINUES NEGOTIATIONS WITH CHINESE CONSORTIUM

    [14.14] FURTHER DIRECT NEGOTIATIONS BETWEEN THE MINISTER FOR
    TRANSPORT AND THE SECOND SURVEYING AND DESIGNING
    INSTITUTE

  • Page 195 of 397

  • Though he signed a contract for construction of the freeway
    on 15 October
    1991, the Minister for Transport continued to conduct
    negotiations with the
    Chinese consortium.

    Letter written on 21 October 1991

    On 21 October 1991, the Minister for Transport wrote a
    letter to Mr Zhu
    Chuanmua, a Senior Engineer with the Second Surveying and
    Designing
    Institute and a member of the SSDI team that had visited
    Port Moresby
    three months earlier, in July 1991.

    It appears the Minister was trying to communicate his
    concern about some
    of the terms in “the final contract” which, the Minister
    says, the SSDI had
    sent on 13 and 23 September 1991.

    The letter reads as follows:

    “SUBJECT: REGARDING THE COMMENT OF FINAL CONTRACTS OF
    THE FREEWAY PROJECT FROM PORT MORESBY TO
    JACKSON AIRPORT (OR) BURNS PEAK PROJECT

    DEAR MR. ZHU,

    I acknowledge in receiving the final contract which your
    institute had written
    on 13th and 23rd of September 1991 passed thru Mr. Sun
    Young Use with
    Appreciation. I and my department had review it and would
    like to apply as
    follow.

    Chapter 14

    174

  • Page 196 of 397

  • According to our Government policy there are four 1/2
    pint to be mentioned.

    1. the total cost of the contraction cannot be over US
    $50 millions, and
    your cost for the contract which you had put in the
    final contract is
    over US$64 million dollars, that is more than the
    other contractors from
    Japan, America, Australia and Hong Kong.

    2. In regards to the supervision of the project, it
    should be supervised by
    our transportation department, as discussed in
    meetings.

    3. The systems of the Surveying, and Designing should
    be in three systems,
    British, Australian, and Papua New Guinean system.

    According to our policy, before construction our
    Government cannot
    per any deposit or advance to the contractor, even
    Moore’s Investment
    Group willing to pay, it would not be accepted,
    what our Government
    will do, will be seeking our bank to guaranty the
    payment thru Bank
    of Papua New Guinea accordingly.

    S. The contract must seek their bank to put up 10%
    Performance bond,,
    and your bank certificate is not accepted.

    Your engineer were here in July, and went thru all the
    meeting, it seems that
    your interpreter had his interpret the whole meaning I
    hope your Institute
    can re-check and advise as soon as possible, awaiting
    for your reply, thanking
    you.

    Yours sincerely
    [Signed]
    HON. ANTHONY TEMO, MP – Minister for Transport,
    Transportation
    Department.• [EXHIBIT 123]

  • Page 197 of 397

  • [14.15] WHAT DID THE MINISTER MEAN BY THE ‘FINAL CONTRACT’?

    It is unclear what the Minister was referring to as “the
    final contract which

    your institute had written on 13th and 23rd of September
    1991”. There is

    no contract bearing either of those dates in the files of
    the Department of

    Transport. Perhaps the Minister was referring to the
    observation report

    and the financial proposal sent to the Department of
    Transport under cover

    of the undated letter from the SSDI, referred to in Chapter
    12 of this report.

    [EXHIBIT 95]

    Chapter 14

    175

    Perhaps there was a final contract signed with the SSDI,
    that the Minister

    for Transport failed to advise anyone else about.

  • Page 198 of 397

  • We have been unable to ascertain what the Minister meant
    by “the final

    contract”.

    [14.16] SIGNIFICANCE OF THE LETTER OF 21 OCTOBER 1991

    Irrespective of whether the Minister had signed a
    contract with the SSDI,

    the significant thing about this letter is that it was
    written six days after the

    Minister signed the contract with Tunson Engineering Co.
    Ltd. That is,

    though he had already signed a contract for construction
    of the freeway

    with that company, the Minister was continuing to
    negotiate the terms of

    the deal with its consortium partner.

    [14.17] MR TEMO’S DEFENCE

    When we made this finding in our preliminary report, Mr
    Temo responded

  • Page 199 of 397

  • as follows:

    ‘NEC had authorised my Ministerial Committee to
    negotiate the best deal for
    PNG by following special tender procedures. There
    was no legal agreement in
    place for any company to proceed everyone knew
    that.’ [EXHIBIT 257, page 51

    Mr Temo consistently claimed the National Executive
    Council had approved

    “special procedures” for this project. He suggested he
    had been

    encouraged to bypass normal tender procedures. If normal
    procedures

    were followed, he said, the project would have taken too
    long to come to

    fruition. He said he was constantly being harangued in
    the Parliament

    about the traffic problems in Port Moresby. Whenever
    there was an

    Chapter 14

    176
    accident on Three Mile Hill, he was blamed. He saw it as his
    duty to the
    Nation to get the project implemented as soon as possible.

  • Page 200 of 397

  • He didn’t
    always get the support he should have received from other
    members of
    the Ministerial Committee on Spring Garden Road or the
    Department of
    Transport. It was therefore necessary to conduct
    negotiations himself.

    [14.18] Mr TEMO’S EXPLANATION REJECTED

    In the opinion of the Ombudsman Commission, none of these
    things
    satisfactorily explain the Minister’s continuing to
    negotiate the terms of the
    agreement with the SSDI, when he had signed a contract for
    construction
    of the freeway just prior to this, with another member of
    the SSDI
    consortium. His actions could only have caused confusion to
    the various
    members of the Chinese consortium, if they had known what
    the Minister
    was doing. It was very bad for the Government and the
    country.

    THE MINISTER FOR TRANSPORT ACTED IRRESPONSIBLY

    [14.19] SUMMARY OF DEVELOPMENTS DURING OCTOBER 1991

    Prior to October 1991, the Hong Kong-based company known as
    Tunson
    Engineering Co. Ltd had no involvement in the Spring Garden
    Road/Poreporena Freeway project. However, during October
    1991,
    representatives of that company travelled to Port Moresby to
    discuss the
    project with the Minister for Transport.

    Chapter 14

    177

    Following these discussions the Minister wrongly entered into a
    contract
    with the company for the construction of the Spring Garden

  • Page 201 of 397

  • Road/Poreporena Freeway, without the advice or knowledge of the
    Department of Transport.

    Despite doing this, the Minister continued to negotiate the terms of
    the
    contract with another member of the Chinese consortium.

    As a matter of administration, the Minister’s conduct during October
    1991
    was, in the opinion of the Ombudsman Commission, naive, incompetent
    and irresponsible.

    * * * * * * * * * *

    Chapter 14

    178

    15. ROLE OF THE WORLD BANK IN THE SPRING
    GARDEN ROAD/POREPORENA FREEWAY PROJECT

    [15.1] TWO WORLD BANK MISSIONS

    The World Bank has an on-going interest in the development of
    Papua
    New Guinea’s transport infrastructure. In 1991, at least two
    World Bank

  • Page 202 of 397

  • Missions visited Port Moresby and made recommendations
    concerning the
    Spring Garden Road/Poreporena Freeway project.

    [15.2] THE FIRST MISSION: JUNE 1991

    The first Mission was carried out from 21 to 26 June 1991 and
    consisted
    of Mr Heins Unger, a municipal engineer. The draft Aide
    Memoire prepared
    following this Mission (we were unable to obtain a final
    version of the
    document) shows that the Mission met with officials from the
    Department
    of Transport, the Office of International Development
    Assistance and the
    National Capital District Commission.

    The purpose of the Mission was to give advice on a wide range
    of World
    Bank-sponsored transport projects, one of which was Spring
    Garden Road.
    The Aide-Memoire dated 26 June 1991 records the following
    observations:

    “The Coffey Geotechnical Investigation of the Spring
    Garden Road scheme
    was reviewed in summary form by the mission and found to
    be thcm3ugh,
    comprehensive and clear in its findings and
    recommendations…

    Chapter 15

    179

    [Regarding] the need of Department of Transport for expert

  • Page 203 of 397

  • advice and
    assistance with solicitation, evaluation and negotiation
    of private sector BOT
    proposals for the construction of the Spring Garden Road
    link. In the mission’s
    view, short term, intermittent support may be the
    preferable option, because
    different expertise is needed at the various stages of the
    project the costs of the
    assistance could also be kept down, since a suitable
    source of funding is still
    being explored. Further advice will be given from Bank
    HQ.” [EXHIBIT 92]

    It is apparent from this document that the idea of getting
    more expert
    advisers from the World Bank to assist the Department of
    Transport in the
    evaluation of proposals for the Spring Garden Road/Poreporena
    Freeway
    project had been raised.

    As a consequence, another World Bank Mission was dispatched
    to Port
    Moresby a few months later.

    [15.3] THE SECOND MISSION: SEPTEMBER 1991

    The second World Bank Mission visited Port Moresby from 24 to
    28
    September 1991. On this occasion, attention was focused
    solely on the
    Spring Garden Road/Poreporena Freeway project.

    The Aide-Memoire of 28 September 1991

    The Mission’s findings and recommendations are contained in
    an Aide-
    Memoire dated 28 September 1991, signed by Ms M C Nguyen, on
    behalf
    of the World Bank, and Mr Amini, on behalf of the Department
    of
    Transport.

  • Page 204 of 397

  • Chapter 15

    180

    The Aide Memoire states:

    “a) The private sector proposals do not meet the requirements of
    the TOR
    [i.e. Terms of Reference], including the selected proposal;

    b) The inability of interested parties to respond adequately to
    the request
    is in part due to unclear distinction between the concepts
    of Build-
    Operate-Transfer (BOT) and the turnkey procurement;

    c) While the economic viability of the project is established,
    the financial
    plan of the project based on recovery through tolls alone is
    unrealistic
    and unworkable;

    d) The untested and novel concept of BOT and toll (in PNG)
    prevented
    respondents from submitting responsive bids;

    e) The technic-Al parameters are left unclear as to whether PNG
    was
    seeking a two or four lane road, one or two tube tunnels,
    and whether
    road surface would be of compacted gravel or asphalt
    concrete, and
    whether an open cut or tunnel was desired;

    f) Land acquisition and environmental impact issues were not
    addressed
    in the request for proposaL Given the land tenure problems
    in PNG
    and potential environmental problems if an open cut is
    desired,
    specifications on these points could help get a more

  • Page 205 of 397

  • responsive interest
    to the project; and

    g) Finally, the uncertain environment in PNG for private sector
    investments
    also contributes to the lack of responsive bids.’
    [EXHIBIT 111, at page 1]

    Other significant findings and recommendations of the World Bank,
    recorded under the heading “Retendering of Spring Garden Road”, were
    as follows:

    ‘An environmental impact study should be prepared to determine
    the
    environmental parameters that should be considered in the design
    of the link
    road- An investigation of the land aquisition in the area to
    determine the
    degree of difficulty in obtaining the right of way.

    Following these studies which could be undertaken in three
    months, Department
    of Transport should issue a new request for proposal (RFP)
    including
    specifications that would help solicit responsive proposals from
    PS [the Private
    Sector]…

    Chapter 15

    181

    If there is no responsive interest from private
    investors after the new tendering,
    it is proposed that Department of Transport seeks public
    funds for financing the
    above project” [EXHIBIT pages 3-41

  • Page 206 of 397

  • [15.4] SUMMARY OF WORLD BANK RECOMMENDATIONS

    Put simply, the World Bank was saying that:

    The Terms of Reference document prepared by the
    Department of Transport in early 1991 was vague and
    inadequate (see Chapter 10).

    If the Government was intent on pursuing private
    sector
    funding of the Spring Garden Road project, further
    studies
    would have to be undertaken to address the problem of
    financial returns and environmental and land
    acquisition
    issues.

    Once these studies were completed – which would take
    about three months – it would be necessary to issue a
    new
    “request for proposal”.

    If the private sector was still not interested in
    funding the
    project, the Department of Transport would have to
    seek
    public funding.

    In other words, the World Bank was advocating a ” back-to-
    the-drawing-
    boards” approach: the project should be re-tendered.

    Chapter 15

    182

    [15.5] WERE THE WORLD BANK’S RECOMMENDATIONS FOLLOWED?

  • Page 207 of 397

  • The recommendations contained in the Aide-Memoire of 28
    September
    1991 were completely ignored. No further financial or
    environmental studies
    were undertaken and the project was not re-tendered.

    Only a couple of weeks after the Aide-Memoire was delivered,
    the Minister
    for Transport signed a contract for construction of the
    freeway with Tunson
    Engineering Co Ltd (see Chapter 14). This contract was not
    pursued,
    however, and in February 1992, the National Executive Council
    approved
    the awarding of the project to another company.

    [15.6] WAS THE MINISTER ADVISED ABOUT THE RECOMMENDATIONS OF THE
    WORLD BANK?

    The Ombudsman Commission asked the Secretary for Transport
    whether
    the World Bank’s recommendations were brought to the
    attention of the
    Minister for Transport.

    His reply was that “any major document is always referred to
    the Ministers
    for their information”. Thus, the Secretary was saying that
    the normal
    practice of his Department is to bring such major documents
    to the
    attention of the Minister.

    The Secretary also said:

    The Minister was aware of the World Bank advice but took
    the view that this
    was just an advice and not binding on an Independent State
    and implied that
    NEC has the final say: [EXHIBIT 254, pant 131

  • Page 208 of 397

  • Chapter 15

    183

    However, the Secretary could not convince us he had
    formally briefed the i
    Minister on the World Bank’s advice. There is no
    documentary evidence
    in any of the Department of Transport files that this had
    been done.

    The Minister for Transport, Mr Temo, said he had not seen
    the World Bank
    report until it was shown to him by the Ombudsman
    Commission and that
    the Secretary had never mentioned it to him.

    The Ombudsman Commission is not necessarily concerned
    about the
    World Bank recommendations not being followed. It was the
    prerogative
    of the National Government to decide whether or not to
    adopt the
    recommendations.

    Our concern is that the Secretary of the Department of
    Transport did not
    bring the recommendations immediately and formally to the
    attention of the
    Minister.

    (15.7] THE IMPORTANCE OF INDEPENDENT ADVICE

    The World Bank recommendations were obviously crucial to
    the future of
    the Spring Garden Road/Poreporena Freeway project. It was
    the duty of
    the Secretary for Transport to immediately and forcefully
    bring them to the
    attention of the Minister: The only way this could
    properly have been done
    was officially, i.e. in writing.

    The Secretary for Transport failed to do this.

    Chapter 15

  • Page 209 of 397

  • 184

    It is not relevant, in our view, to suggest that the Minister would
    have
    ignored the World Bank recommendations. In the opinion of the
    Ombudsman Commission, it is never an excuse to say that advice was
    not
    given to a Minister because it was thought, or even known, that the
    advice
    would not be followed.

    The integrity and efficiency of our Public Service depends upon
    Ministers
    being promptly and fearlessly advised of all relevant matters – even
    when
    the advice is something the Minister does not want to hear. If we
    get to
    the stage where our Ministers only get the advice that they want to
    hear,
    we will be in a very sorry state. The professionalism of the Public
    Service
    will deteriorate.

    The Ombudsman Commission concludes that the failure of the Secretary
    for Transport to formally convey the World Bank recommendations
    immediately to the Minister for Transport in late September 1991 was
    a
    bad piece of administration.

    * * * * * * * * * *

    Chapter 15

    185

  • Page 210 of 397

  • 16. FATE OF THE POLICY SUBMISSION FAVOURING THE
    CHINESE CONSORTIUM: DECEMBER 1991

    [16.1] BACKGROUND TO NATIONAL EXECUTIVE COUNCIL SUBMISSION OF 17
    JULY 1991

    In July 1991 the Department of Transport had prepared a
    Policy
    Submission entitled “Financing the Construction of the Spring
    Garden
    Freeway” (see Chapter 11).

    This document contained an evaluation of five proposals. It
    concluded by
    recommending the project be awarded to a Chinese consortium
    consisting
    of the Second Surveying and Designing Institute of the
    People’s Republic
    of China and various Hong Kong-based companies.

    The document was the focus of discussion at the meeting of
    the Ministerial
    Committee on 18 July 1991. It was used by the Committee as
    the basis
    for its decision to recommend negotiations be commenced with
    the
    Chinese consortium. (Though the Minister for Transport had,
    on his own
    accord, already commenced private negotiations with the
    consortium.)

    In Chapter 11 the Ombudsman Commission criticised that
    decision and the
    document on which it was based. The method used in the
    document to
    select the Chinese consortium was vague and unsatisfactory.
    There had
    not been a genuine attempt to objectively evaluate the five
    short-listed
    proposals.

    Chapter 16

    186

    In this chapter, we trace the fate of the document of 17 July
    1991, after its
    consideration by the Ministerial Committee.

  • Page 211 of 397

  • SUBMISSION FAVOURING THE CHINESE CONSORTIUM FILED IN OCTOBER 1991

    [16.2] THE POUCY SUBMISSION DATED 17 JULY 1991 WAS FILED IN THE
    NATIONAL EXECUTIVE COUNCIL IN OCTOBER 1991

    The document considered by the Ministerial Committee was not
    amended
    following the meeting of 18 July 1991. It was filed in the
    National Executive
    Council during October 1991.

    Though there is no record of this in the files of the
    Department of
    Transport, we are satisfied, after considering the evidence
    of the Secretary
    for Transport, that the document was filed during October
    1991 by the
    Head of the Policy Secretariat, Mr Hitolo.

    [16.3] SECRETARY FOR TRANSPORT CLAIMS THE POUCY SUBMISSION WAS
    FILED WITHOUT HIS KNOWLEDGE

    Mr Amini testified that in October 1991 he attended an
    International
    Maritime Conference in London. He was accompanied by the
    Minister for
    Transport, the Prime Minister’s personal secretary, the
    Principal of the
    Madang Nautical College and the First Assistant Secretary in
    the Maritime
    Division of the Department of Transport, Mr Zurenuoc.

    Chapter 16

    187

    Mr Amini said the Minister for Transport was supposed to
    present the case
    for Papua New Guinea at the Council held in conjunction with
    the
    conference. However, he claimed the Minister left the
    conference early and
    returned to Port Moresby via Hong Kong, where he stayed for a
    few days.

    The Ombudsman Commission discovered that on this visit to
    Hong Kong –
    the Minister’s third in 1991 – he was again accommodated and

  • Page 212 of 397

  • entertained
    at the expense of members of the Chinese consortium bidding
    for the
    Spring Garden Road/Poreporena Freeway project.

    Mr Amini said he was forced to present the case for Papua New
    Guinea
    at the International Maritime Organisation conference in the
    absence of the
    Minister for Transport; and the case was lost, Mr Amini said.

    Mr Amini testified that when he returned from the conference
    he discovered
    that the Policy Submission dated 17 July 1991 had been filed
    in the
    National Executive Council in his absence on the direction of
    the Minister
    for Transport. Mr Amini said he was very annoyed about this,
    because the
    Submission had not been considered by the Resource Management
    Committee. Also, he said, it was wrong for any Policy
    Submission to leave
    the Department without his approval.

    [16.4] MR TEMO’S EVIDENCE

    When we questioned Mr Temo, his recollection of these events
    was less
    precise than Mr Amini’s.

    In his response to our preliminary report, Mr Temo stated:

    Chapter 16

    188

    “The Secretary for Transport
    was always aware of this even when he was in
    London or USA. His
    Department was briefing him all the time. Mr. Amini
    knew the progress of such
    event. If his Department was aware then Brian
    Amini could not deny. He
    could not carry the Department with him around.

    Mr. Amin and all FAS in the
    Department were summoned to explain about

  • Page 213 of 397

  • the Burns Peak project in
    NEC 3 times. Mr. Amini was seen by NEC members
    all the time.

    There was so many different
    Chinese companies and when they come to see
    me, I do not go and talk
    into them in a secret place. I call on the Secretary
    and other Department
    officials to brief us.

    I got advice from the
    Department before proceeding to do the work of Chairman
    of Ministerial Committee.

    All NEC submissions are
    prepared by the Department, checked and signed by
    Mr. Brian Amini or his
    delegate.

    I never put in any input in
    wording or selection criteria. If a company group
    come to me I refer the to
    the Department or jointly have a meeting.•
    [EXHIBIT 257, page 51

    Mr Temo also stated that he had, in fact,
    presented the papers on behalf
    of Papua New Guinea at the International
    Maritime Organisation
    conference.

    [16.5] SUMMARY OF CIRCUMSTANCES SURROUNDING FLUNG
    OF THE
    POUCY SUBMISSION FAVOURING THE CHINESE
    CONSORTIUM

    The Ombudsman Commission finds the
    evidence of the Secretary for
    Transport more convincing than that of Mr
    Temo. Mr Amini’s evidence as
    to the movements of the Minister during
    October 1991 is corroborated by
    evidence given by Mr Leo Moore, who
    entertained the Minister on his
    Hong Kong stopover. The Ombudsman
    Commission has also examined
    the entries appearing in the Minister’s

  • Page 214 of 397

  • passport for the relevant period.

    Chapter 16

    189

    We therefore accept Mr Amini’s version of events as correct.
    That is:

    The Policy Submission dated 17 July 1991 was filed in
    the
    National Executive Council during October 1991.

    It was filed by Mr Hitolo at the direction of the
    Minister for
    Transport.

    It was filed without the knowledge or approval of the
    Secretary for Transport.

    IMPROPRIETY BY MINISTER FOR TRANSPORT

    [16.6] MATTERS FOR CONCERN

    The Ombudsman Commission shares the concerns raised by the
    Secretary
    for Transport as to the way in which the Policy Submission
    favouring the
    Chinese went to the National Executive Council. tt is sound
    administrative
    practice that, whenever a Minister contemplates making an
    important Policy
    Submission to the National Executive Council, it should be
    presented in
    close consultation with the head of his Department.

    There are also other matters which concern the Ombudsman
    Commission
    about the filing of this particular Policy Submission.

    On 5 October 1991 the Minister for Transport had signed a

  • Page 215 of 397

  • contract for the
    construction of the freeway with Tunson Engineering Co Ltd of
    Hong Kong
    (see Chapter 14).

    Chapter 16

    190

    So, the impropriety that had developed was this: the Minister
    for Transport
    was attempting to present a submission to the National
    Executive Council,
    authorising his Department to commence negotiations with the
    Second
    Surveying and Designing Institute, when he had already, just
    prior to this,
    signed a contract with the SSDI’s consortium partner, Tunson
    Engineering
    Co Ltd, for the construction of the freeway.

    Not only that, on 21 October 1991 he wrote directly to the
    SSDI in China
    trying to renegotiate the terms of their financial proposal
    (which was
    different to the one in the contract he had signed with
    Tunson Engineering
    Co Ltd).

    These disturbing developments show how important it is for
    normal and
    established public tender procedures to be followed in
    projects of this
    nature.

    [16.7] THE POLICY SUBMISSION WAS NOT ACCEPTED BY THE NATIONAL
    EXECUTIVE COUNCIL

    As it turned out, the National Executive Council did not get
    the opportunity
    to debate the Policy Submission favouring the Chinese
    consortium. The
    Minister’s actions were short-circuited by the diligence of
    the Secretary to
    the National Executive Council, Mr P M Eka OBE. Mr Eka
    rejected the
    submission, because proper procedures for filing of National
    Executive
    Council submissions had not been followed.

    In a letter to the Secretary for Transport dated 4 December
    1991, Mr Eka

  • Page 216 of 397

  • advised that he was returning the fifty copies of the Policy
    Submission
    entitled “Financing the Construction of the Spring Garden
    Freeway.
    [EXHIBIT 127]

    Chapter 16

    191

    Mr Eka rejected the Submission because comments from the
    Department
    of Finance and Planning and the Department of Attorney-
    General had not
    been sought. [EXHIBIT 127]

    [16.8] NATIONAL EXECUTIVE COUNCIL PROCEDURES

    Chapter 2 of the National Executive Council Submissions
    Handbook
    prescribes the requirements for presentation of Policy
    Submissions.
    Paragraph 2.7(d) states:

    “Comments from the five Central Agencies and all other
    Ministries affected by
    the Proposal must be included. Particular care should be
    taken to ensure that
    views of all affected Ministries are obtained in writing
    prior to the Submission
    being referred to the NEC Secretariat Submissions
    requiring views to be sought
    in the NEC Meetings are not accepted,’ [E7GIIBIT 1]

    The “five central agencies” are prescribed in Paragraph 1.14
    of the
    Handbook. They are:

    the Department of Attorney-General;

  • Page 217 of 397

  • the Department of Finance and Planning;

    the Department of Personnel Management;

    the Department of Provincial Affairs; and

    the Department of Prime Minister and National
    Executive
    Council.

    Chapter 16

    192

    The Ombudsman Commission notes that Section D of the Policy

    Submission of 17 July 1991, under the heading “Views of other
    Ministers
    Affected”, simply states:

    °Being sought.• [EXHIBIT 99, at page 7 ]

    Clearly, there had been a failure to comply with the proper
    National

    Executive Council’s procedures. We therefore find that the
    Secretary to the
    National Executive Council acted properly in rejecting the
    Policy

    Submission.

  • Page 218 of 397

  • SUBMISSION FAVOURING CHINESE CONSORTIUM WAS NOT RE-PRESENTED

    [16.9] WHAT HAPPENED TO THE POLICY SUBMISSION AFTER IT WAS
    REJECTED BY THE SECRETARY TO THE NATIONAL EXECUTIVE
    COUNCIL?

    Following rejection of the Policy Submission, the Secretary
    for Transport

    took immediate steps to obtain the views of other Departments.
    To his

    credit, he went further than required. In a handwritten note
    dated 6
    December 1991, addressed to one of his First Assistant
    Secretaries, the

    Secretary issued an instruction in the following terms:

    ‘As discussed with you 5/12, I’m disappointed that this
    paper went through
    Minister without my approvaL The procedures required by NEC
    mg be done
    without exception. All comments from other Departs must be
    included esp the
    World Bank, DFP, Foreign Affairs, Lands, DOW, PM’s Dept,
    Personnel Mgt Dept,
    Environment, NCDC, Attorney General, OIDA etc. Urgent
    action.’
    [EXHIBIT 1271

    Chapter 16

    193

    [16.10] CIRCULATION OF THE POLICY SUBMISSION

    The Policy Submission of 17 July 1991 was subsequently
    circulated to the

  • Page 219 of 397

  • Departments specified by Mr Amini, as well as to the
    Department of Trade
    and Industry. This was done under cover of standard letters
    dated 6
    December 1991. [EXHIBIT 128]

    [16.11] SLACK RESPONSE BY OTHER DEPARTMENTS, PARTICULARLY FINANCE
    AND PLANNING

    Only one of the Departments which had been asked to comment,
    did so:
    the Department of Trade and Industry. [EXHIBIT 133]

    This was a disappointing response. In particular, we single
    out the
    Department of Finance and Planning for its failure to take
    the opportunity
    to demand more information. The Policy Submission indicated
    that the
    total cost of the project would be in the vicinity of $US 50
    million.
    Obviously the financial and budgetary implications were
    going to be
    enormous.

    In the opinion of the Ombudsman Commission it was
    irresponsible of the
    Department of Finance and Planning not to respond to the
    Policy
    Submission. It is that Department’s responsibility and
    therefore should be
    its practice to comment on the budgetary implications of all
    major projects
    undertaken by or on behalf of the State.

    Chapter 16

    194

    [16.12] WAS THE POLICY SUBMISSION OF 17.7.91 RE-PRESENTED?

    On the surface, the circulation of the Policy Submission to
    the other
    Departments in December 1991 meant that proper procedures
    were being
    complied with. But that was not, in fact, the case.

    The Policy Submission circulated in December 1991 was never

  • Page 220 of 397

  • re-
    presented to the National Executive Council. There was
    another Policy
    Submission presented to the National Executive Council in
    February 1992,
    resulting in the decision to award the project to Kinhill
    Kramer Pty Ltd. But
    this Policy Submission was not circulated for the comments
    of other
    Departments.

    The February 1992 submission was not the same as the one
    circulated in
    December 1991. The February 1992 submission differed from
    the one
    circulated in December 1991 (i.e. the one dated 17 July
    1991) in a very
    significant way.

    The February 1992 submission gave a choice between two
    proposals: the
    Tunson/SSDI proposal and a proposal by Kinhill Kramer. The
    submission
    which the various Departments were invited to comment on had
    unequivocally favoured the SSDI proposal. The name “Tunson”
    was not
    referred to and the only reference to “Kinhill Kramer” was
    as a consortium
    partner in an old proposal promoted by Kumagai Gumi.

    [16.13] MORE MATTERS OF CONCERN

    This state of affairs gave rise to some obvious questions:

    Chapter 16

    195

    Why didn’t any of the other Departments get the chance
    to
    comment on the February 1992 submission?

    How could a National Executive Council submission
    change
    so dramatically in a short space of time?

    Why was Kinhill Kramer permitted to lodge a late
    proposal?

    Why was Kinhill Kramer given equal ranking to the
    Chinese

  • Page 221 of 397

  • proposal in the 1992 submission, when previously it was
    part
    of the Kumagai Gumi proposal and ranked number three?
    We will address these questions later in this report.

    * * * * * * * * * *

    Chapter 16

    196

    17. CONCERNS ABOUT CREDENTIALS OF
    TUNSON ENGINEERING CO LTD:
    DECEMBER 1991 – JANUARY 1992

    [17.1] DEPARTMENT OF TRANSPORT CONCERNED ABOUT BONA FIDES OF
    TUNSON ENGINEERING CO LTD

    In December 1991, concerns were being raised within the
    Department of
    Transport as to the bona fides of the Tunson Engineering Co
    Ltd proposal,
    especially its financial aspects. These concerns were, of
    course, quite
    legitimate.

    Apart from the obvious technical defects in the contract the
    Minister had
    signed with the company on 15 October 1991 (see Chapter 14)
    the
    Tunson proposal did not comply with the Terms of Reference
    which the
    Department of Transport had circulated. The Terms of
    Reference had
    required the project to be implemented on a Build-Operate-

  • Page 222 of 397

  • Transfer basis,
    whereas the Tunson contract involved turnkey financing.

    [1 7 21 THE MOST IMPORTANT CONCERN

    Not only that, nobody in the Department of Transport knew
    anything about
    Tunson Engineering Co Ltd or any of the people involved in
    it. Tunson had
    never operated in Papua New Guinea before. It was not known
    whether
    it was a reputable company, whether it had any experience in
    design,
    financing, construction or management of road projects or
    whether it had
    sufficient financial resources to undertake a task of the
    magnitude of the
    Spring Garden Road/Poreporena Freeway project.

    Chapter 17

    197

    This alarming situation had arisen because the negotiations
    which led to
    the contract of 15 October 1991 were conducted secretly by
    the Minister
    for Transport, Mr Temo.

    INVESTIGATIONS CARRIED OUT BY THE DEPARTMENT OF TRANSPORT

    [17.3] DEPARTMENT OF TRANSPORT CONDUCTS ITS OWN INVESTIGATION

    Quite fortuitously, at the time these concerns were being
    aired, the
    Department of Transport had acquired the services of a
    technical adviser
    from Hong Kong, Mr Amin Ebrahim, who was engaged from the
    consulting organisation Wilbur Smith Associates.

    The Department had entered into an arrangement with Mr
    Ebrahim
    whereby he worked in Port Moresby on a fortnight-on-
    fortnight-off basis;
    at the end of each fortnight, he returned home to Hong Kong.
    So, Mr
    Ebrahim was requested to conduct inquiries into Tunson
    Engineering Co
    Ltd on one of his visits to Hong Kong.

  • Page 223 of 397

  • [17.4] COMPANY SEARCH OF TUNSON ENGINEERING CO LTD

    Mr Ebrahim arranged a company search of Tunson Engineering Co
    Ltd
    in early January 1992. He also attempted (unsuccessfully) to
    arrange a
    meeting with the company’s managing director, Mr Siu Chu
    Yuen.
    [EXHIBIT 131]

    Chapter 17

    198

    The company search revealed very little. Mr Ebrahim
    discovered the
    company had only recently been incorporated (in June 1990)
    and all but
    one of its 500,000 shares had been allocated to Mr Siu Chu
    Yen. However,
    the search did not show what the company’s paid-up capital
    was. Other
    details about the company (eg the state of its bank accounts
    and its
    balance sheets and other financial statements) were also
    unavailable.
    [EXHIBIT 130]

    Consequently, this company search was practically useless.
    Tunson
    Engineering Co Ltd could well have been a one-man shelf
    company, with
    a letterhead as its major asset, and the Department of
    Transport would not
    have known.

    [17.5] TECHNICAL ADVISER RECOMMENDS RE-TENDERING OF THE PROJECT

    When Mr Ebrahim returned to Port Moresby in early January
    1992, he
    reported his concerns in a brief to the Secretary for
    Transport dated 9
    January 1992. He gave a detailed analysis of the numerous
    defects in the
    Tunson contract and recommended that the World Bank’s advice
    be
    followed, ie that the project be “re-tendered”. [EXHIBIT 132]

  • Page 224 of 397

  • This recommendation was not followed. Instead, the Department
    of
    Transport persisted with the task of trying to find out more
    about Tunson
    Engineering Co Ltd.

    Chapter 17

    [17.6] DEPARTMENT OF TRANSPORT OFFICERS MEET
    REPRESENTATIVES OF199
    TUNSON ENGINEERING CO LTD IN PORT MORESBY:
    14 JANUARY 1992

    Since February 1991 (when the Minister for
    Transport first went to Taiwan
    and Hong Kong) Mr Leo Moore had maintained
    a watching brief over all
    negotiations concerning the Spring Garden
    Road/Poreporena Freeway
    project. His role in the project was never
    clearly defined. However, from
    the oral evidence he gave to the Ombudsman
    Commission, it is clear he
    had ties with all the various Hong Kong-
    based companies that had been
    a part of the Chinese consortium. He had an
    interest in the outcome of all
    negotiations.

    Mr Moore was regarded by the Department of
    Transport as the Port
    Moresby representative of Tunson
    Engineering Co Ltd, even though the
    Department had been advised that Port
    Moresby-based consulting
    company Tauwala Consultants Pty Ltd had
    been appointed by Tunson to
    act as their agent. [EXHIBITS 120, 121]

    When the officers of the Department decided
    to intensify their efforts to
    check the bona fides of the Tunson
    proposal, they decided to interview Mr
    Moore. He and his wife were called to a
    meeting with Department of
    Transport officials in the office of the

  • Page 225 of 397

  • Secretary on 14 January 1992. The
    meeting was chaired by the Acting Secretary
    for Transport, Mr Zurenuoc.

    [17.7] THE REPRESENTATIVES OF THE CHINESE
    CONSORTIUM STILL
    BELIEVED IN JANUARY 1992 THAT THE PROJECT
    WAS THEIRS

    The officers of the Department of Transport
    informed Mr and Mrs Moore
    of the fundamental problem they saw in the
    contract signed by the Minister
    for Transport on 15 October 1991: Tunson
    Engineering Co Ltd expected
    to be paid for building the freeway – but
    this had not been budgeted for.

    Chapter 17

    200

    It was explained that the project was supposed to be financed
    on a Build-
    Operate-Transfer basis. The contract did not meet this
    requirement. The
    Department also interrogated Mr and Mrs Moore on the
    background of
    Tunson Engineering Co Ltd. They asked the sort of questions
    that should
    have been asked by the Minister for Transport before he
    entered into any
    serious negotiations with this company.

    Following this meeting, the request for more information on
    Tunson
    Engineering Co Ltd was put in writing. [EXHIBITS 135, 141]

    In his evidence to the Ombudsman Commission, Mr Leo Moore
    said he
    was completely taken aback by the attitude of the Department
    of Transport
    officers at that meeting. As far as he was concerned, the
    deal between
    Tunson and the Minister for Transport had already been
    finalised. He
    therefore did not understand why the Department of Transport
    was
    seeking further details about the company. He was offended by
    the
    aggressive manner in which questions were put to him and his
    wife.

  • Page 226 of 397

  • The Ombudsman Commission accepts that this was Mr Moore’s
    genuine
    reaction to this incident. For many months he had been
    involved in
    negotiations with the Minister for Transport. He was shocked
    to find that
    officers in the Minister’s Department would be asking him
    detailed
    questions about things that were really, as he understood the
    situation, the
    business of the Minister.

    [17.8] DID THE DEPARTMENT OF TRANSPORT ACT RESPONSIBLY?

    While this may have been an understandable reaction for a
    person of Mr
    Moore’s background, the Ombudsman Commission does not
    criticise the
    officers of the Department for their actions. The Acting
    Secretary, Mr

    Chapter 17

    201
    Zurenuoc, is to be congratulated for realising the dangerous
    situation
    created by execution of the contract of 15 October 1991 and
    for taking the
    initiative and calling the meeting with Mr Moore.

    The Ombudsman Commission’s only criticism is that this
    meeting should
    have been called a couple of months earlier, as soon as the
    Department
    discovered what the Minister had done.

    [17.9] THE DECISION-MAKING PROCESS HAD BROKEN DOWN

    The meeting between the Department of Transport and Mr and
    Mrs Moore
    gives an indication of the farce that had developed by the
    beginning of
    1992: the Minister had already signed a contract for the
    construction of the
    freeway, but three months later his Department was still
    trying to find out
    whether the proposal was genuine. In the course of doing
    that, officers of
    the Department were interrogating a foreigner who – though
    having a

  • Page 227 of 397

  • vested interest in the project – had no formal connection
    with the company
    *selected” by the Minister, and who was totally confused and
    offended by
    their attitude.

    This was all happening just six weeks before the National
    Executive
    Council decided to award the contract for the construction of
    the freeway
    to a completely different company!

    The decision-making process had become a complete shambles
    and it is
    an embarrassment to our country that this sort of thing was
    allowed to
    happen, because the Minister for Transport took it upon
    himself to handle,
    negotiate and sign agreements without consulting his
    Department.

    Chapter 17

    202
    [17.10] DEPARTMENT OF TRANSPORT SEEKS HELP FROM OTHER
    DEPARTMENTS

    Despite the wide circulation of the draft submission
    “Financing the
    Construction of the Spring Garden Freeway”, the only
    Department to
    respond to the request for comments was the Department of
    Trade and
    Industry (see Chapter 16).

    As stated earlier, it is disappointing that other
    Departments did not
    comment on the draft submission. It is most irresponsible of
    those
    Departments, especially the “key” Departments.

    It is also disappointing that, when the Department of
    Transport formally
    sought advice from two Departments on the contract the
    Minister for
    Transport signed with Tunson, no useful assistance was
    given.

  • Page 228 of 397

  • OTHER DEPARTMENTS GUILTY OF DEFECTIVE ADMINISTRATION

    [17.11] ADVICE SOUGHT FROM DEPARTMENT OF FINANCE AND PLANNING
    AND DEPARTMENT OF ATTORNEY-GENERAL

    On 15 January 1992, the Acting Secretary, Mr Zurenuoc, wrote
    to the
    Office of International Development Agency in the Department
    of Finance
    and Planning. He enclosed a copy of the Tunson contract and
    asked that
    it be reviewed, so the Department of Transport would be in a
    better
    position to advise the Minister for Transport. [EXHIBIT 137]

    Chapter 17

    203

    On the same day, Mr Zurenuoc wrote a similar letter to the
    Department of
    Attorney-General. [EXHIBIT 138]

    Mr Zurenuoc advised the Minister for Transport that he had
    requested this
    advice. [EXHIBIT 136]

    [17.12] INADEQUATE RESPONSE TO REQUESTS FOR ADVICE

    Each of these letters requesting advice should have sent
    alarm bells
    ringing within the Departments which received them. it
    should have been
    obvious to anyone with basic Knowledge of public works
    contracts and the
    requirements of public sector financing that the contract
    with Tunson
    Engineering Co Ltd was seriously and dangerously flawed and
    that the
    Minister for Transport had no right to sign it.

    Any Department reasonably alert to its responsibilities to
    the State, would
    have realised – by a quick examination of the contract –
    that something
    was very, very wrong.

    Unfortunately, however, the responses were inadequate.

  • Page 229 of 397

  • [17.13] DEPARTMENT OF FINANCE AND PLANNING GUILTY OF DEFECTIVE
    ADMINISTRATION

    The Director of the Office of International Development
    Agency in the
    Department of Finance and Planning, Mr Pepson, responded in
    a letter
    dated 13 February 1992:

    Chapter 17 ■

    204

    “I regret to inform you that we are not in a position to
    comment as we
    note the Minister has already signed the contract and
    also we are not
    in the full picture on the status of the
    proposaL” [EXHIBIT 146

    This was a poor response by the Department of Finance and
    Planning.
    The Minister for Transport obviously had no right to sign
    the contract with
    Tunson Engineering Co Ltd. Furthermore, the contract
    purported to
    commit the State to a minimum outlay of $US 50 million,
    which was
    entirely un-budgeted expenditure.

    By failing to offer any advice, the Department of Finance
    and Planning was
    acting in dereliction of its duties to the State and
    therefore was guilty of
    defective administration.

    [17.14] DEPARTMENT OF ATTORNEY-GENERAL ALSO GUILTY OF DEFECTIVE
    ADMINISTRATION

    The only response made by the Department of Attorney-General
    was in a
    letter dated 30 January 1992, from Senior Legal C Mr Singin.
    He

  • Page 230 of 397

  • acknowledged receipt of the contract documents and said the
    Department’s comments would be forwarded in due course. But
    they
    never were. [EXHIBIT 144]

    The Acting State Solicitor, Mr Z Gelu, conceded to the
    Ombudsman
    Commission that written advice was not given to the
    Department of
    Transport about the Tunson contract. In his response to our
    preliminary
    report, Mr Gelu said:

    ‘Though I failed to offer written advice, my officers
    namely Messrs. Robert
    ‘rung and Sumasy Singin provided verbal advice to the
    Department of
    Transport during their consultative meeting. The officers
    were representing
    the Department of Attorney General in these
    meetings.’ [EXHIBIT 2621

    Chapter 17

    205

    We do not regard this as an adequate explanation. The
    meetings referred
    to by Mr Gelu were the meetings held in March and April 1992
    during the
    course of negotiations with Kinhill Kramer. Our concern,
    however, at this
    point, is with the period in January 1992.

    In January 1992, the Department of Attorney-General was
    given notice of
    a contract that was manifestly flawed, which contained
    provisions
    purporting to bind the State to large and long term
    financial commitments
    concerning a number of road projects of national
    significance and which
    had been signed by a Minister clearly acting contrary to the
    Public
    Finances (Management) Act.

    In these circumstances, there was a duty to act immediately
    and give
    written advice to the Department of Transport on what it

  • Page 231 of 397

  • should do. The
    Department of Attorney-General failed to discharge this duty
    and was
    guilty of defective administration.

    [17.15] SUMMARY OF THE DEPARTMENT OF TRANSPORTS ATTEMPTS TO
    INVESTIGATE CREDENTIALS OF TUNSON ENGINEERING CO LTD

    During December 1991 and January 1992 the Department of
    Transport
    tried in vain to find out essential background information
    on the company
    with which the Minister for Transport had signed a contract
    for
    construction of the freeway.

    Assistance was also sought from the Department of Finance
    and Planning
    and the Department of Attorney-General. Both of these
    Departments failed
    in their duty to offer assistance, even though it was clear
    that the Minister
    for Transport had acted unlawfully in signing the contract.

    Chapter 17

    206

    As a result, in January 1992, the Department of Transport was still
    in a
    quandary as to what to do about that contract.

    That problem was soon to become irrelevant, however, because on 13
    February 1992 the Minister for Transport put pressure on his
    Department,
    that was to lead the project in an entirely different direction: he
    suddenly
    instructed his Department to prepare a Policy Submission to the
    National
    Executive Council and consider a very late proposal by Kinhill
    Kramer Pty
    Ltd of Port Moresby. These developments are recorded in Chapters 18
    and 19.

    * * * * * * * * * *

  • Page 232 of 397

  • Chapter 17

    207

    18. MINISTER FOR TRANSPORT EXPEDITES PREPARATION
    OF NEW POUCY SUBMISSION:
    FEBRUARY 1992

    [18.1] ASSUMPTION THAT THE PROJECT WOULD BE AWARDED TO CHINESE
    CONSORTIUM

    Ever since the Ministerial Committee decided to recommend
    awarding the
    contract to the Chinese consortium, it had been assumed that
    decision
    would go to the National Executive Council for ratification.

    The Minister for Transport pre-empted this process by
    negotiating directly
    with the Chinese consortium on a number of occasions (see
    Chapters 12
    and 14). But it seems to have been assumed that the matter
    would
    eventually go to the National Executive Council and that the
    Minister would
    recommend that the project be formally awarded to the Chinese
    consortium. This had been the purpose of the draft submission
    ‘Financing
    the Construction of the Spring Garden Freeway’ (see Chapters
    11 and
    16).

    18.2] A SIGNIFICANT TURN OF EVENTS

    In February 1992 there was a significant turn of events: a
    new National

  • Page 233 of 397

  • Executive Council Policy Submission was prepared. But rather
    than
    favouring the Chinese consortium, the new submission gave the
    National
    Executive Council a choice of two proposals: the Chinese
    proposal and
    a proposal by Kinhill Kramer Pty Ltd of Port Moresby.

    Chapter 18

    208

    In this chapter we trace the events that led to this new
    submission being
    presented to the National Executive Council.

    SECRETARY FOR WORKS BRIEFS THE MINISTER FOR TRANSPORT

    [18.3] MINISTER FOR TRANSPORT ASKS SECRETARY FOR WORKS FOR
    BRIEFING ON SPRING GARDEN ROAD PROJECT
    In early February 1992, the Minister for Transport asked the
    Secretary for
    Works, Mr Hitolo, for a briefing on the Spring Garden Road
    project.

    Mr Hitolo did not advise the Secretary of the Department of
    Transport, Mr
    Amini, that he was briefing the Minister for Transport.

    [18.4] MINISTERS SHOULD NOT OBTAIN “SECRET’ BRIEFS FROM
    DEPARTMENTS FOR WHICH THEY HAVE NO RESPONSIBILITY

    The Ombudsman Commission regards this as a bad administrative
    practice. If the head of a department is requested to provide
    a brief to a
    Minister other than the one carrying political responsibility
    for the
    department he is in charge of, he should advise the head of
    that Minister’s
    department that he has been asked to provide the brief,
    either before or
    immediately after it is given.

    Chapter 18

  • Page 234 of 397

  • 209

    This basic administrative procedure is necessary to ensure
    consistency in
    the advice given to Ministers and to avoid the chaos that
    inevitably results
    when Ministers receive uncoordinated advice from a number of
    different
    sources.

    [18.5] WHY DID THE MINISTER FOR TRANSPORT ASK THE SECRETARY FOR
    WORKS FOR ADVICE?

    The Minister for Transport acted as he did because the
    Secretary for
    Works, Mr Hitolo, until a short time beforehand, had headed
    the Policy
    Secretariat in the Department of Transport. He had been
    responsible for
    the Spring Garden Road/Poreporena Freeway project for a
    considerable
    time and had briefed the Minister for Transport on a number
    of occasions.
    From the evidence given by Mr Leo Moore, it is also apparent
    Mr Hitolo
    knew a lot more about the negotiations with the Chinese
    consortium than
    did the Secretary for Transport.

    [18.6] IT WAS WRONG OF THE SECRETARY FOR WORKS NOT TO ADVISE
    THE SECRETARY FOR TRANSPORT

    When we suggested in our preliminary report that Mr Hitolo
    had erred in
    briefing the Minister for Transport, he said that he had done
    so because,
    at that time, Mr Temo was the Acting Deputy Prime Minister.
    He also gave
    a number of other reasons for his actions. These were:

    Chapter 18

    210

    that presentation of a draft National Executive Council
    submission recommending involvement of Motu-Koitabu

  • Page 235 of 397

  • landowners in the project had been delayed by the
    Office of
    the Secretary for Transport; and

    that landowners were becoming frustrated and suspicious
    about delays in getting the project started and their
    co-
    operation was critical to the smooth implementation of
    the
    project; and

    that the Government had to make a quick decision on the
    type of financing required for the project. [EXHIBIT
    261]

    The Ombudsman Commission appreciates that the Secretary for
    Works
    genuinely believed he was acting properly in briefing the
    Minister for
    Transport. Our concern is not so much that he provided the
    brief. What
    we are critical of is Mr Hitolo’s failure to advise the
    Secretary for Transport
    of what he had done.

    As a matter of sound administrative practice and common
    courtesy, the
    Secretary for Works should have advised the Secretary for
    Transport he
    had received the request from the Minister for Transport. His
    failure to do
    so was defective administration.

    [18.7] THE POSITION OF ACTING DEPUTY PRIME MINISTER IS NOT
    RECOGNISED BY LAW

    One of the reasons given by the Secretary for Works for
    briefing the
    Minister for Transport was that the Minister was, at the
    time, Acting Deputy
    Prime Minister. However, there is no such position recognised
    by the

    Chapter 18

    211
    Constitution or any Act of the Parliament. The Prime Minister
    Act (Chapter
    No. 27 of the Revised Laws) which creates the office of
    Deputy Prime
    Minister and allows the office-holder to be Acting Prime
    Minister in certain

  • Page 236 of 397

  • situations, does not refer to an “Acting Deputy Prime
    Minister”.

    Though the Minister for Transport may have carried the
    unofficial title of
    Acting Deputy Prime Minister, he had no extra official powers
    or
    responsibilities beyond those conferred on him as Minister
    for Transport.

    One of the themes of this report is that there is a need for
    all our Ministers
    and Departmental Heads to become fully acquainted with the
    limits of
    Ministerial powers imposed by the Constitution. The briefing
    of the Minister
    for Transport by the Secretary for Works is an example of the
    type of
    confusion about Ministerial powers that seems to exist. This
    important
    issue is dealt with further in Chapter 39.

    [18.8] PURPOSE OF THE SECRETARY FOR WORKS’ BRIEF TO THE MINISTER
    FOR TRANSPORT

    The purpose of Mr Hitolo’s brief was to bring the Minister
    for Transport up
    to date on what was happening with the project. But Mr Hitolo
    did not
    have a great deal to report. He noted that the draft National
    Executive
    Council submission favouring the Chinese had been prepared by
    the
    Department of Transport in July 1991, but stated that the
    Department was
    still “holding onto it” because views of other Departments
    had not been
    received. [EXHIBIT 145, at page 3]

    Chapter 18

    212

    [18.9] NO MENTION OF KINHILL KRAMER

    The most significant aspect of Mr Hitolo’s brief was that he
    assumed the

  • Page 237 of 397

  • Chinese proposal was still the favoured option. There was no
    indication
    that the Kumagai Gumi/Kinhill Kramer proposal was being
    reconsidered or
    that Kinhill Kramer was to be given the opportunity to lodge
    a fresh
    proposal.

    In retrospect this is very interesting, because it was only
    eighteen days
    after this brief was presented to the Minister for
    Transport, that Kinhill
    Kramer was selected by the National Executive Council to
    undertake the
    project. It is apparent therefore that, iess than three
    weeks before that
    decision, the Secretary for Works was completely unaware of
    the Kinhill
    Kramer proposal.

    But it was not only the Department of Works that was
    ignorant of the
    Kinhill Kramer proposal. The Department of Transport was
    also unaware
    of it, until at least seven days before the National
    Executive Council’s
    decision in favour of that company.

    MINISTER INSTRUCTS DEPARTMENT OF TRANSPORT TO EXPEDITE POLICY
    SUBMISSION

    [18.10] MINISTER FOR TRANSPORT INSTRUCTS HIS DEPARTMENT TO FINALISE
    SUBMISSION TO NATIONAL EXECUTIVE COUNCIL

    On 13 February 1992 the Minister for Transport wrote to the
    Secretary for
    Transport in the following terms:

    Chapter 18

    213

    ‘RE: BURNS PEAK NEC SUBMISSION

    This matter has been dragging on for quite sometime. I
    would like to have the
    matter discussed at the next NEC meeting which is on the
    19th of February,
    1992,

  • Page 238 of 397

  • You are required to have the submission in order for
    presentation on the above date. Discuss with me on any hold
    up on the matter.’ [EXHIBIT 147]

    i.11] NO INDICATION THAT KINHILL KRAMER PTY LTD WOULD BE
    CONSIDERED

    There is no indication in the Minister’s instruction that he
    had changed his
    mind about favouring the Chinese consortium. There is no
    suggestion an
    invitation would be extended to any other consortium to put in
    a late bid.
    The Secretary was simply required to have “the submission”
    ready for
    presentation.

    The fact that the Minister did not ask that the submission be
    altered adds
    to the mystery surrounding the subsequent lodgment of the
    Kinhill Kramer
    proposal.

    The Minister’s instruction was received in the Department of
    Transport
    Secretariat the following day, 14 February 1992, and the
    Secretary made
    the following handwritten notation on it:

    ‘Pis action urgently
    Finance and Attorney General Depts views must be
    obtained.’ (EXHIBIT 147)

  • Page 239 of 397

  • Chapter 18

    214

    [18.12] VIEWS OF OTHER DEPARTMENTS WERE NOT OBTAINED

    It is interesting to note the Secretary’s insistence that
    views be obtained
    from the Department of Finance and Planning and the
    Department of
    Attorney-General. They never were. Both these Departments
    were given
    the opportunity to comment on the previous draft submission
    (the one
    circulated in December 1991 favouring the Chinese
    consortium) – but they
    failed to respond.

    Neither Department was given the opportunity to comment on
    the
    submission which led the National Executive Council to the
    decision in
    favour of Knhill Kramer Pty Ltd.

    [18.13] DEPARTMENT OF TRANSPORT’S IGNORANCE OF THE KINHILL KRAMER
    PROPOSAL

    On 17 February 1992 the Secretary for Transport wrote to the
    Secretary
    for Works.

    This was, in effect, a protest note. Mr Amini had just
    obtained a copy of
    the brief Mr Hitolo gave to the Minister for Transport and
    was obviously
    very cross that the Secretary for Works had prepared it,
    rather than
    himself. Mr Amini stated:

    ‘The matter of Spring Garden Road is the responsibility
    of the Department of
    Transport until such time as the consortium is selected
    and all the detailed

  • Page 240 of 397

  • contracting arrangements are completed. At the time of
    design and
    construction, the DOW will be fully involved.” [EXHIBIT
    149]

    Chapter 18

    215

    Later in this letter, Mr Amini made a very frank and startling
    admission:

    “In the draft NEC submission dated 17 July 1991 on the financing
    of Spring
    Garden Road prepared by you while you were with the Department of
    Transport, you evaluated five consortiums, however, we do not
    have any
    proposals from any companies except the Chinese consortium- If
    you do have
    any of the information, please arrange to send it to me at your
    earliest
    convenience.” [EXIBBIT 149, emphasis added]

    In other words, Mr Amini was saying this: of the five proposals
    short-
    listed for the consideration of the Ministerial Committee in July
    1991, only
    one was still in the possession of the Department of Transport as at
    17
    February 1992 – the Chinese one.

    This was only seven days before the National Executive Council
    decision
    in favour of Kinhill Kramer.

  • Page 241 of 397

  • This disturbing situation prompted two questions for the Ombudsman
    Commission during the course of the investigation:

    What had happened to the remaining four proposals? and

    Was the Kinhill Kramer proposal that was eventually
    approved by the National Executive Council one of the four
    “lost”, or was it a new proposal?

    Chapter 18

    216

    [18.14] WHAT HAD HAPPENED TO THE FOUR LOST PROPOSALS?

    This question has already been addressed in Chapter 11: the
    proposals
    were left in the Minister for Transport’s office on 18 July
    1991 and have
    never been seen since. The Department of Transport had not
    kept copies
    of them, nor requested copies from the companies which
    submitted them.

    [18.15] WAS THE KINHILL KRAMER PROPOSAL A NEW PROPOSAL?

    The Ombudsman Commission put this question to the Executive
    Chairman
    of Kinhill Kramer Pty Ltd, Mr Frank Kramer. He testified
    that previously
    Kinhill Kramer had submitted a joint proposal with Kumagai
    Gumi Ltd. But
    Kumagai Gumi had lost interest in the project and Kinhill
    Kramer decided
    to submit its own proposal.

  • Page 242 of 397

  • This candid response begged other questions:

    Was Kinhill Kramer invited to submit a new proposal?

    If so, when?

    Who invited Kinhill Kramer to submit their proposal?

    These important issues are explored in Chapter 19.

    Chapter 18

    217

    19. HISTORY OF THE PROPOSAL BY
    KINHILL KRAMER PTY LTD

    [19.1] INITIAL INTEREST OF KINHILL KRAMER

    The Executive Chairman of Kinhill Kramer Pty Ltd, Mr F M
    Kramer CBE,
    said his company first became interested in the Spring Garden
    Road/Poreporena Freeway project as early as 1987 or 1988,
    when Mr Roy
    Yaki was the Minister for Transport in the Government led by
    the Rt. Hon.
    Paias Wingti. Mr Yaki had sent Kinhill Kramer a letter
    explaining the priority to be given to the project.
    to be given to the project.

    However, nothing came of this and, according to Mr Kramer,
    the project
    “went quiet for several years”.

    INTEREST SHOWN IN THE PERIOD 1990 – FEBRUARY 1992

    [19.2] TECHNICAL FEASIBILITY REPORT SUBMITTED IN 1990

    The next time Kinhill Kramer showed interest was the first
    half of 1990,

  • Page 243 of 397

  • when it submitted a ‘Technical Feasibility Report’ to the
    Department of
    Transport. [EXHIBIT 7B]

    Chapter 19

    218

    Mr Kramer said this document was given to the Department of
    Transport
    on an unsolicited basis. Its purpose, he said, was to
    demonstrate the
    advantages of constructing an arterial road link from
    downtown Port
    Moresby to Jacksons Airport, to provide a comparison of the
    tunnel/cut
    options and to give an estimate of the project cost.

    The cost of the project was estimated to be K40 million.
    [EXHIBIT 7B at page 15]

    [19.3] NEXT EXPRESSION OF INTEREST: JUNE 1990

    The next time Kinhill Kramer expressed interest was June
    1990, following
    the advertisement inviting expressions of interest.

    By this time Kinhill Kramer had come to an arrangement with
    Kumagai
    Gumi Co Ltd of Japan, a company which Kinhill Kramer had
    worked with
    on other projects in Papua New Guinea: the Morobe Sports
    Complex in
    Lae and PTC Haus and Revenue Haus in Port Moresby.

    A letter dated 25 June 1990 was sent to the Department of
    Transport by
    the “Kumagai Gumi-Kinhill Kramer Consortium”. It stated:

    ‘Dear Sir,

  • Page 244 of 397

  • RE PROPOSED SEAPORT – AIRPORT ARTERIAL LINK
    (INCORPORATING THE BURNS PEAK TUNNEL)

    We refer to various meetings during the past few weeks
    (HTTOLO/ICIMURA)
    regarding the above proposed project.

    We are pleased to advise that Kumagai Gumi Co. Ltd. of
    Japan and ICinhill
    Kramer Pty. Ltd. of P.N.G. have formed a consortium for
    this project.

    Chapter 19

    219

    The Consortium offers the following advantages to the Department.

    (i) Attractive semi-concessional finance package which is already
    known
    and acceptable to the Department of Finance and Planning and
    which
    is currently being used by the P.N.G. Government for a variety
    of
    projects.

    Through Kumagai Gumi Co. Ltd., the Consortium offers tunnelling
    and
    construction expertise from one of Japan’s leading companies in
    these
    fields.

    Through Kinhill Kramer, the Consortium offers the region’s
    largest
    engineering design capabilities for major engineering projects.

    (iv) The Consortium has already commenced a Toll/Revenue Study which
    is expected to be completed in approximately 3 weeks.

    (v) Given the above factors, this Consortium is the only one who
    may be
    in a position to complete the project by the end of 1991.

  • Page 245 of 397

  • For your information, we enclose herewith our two company’s
    brochures, Terms
    and Conditions of the Finance Package available, and a set of
    drawings for the
    project

    The basic proposal is to divide the project into three stages as
    follows:

    Stage 1: From the sea-port area to Wards Road including the first
    barrel
    of a twin-barrel tunneL

    Stage 2 Section from Wards Road to the Kennedy Rd/Boroko Dr./Geauta
    Dr. Curie.

    Stage 3: The Section from Kennedy Rd./Boroko Dr./Geauta Dr. Circle
    to the Airport., including the second barrel of the tunneL

    Details of the total proposal can be finalised by mutual
    arrangement.

    The offer is for a full TURN-KEY package comprising design,
    construction and
    finance.

    Should you be interested in our offer, please contact the
    undersigned.

    Yours faithfully,
    KUMAGAI GUMI KIN LL KRAMER CONSORTIUM
    [Signed]
    MR Y. KIMURA
    General MANOWI
    [EXHIBIT 16]

    Chapter 19

    220

    • [19.4] TERMS AND CONDITIONS OF THE KUMAGAI GUMI-KINHILL KRAMER

  • Page 246 of 397

  • FINANCE PACKAGE NOT IN POSSESSION OF THE DEPARTMENT OF
    TRANSPORT

    The letter of 25 June 1990 suggests the terms and
    conditions of the
    finance package were to be enclosed with the letter.
    However, when we
    examined the files of the Department of Transport, no
    record of these
    terms and conditions could be found.

    When Mr Kramer was asked to produce this letter and its
    enclosures, he
    produced the letter, but the only enclosures attached
    were two identical
    drawings entitled “Moresby-Jacksons/Airport Arterial
    Link Through Burns
    Peak”. [EXHIBIT 16 ]

    The Ombudsman Commission was left in a quandary as to
    what the terms
    and conditions of Kumagai Gumi-Kinhill Kramer’s 1990
    finance package
    actually were. It was only when all the files of the
    Department of Works
    were made available, that we could piece together what
    appeared to be
    the true situation.

    [19.5] WHAT WAS THE KUMAGAI GUMI_KINHILL KRAMER ‘FINANCIAL
    PACKAGE’?

    The files of the Department of Works suggest that there
    were four one-
    page documents attached to the letter of 25 June 1990.
    These were:

    Chapter 19

    221

    1 A document entitled “Information Received from the Export-
    Import Bank of Japan”. This document stated that the typical
    terms and conditions of EXIM financing included an interest
    rate of 7.6% per annum, repayable 5-8 years after the
    completion of the project. [EXHIBIT 16A]

  • Page 247 of 397

  • 2. A flowchart entitled “Kumagai Gumi Co Ltd Overview Flow”.
    This document purported to show some financial
    relationships between the PNG Government, Kumagai Gumi
    Ltd, an un-named Japanese trading company and the EXIM
    Bank. However, as the flowchart was not referred to in the
    letter of 25 June, 1990, it was difficult to understand its
    relevance to the expression of interest. [EXHIBIT 16B]

    3. A document entitled “Operational Framework”. This document
    appeared to describe the various lending schemes available
    from the EXIM Bank. However, the EXIM Bank was not
    actually referred to and so a person reading the document
    could easily have been confused about its relevance.
    [EXHIBIT 16C]

    4. A document entitled “Note to the EXIM Bank Loan
    Conditions”. Like the first document referred to above, the
    purpose of this document appears to have been to describe
    the conditions attached to EXIM Bank financing. The copy of
    the document we obtained from the Department of Works’
    files is confusing, as various sections have been crossed-
    out and others inserted, in an unknown person’s handwriting.
    We are unclear whether the document was presented to the
    Department of Transport in this form. [EXHIBIT 16D]

    Chapter 19

    222

    These four documents were appended to the letter of 25 June
    1990 in a
    way that was, in our view, quite confusing.

    When we suggested this in our preliminary report, Mr Kramer
    replied that
    the documents were appended in a way that was the “industry
    norm”
    given the circumstances. He described the expression of
    interest as a
    “carefully considered business communication prepared by and
    with one
    of the world’s great engineering enterprises”.
    [EXHIBIT 253 paragraphs 5 and 8]

    Be that as it may, our view is that the Department of
    Transport or any
    other governmental body receiving proposals from private
    corporations for

  • Page 248 of 397

  • kina projects should insist on a much higher standard
    of
    documentation.

    [19.6] MR HITOLO’S EXPLANATION

    When we suggested in our preliminary report that the Kumagai
    Gumi-
    Kinhill Kramer proposal was vague and should not have been
    regarded as
    acceptable, we received the following response from Mr
    Hitolo, the former
    head of the Policy Secretariat in the Department of
    Transport:

    “Kumagai Gami-lCinhfil Kramer consortium proposal is the
    classical example
    of the other three proposals that got lost except for the
    Chinese. In fact they
    never submitted a definite proposal consistent with the
    B.O.T. concept of the
    Terms of Reference. So in fact most of them were vague and
    unprofessionally
    done purely letter show of interest or trying to buy time
    for them to organise
    finandng. Hence, the deadline was extended 2 or 3 times as
    I cannot recall
    properly but I know I had discussions with some of the 5
    short listed
    companies. The deadline had expired and the so-called
    Ministerial Committee
    was to be briefed. The Secretary of Department of
    Transport directed Mr
    Parakei and me to brief them and the so-called proposals
    were taken up to
    Parliament. At least he should have stopped it or attend
    himself but this is the
    type of attitude he has been portraying throughout the
    project’.
    [EXHIBIT 265, pant 12]

    Chapter 19

  • Page 249 of 397

  • 223

    Mr Hitolo is suggesting the Department of Transport was put
    under
    pressure by the Minister for Transport to rank the proposals
    for the
    Ministerial Committee meeting in July 1991. He concedes that
    most of the
    proposals, including Kinhill Kramer’s, were only letters of
    interest, rather
    than firm proposals. Under normal circumstances, most of the
    proposals
    would not have been regarded as acceptable.

    [19.7] THE KINHILL KRAMER FINANCIAL PROPOSAL WAS NEVER PUT IN
    PRECISE TERMS

    There was no other occasion on which Kinhill Kramer’s
    financial proposal
    was formally put to the Department of Transport in more
    precise terms
    than in the letter of 25 June 1990. Mr Kramer said that
    further details were
    delivered to the relevant persons and departments on
    numerous
    occasions after June 1990. [EXHIBIT 253, paragraph 5]

    However, this must have been done on an informal basis, as
    there is no
    record of these events in any of the Departmental files and
    Mr Kramer did
    not provide us with any record of the meetings.

    [19.8] FURTHER CORRESPONDENCE IN JULY 1990
    The next occasion on which Kumagai Gumi-Kinhill Kramer
    expressed
    interest was in a letter dated 31 July 1990. This was in
    response to a
    letter from the Department of Transport, inviting a detailed
    proposal from
    the consortium. [EXHIBIT 31]

    Chapter 19

    224

    We reported in Chapter 6 that the Department of Transport was

  • Page 250 of 397

  • wrong to
    only invite proposals from a select group of companies. The
    Kumagai
    Gumi-Kinhill Kramer consortium was among the selected group.

    However, the letter of 31 July 1990 did not elaborate on the
    financial
    proposal that had earlier been given to the Department.

    [19.9] TRAFFIC REVENUE STUDY: AUGUST 1990

    Mr Kramer stated to the Ombudsman Commission that around
    August
    1990, he had submitted a document to the Department of
    Transport
    entitled “Port Moresby to Jacksons Airport Arterial Road Link
    Via Burns
    Peak Tunnel Preliminary Traffic and Revenue Report”. This
    document was
    prepared by Kinhill Cameron McNamara Pty Ltd of Milton,
    Queensland,
    Australia. [EXHIBIT 37]

    The report provided an analysis of expected revenue on the
    assumption
    that certain parts of the Spring Garden Road network would
    become a
    tollway.

    Mr Kramer indicated that, like the “Technical Feasibility
    report” presented
    to the Department of Transport in the first half of 1990, the
    Traffic and
    Revenue Report had been given to the Department of Transport
    on an
    unsolicited basis as an indication of the seriousness of the
    interest in the
    project by the Kumagai Gumi-Kinhill Kramer consortium.

    Chapter 19

    225

    [19.10] FURTHER INTEREST EXPRESSED BY KUMAGAI GUMI-KINHILL KRAMER;
    MAY 1991

    In early 1991 the Department of Transport had prepared a

  • Page 251 of 397

  • document
    entitled ‘Terms of Reference for Spring Garden Road”. In
    Chapter 10 we
    criticised this document: it was vague and poorly prepared.
    These
    concerns were also expressed by the World Bank (see Chapter
    15).

    Another concern was that, like the July 1990 invitation for
    proposals, the
    Terms of Reference document was only circulated to a few of
    the
    companies which had expressed interest in the project. The
    Kumagai
    Gumi-Kinhill Kramer consortium was again among the selected
    group.

    On 20 May 1991 the Kumagai Gumi-Kinhill Kramer consortium
    wrote a
    brief letter to the Department of Transport, in response to
    the Terms of
    Reference document. The letter, again, did not elaborate on
    earlier
    correspondence and stated that the details of the finance
    could be
    “finalised by mutual arrangement.” [EXHIBIT 86]

    [19.11] NO FURTHER CORRESPONDENCE AFTER MAY 1991

    There was no further correspondence between the Kumagai
    Gumi-Kinhill
    Kramer consortium and the Department of Transport after the
    letter of 20
    May 1991.

    Kumagai Gumi Ltd had no further involvement in the project.
    As to Kinhill
    Kramer Pty Ltd, their next involvement was in February 1992
    when they
    were invited to submit another-proposal.

    Chapter 19

    226

    [19.12] FINDINGS REGARDING THE KUMAGAI GUMI-KINHILL KRAMER
    PROPOSAL

    In light of the above, the Ombudsman Commission makes the
    following

  • Page 252 of 397

  • findings regarding the proposal by the Kumagai Gumi-Kinhill
    Kramer
    Consortium:

    1. The consortium formally expressed interest in the
    project on
    three occasions: June 1990, July 1990 and May 1991.

    2. On the first occasion, the consortium’s financial
    proposal was
    attached to the letter of interest. The proposal
    should not,
    in the opinion of the Ombudsman Commission, have been
    regarded by the Department of Transport as a firm
    proposal
    for financing the project. It should only have been
    regarded
    as an expression of interest. The next two letters of
    interest
    failed to give further details.

    3. As a result of the Minister for Transport’s arbitrary
    shortlisting
    procedure in the first half of 1991, Kumagai Gumi-
    Kinhill
    Kramer was one of five consortiums considered by the
    Ministerial Committee at the meeting of 18 July 1991.
    It was
    ranked number three. (See Chapter 9.)

    4. It is impossible to conclude precisely the form in
    which the
    Kumagai Gumi/Kinhill Kramer proposal was presented to
    that
    meeting, because it was one of the four proposals
    subsequently lost. However, it is clear there was
    never at any
    time a single document which embodied the Kumagai
    Gumi
    Kinhill Kramer proposal.

    Chapter 19

    227

    5. It appears the proposal consisted of the three
    letters of
    interest, the collection of documents which
    constituted the
    financial proposal and the Technical Feasibility
    Report
    prepared by Kinhill Kramer in April 1990.

  • Page 253 of 397

  • 6. Thus, the proposal submitted by Kinhill Kramer Pty
    Ltd in
    February 1992 was an entirely new proposal, in which
    Kumagai Gumi Ltd had no involvement at all.

    THE FEBRUARY 1992 PROPOSAL

    [19.13] NO RECORD OF LODGMENT IN DEPARTMENT OF TRANSPORT FILES

    As the Commission has remarked many times in this report,
    the extent to
    which important decisions, policies and events were being
    documented by
    the Department of Transport left a great deal to be desired.
    We make the
    same comment in relation to the events of February 1992,
    when Kinhill
    Kramer Pty Ltd lodged the proposal which resulted in it
    being awarded
    the contract for the Spring Garden Road/Poreporena Freeway
    project.

    There is no record in the Department’s files of when that
    proposal was
    lodged or why IGnhill Kramer was permitted to lodge it. Nor
    is there any
    record of its evaluation by officers of the Department. In
    fact, the only
    record of its existence is its inclusion as an appendix to
    the Policy
    Submission which led to the decision by the National
    Executive Council in
    the company’s favour on 24 February 1992.

    When we made these allegations in our preliminary report,
    the Secretary
    for Transport responded in the following terms:

    Chapter 19

    228

    The Department received this additional information from
    the Minister, who
    requested the information direct from the developer for
    clarification purposes
    at a meeting with the consortium. As I have said above,
    if a proposal has the

  • Page 254 of 397

  • potential to deliver the services, but lacks details,
    additional information can be
    sought.” [EXHIBIT 254, pars 141

    With due respect to Mr Amini, he has not addressed the point
    of our
    criticism.

    A full and proper record should have been made of the
    receipt of the
    Kinhill Kramer proposal. At the very least, a date-received
    stamp on the
    proposal should have indicated when it was received. There
    should have
    been some indication of when, how and by whom the proposal
    was
    evaluated. However, there was just no record of its
    lodgment.

    In the opinion of the Ombudsman Commission this is not good
    enough.
    The lodgment of a proposal for a multi-million kina project
    – especially the
    proposal which is successful – should not be shrouded in
    mystery. The
    Department of Transport failed in its duty to keep a proper
    public record
    of this important event.

    [19.14] ORAL EVIDENCE GIVEN TO THE OMBUDSMAN COMMISSION

    Because of the gap in the Departmental records, the
    Ombudsman
    Commission was forced to rely on oral evidence given in the
    course of the
    investigation to determine the circumstances in which the
    proposal was
    lodged. We considered evidence from the Executive Chairman
    of Knhill
    Kramer, Mr Kramer, the Minister for Transport, Mr Temo and
    the Secretary
    for Transport, Mr Amini.

  • Page 255 of 397

  • Chapter 19

    The evidence of Mr Kramer

    Mr Kramer stated that the February 1992 proposal was submitted as a
    result of a telephone call by an officer of the Department of
    Transport. He
    said the caller advised him that, of all the consortiums which had
    bid for
    the project, there were only two that the Government was still
    interested
    in: the Kumagai Gumi-Kinhill Kramer consortium being one of them. Mr
    Kramer said the caller invited him to update his bid or re-confirm
    it.

    Mr Kramer could not recall who the caller was. Inquiries by the
    Ombudsman Commission during this investigation have also failed to
    reveal the identity of the caller. There is no evidence on the
    Department
    of Transport’s files of this important phone call being made.

    As to the date of the telephone call, Mr Kramer stated, after
    checking
    records kept in his company’s office, that it was on or about 17
    February
    1992.

    Evidence of the Secretary for Transport
    Mr Amini said the Department had reluctantly considered this late
    proposal
    because they had been instructed to do so by the Minister for
    Transport.
    There had been a meeting between the Minister for Transport and
    representatives of Kinhill Kramer which had taken place before the
    Klnhill
    Kramer proposal was lodged.

    As to the date of lodgment, Mr Amini stated that it was at “the last
    minute”.
    By that, he meant that it was only a day or so before the meeting of
    the
    Resource Management Committee which was held on 20 February 1992
    (see Chapter 20).

    Chapter 19

    230

  • Page 256 of 397

  • Evidence of the Minister for Transport

    Mr Temo’s recollection of these events was not very clear,
    but he
    indicated that all of the consortiums which had been
    shortlisted in 1991
    were invited to update their proposals. Mr Temo said only
    Kinhill Kramer
    was “still interested”.

    Mr Temo denied giving Kinhill Kramer favoured treatment:

    ‘Kinhill Kramer proposal was brought in by the
    Department’s advise that the
    Chinese proposals were confusing because of change of
    companies. Also we
    need to have 1 or 2 companies who are already based in
    PNG and who have
    registered interest and have a reasonable grading in the
    Department’s criteria.

    The Secretary advised that the Chinese wanted to bring in
    a lot of Chinese to
    be as labourers they did not have reputation. The
    Secretary advised we should
    give the NEC a choice of expensive, neat and quality work
    and cheap and poor
    Pe°Ple-
    As a result the NEC decision to go for Kinhill Kramer, I
    did not favour any
    company after the Department’s advice` [EXHIBIT 257 pages
    5-61

    [19.15] FINDINGS OF THE OMBUDSMAN COMMISSION REGARDING THE
    FEBRUARYAN2TROPOSAL: KINHILL KRAMER PTY LTD WAS INVITED
    TO LODGE A LATE PROPOSAL

    We do not accept Mr Temo’s claim that all shortlisted
    consortiums were
    given the opportunity to update their proposals. There is no
    evidence in
    the Department of Transport’s files that this was done and
    Mr Temo was
    unable to produce any documentary evidence to corroborate

  • Page 257 of 397

  • the claim.
    We found Mr Amini’s evidence to be more credible than Mr
    Temo’s.

    Chapter 19

    231

    We accordingly conclude that Kinhill Kramer was invited by
    the
    Department of Transport to submit a late proposal and that
    the invitation
    was issued on the instructions of the Minister for
    Transport.

    The opportunity given to Kinhill Kramer to lodge a late
    proposal was 1o1
    given to any other company which had expressed interest in
    the project

    When Mr Kramer was invited to comment on this finding in
    our preliminary
    report, he denied his company had been invited to submit a
    fresh bid. The
    invitation, he said, was only to “update” the 1990
    proposal.

    Irrespective of the exact wording of the invitation – i.e.
    whether the
    telephone caller asked Mr Kramer to “update” the proposal
    or to submit I

    a fresh bid – we conclude that Kinhill Kramer took the
    opportunity to lodge
    a fresh proposal.

  • Page 258 of 397

  • 19.16] KINHILL KRAMER PTY LTD WAS GIVEN FAVOURED TREATMENT

    In his written response to the Ombudsman Commission’s
    preliminary
    report, Mr Kramer denied that it was unfair to other
    interested parties, to
    allow Kinhill Kramer to lodge a proposal in February 1992:

    ‘Your investigators miss the point in rejecting
    Minister Temo’s ‘claim’ that all
    shortlisted consortiums were given the opportunity to
    update their proposals.

    The Tunson Engineering proposal, for one, needed no
    updating. It was only a
    matter of months old – by contrast with the Kumagai
    Gumi proposal (some 2
    years out of date). There could have been no
    unfairness in inviting novation
    of our proposal, in those circumstances.” (EXHIBIT
    253, paragraph 11]

    We accept Mr Kramer’s point that the proposal by Tunson
    Engineering Co
    Ltd did not need updating. But many other proposals di d
    need updating.

    Chapter 19

    232

    [19.17] WHY WERE OTHER CONSORTIUMS NOT CONTACTED?
    We do not understand why other companies whose proposals
    were also
    out of date were not given the opportunity to update them.
    None of the
    three consortiums shortlisted for consideration by the
    Ministerial
    Committee in July 1991, were given this opportunity. Those
    consortiums
    were:

    Periquan’s International Resources Pty Ltd and Pan
    Asia
    Management Consultants Centre

  • Page 259 of 397

  • Tasman Pacific International and Crooks Mitchell
    Peacock
    Stewart Pty Ltd

    McConnell Dowell. [See Chapter 11]

    In particular, it is very strange the Periquan consortium –
    ranked ahead of
    Kumagai Gumi-Kinhill Kramer in July 1991 – was not invited
    to update its
    bid.

    The Ombudsman Commission concludes that Kinhill Kramer Pty
    Ltd was
    given favoured treatment.

    It was unfair to the other companies which had expressed
    interest in the
    project for only IGnhill Kramer to be allowed to submit a
    late proposal. It
    was a totally unsatisfactory situation. It was wrong of the
    Minister for
    Transport to direct his Departmental Head to consider a late
    proposal
    from only one company.

    When this sort of thing happens, it is hardly surprising
    that allegations of
    bribery and corruption surface.

    Chapter 19

    233

    WHEN WAS THE KINHILL KRAMER PROPOSAL LODGED?

    [19.18] DATE OF LODGMENT OF THE PROPOSAL

    The Ombudsman Commission is satisfied that by the time the
    Resource
    Management Committee met on 20 February 1992, the Kinhill
    Kramer
    proposal had been lodged. The records of that meeting reveal
    that the
    Kinhill Kramer proposal was considered. [EXHIBITS 151A &
    152]

    This means the proposal was lodged at some time before 20
    February
    1992.

    The Ombudsman Commission also concludes that the proposal

  • Page 260 of 397

  • was
    lodged no earlier than 17 February 1992, for the following
    reasons:

    Mr Kramer testified he had received the phone call
    inviting
    the proposal on or about that date.

    Mr Amini’s letter to the Secretary for Works of 17
    February
    1992, clearly shows that the only proposal in the
    possession
    of the Department of Transport on that date was the
    proposal by the Chinese consortium (see Chapter 18
    and
    EXHIBIT 149).

    Thus, the Kinhill Kramer proposal was in all probability
    lodged on 18 or 19
    February 1992: only five or six days before the National
    Executive Council
    decided to award the project to this company.

    Chapter 19

    234

    The Ombudsman Commission finds it incredible that following a
    decision-
    making process that had been proceeding for more than two years
    (since
    NEC Decision 14/90 on 24 January 1990) the decision on such an
    important project, with its huge financial implications for the
    State, could
    be made in this way.

    * * * * * * * * * *

  • Page 261 of 397

  • Chapter 19

  • Page 262 of 397

  • 235

    20. RESOURCE MANAGEMENT COMMITTEE RECOMMENDS
    RE-TENDERING OF PROJECT: 20 FEBRUARY 1992

    1

    [20.1] MEETING HELD TO DISCUSS THE PROJECT

    On 20 February 1992 a meeting of the Resource Management
    Committee
    was held to discuss the Spring Garden Road/Poreporena
    Freeway project.
    This meeting was necessary because of the administrative
    requirement
    that submissions to the National Executive Council
    involving un-budgeted
    allocation of resources be considered by the Resource
    Management
    Committee and the National Planning Committee, before
    being finally
    presented. [National Executive Council Submissions
    Handbook, paragraph
    1.23, Exhibit 1]

    The Secretary for Transport, Mr Amini, was present at the
    meeting and
    introduced the Policy Submission entitled “Financing the
    Construction of
    the Spring Garden Freeway”.
    1

    It is clear that, by this stage, the version of the Policy
    Submission being
    discussed was the one actually presented to the National
    Executive
    Council on 24 February 1992, i.e. the one which gave a
    choice of two 1
    consortiums: the Chinese and Kinhill Kramer. [NEC Policy
    Submission No.
    33/92, EXHIBIT 148]

  • Page 263 of 397

  • I

    Chapter 20

    236

    [20.2] RECOMMENDATIONS OF THE RESOURCE MANAGEMENT COMMITTEE

    After the meeting, the Chairman, Mr B Bai CBE, prepared a
    submission
    from the Resource Management Committee to the National
    Planning
    Committee. [EXHIBIT 151 A]

    The submission expressed the following views:

    The Resource Management Committee was not impressed
    with either the Chinese (Tunson Engineering) proposal
    or the
    Kinhill Kramer proposal: neither was considered
    suitable as
    they were based on turnkey financing, ‘Which is too
    expensive for the Government” (paragraph B3).

    Rather than build a freeway from downtown Port Moresby
    to
    the Airport, it would be better to proceed in stages;
    the first
    stage being the Champion Parade-Wards Road section,
    through Burns Peak: “this will enable financing for the
    construction to be easily secured” (paragraph B4).

    The project should be re-tendered: “the Department of
    Transport in calling for tenders should specify and
    advertise
    widely on both Build-Operate-Transfer and Turnkey
    proposals. It should also specify that the Government
    would
    prefer the Build-Operate-Transfer proposal” (paragraph
    B5).

    If the Government cannot secure finance, a loan could
    be

  • Page 264 of 397

  • negotiated to fund the project (paragraph B7).

    Chapter 20

    237

    [20.3] RECOMMENDATIONS CONVEYED TO MINISTER BY SECRETARY FOR
    TRANSPORT

    The Secretary for Transport conveyed the recommendations of
    the
    Resource Management Committee to the Minister for Transport
    on 21
    February 1992. Mr Amini stated:

    Both the proposals, namely the Chinese and the Kinhill
    Kramer’s are turn-
    key proposals. The country has had very bad experience
    from turn key projects.
    Normally, Papua New Guinea does not benefit from turnkey,
    and the benefits
    are derived by the country which provides the funding.
    Also, the turnkey
    financing is very expensive. Although turnkey method of
    financing as proposed
    by the Chinese and Kinhill’ Kramer is convenient, it is
    not in the interest of
    PNG’ [EXHIBIT 152, paragraph 5]

    In the opinion of the Ombudsman Commission, Mr Amini acted
    property
    in bringing these matters to the attention of the Minister.
    As we have
    emphasised throughout this report, the Government’s top
    advisers have
    a duty to give advice fearlessly and forcefully at all times,
    which means it
    is usually necessary to give the advice in writing or confirm
    verbal
    briefings or advice in writing.

  • Page 265 of 397

  • [20.4] SECRETARY FAILED TO ADVISE MINISTER OF REQUIREMENTS OF
    PUBUC FINANCES (MANAGEMENT) ACT

    However, we find it necessary to make a criticism of Mr
    Amini’s advice to
    the Minister.

    We point out that this is a criticism of the Secretary for
    Transport – not a
    condemnation. We appreciate the difficult position he had
    been put in by
    the Minister for Transport’s indiscretion in October 1991,
    when he signed
    the contract for construction of the freeway with Tunson
    Engineering Co

    Chapter 20

    238

    Ltd. We do not intend to cast all the blame on the Secretary for a
    wrongful act of the Minister. The Minister must, clearly, carry
    responsibility
    for his decision to sign that contract (see Chapter 14).

    Our criticism is that, though the Secretary properly suggested to
    the
    Minister in February 1992 that the Champion Parade to Wards Road
    section of the project be put to tender, he did not say why it was
    so
    important to do this.

    As we show in Chapter 35, this project was subject to the normal
    public
    tender procedures in the Public Finances (Management) Act. The
    Secretary should have pointed this out to the Minister. The message
    should have been clearly and unambiguously given to the Minister
    formally, in writing – that his signing of the contract in October
    1991 had
    been unlawful and that it was necessary to follow normal tender
    procedures.

    Mr Amini responded to this allegation in the following terms:

  • Page 266 of 397

  • ‘The Minister was appropriately advised and, as further step, I
    sought advice
    from the Department of Attorney General, Department of Finance
    and Planning
    and the Loans Borrowing Committee but none responded. As far as I
    am
    concerned, what was critical was that the Minister did not have
    the delegated
    powers to sign the contract. That is what I highlighted to him.
    That advice did
    work and no harm was done. The effectiveness of my actions should
    be
    acknowledged.’ [EXHIBIT 254, para 161

    In the opinion of the Ombudsman Commission, this does not adequately
    explain the Secretary’s failure to advise the Minister of the
    requirements of
    the Public Finances (Management) Act, either on this occasion (the
    brief
    of 21 February 1992) or any other occasion.

    Chapter 20

    239

    We have found that the Secretary for Transport did not at any
    time during
    the life of the project, advise the Minister in writing of
    the need to follow
    the public tender procedures in the Public Finances
    (Management) Act.

    As permanent head of the Department of Transport, it was the
    Secretary’s
    duty to ensure that the provisions of the Act were complied
    with in relation
    to his Department. He failed to discharge this important
    duty.

    [20.5] THE SECRETARY’S ADVICE WAS TOO LATE

    The Ombudsman Commission concludes that, while the Secretary

  • Page 267 of 397

  • for
    Transport acted properly in bringing the recommendations of
    the
    Resource Management Committee to the attention of the
    Minister, it really
    was a case of “too-little-too-late”.

    The crucial advice he gave on 21 February 1992 – only three
    days before
    the National Executive Council decided to award the project
    to Kinhill
    Kramer – should have been given in much clearer terms and a
    long time
    before it eventually was.

    [20.6] CHAIRMAN OF RESOURCE MANAGEMENT COMMITTEE PRESENTS
    RECOMMENDATIONS TO THE NATIONAL EXECUTIVE COUNCIL

    The usual procedure with recommendations of the Resource
    Management
    Committee is that they are presented to the National Planning
    Committee,
    before going to the National Executive Council. [EXHIBIT 1,
    para 1.23]

    Chapter 20

    240

    In this case, however, the National Planning Committee
    was by-passed
    and the recommendations were forwarded direct to the
    National Executive
    Council.

    The recommendations were tabled in the National
    Executive Council and
    the Chairman of the Resource Management Committee, Mr
    Bai, on
    direction from the Prime Minister, presented the
    Committee’s views at the
    National Executive Council meeting on 24 February 1992.
    [EXHIBITS 151 A – 151 B]

    [20.71 RESOURCE MANAGEMENT COMMITTEE RECOMMENDATIONS
    REJECTED

    All the recommendations of the Resource Management

  • Page 268 of 397

  • Committee were
    rejected. Instead, the National Executive Council
    decided to award the
    project – a freeway from downtown Port Moresby to
    Jacksons Airport – to
    Kinhill Kramer Pty Ltd.

    * * * * * * * * * *

    Chapter 20

    241

    . THE MINISTER FOR TRANSPORT’S POLICY
    SUBMISSION OF FEBRUARY 1992

    21.1] POLICY SUBMISSION NO. 33 OF 1992: A NEW SUBMISSION

    The Minister for Transport presented Policy Submission No.
    33/92 to the
    National Executive Council at its meeting on 24 February
    1992.
    [EXHIBIT 148]
    Though this document carried the same title as the
    submission dated 17 I
    July 1991 and filed in October 1991, it was a
    fundamentally different
    document (see Chapter 16).
    Whereas the submission dated 17 July 1991 strongly
    favoured the I
    Chinese consortium and ranked a joint proposal from
    Kumagai Gumi and
    Kinhill Kramer as number three in a short-list of five,
    Policy Submission No.
    33/92 gave a choice of two proposals: the Chinese proposal

  • Page 269 of 397

  • and a
    proposal dated February 1992 from Kinhill Kramer Pty Ltd.

    21.2] THE HURRIED PREPARATION OF THE POUCY SUBMISSION

    The Secretary for Transport testified that Policy
    Submission No. 33/92 was
    prepared by his Department on the instructions of the
    Minister for
    Transport. He further stated that the views expressed in
    it were those of
    his Department.
    11]

    Chapter 21

    242

    Mr Amini conceded the Policy Submission was prepared in a
    rush. Indeed,
    it must have been. The Commission found in Chapter 19 that a
    proposal
    from Kinhill Kramer had been lodged on 18 or 19 February 1992
    and in
    Chapter 20 it was shown that Policy Submission No. 33/92 –
    which
    evaluated the Kinhill Kramer proposal – was considered by the
    Resource
    Management Committee at its meeting on 20 February 1992.

    So, the Policy Submission must have been prepared by the
    Department
    of Transport on 18 or 19 February 1992 after the proposal had
    been
    lodged. We note that it carries the date 14 February 1992.
    However, that
    date cannot be accurate because the proposal was not lodged
    until after
    17 February 1992.

    [21.3] THE SUBMISSION WAS POORLY PREPARED AND DEFECTIVE

    The fact that Policy Submission No. 33/92 was prepared

  • Page 270 of 397

  • hurriedly is borne
    out by the quality of the document. It was poorly prepared
    and seriously
    defective in a number of important areas.

    When we made findings to that effect in our preliminary
    report, the
    Secretary for Transport responded as follows:

    ‘NEC Secretariat follows strict guidelines, if it was
    poorly done as alleged they
    would have rejected it. Again when it went -to NEC, no
    such comments were
    made I was there. The submission was prepared by Mr
    Parakei, assisted by a
    World Bank technical assistant. This person is now in
    charge of the multi-
    billion dollar new Hong Kong Airport project’ [EXHIBIT
    254, para 171

    Chapter 21

    243

    With due respect to Mr Amini, he has not answered our
    criticism of the
    Policy Submission. The fact that it was not rejected by the
    National
    Executive Council Secretariat and not adversely commented on
    by
    members of the National Executive Council is no guarantee of
    its quality.

    The Ombudsman Commission retains the view that Policy
    Submission No.
    33/92 was poorly prepared and seriously defective. In this
    and the
    succeeding chapter, we explain our reasons for making this
    finding.

  • Page 271 of 397

  • POOR PRESENTATION OF ISSUES

    [21.4] THE COLLECTION OF CONFUSING APPENDICES

    In finding that Policy Submission No. 33/92 was poorly
    presented, we are
    not referring to the cosmetic appearance of the document. If
    the
    document were to be judged on its appearance, it would have
    to be said
    it appears to be well presented. But the appearance is
    deceptive: a book
    must not be judged by its cover.

    In terms of its presentation of issues, the document is very
    weak. It
    contains numerous appendices, none of which are marked
    alphabetically
    or numerically and none of which are referred to in the text
    of the
    submission. As a consequence, it would have been extremely
    difficult for
    anyone without an intimate knowledge of the project to
    appreciate the
    significance of the appended documents.

    Chapter 21

    244

    All Policy Submissions to the National Executive Council
    should be
    carefully and professionally compiled, so as to present
    issues in a lucid
    and methodical manner to avoid confusion.

    Policy Submission No. 33/92 failed to meet these
    requirements. The ten
    page text of the submission was accompanied by a collection
    of twenty-
    two appendices. The Ombudsman Commission has examined each of
    these and found most to be meaningless and confusing and in
    some
    cases very misleading.

  • Page 272 of 397

  • [21.5] EXAMINATION OF THE DOCUMENTS APPENDED TO THE POLICY
    SUBMISSION

    The twenty-two appendices (which the Ombudsman Commission has
    itself
    numbered for the purpose of this report) and our comments on
    each of
    them, are as follows:

    Appendix 1: this was the document recording the decisions of
    the
    Ministerial Committee on 18 July 1991.
    It related to paragraph 24 of the submission. However there
    was no cross-
    reference in that paragraph to this document. Readers of the
    submission
    were therefore left to their own devices to assess its
    significance.

    Appendix 2: the contract agreement between Tunson Engineering
    Co Ltd
    and the Minister for Transport of 15 October 1991.
    This document related to paragraph 26 of the submission, but
    again there
    was no cross-reference to the document in the text of the
    submission.

    Chapter 21

    245

    Appendix 3: a letter from the Secretary for Transport to the
    Secretary for
    Works dated 5 December 1991.
    This letter was presumably meant to show that the views of the
    Department of Works on Policy Submission No. 33/92 were sought. But
    the letter of 5 December 1991 was actually seeking views on the
    previous
    draft National Executive Council submission (ie the one dated 17
    July
    1991) – not Policy Submission No. 33/92. It was very misleading to
    include
    this letter as an appendix to the submission.

    Appendix 4: an undated memorandum from Tunson Engineering Co Ltd
    to the Minister for Transport regarding the details of a bank
    account.
    This document is not referred to in the text of the submission. It
    is an
    entirely meaningless and irrelevant document.

  • Page 273 of 397

  • Appendix 5: the World Bank Aide-Memoire of 28 September 1991. This
    document related to paragraph 26 of the submission, but there was no
    cross-reference to the document in the text of the submission. The
    text
    also failed to draw attention to the most significant recommendation
    in the
    Aid-Memoire: that the project be re-tendered.■
    Appendix 6: a two page undated and unsourced document entitled
    “Information Received from the Export-Import Bank of Japan”.
    This is a completely meaningless document. It bears no relation to
    anything discussed in the submission.

    Appendix 7: a one page unsourced and undated document headed
    “Operational Framework”.
    This is also a completely meaningless document. It bears no relation
    to
    anything discussed in the text of the submission.

    Chapter 21

    246

    Appendix 8: a letter from the Secretary for Transport to the
    Secretary of
    the Department of Prime Minister dated 5 December 1991.
    Like Appendix 3, it gives the impression that the views of another
    Department had been sought. But the only occasion on which the views
    of the Department of Prime Minister were sought on Policy Submission
    No.
    33/92 was during the course of the Resource Management Committee
    meeting on 20 February 1992. And the Resource Management Committee
    recommended that the project be re-tendered.

    Appendix 9: an unsourced and undated document headed “Appendix B
    Preliminary Traffic and Revenue Report”.
    This document is not referred to in the text of the submission. In
    the way
    it is presented, it is just a meaningless set of toll revenue
    figures
    estimated by an unknown person.

    Appendix 10: an unsourced sixteen page document entitled “Port
    Moresby
    to (Jacksons) Airport Arterial Road Link Via Burns Peak Tunnel
    Technical
    Feasibility Report April 1990”.
    This document actually forms a part of the February 1992 Turnkey
    Proposal by Kinhill Kramer Pty Ltd. But in its presentation, it
    appears to
    be yet another unsourced document, bearing no necessary relation to

  • Page 274 of 397

  • any
    of the proposals referred to in the text of the submission. Without
    a
    proper explanation of its relevance, the inclusion of this document
    as an
    appendix is utterly confusing.

    Appendix 11: a map of the City of Port Moresby.
    There were no maps referred to in the text of the submission. This
    map
    does not show with any precision the scope of the project the
    National
    Executive Council was being asked to approve.

    Chapter 21

    247

    Appendix 12: an unsourced line drawing no. 75024, entitled “Moresby-
    Jacksons/Airport Arterial Link Through Burns Peak: Typical Section &
    Details”.
    The Ombudsman Commission is at a loss to understand the relevance of
    this document. It is entirely meaningless.

    Appendix 13: an unsourced line drawing no. 75025, entitled “Moresby-
    Jacksons/Airport Arterial Link Through Burns Peak: Dual Lane Bridge
    Typical Cross Section”.
    Yet another meaningless appendix.

    Appendix 14: an unsourced line drawing no. 75026, entitled “Moresby

    Jacksons/Airport Arterial Link Through Burns Peak: Typ Tunnel Cross
    Sections”.
    This document was also not referred to in the text of the
    submission.
    Perhaps this document and Appendices 11 and 12 were appended to
    give the appearance that the technical aspects of the project had
    been
    addressed. But they were nothing more than a confusing collection of
    meaningless technical drawings of no relevance whatsoever to the
    text of
    the submission.

    Appendices 15. 16. 17 and 18: standard letters from the Secretary
    for
    Transport to the Departments of Lands and Physical Planning, Trade
    and
    Industry, Attorney-General and Finance and Planning inviting
    comments on
    a draft NEC Submission.
    We have already commented above on the illusion created by including

  • Page 275 of 397

  • these types of letters as appendices. The letters were seeking
    comments
    on the previous submission, i.e. the one which did not favour the
    selection
    of Kinhill Kramer Pty Ltd.

    Chapter 21

    248

    Appendix 19: a letter from the Acting Secretary for Transport to the
    Department of Attorney-General dated 15 January 1992 seeking advice
    on the contract agreement signed by the Minister with Tunson
    Engineering
    Co Ltd.
    This document was not referred to in the text of the Policy
    Submission.
    Its inclusion could only confuse readers of the Policy Submission.

    Appendix 20: a letter from the Acting Secretary for Transport to the
    Office
    of International Development Agency dated 15 January 1992.
    This document was also not referred to in the text of the
    Submission. It is
    another meaningless document.

    Appendix 21: an unsourced two page document entitled “Financial
    Terms”.
    This document was actually quite important. When the Executive
    Chairman
    of Kinhill Kramer Pty Ltd gave evidence to the Ombudsman Commission,
    he testified that this particular two page document, which he
    referred to
    as ”the financial envelope”, had been enclosed – as a separate
    document –
    when the Kinhill Kramer proposal was lodged with the Department of
    Transport. It therefore represented the financial terms on which the
    company was offering to undertake the project.
    The Policy Submission gave no indication that this is what the
    document
    was. It appears – like most of the other appendices – to be yet
    another
    unsourced, undated, meaningless, irrelevant document.

    Appendix 22: the February 1992 Turnkey Proposal by the Kinhill
    Kramer
    Consortium.
    This thirteen page document was probably the most important
    appendix.
    However, it was not expressly referred to in the text of the
    submission.

  • Page 276 of 397

  • Any person – especially a busy Minister – who was required to
    quickly
    read the text of the submission may not have realised the
    significance of
    this document and could quite easily have skipped over it.

    Chapter 21

    249

    As we explain below, the Kinhill Kramer proposal was, in
    fact, quite vague.
    With respect, if the members of the National Executive
    Council had
    realised how vague the proposal really was, they may not
    have voted in
    favour of it.

    [21.6] WAS THE POUCY SUBMISSION MEANT TO BE CONFUSING?

    Policy Submission No. 33/92 was so confusing in its
    presentation, the
    question must be raised whether this was intentional.
    We refrain from making that finding. Our view of the
    situation is that,
    following the Minister for Transport’s direction of 13
    February 1992, the
    Department of Transport was required to hurriedly compile
    the submission.
    The Department’s efforts to put together a proper
    submission were
    hampered by the Minister’s instruction that it include the
    late proposal by
    Kinhill Kramer Pty Ltd.

    That proposal had to be evaluated and the Department’s
    assessment of
    it incorporated in the submission. This assessment was
    also done in a
    hurry. With the Minister putting pressure on the
    Department and the
    deadline for filing the submission fast approaching, it
    appears that a
    number of documents were hastily and carelessly appended
    to the text of
    the submission to give it a bulky appearance. The members
    of the
    National Executive Council were expected to find their own
    way through
    the jungle of papers.

    In addition to the confusion that the presentation of the

  • Page 277 of 397

  • document must
    have caused, the Ombudsman Commission is surprised the
    National
    Executive Council entertained it, when its contents were
    seriously
    defective.

    Chapter 21

    250

    DEFECTS IN THE POLICY SUBMISSION

    [21.71 SEVEN SERIOUS DEFECTS IN THE POLICY SUBMISSION 1992

    In the opinion of the Ombudsman Commission, the text of
    Policy
    Submission No. 33/1992 is seriously defective in a number of
    important
    areas.

    The Ombudsman Commission has identified seven serious
    defects. These
    relate to:

    1. The establishment of the Ministerial Committee.

    2. The illusion that an equal opportunity had been given
    to
    numerous companies and consortiums to submit proposals.

    3. The failure to properly advise the National Executive
    Council
    of the recommendations of the World Bank.

    4. The failure to give any explanation of non-compliance
    with
    the Public Finances (Management) Act and the Public
    Works
    Committee Act.

    5. The failure to refer to the recommendations of the
    Resource
    Management Committee.

    6. The failure to properly explain the history of the
    Kinhill Kramer
    proposal.

    7. The favourable assessment of the Kinhill Kramer
    proposal.

  • Page 278 of 397

  • Chapter 21 II

    i

    251
    a

    [21.8] FIRST DEFECT: ESTABLISHMENT OF THE MINISTERIAL COMMITTEE
    I
    Paragraph 7 of the Policy Submission No. 33/92 refers to
    “a special ■
    Ministerial Committee” being established by the National
    Executive Council
    to speed up development of this project. However, no such
    Committee ■
    was ever established (see Chapter 11).

    The members of this committee assumed powers and
    responsibilities
    which they did not lawfully have.

    [21.9] SECOND DEFECT: ILLUSION THAT AN EQUAL OPPORTUNITY HAD
    BEEN GIVEN TO ALL COMPANIES AND CONSORTIUMS TO SUBMIT
    PROPOSALS

    Paragraphs 8 and 9 refer to the various expressions of
    interest that were
    lodged and clearly give the impression that all of the
    companies and
    consortiums were given a fair opportunity to lodge
    proposals for the
    project. As the Ombudsman Commission explained earlier in
    this report,
    that was far from the truth (see particularly Chapter 9).

    The shortlist for this project was arbitrarily prepared by
    the Minister for
    Transport without advice or consultation. Some companies
    which had
    expressed interest did not even receive an acknowledgement
    from the
    Department of Transport. Some unknown foreign companies
    which had no
    experience operating in Papua New Guinea were given
    special treatment
    by the Minister for Transport. Other companies were
    shortlisted, though
    they had no experience at all in road construction or
    design.

  • Page 279 of 397

  • Chapter 21

    252

    The statement in paragraph 8 that the proposals of fifteen
    consultants
    were presented to a Steering Committee meeting on 31 July
    1990 is false
    and misleading (see Chapter 7).

    There was never any meeting at which all of the proposals
    were fairly and
    objectively evaluated

    [21.10] THIRD DEFECT: FAILURE TO PROPERLY REPORT THE
    RECOMMENDATIONS OF THE WORLD BANK

    The World Bank reccommended in September 1991 that the
    Spring Garden
    Road/Poreporena Freeway project be re-tendered (see Chapter
    15).

    Paragraph 25 of the Policy Submission referred to the World
    Bank Mission
    which made this recommendation but did not make any mention
    of that
    recommendation.

    The National Executive Council was not advised of this
    crucial piece of
    advice from the World Bank.

    [21.11] FOURTH DEFECT: FAILURE TO EXPLAIN NON-COMPLIANCE WITH
    NORMAL TENDERING PROCEDURES

    The decision-making process which led to the State entering
    into the
    contract with Kinhill Kramer Pty Ltd on 27 May 1992 was
    fundamentally
    unlawful. Legislation such as the Public Finances
    (Management) Act and
    the Public Works Committee Act was completely ignored (see
    Chapters 35
    and 36).

    Chapter 21

  • Page 280 of 397

  • 253

    The Policy Submission should have given some explanation as
    to why
    these laws were by-passed. It did not do this.

    [21.12] FIFTH DEFECT: FAILURE TO REFER TO THE RECOMMENDATIONS OF
    THE RESOURCE MANAGEMENT COMMITTEE
    Only four days before the National Executive Council decided
    to award the
    project to Kinhill Kramer Pty Ltd, the Resource Management
    Committee
    recommended that the project be implemented in three
    distinct phases
    and put to tender.

    The Policy Submission failed to refer to either of these
    crucial
    recommendations.

    [21.13] SIXTH DEFECT: FAILURE TO EXPLAIN THE HISTORY OF THE KINHILL
    KRAMER PROPOSAL

    Paragraph 8 claimed that some of the fifteen original
    companies which
    expressed interest in the project had sought an extension of
    time to lodge
    their proposals, but that these requests had been rejected.
    Paragraph 13
    stated that of the original fifteen, only the Kinhill Kramer
    consortium
    presented a detailed technical and financial proposal. These
    statements
    were very misleading and false.

    The truth is that many of the original fifteen companies
    were not given a
    fair opportunity to submit proposals. Also, in its original
    proposal, Kinhill
    Kramer Pty Ltd was linked with Kumagai Gumi Ltd of Japan.
    The proposal
    which was before the National Executive Council in February
    1992 was a
    new proposal, not involving Kumagai Gumi Ltd. Kinhill Kramer
    had been

    Chapter 21

    254
    given a considerable extension of time. In fact, as we
    revealed in Chapter

  • Page 281 of 397

  • 19, the new proposal was lodged only five or six days
    before the National
    Executive Council met.

    The Policy Submission should have carefully explained
    all this for the
    benefit of the members of the National Executive
    Council.

    [21.14] SEVENTH DEFECT: FAVOURABLE ASSESSMENT OF THE KINHIll,
    KRAMER PROPOSAL

    The most serious defect in National Executive Council
    Policy Submission
    No. 33/92 was its unjustified favourable assessment of
    the Kinhill Kramer
    proposal.

    This unrealistic assessment is something which, we
    believe, affected the
    integrity of the whole decision-making process
    concerning this project. It
    is dealt with as a separate matter in the next chapter.

    * * * * * * * * * *

    Chapter 21

    255

    22. FAVOURABLE ASSESSMENT OF THE

  • Page 282 of 397

  • KINHILL KRAMER PROPOSAL

    [22.1] THE NATIONAL EXECUTIVE COUNCIL POLICY SUBMISSION WAS

    SERIOUSLY DEFECTIVE

    We have concluded that the Policy Submission which
    resulted in the

    project being awarded to Kinhill Kramer Pty Ltd was
    poorly prepared and

    seriously defective (see Chapter 21).

    One of the most serious defects was the favourable
    assessment of the

    I
    Kinhill Kramer proposal. That assessment was
    unjustified.

    I
    When this opinion was expressed in our preliminary
    report, we received

    responses from two persons: the Secretary for
    Transport, Mr Amini and

    I
    the Executive Chairman of Kinhill Kramer Pty Ltd, Mr
    Kramer.

    Mr Amini’s response was as follows:
    I

  • Page 283 of 397

  • I
    ‘This is a matter of professional judgement.
    The detailed proposals were all
    put before National Executive Council. Nothing
    was hidden from them. I
    believe National Executive Council always make
    an informed decision. My
    Department, however, did argue for more time
    but this request was rejected I
    by National Executive Council. This is not
    defective administration.’
    [EXHIBIT 254, para 18]

    1

    Chapter 22

    256

    Mr Kramer’s response was similar to Mr Amini’s:

    “Are you suggesting that the most serious defect(s)” was
    the “favourable
    assessment of the Kinhill Kramer proposal”. What does this
    mean? The
    assessment was made by the Department of Transport and
    presumably proper
    advice was obtained in respect of such assessment The
    statements in the
    report in relation to this heading are made without any
    proper evidence of same
    and show, with respect, a very limited understanding of

  • Page 284 of 397

  • the bureaucratic
    procedures in respect of matters such as this.” [EXHIBIT
    253, pars 131

    Having considered these responses, the Ombudsman Commission
    retains
    the view that the favourable assessment of the Kinhill Kramer
    proposal in
    the Policy Submission was unjustified. In this chapter, we
    explain the
    reasons for drawing that conclusion.

    Before we do that, it is necessary to specify what the
    Kinhill Kramer
    proposal consisted of, when it was evaluated by the
    Department of
    Transport.

    OUTUNE OF THE KINHILL KRAMER PROPOSAL

    [22.2] WHAT DID THE KINHILL KRAMER PROPOSAL CONSIST OF?

    This is not a straightforward issue, because there is no
    official record of
    the Department of Transport receiving the Kinhill Kramer
    proposal (see
    Chapter 19). It was therefore difficult to conclude, by just
    looking at the
    Department’s files, what exactly the Kinhill Kramer proposal
    was. In
    addition, because of the confusing manner in which Policy
    Submission No.
    33/92 was compiled, it was virtually impossible for anyone
    reading it to
    work out what the Kinhill Kramer proposal consisted of.

    Chapter 22

  • Page 285 of 397

  • 257

    However, after questioning the Executive Chairman of
    Kinhill Kramer Pty
    Ltd, Mr Kramer, we are satisfied that the proposal
    lodged on 18 or 19
    February 1992 actually consisted of two separate
    documents:

    1. A spirally-bound document, consisting of twenty-
    nine pages (not
    numbered consecutively), entitled:

    “Independent State of Papua New Guinea
    Department of
    Transport Seaport/Airport Link
    Incorporating Burns Peak
    Tunnel and Spring Garden Road Turnkey
    Proposal The IGnhill
    Kramer Consortium February, 1992”.
    [EXHIBIT 150]

    2. A stapled document of two pages, entitled:

    “Financial Terms”. [EXHIBIT 151]

    [223] THE TURNKEY PROPOSAL DOCUMENT

    This document consisted of twelve pages of text, which
    formed the main
    part of the proposal, and two appendices.

    [22.4] THE TEXT OF THE PROPOSAL

    The proposal was introduced in the following terms:

    ‘The Joint Venture Consortium of Kinhill Kramer
    and a Major Contractor
    through their many years of construction
    involvement in Papua New Guinea.
    Fully appreciate the environmental, social,
    political and financial aspects of a

  • Page 286 of 397

  • project of this magnitude. In response to known
    Terms of Reference the Joint
    Venture Consortium shall assemble in the
    Preliminary Planning Phase an
    experienced multi-disciplined team to fully
    investigate and develop an economic
    solution in which in the social and environmental
    criteria will take precedence.’
    [EXHIBIT 15O, para. I.0)

    Chapter 22

    258

    The text of the proposal continued:

    “The Joint Venture Consortium shall consist of two
    principle partners being
    Kinhill Kramer and a Major Civil Engineering and
    Construction and Consulting Engineering. [sic]
    The Project Management and preliminary design
    phase followed by detail
    design and construction supervision will be
    undertaken by Kinhill Kramer the
    background of Kinhill Kramer is set out in the
    attached appendices.

    During the Construction Phase, Kinhill Kramer
    shall act as the Superintendent
    of the Works. Any disputes between the
    Government’s Executing Agency and
    the Construction Consortium shall be resolved at
    the sole discretion of the
    Superintendent.

    Construction works including detailed tunnel
    design shall be undertaken by
    a Major contractor (yet to be named). The
    Contractor shall also arrange the
    financing of the project. The background of the
    Contractor shall be provided
    at a later stage.” [EXHIBIT 150, pars 2.0,
    emphasis added]

    [22.5] KINHILL KRAMER DID NOT HAVE A CONSORTIUM

  • Page 287 of 397

  • The significant thing to note is that, though the
    proposal was lodged in the
    name of “the Kinhill Kramer consortium”, Kinhill Kramer
    did not have a
    consortium at all. It was a sole proposal by Kinhill
    Kramer Pty Ltd. At the
    time of lodgment of the proposals, the other member(s)
    of “the
    Consortium” did not exist

    When this point was made in our preliminary report, the
    Executive
    Chairman of Kinhill Kramer Pty Ltd responded in the
    following terms:

    ‘The fact that the Kinhill Kramer Consortium did
    not have a company to do
    the contracting work is not surprising. There are
    any number of major
    contractors available who are qualified and have
    expertise to carry out this
    type of work. There is no attempt by myself in the
    proposal to mislead the
    State. My statements envisaged “a consortium*.
    This was accepted by the
    State. At all times, our nomination of the
    contractor was subject to National
    Executive Council approval. Selection of the
    contractor would have been, in
    the circumstances, a condition precedent to
    overseas funding (as you are
    obviously aware).” [EXHIBIT 253, pars 15]

    Chapter 22

    259

    [22.6] FINANCIAL TERMS IN THE TURNKEY PROPOSAL
    a

  • Page 288 of 397

  • The other feature of the text of the Turnkey Proposal
    document is the

    section headed “Financial Terms”. It states:

    ‘The Lump Sum Cost of the Project shall be Sixty
    Million Kina (IC60,000,000) for
    stages 1, 2 and 3 which consist of a four (4) lane
    road link between downtown
    Port Moresby and Jackson’s Airport including a 2
    lane single barrel tunnel
    through Burn’s Peak.

    In addition to this Lump Sum Cost a Five Million
    Kina (K5,000,000) contingency
    sum has been allowed for. The use of the
    contingency sum shall be jointly at
    the discretion of the Secretary of the Department
    of Transport and the
    Executive Chairman of Kinhill Kramer.

    The Consortium shall arrange a loan for the entire
    construction cost of Sixty
    Million Kina together with the Five Million Kina
    contingency sum. The terms
    of the repayment shall be 10 – 15 years repayment
    period with a 3 year initial
    grace period and at an interest rate not exceeding
    10%.

    The commencement of loan period and the grace
    period shall coincide with
    the signing of formal contract between the
    Consortium and the Government’s
    Executing Agency. The contract shall be exempt from
    all Government Import
    Duties and taxes.” [EXHIBIT 150, para. 6.0]

    It will be observed that the conditions on which the lump
    sum price of the

    project would be paid by the State were expressed in very
    broad terms:

    the interest rate was not specified, except to say it
    would not exceed 10%

  • Page 289 of 397

  • and the period for repayment of the loan was stated
    generally to be “10 –

    15 years”.

    [22.7] THE APPENDICES

    There are two appendices which also formed part of the
    Turnkey Proposal

    document. (The contents page of the proposal indicated
    there were three

    appendices, but the first one – “Company Profiles” – is
    missing; perhaps

    because, when the proposal was completed, Kinhill Kramer
    did not have

    a consortium partner.)

    Chapter 22

    260

    The two appendices are:

    “Appendix B: Preliminary Traffic and Revenue Report”.
    This is a one page summary of the document of August
    1990, [EXHIBIT 37] which gives an analysis of expected
    revenue on the assumption that certain parts of the
    Spring
    Garden Road network would become subject to a toll.

    “Appendix C: Port Moresby to (Jacksons) Airport
    Arterial
    Road Link via Burns Peak Tunnel Technical Feasibility

  • Page 290 of 397

  • Report
    April 1990″. [EXHIBIT 7B]
    This is the document which, Mr Kramer said, had been
    submitted to the Department of Transport in 1990.

    [22.8] THE “FINANCIAL TERMS” DOCUMENT

    This was the second part of the Kinhill Kramer proposal.

    Mr Kramer stated that this two-page stapled document – which
    he referred
    to as “the Financial Envelope” – was “attached” to the
    “Turnkey Proposal”
    document. Though the “Financial Envelope” was physically
    separate from
    the spirally bound main proposal, the two documents were
    clearly meant
    to be read together.

    It is apparent that the purpose of the “Financial Envelope”
    was to
    elaborate on the rather general terms in which the
    corresponding section
    of the “Turnkey Proposal” document was expressed.

    Chapter 22

    261

    [22.9] THE KINHILL KRAMER PROPOSAL WAS PREPARED IN A RUSH

    It is also apparent, from the way in which the Kinhill
    Kramer proposal was
    presented (e.g there were a number of typographical errors
    and the “Key
    Personnel” section did not mention the company’s Executive
    Chairman) •
    that the Kinhill Kramer Proposal was prepared in a rush.

    Also, the fact that the Financial Terms document was
    physically separate
    from the Turnkey Proposal document, shows that the
    proposal was
    hurriedly put together.
    Mr Kramer admitted as much in his evidence to the
    Ombudsman ■
    Commission. He testified that, as soon as he got the phone
    call from the
    Department of Transport on 17 February 1992, inviting him

  • Page 291 of 397

  • to “update” the
    Kinhill Kramer bid, he contacted Kumagai Gumi Ltd to see
    if they were still
    interested.

    When Kumagai Gumi said they were not still interested, Mr
    Kramer was
    put in quite a predicament: he had to lodge a proposal
    without a
    consortium partner. And because he didn’t have a
    consortium partner, he
    could not say who the financier would be.

    Kinhill Kramer Pty Ltd had always intended to arrange
    finance for the
    project through an export finance corporation such as the
    EXIM Bank of
    Japan or the Export Finance Insurance Corporation of
    Australia. But these
    institutions invariably insist that the major contractor
    is a resident of the
    country exporting finance for the project. So, if Kinhill
    Kramer didn’t have
    a contractor, they also didn’t have a financier.

    When these findings were made available in our preliminary
    report, Mr
    Kramer made the following comments:

    Chapter 22

    ‘The heading under this section [Le.’the Kinhill Kramer
    proposal was prepared
    in a male] is subjective and improper. It is further
    evidence of the bias shown
    in the report. Paragraph 2 under this heading is absurd.
    I do not understand
    how the physical presentation of a document could show
    ‘that it was hurriedly
    put together’. Indeed if it was ‘hurriedly put together’
    what does this mean?.
    Presumably it means it was done in a hurry.’ [EXHIBIT
    253, para

    We note that Mr Kramer did not deny that the proposal was
    done in a
    hurry. There is no other conclusion that can be drawn.

    The finding that the proposal was prepared in a rush is not
    meant as a

  • Page 292 of 397

  • criticism of Kinhill Kramer or its Executive Chairman. It is
    simply a finding
    of fact, which is reported here to illustrate the unusual
    circumstances
    leading to and in which the National Executive Council came
    to make its
    decision on 24 February 1992.

    THE PRICE OF THE PROJECT

    [22.10] DIFFICULTIES IN PRICING THE PROJECT

    As to the task of quoting a lump sum price for the project,
    this also
    presented Mr Kramer with some difficulty. He stated to the
    Ombudsman
    Commission that he was concerned that the company did not
    have
    sufficient information on which to base a price. He said
    that Kinhill Kramer
    Pty Ltd, was reluctant to submit a price to the Department
    of Transport
    without having had an opportunity to consider the
    geotechnical report of
    Coffey Partners International, which had been arranged by
    the Department
    of Works (see Chapter 8).

    Chapter 22

    263

    [22.11] DEPARTMENT OF TRANSPORT HAD CONSISTENTLY FAILED TO
    SPECIFY THE SCOPE OF THE PROJECT

    Mr Kramer’s claim that he had insufficient information on
    which to base a
    price is an understatement. As we have noted a number of
    times

  • Page 293 of 397

  • previously, the scope of the Spring Garden Road/Poreporena
    Freeway
    project was poorly defined from the very beginning – when
    the National
    Executive Council decided that “the Burns Peak Road” should
    be
    constructed.

    It was, by February 1992, more than two years since that
    vague decision
    was made and in all that time the Department of Transport
    had been
    unable to define, with any precision, the route of the
    freeway or its basic
    engineering characteristics. Even in February 1992 – almost
    a year after
    the results of the geotechnical investigation were released
    – no decision
    had been made on the tunnel/cut option.

    Mr Kramer said that, when the Kinhill Kramer proposal was
    lodged, the
    company had not seen the results of the geotechnical
    investigation. In
    these circumstances, any figure that Kinhill Kramer Pty Ltd
    were to quote
    would, at best, have to be a rough “guesstimate”.

    This was a very unsatisfactory situation. In the opinion of
    the Ombudsman
    Commission it is very poor administrative practice – and it
    defies common
    sense – to expect companies to submit firm proposals when
    the exact
    scope of a project is not known. The Department of Transport
    must be
    held responsible for allowing this unsatisfactory situation
    to develop. The
    Terms of Reference released – selectively – in early 1991
    did not specify
    the end points of the freeway. Twelve months after that, the
    Department
    of Transport still hadn’t specified exactly what it wanted.

    Chapter 22

    264

    [2212] K25 MILLION INCREASE IN THE PRICE OF THE PROJECT

  • Page 294 of 397

  • There is one part of Kinhill Kramer’s February 1992 proposal
    that needs
    to be specially noted: the substantial increase in the price
    of the project.

    When Kinhill Kramer submitted its “Technical Feasibility
    Report” to the
    Department of Transport in April 1990 it quoted a price for
    the Spring
    Garden Road/Poreporena Freeway project of K40 million (see
    Chapter 19
    and Exhibit 7B, page 15).

    But, when the February 1992 proposal was submitted, the price
    had
    increased to K65 million.

    This obviously should have been a matter of concern to the
    Department
    of Transport when it was evaluating the February 1992
    proposal. How can
    the cost of a road project increase – without explanation –
    by more than
    60% in less than two years? How could such a huge increase be
    overlooked by the Department of Transport in its evaluation?

    The following explanation of the K25 million increase in the
    price of the
    project was provided by Mr Kramer:

    ‘The 1990 figure (MOM) was a highly qualified ESTIMATE or
    the likely cost
    of the project, on 1990 prices.
    A price produced some 2 years later must, first, be
    adjusted for inflation
    (escalation) at 10%.

    That, alone, escalates the K4OM to around the project bid
    calculated to the
    medium point of actual constructions period.

    Much more importantly, the February 1992 bid was no longer
    an ESTIMATE
    but fl2(1:2AMMMAPMa accepting liability for all and any
    increases and
    contingencies’. [EXHIBIT Z53, para 181

  • Page 295 of 397

  • Chapter 22

    265

    [22.13] 1990 PRICE ALTERED BY KINHILL KRAMER

    We noted earlier in this chapter that the 1990 document was
    included as

    one of the appendices to the February 1992 proposal.
    However, pages 10

    and 15 of the 1990 document – which deal with the project
    cost – were

    altered when these pages were annexed to the. 1992
    proposal.

    Page 10 of the 1990 document stated:

    “Subject to prevailing costs, at the time of
    commissioning of the new proposed
    Arterial Road and Tunnel the cost of construction
    would be in the range of
    KINA 40.0 million, and the cost breakdown is given in
    Table 3.’
    [EXHIBIT 7B, page 15]

    By contrast, the altered version, attached to the February
    1992 proposal,

    stated:

  • Page 296 of 397

  • “Subject to prevailing costs, at the time of
    commissioning of the new proposed
    Arterial Road and Tunnel the cost of construction
    would be in the range of
    KINA 60,0 million, and the cost breakdown is given in
    Table 3 based on 1992
    construction rates.” [EXHIBIT 150, page 15 of Appendix
    C]

    Page 15 of the 1990 document, which contained the cost
    breakdown, was

    also altered when it appeared in the February 1992
    proposal. A

    comparison of the different versions of the cost breakdown
    reveals that all

    cost items were increased markedly, as follows:

    Chapter 22

  • Page 297 of 397

  • 266

    DESCRIPTION COST SHOWN IN COST SHOWN IN ALTERED
    ORIGINAL 1990 VERSION ANNEXED TO 1992
    DOCUMENT PROPOSAL

    Relocation cost K 500,000.00 K 750,000.00
    Roadworks K12,600,000.00 K 24,250,000.00
    Bridgeworks K 2,100,000.00 K 7,000,000.00
    Tunnel Works K16,250,000.00 K 20,000,000.00
    Traffic Lights K 1,500,000.00 K 2,000,000.00
    Contingencies K 3,295,000.00 K 5,000,000.00
    Fees K 2,295,000.00 K 6,000,000.00
    Total Say K40,000,000.00 K 60,000,000.00
    [See EXHIBIT 7B, page 15 & EXHIBIT 150, page 15 of Appendix C]

    The point to be emphasised here is that, since the April 1990
    document
    was attached as an appendix to the February 1992 proposal, it was
    reasonably to be expected it would be a replica of the April 1990
    document. There was no indication that the figures in the appendix
    had
    been altered or ‘updated’.

    Mr Kramer stated that the amendment of the 1990 schedule to 1992
    values was made expressly at the direction of the Department of
    Transport, which had the 1990 document. He rejected the suggestion
    that
    the alteration of the figures could have been misleading.
    [EXHIBIT 253, para 18]

    Chapter 22

  • Page 298 of 397

  • 267

    [2214] DEPARTMENT OF TRANSPORT SHOULD HAVE EXPLAINED K25 MILLION
    PRICE INCREASE

    Having considered Mr Kramer’s explanation, we still do not
    believe it was
    right for the Department of Transport to allow a document
    dated April
    1990 to be annexed to a 1992 document and altered without
    any
    indication being given that the 1990 document had been
    altered.
    [EXHIBIT 253, para 18]

    The Department of Transport should not have asked for or
    accepted the
    document in that form. At the very least, the Department
    should have
    indicated in the Policy Submission to the National Executive
    Council that
    the 1990 figures had been updated. The Department should
    have
    explained why the estimated price of the project had
    appeared to have
    risen K25 million in less than two years and whether this
    was
    reasonable.

    KINHILL KRAMER PTY LTD GIVEN FAVOURABLE ASSESSMENT DESPITE ITS VAGUE
    PROPOSAL

    [22.15] THE RECOMMENDATIONS OF POLICY SUBMISSION NO 33 OF 1992

    The aspect of Policy Submission No. 33 of 1992 which made it
    very
    different to the previous one prepared by the Department of
    Transport
    was that it gave the National Executive Council a choice of
    two
    consortiums:

    Chapter 22

    268

    The Chinese consortium, which the Submission referred
    to

  • Page 299 of 397

  • as the “Tunson Engineering consortium”.
    .QB

    The “Kinhill Kramer consortium”, which was referred
    to as a
    consortium, even though the proposal had been lodged
    by
    Kinhill Kramer on its own.

    The recommendations of the Policy Submission were expressed
    in the
    following terms:

    “It is recommended that either consortium can be
    selected. Tunson Engineering
    consortium is proposing a better financial package
    provided the source of
    funding is confirmed. The Kinhill Kramer consortium has
    advantage of
    experience and quality product.

    It is also recommended that NEC direct Department of
    Finance and Planning
    and Department of Transport to carry out further
    negotiations with the
    approved consortium in consultation with the Department
    of Attorney General.
    Alternatively, it may be desirable to seek B.O.T or full
    turnkey proposals for
    design, construction and finance from all the companies
    and consortiums who
    registered interest’ [EXHIBIT 148, page 10]

    [22.16] NEITHER CONSORTIUM DESERVED TO BE SELECTED

    This was a very strange set of recommendations. The third
    paragraph
    seems to be an admission that all companies and consortiums
    which had
    expressed interest in the project had not been asked for
    proposals. This
    was, of course, quite true.

  • Page 300 of 397

  • Chapter 22

    269

    In making this recommendation the Minister for Transport and
    the
    Department of Transport seem to have expressed a lack of
    confidence in
    their recommendation in the first paragraph that “either
    consortium can be
    selected”. The Ombudsman Commission considers that such a
    lack of
    confidence was warranted.

    In the opinion of the Ombudsman Commission, neither
    consortium
    deserved to be selected. The decision-making process that led
    to the
    National Executive Council being faced with this choice of
    two proposals
    was a shambles. There was insufficient information on which
    the National
    Executive Council could base an informed decision.

    Unfortunately, the Department of Transport was under pressure
    from the
    Minister to expedite the project. So, rather than
    recommending to the
    Minister that the project be put to tender in the normal and
    lawful manner,
    the Department inserted the vague recommendation that “it may
    be
    desirable” to seek more proposals.

    [2217] THE FAVOURABLE ASSESSMENT OF KINHILL KRAMER PTY LTD

    Though the submission recommended that “either consortium can
    be
    selected”, this was not actually consistent with the
    comparison of the two
    proposals provided. On page 8, five criteria were identified
    and the
    proposals were ranked as follows:

  • Page 301 of 397

  • Chapter 22

    270

    CRITERION KINHILL KRAMER TUNSON

    Financier’s credibility excellent not clear

    Financial package satisfactory to excellent
    good

    Relevant experience excellent confined to
    China and not
    clear

    Expected quality of excellent satisfactory
    tunnel

    Employment Papua New Guinea could be Chinese for
    at least for unskilled labour
    unskilled work

    [EXHIBIT 148, page 8]

    Kinhill Kramer was ranked more favourably than the Chinese
    consortium
    on all but one of the criteria (the financial package). It is not
    surprising
    therefore that, though the final recommendation was that either
    proposal
    could be selected, the National Executive Council decided in favour
    of
    Kinhill Kramer.

    However, a dose examination of Kinhill Kramer’s ranking on four of
    the

  • Page 302 of 397

  • five criteria shows the whole decision-making process to be very
    suspect
    and verging on a farce.

    Chapter 22

    271

    FINANCIAL CRITERIA

    [22.18] THE CRITERION OF “FINANCIER’S CREDIBILITY”

    On this criterion, Kinhill Kramer was ranked “excellent”.
    The Ombudsman
    Commission finds this quite remarkable, because there was no
    indication
    given in the Kinhill Kramer proposal of who the financier
    was going to be.

    The Ombudsman Commission is at a loss to see how any
    reasonable
    person could conclude from the Kinhill Kramer proposal that
    their
    financier’s credibility was “excellent”. Nobody – including
    Kinhill Kramer –
    knew where the finance was going to come from. The reason
    for this was
    explained earlier: after Kumagai Gumi dropped out of the
    negotiations,
    Kinhill Kramer did not have a consortium partner to do the
    construction
    work and so their source of finance was not known.

    Mr Kramer explained to the Commission that the documents
    were drafted
    in such a way that it was a matter for the consortium to
    obtain the proper
    finance within the parameters set in the proposal. We accept
    that that was,
    in fact, the situation. [EXHIBIT 253, paragraph 19] •

    Nevertheless the Ombudsman Commission concludes that it was
    irresponsible of the Department of Transport to give the
    company an
    “excellent’ ranking on the issue of “financier’s
    credibilityTM, when the

  • Page 303 of 397

  • proposal did not name who the financier was going to be.

    Chapter 22

    272

    [22.19] THE CRITERION OF “FINANCIAL PACKAGE’

    On the issue of “financial package”, Kinhill Kramer was said
    to be
    “satisfactory to good”. But satisfactory to good, compared
    to what? The
    Policy Submission made the following comments:

    “From the cost point of view, Kinhill Kramer at K60m
    would be a less attractive
    consortium to Tunson Engineering at US$49383m.
    From the point of view of financial package, Tunson
    Engineering consortium
    has proposed a better package.° [EXHIBIT 148, page 71

    It is apparent that the only benchmark against which the
    Kinhill Kramer
    financial package was being judged was the financial package
    contained
    in the contract agreement the Minister for Transport had
    signed with
    Tunson Engineering Co. Ltd on 15 October 1991 (see Chapter
    14).

    We have already remarked on the atrocious quality of that
    document. It
    was so bad it could not be taken seriously. There was also
    the problem
    of whether that financial package truly represented the
    Chinese
    Consortium’s proposal. The Minister for Transport had been
    negotiating
    deals with at least three different Hong Kong-based
    companies during
    1991, as well as a couple of different agencies of the
    Chinese

  • Page 304 of 397

  • Government; so how could it be said that the package
    referred to in the
    Tunson contract was the real one?

    There was also a huge question-mark surrounding the bona
    fides of the
    Tunson company. The Department of Transport had still not
    established
    whether the company was genuine.

    Chapter 22

    273

    [22.20] THERE WAS NO GENUINE STANDARD AGAINST WHICH THE KINHILL
    KRAMER PROPOSAL COULD BE JUDGED

    In these circumstances, it was very dangerous to use the
    Tunson financial
    package as a basis for comparison with the Kinhill Kramer
    package. The
    point is, there was no genuine standard against which the
    Kinhill Kramer
    financial package could be judged. Kinhill Kramer was
    quoting an all-up
    cost of K65 million, but there was no guarantee that that
    figure was
    realistic or that it represented value for money.

    [2 91] THE SECRETARY FOR TRANSPORTS COST ANALYSIS

    When we suggested in our preliminary report that the
    Department of
    Transport had failed to check Kinhill Kramer’s price, the
    Secretary for

  • Page 305 of 397

  • Transport , Mr Amini, disagreed:

    This statement is incorrect The Department did
    check the price of 1065
    million. The Department in accepting the cost was
    guided by the World Bank
    financed Port Moresby Road Needs Study which was
    undertaken by Ow Arup
    Consultants. The study estimated the cost of the
    section of the project The
    report was reviewed by Department of Transport,
    Department of Works,
    Department of Finance and Planning and the World
    Bank and was accepted.’
    [EXHIBIT 254, pare 191

    Mr Amini’s cost analysis can be summarised as follows:

    Town to Boroko Drive K40 million
    Boroko Drive to Airport K 5 million
    Fly-overs K 5 million
    Detailed design K 5 million
    Cost increases K16 million
    TOTAL COST K 71 MIWON

    Chapter 22

    274

    With respect to the Secretary for Transport, we find his explanation
    unsatisfactory. The analysis he provided was in the form of a
    response
    to the preliminary findings of the Ombudsman Commission. However,
    there was no document in the Department of Transport files which
    supported his analysis.

    It appears that the Secretary has only provided the Ombudsman
    Commission with a retrospective justification of why, in his view,
    the price
    of K65 million was acceptable.

    He has been unable to convince us that any proper cost analysis of
    the
    project was undertaken before the Kinhill Kramer financial package
    was
    described in the Policy Submission as “satisfactory to good”.

  • Page 306 of 397

  • Even if we accept that the analysis presented by Mr Amini was
    undertaken
    when the Kinhill Kramer proposal was being evaluated, it was, in our
    opinion, a bad piece of administration to evaluate the cost of a
    definite
    proposal for a project by comparing it with (what could only have
    been)
    a rough estimate made in the course of a general study of the road
    needs
    of Port Moresby.

    The Ombudsman Commission maintains the view, expressed in the
    preliminary report, that there was no genuine standard against which
    the
    Kinhill Kramer proposal could be judged and that the Department of
    Transport failed to properly check Kinhill Kramer’s price.

    Chapter 22

    275

    [22.22] WAS THE PRICE QUOTED BY KINHILL KRAMER TOO HIGH?

    In making the finding that there was no genuine
    standard against which
    the Kinhill Kramer financial package could be judged,
    the Ombudsman
    Commission is not saying that the price quoted by
    Kinhill Kramer was
    definitely too high.

    This point needs to be emphasised because, in his
    response to our draft
    report, the Executive Chairman of Kinhill Kramer Pty
    Ltd was concerned
    that the Ombudsman Commission had made a judgment on
    this issue.
    Mr Kramer stated:

    ‘Repeatedly, your investigators show bias in

  • Page 307 of 397

  • their treatment of our February
    1992 bid price – wrongly putting it in a
    context of Tunson’s figure of K47114 –
    odd. This was NOT the comparable figure.

    Was it deliberate malice that led your
    investigators to omit the further K17M
    – odd for overpasses? Any why do they fail to
    disclose the ‘strings’ attached
    to the Chinese bid?

    The relevance of these comments is that the
    writer was repeatedly dismayed
    upon reading your draft to note the repeated
    and plainly malicious
    characterisation of our bid as incapable of
    comparison. There cannot always
    be a convenient benchmark for the indolent
    investigator – in this case, our bid
    has to be judged on its own merits. If that
    requires careful expert engineering
    assessment of our bid’s component elements, so
    be it.’ [EXHIBIT 253, para 11]

    Mr Kramer also provided copies of submissions made to
    the Ellis
    Commission of Inquiry concerning the price of the
    project, to support his
    claim that the price of K65 million was not excessive.
    (A Commission of
    Inquiry into the Spring Garden Road/Poreporena Freeway
    project was
    established on 30 August 1992; see Chapter 34.)

    Chapter 22

    276

    Counsel’s submissions

  • Page 308 of 397

  • Counsel for Kinhill Kramer, S.M. Littlemore, made the following
    submissions during the course of the Inquiry:

    The Kinhill Kramer February bid was not excessive, in all the
    circumstances.
    It represents no more than 10% escalation of the 1990 estimate
    (NB that was an
    estimate and not a guaranteed maximum price); it is less than Mr
    Clark would
    have fixed it at; it is much more favourable than the Chinese Bid
    – which was
    highly qualified, open-ended, conditional upon the granting of
    further mad
    building contracts at, obviously, massive budgets, and was
    plainly contrary to
    the National Interest in that it would have imported coolie
    labour; yet had been
    Ministerially approved!

    It is a figure at which the mad would have been built – at a high
    standard (Mr
    Sharp agrees) and with the customary high quality of Kinhill
    Kramer projects
    (see Commission Document 0.181page 10).

    My clients are entirely confident that hindsight will prove the
    State lost a
    bargain when it cancelled this Contract.

    Nobody else has offered to build this mad at any price under
    these conditions,
    and nor will they in future.” [EXHIBIT 249B, Page 9]

    The Clark report

    A report from J A Clark, of the Australian consulting firm Jackson
    Clark
    Pty Ltd, emphasised the considerable risks undertaken by the Kinhill
    Kramer consortium as a result of the special nature of the design-
    finance-
    construct contract that was to be entered into:

    “I consider that the terms of the Contract impose risks and
    obligations on the
    Consortium that would usually be borne by a Principal to the

  • Page 309 of 397

  • Contract I
    believe that the terms of the Contract had the effect of making
    the Contract
    Amount a fixed price inclusive of any claims the Consortium may
    make and
    thus the Consortium was prudently required to make some judgment
    as to the
    risks of carrying out their obligations under the Contract and to
    include what
    they considered to be an appropriate monetary allowance in the
    Amount they
    agreed to perform those obligations.

    Chapter 22

    277

    In the usual form of Contract for mad works of this nature used
    in Papua New
    Guinea or elsewhere allowances for the costs of many of the
    those risks would
    not be included in the Contract Amount but would be the subject
    of additional
    payments by the Principal to the Contractor if and to the extent
    those risks
    emerged as actual events.” [EXHIBIT 249A, page 4]

    This report emphasised the substantial cost risks arising from the
    unknown quality of the material accruing from the excavation of
    Burns
    Peak, the inability of the consortium to recover the costs of any
    delays by
    way of claims on the State, the uncertainty surrounding the extent
    of
    relocation of public utilities, the likely problem of land
    acquisition and the
    consortium’s obligation to arrange finance for the project within
    the
    maximum rate provided for in the contract of 9.5%.

    The report concluded:

  • Page 310 of 397

  • ‘n my opinion and experience all of the above matters represent
    substantial
    risks which are likely to occur on a mad construction project in
    Papua New
    Guinea. In my experience significant costs would result from
    their occurrence.
    The question of what financial provision should be made for
    those risks is a
    matter for those who would be accepting the risks and their
    assessment of them
    together with their ability to overcome them as they arose.
    Whatever provision
    was allowed would be additional to costs which were taken from
    the more
    usual type of construction contract. The events giving rise to
    such cost
    allowance may not occur at all, occur in part, or occur in
    excess of the
    allowance but that is the risk a contractor accepts in such a
    contract as this.

    In return the Principal has obtained the benefit of a fixed cost
    for the project
    without him being exposed to the cost of these substantial
    risks.

    If the Contract Amount for the Poreporena Freeway is to be
    compared against
    the cost of other freeway projects it is important that the
    comparison be made
    with a project having a similar work content and similar risk to
    the contractor.’
    [EXHIBIT 249A page 8]

    Chapter 22

    278

    [2223] CONCLUSION AS TO THE PRICE OF THE PROJECT AND THE RANKING

  • Page 311 of 397

  • GIVEN TO THE KINHILL KRAMER FINANCIAL PACKAGE

    We reiterate that we have nat concluded that the price of K65
    million for
    the Spring Garden Road/Poreporena Freeway project was
    definitely too
    high. Nor have we said that the State obtained a bad deal
    when this
    price was agreed to.

    But what we do say is this: if the State was getting value
    for money or
    as Kinhill Kramer asserted – “a bargain”, that situation had
    only come
    about by pure accident.

    During the course of this investigation, nothing could
    convince the
    Ombudsman Commission that the decision to award the project
    to the
    Kinhill Kramer consortium had been made in a competent,
    rational,
    methodical or professional manner.

    Many other companies had expressed interest in this project,
    but they
    were prevented from providing any competition for the Kinhill
    Kramer
    proposal by the arbitrary and mysterious short-listing
    process that
    occurred in 1990 and 1991 and by the Minister for Transport’s
    decision to
    invite only Kinhill Kramer to update its proposal, when the
    National
    Executive Council was on the verge of making its decision in
    February
    1992

    So, although the Kinhill Kramer financial package was
    described in the
    Policy Submission as “satisfactory to good”, it could well
    have been one
    of the most expensive options available to the Government,
    since there
    was no public tender.

    Chapter 22

    279

  • Page 312 of 397

  • The Ombudsman Commission therefore concludes that, at the
    time the
    National Executive Council made its decision in favour of
    Kinhill Kramer,
    nobody could possibly have known how good the Knhill Kramer
    financial
    package was. It was entirely irresponsible for the
    Department of Transport
    to proffer the view that it was “satisfactory to good”.

    ENGINEERING CRITERIA

    [22.24] THE CRITERIA OF “RELEVANT EXPERIENCE” AND “EXPECTED QUALITY
    OF TUNNEL”

    On both of these criteria Kinhill Kramer was ranked
    “excellent”. These
    rankings reaffirmed the comparisons drawn earlier in the
    Policy
    Submission, where it was stated:

    ‘From the point of view of experience, Kinhill Kramer
    consortium offers
    tunneling and construction expertise having the region’s
    largest engineering
    design capabilities.
    Turman Engineering Consortium’s, and more specifically
    the Second Surveying
    and Designing Institute’s experience is confined to China
    which still uses old
    Russian methods of design.’ [EXHIBIT 148, page 7]

    The claim that Kinhill Kramer has “the region’s largest
    engineering design
    capabilities” is a direct quote from the letter to the
    Department of
    Transport from the then Kumagai Gumi-Kinhill Kramer
    Consortium dated

  • Page 313 of 397

  • 25 June 1990. [EXHIBIT 16, page 1, para (iii) referred to in
    Chapter 19]

    Chapter 22

    280

    In his response to the Ombudsman Commission’s preliminary
    report the
    Executive Chairman of Kinhill Kramer Pty Ltd maintained that
    Kinhill Kramer
    is the region’s largest engineering design firm. [EXHIBIT
    253, para 20] We
    make no comment on this claim. Our point is that the direct
    quote from
    one of the consortium’s own letters to the Department is not
    the sort of
    objective assessment that should have been contained in a
    Policy
    Submission of this nature. It must be comparatively assessed
    independently.

    As to the claim that the Chinese consortium “still uses old
    Russian
    methods of design”, the Ombudsman Commission was unable to
    find any
    basis for this very prejudicial statement.

    The most alarming aspect of Kinhill Kramer’s “excellent”
    ranking on
    “relevant experience” and “expected quality of tunnel” is,
    as pointed out
    earlier, Kinhill Kramer had not decided on a contractor to
    undertake the
    construction phase of the project.

    [22.25] KINHILL KRAMER DID NOT HAVE A CONTRACTOR

  • Page 314 of 397

  • In Part 2 of their proposal Kinhill Kramer described their
    own role as being
    confined to project management, preliminary design, detail
    design and
    construction supervision:

    “Construction works including detailed tunnel design
    shall be undertaken by
    a Major contractor (yet to be named). The Contractor
    shall also arrange the
    financing of the project. The background of the
    Contractor shall be provided
    at a later stage.” [EXHIBIT 150]

    Chapter 22

    281

    This was reaffirmed in Part 3.6 of the submission:

    The Major Contractor shall undertake all the construction
    works for the project
    including the construction of the tunnel through Burns
    Peak.”
    [EXHIBIT 1501

    In these circumstances, it was almost deceitful to suggest
    that the Kinhill
    Kramer consortium’s experience and the expected quality of
    the tunnel
    they would build were “excellent”. How could Kinhill Kramer
    possibly be
    given such a favourable assessment when it was not known
    what
    company was going to build the tunnel and the rest of the
    freeway?

    WHO WAS RESPONSIBLE FOR THE IMPROPER ASSESSMENT OF KINHILL KRAMER?

  • Page 315 of 397

  • [22.26] SUMMARY OF THE DEPARTMENT OF TRANSPORTS ASSESSMENT OF
    THE KINHILL KRAMER PROPOSAL

    The Kinhill Kramer proposal evaluated by the Department of
    Transport was
    given a very favourable assessment.

    On each of the criteria “financier’s credibility”, “relevant
    experience” and
    “expected quality of tunnel”, Kinhill Kramer was given an
    “excellent”
    ranking. This was despite the fact that nobody – including
    Kinhill Kramer
    Pty Ltd – knew who was going to build or finance the
    freeway.

    We can only assume that a great deal of credit was being
    given to Kinhill
    Kramer on account of its past performance and experience in
    project
    supervision.

    Chapter 22
    tw

    282

    No proper checks had been done on whether Kinhill Kramer’s
    quote of
    K65 million plus interest represented value for money. And no
    mention
    was made of the fact that Kinhill Kramer’s price in 1990 was
    only K40
    million.

    There was no genuine standard against which the figure of K65
    million
    could be judged. The only other option offered to the
    National Executive
    Council was the proposal of Tunson Engineering Co. Ltd. But
    there were

  • Page 316 of 397

  • so many problems with it, it simply should not have been
    taken seriously.

    The favourable assessment of the Knhill Kramer proposal was
    therefore
    quite unjustified. Not only that, it was irresponsible. It
    was the Department
    of Transport who made this assessment. However, the blame for
    allowing
    this situation to arise does not rest only with the
    Department of Transport.

    (22-27]THE IMPORTANCE OF FOLLOWING CORRECT PROCEDURES
    The problem of having to make a last-minute evaluation of a
    very late
    proposal from only one company would not have arisen if
    proper
    procedures had been followed by the Minister for Transport in
    the first
    place.
    If the project had been put to public tender, all interested
    parties would
    have had an equal opportunity to lodge a proposal.

    A competitive bidding environment would have been created and
    there
    would have been ample time for a careful and methodical
    assessment of
    the available alternatives, by an experienced Supply and
    Tenders Board –
    not by the Minister for Transport or a self-appointed
    “Ministerial
    Committee” or a selected group of officers within one
    Department.

    Chapter 22

    283

    Furthermore, if normal procedures had been followed, the rumour and
    innuendo which have surrounded the National Executive Council’s
    decision
    to award the project to the Kinhill Kramer consortium would not have
    flourished.

    * * * * * * * * * *

  • Page 317 of 397

  • Chapter 22

    284

    23. NATIONAL EXECUTIVE COUNCIL DECIDES TO AWARD
    PROJECT TO KINHILL KRAMER CONSORTIUM:
    24 FEBRUARY 1992

    [23.1] DECISION MADE ON MONDAY 24 FEBRUARY 1992

    The National Executive Council made its decision on which
    consortium
    would be awarded the Spring Garden Road/Poreporena Freeway
    project
    on Monday 24 February 1992.

    NEC Decision No. 36/92 was recorded in the following terms:

    On 24th February, 1992 Council:-
    1, approved Kinhill Kramer consortium as the
    successful tenderer

  • Page 318 of 397

  • to finance the construction of the Spring Garden
    Freeway; and

    2. directed the Departments of Transport, Attorney
    General and
    Finance and Planning to immediately carry out
    further
    negotiations with Kinhill Kramer with a view to
    finalising all
    contractual and financial arrangements within two
    (2) months
    as of the date of this decision.” [ITT 153)

    [232] CIRCUMSTANCES IN WHICH THE DECISION WAS MADE

    The best thing that can be said about this decision is that
    it was made
    without a proper regard for normal procedures. But there are
    many other
    inferences that might be drawn from the circumstances in
    which it was
    made.

    Chapter 23

    285

    To recap, it must be borne in mind that on 17 February 1992 –
    only seven days before the National Executive Council made its
    decision – the
    days before the National Executive Council made its decision –
    the
    Department of Transport knew nothing about the approved
    proposal. It
    was hastily put together on 18 or 19 February 1992 and the
    Department
    of Transport was instructed by the Minister for Transport to
    quickly
    evaluate it. The proposal was, by necessity, short on detail
    and vague.
    The company awarded the project did not, at that stage, have a
    consortium partner to build the freeway and no finance had been
    arranged. Nevertheless, the proposal was rated highly by the
    Department
    of Transport.

  • Page 319 of 397

  • The proposal went to the National Executive Council without
    being
    evaluated by the Department of Works or the Department of
    Finance and
    Planning. Normal tender procedures were ignored.

    Despite the obvious shortcomings in the proposal and the fact
    that there was no other against which it could properly be
    compared and despite
    was no other against which it could properly be compared and
    despite
    there being no evidence that anybody had properly checked
    whether the
    quoted price of K65 million was realistic, the National
    Executive Council decided to approve it.
    decided to approve it.

    L3] ALLEGATIONS OF BRIBERY AND CORRUPTION
    L3] ALLEGATIONS OF BRIBERY AND CORRUPTION

    The Ombudsman Commission is not surprised that following
    announcement of the decision, there were numerous allegations
    of bribery and corruption. We do not propose to recite them
    because they were not
    and corruption. We do not propose to recite them because they
    were not
    supported by evidence.

    Chapter 23

    286

    However, we refrain from finding that there was no bribery or
    corruption
    involved in the decision-making process which led to the
    National
    Executive Council decision. Having considered all the
    circumstances which
    led to the decision and, in particular, the consistent
    failure to follow normal
    procedures, we cannot say that there was no corruption.

  • Page 320 of 397

  • [23.4] CHALLENGES TO OPEN FINDING ON THE CORRUPTION ISSUE

    When we stated in our preliminary report that we refrained
    from finding
    there was no bribery or corruption we were challenged by two
    respondents.

    The Executive Chairman of Kinhill Kramer Pty Ltd. Mr Kramer,
    stated:

    ‘The draft report asserts that ‘many other inferences can
    be drawn from the
    circumstances in which (the decision) was made’.

    That is wrong.

    It is trite to say that inferences can only be drawn from
    proves facts.

    There is – as you acknowledge — NO EVIDENCE of any
    bribery or corruption.

    The ‘environment of corruption” reference – is patently
    borrowed from the
    findings of the NSW LC.A.0 inquiry into the Metherell
    allegations and, as
    such, is superficial and unworthy. [EXHIBIT 253, paragraph
    211

    The Chairman of the National Executive Council at the
    relevant time. Prime
    Minister Namallu stated:

    With due respect, I must beg to take issue with your
    highly offensive words.-
    To suggest that you “refrain from finding that there was
    no bribery’, is
    completely unnecessary.
    In stating what you stated * you clearly intended to place
    in the minds of the
    readers that the Cabinet members have been corrupted, but
    you can’t prove it!

    Chapter 23

  • Page 321 of 397

  • 287

    You next … create the environment “under which a
    reasonable mind could
    assume corruption’. We suggest this is defamatory. Your
    allegations are
    unbecoming and unfitting for a high constitutional office:

    The dangerous trend you now set whereby the National
    Executive
    Council decisions are exposed to adverse public comment
    and

    The consequent danger of exposing State Ministers to
    ridicule and
    unfounded, unsubstantiated scandalous comment.

    You, as Constitutional Office holders owe a duty to
    conduct your affairs with
    dignity, proper decorum and to suggest nothing or
    insinuate nothing that is
    not a fact or truth.

    We respectfully suggest you delete from your report, the
    [paragraphs where
    the Ombudsman Commission indicated that it refrained from
    finding that there
    was no bribery or corruption]. It adds nothing to your
    general objectives,
    suggests corruption and bribery and creates distress and
    anxiety amongst all
    former National Executive Council members.

    Questions of bribery and corruption should be taken up
    specifically so that
    individual leaders, if any, may be dealt with according to
    law and not tried
    and convicted by innuendo, insinuation and
    suspicion.’ [EXHIBIT 256, page 2]

    [23.5] THE DECISION-MAKING PROCESS MUST BE ABOVE SUSPICION

    With respect to the two respondents who challenged our
    preliminary
    findings, the Ombudsman Commission states categorically that
    it reserves

  • Page 322 of 397

  • the right, in investigations of this nature, to form and
    report an opinion on
    the likelihood that corruption was involved in the decision-
    making
    processes of government.

    If, as in this case, we have found no proof of corruption, it
    does not follow
    that we will ignore the issue altogether.

    One of the central themes of this report is that the decision
    – making
    process must be above suspicion.

    Chapter 23

    288
    Decisions such as who is going to be awarded a multi-million
    kina
    contract to build a freeway and how much it is going to cost
    should be
    made fairly, openly and in accordance with law.

    When decisions are not made in this way, people become
    suspicious,
    allegations of corruption inevitably arise and reputations
    suffer. That is the
    price paid by all those involved in the making of these
    decisions, and also
    by those who benefit from them.

    Procedures are provided by law and they must be followed for
    the benefit
    and interests of all concerned.

    [23.61 MEEIMBORMENTIDELGOBERIEMON

    In the opinion of the Ombudsman Commission, the environment
    for
    corruption was created by the way in which normal and
    established
    procedures were disregarded soon after the National Executive

  • Page 323 of 397

  • Council
    decided in January 1990 to go ahead with the project; in
    particular by the
    way in which the Minister for Transport, Mr Temo, took
    control of the
    decision-making process.

    Many of the ingredients of corruption were present, due to:

    a flagrant disregard of normal tender procedures

    selected companies being invited to lodge proposals

    private negotiations involving the Minister for
    Transport
    being conducted in overseas locations without the
    knowledge of his own Department or the National
    Executive Council

    Chapter 23

    289

    a very late proposal being invited from only
    one
    compa y, and

    a disregard of proper procedures for
    presentation of
    submissions to the National Executive Council.

    This is the sort of situation in which corruption can flourish.

    Put simply, the National Executive Council decision to approve the
    contractor for the Spring Garden Road/Poreporena Freeway project was
    made in very unusual circumstances – not in the way we would expect
    decisions involving large amounts of public money to be made.

    In the following chapters, the Ombudsman Commission records the
    events
    that took place after that decision was made. Many of the things
    that
    happened – though they did not prove that corruption was involved –
    did
    nothing to alleviate our concerns about the circumstances which led
    to the
    decision.

    * * * * * * * * * *

  • Page 324 of 397

  • Chapter 23

    290

    24. OVERVIEW OF EVENTS BETWEEN APPOINTMENT OF
    KINHILL KRAMER CONSORTIUM AND SIGNING OF CONTRACT:
    FEBRUARY – MAY 1992

    [24.1] THREE MONTH PERIOD UNDER REVIEW

    The National Executive Council decided to award the project
    to the Kinhill
    Kramer consortium on 24 February 1992. Three months later, on
    27 May
    1992, the Governor-General signed a contract for the design,
    finance and
    construction of the Poreporena Freeway.

    Chapters 25 – 32 trace the events that occurred during that
    period. It was
    a hectic and turbulent time, especially in the second half of
    April and early
    May 1992 when the National Executive Council received
    conflicting advice
    on the course of action that should be taken.

    In this chapter we provide an overview of what happened,
    before
    recording the events in detail in the following chapters.

    [24.2] THE NATIONAL EXECUTIVE COUNCIL DECISION NO. 36/92 OF 24
    FEBRUARY 1992

    There are two aspects of National Executive Council Decision
    No. 36/92
    that need to be noted:

    Chapter 24

  • Page 325 of 397

  • 291

    1. The failure to include a number of key Government
    agencies
    in the negotiating team.

    2. The imposition of a deadline for completion of
    negotiations.

    [24.3] KEY GOVERNMENT AGENCIES. E G. DEPARTMENT OF WORKS, NOT
    INCLUDED IN THE NATIONAL EXECUTIVE COUNCIL DECISION

    The National Executive Council directed that negotiations
    with the Kinhill
    Kramer consortium be carried out by the Department of
    Transport, the
    Department of Finance and Planning and the Department of
    Attorney-
    General. There was no mention of other key government
    agencies such
    as the Electricity Commission, the National Capital District
    Commission and
    the Department of Works.

    It appears that this was not an oversight. The Minister for
    Transport’s
    Policy Submission, which led to the National Executive
    Council decision,
    made no reference to any of these other agencies. [EXHIBIT
    148, at page
    10]

    It is regrettable that these key agencies were not included
    in the National
    Executive Council decision. The Department of Works, in
    particular, is one
    of the National Government’s key implementing agencies for
    public works
    projects and its administrative structures are geared to
    negotiation of
    contracts for road projects and the construction and
    maintenance of
    roads. It was necessary for the State’s negotiating team to
    have access
    to the experience of the Department of Works and its skilled
    officers, so
    that an informed position could be taken on the technical
    engineering
    aspects of the contract documents. It is also one of the
    discrete functions
    of the Department of Works to “design, plan, supervise,

  • Page 326 of 397

  • execute and

    Chapter 24

    292
    maintain Government works”. (See the Determination of the
    Functions of
    Departments made under the Public Services (Management) Act,
    discussed in Chapter 40 of this report.)

    Though it transpired that the Department of Works was later
    involved in
    the negotiations, the Ombudsman Commission can see no good
    reason
    for that Department not being formally included in the
    National Executive
    Council decision.

    [24.4] DEADLINE IMPOSED BY THE NATIONAL EXECUTIVE COUNCIL,

    The second significant aspect of the National Executive
    Council decision
    of 24 February 1992 is that there was a time limit imposed:
    “all contractual
    and financial arrangements” were to be finalised within two
    months. Thus
    24 April 1992 became regarded as the deadline for completion
    of
    negotiations.

    This was a disastrous decision, in the circumstances. The
    meeting of the
    deadline became an overwhelming pre-occupation of the
    Department of
    Transport; so much so, that insufficient attention was paid
    to ensuring the
    interests of the State were properly protected by the terms
    of the contract.

    We believe it was inappropriate for the National Executive
    Council to set
    a deadline for conclusion of contractual negotiations in this
    particular case.
    In view of the complexity of the technical engineering
    aspects of the
    project and its vast budgetary implications the National
    Executive Council
    should have realised it would be dangerous to rush the
    negotiations. If
    there was a concern about getting the project started – but
    we do not see
    why there should have been – this could have been dealt with

  • Page 327 of 397

  • by asking
    the relevant Departments to report back to the National
    Executive Council
    at regular intervals on the status of the negotiations.

    Chapter 24

    293

    When we expressed these views in our preliminary report, the
    Chairman
    of the National Executive Council at the relevant time, Mr Namaliu,
    responded as follows:

    ‘You suggested the National Executive Council decision 3W92 was
    inappropriate
    and dangerous. That is a matter of opinion.

    Experience suggests that unless you give deadlines to
    departments, you are not
    likely to get any immediate responses. Evil minded people see
    evil in
    everything, we discharged our constitutional duties in good
    faith, taking into
    account the Government’s policies to create employment and to get
    the work
    done quickly.’ [EXHIBIT 256, page 3]

    Notwithstanding Mr. Namaliu’s views, the Ombudsman Commission sees
    no good reason for the National Executive Council wanting to impose
    a
    strict limit on the negotiations.

    We appreciate that it is sometimes necessary to give deadlines to
    departments, as an incentive to get policies implemented
    efficiently. But
    this was a very special project. It was not being implemented in the
    normal manner. The legal issues created by the use of the turnkey
    contract were quite involved. There were also complex engineering
    issues
    to address. None of the customary land in the vicinity of Burns Peak
    had
    been acquired. The budgetary and financial implications of a project
    of this
    magnitude were vast, and it should have been obvious that, because
    normal budgetary procedures had not been followed, it would be
    necessary for the State’s negotiating team to take special care to

  • Page 328 of 397

  • ensure
    that Papua New Guinea was getting a good deal and value for money
    from the successful consortium.

    The Ombudsman Commission strongly maintains the view that it was
    vital,
    in this case, for the State’s negotiating team not to be put under
    unnecessary pressure by the National Executive Council.

    Chapter 24

    294

    Unfortunately, the fact that a strict deadline was imposed
    added to the
    suspicion of corruption created by the unusual circumstances
    leading to
    the selection of the consortium to undertake the project.

    [24.5] CHRONOLOGY OF EVENTS

    The following chronology highlights significant events in the
    period
    between the National Executive Council decision of 24
    February 1992 and
    the signing of the contract on 27 May 1992.

    An asterisk (“*”) is used to highlight meetings of the
    National Executive
    Council at which the Spring Garden Road/Poreporena Freeway
    issue was
    discussed.

    FEBRUARY 1992
    *24 February National Executive Council Decision 36/92 to
    award project
    to Kinhill Kramer consortium.[EXHIBIT 153]

    MARCH 1992
    2 March First meeting between Kinhill Kramer and the State,
    represented by officers of Department of Transport
    and
    Department of Works. [EXHIBIT 155]

  • Page 329 of 397

  • 6 March Meeting between Kinhill Kramer and the State.
    [EXHIBIT
    157]

    Chapter 24

    295

    10 March Department of Works expresses serious concerns to
    Department of Transport about the Kinhill Kramer proposal:

    “… Kinhill Kramer have simply pulled their estimates
    out of the
    air”. [EXHIBIT 158]

    13 March Steering committee meeting. [EXHIBIT 159]

    13 March Secretary for Works writes to Secretary for Transport:

    am very surprised that.. a very late submission dated
    February 1992 by Kinhill Kramer which seemed to say
    almost
    the same terms and conditions in the Chinese proposal
    is the
    favourable one.

    Already there are complaints from other 100% national
    owned
    companies-.• [EXHIBIT 1601

    18 March Secretary for Transport writes to World Bank seeking urgent
    assistance in the form of a legal adviser and technical
    expert.
    (But there was no response.) [EXHIBIT 162]

    20 March Meeting between Kinhill Kramer and the State. [EXHIBIT
    164]

    23 March Steering committee meeting. Department of Works
    representatives indicated:

  • Page 330 of 397

  • “…even at this late stage, something else should be
    done. Let
    Kinhill Kramer complete the design, Government pay
    Kinhill
    Kramer for the design, renegotiate with Kinhill Kramer
    to design
    to Department of Works standards and call tenders for
    construction.• [EXHIBIT 1661

    23 March Beca Worley write to Department of Works offering
    consultant
    assistance. [EXHIBIT 167]

    Chapter 24

    296

    APRIL 1992

    3 April Meeting between Kinhill Kramer and the State.
    Department
    of Attorney-General and Department of Finance and
    Planning
    absent. [EXHIBIT 168]

    6 April Steering committee meeting. Department of Attorney-
    General
    and Department of Finance and Planning absent again.
    [EXHIBIT 169]

    WEEK COMMENCING MONDAY 13 APRIL 1992

    15 April Morning: steering committee meeting called by
    Department
    of Attorney-General and Department of Finance and
    Planning
    – concerned that they did not have a copy of Kinhill
    Kramer’s
    financial proposal. [EXHIBIT 175]

    15 April Afternoon: meeting between Kinhill Kramer and the
    State,
    1.00 pm, to discuss second draft of the contract
    documents.
    [EXHIBIT 176]

  • Page 331 of 397

  • 16 April Beca Gure commence review of contract documents.
    [EXHIBIT 178]

    16 April Consortium agreement signed between Kinhill Kramer
    Pty Ltd
    and Curtain Bros (Old) Pty Ltd. [EXHIBIT 179]

    Chapter 24

    297

    WEEK COMMENCING MONDAY 20 APRIL 1992

    21 April Maunsell Consultants commences review of draft contract.
    [EXHIBIT 180]

    22 April Department of Transport files National Executive Council
    Policy Submission No. 82/92, recommending execution of
    draft contract. [EXHIBITS 181, 183]

    THURSDAY 23 APRIL 1992

    23 April Results of Beca Gure review delivered to Department of
    Works:

    ‘In its present form the proposed contract is very
    heavily i
    weighted in favour of the consortium — the draft
    documents as
    reviewed are seriously flawed and should be totally
    rewritten.’
    POIDITT 184]

    23 April Department of Works advises Department of Transport:
    1

    1— at this time and date we do not believe that the

  • Page 332 of 397

  • State should
    agree with the documents as they now
    stand.’ [EXHIBIT IBS]

    23 April Preliminary review by Maunsell Consultants given to
    Department of Works, advising that certain:

    1—fundamental requirements must be met without
    which the
    project cannot proceed in any proper
    fashion.’ [EXHIBIT 187]

    Chapter 24

    298

    *23 April National Executive Council meeting: Departments ofi
    Transport, Attorney-General and Finance and Planning
    directed to finalise the contract for presentation to
    National
    Executive Council on Wednesday 29 April. [EXHIBIT 186]

    FRIDAY 24 APRIL 1992

    24 April Secretary for Transport advises officer in charge of
    negotiations that a number of Departments are not
    supporting the signing of the draft contract and instructs
    him
    to ensure “everything is in order” before National
    Executive
    Council meeting on 29 April. [EXHIBIT 190]

    24 April Department of Works formally advises Department of
    Attorney-General that if the draft contract is signed in
    its

  • Page 333 of 397

  • present form:

    “…the State will be seriously disadvantaged”.
    EXHIBITS 191,
    192]

    MONDAY 27 APRIL 1992

    27 April Secretary for Works writes to Chairman of Resource
    Management Committee, to express:

    ‘…deep concern about the way this project is
    proceeding without
    due protection for the interests of the State’.
    [EXHIBITS 193,
    196]

    Chapter 24

    299

    27 April Secretary for Transport advises Department of Works that
    because of their delaying tactics, he was directing the
    Kinhill
    Kramer consortium to deal only with the Department of
    Transport. [EXHIBITS 194, 195]

    27 April Second part of Beca Gure review delivered to Department of
    Works, raising further concerns about draft contract:

    “…overall, this contract is not sufficiently defined
    to identify the
    full costs of the project to the Government of Papua
    New
    Guinea.’ [EXHIBIT 1961

  • Page 334 of 397

  • 27 April Department of Transport arranges overnight review of
    contract documents by Cardno & Davies. [EXHIBIT 201]

    TUESDAY 28 APRIL 1992

    28 April Secretary for Works advises Secretary for Transport:

    We are in favour of the project in principle but
    continue to
    advise that unsatisfactory aspects of the current
    contract
    documentation and the land issues, should be sorted
    out Infos
    a final agreement is signed.

    These objections are not raised to frustrate and delay
    but to
    provide proper protection of the State’s
    interest.’ [EXHIBIT MO]

    28 April ElQom formally advises Department of Transport of serious
    concerns about the draft contract:

    The Terms of Payments seem generously biased to the 11
    contractor and progress payments are not linked to
    work
    performance.” [EXHHHT 2021

    Chapter 24

    300

    28 April Cardno & Davies review given to Department of Transport,
    pointing out defects in the draft contract. [EXHIBIT 204]

    28 April Department of Works drafted letter to Prime Minister for
    signature of Minister for Works, strongly objecting to
    execution of the contract in its present form. [EXHIBIT
    209]

  • Page 335 of 397

  • WEDNESDAY 29 APRIL 1992

    29 April Morning: Department of Finance and Planning prepares
    analysis of alternative methods of financing the project,
    emphasising disadvantages of turnkey financing. [EXHIBIT
    199]

    29 April Morning: Secretary of Department of Attorney-General hand-
    delivers letter to Office of Prime Minister, advising he
    will not
    issue a certificate of legal correctness for the draft
    contract.
    [EXHIBIT 211]

    *29 April Afternoon: National Executive Council meeting: Department
    of Attorney-General given nine days in which to complete
    the
    certificate of legal correctness. [EXHIBIT 210]

    FRIDAY 1 MAY 1992

    1 May Senior Department of Transport officer suggests that
    Department of Works be re-involved in contract
    negotiations.
    [EXHIBITS 215, 216, 222]

    Chapter 24

    301

    1 May Acting Minister for Finance and Planning suggests that NEC
    meeting be brought forward to 6 May. [EXHIBIT 217]

    MONDAY 4 MAY 1992

    4 May Secretary for Transport advises Secretary of the Department
    of Attorney-General against complete re-draft of the
    contract.
    [EXHIBIT 219]

    WEDNESDAY 6 MAY 1992

    6 May Acting State Solicitor (Department of Attorney-General) gives
    legal clearance for the contract, but draws attention of
    National Executive Council to numerous serious defects in
    the contract documents. [EXHIBIT 224]

    *6 May National Executive Council Meeting Decision No. 83/92:

  • Page 336 of 397

  • directed the Department of Transport and the
    State Solicitor’s Office to Immediately confer
    and verify” some of the defects in the draft
    contract; and

    advised the Governor-General to execute the
    contract “upon finalization of … above”. [EXHIBIT
    225]

    Chapter 24

    302

    THURSDAY 21 MAY 1992

    21 May Acting State Solicitor advises Governor-General to
    sign the
    contract. [EXHIBITS 230, 231]

    WEDNESDAY 27 MAY 1992

    27 May Certificate of Technical Correctness presented by
    Secretary
    for Transport. [EXHIBIT 232]

    27 May CONTRACT SIGNED

    [24.6] RECORD OF EVENTS

    The Ombudsman Commission records and comments on the events
    of
    the period from 24 February to 27 May 1992 in the following
    way:

    Chapter 25 deals with the initial negotiations between
    Kinhill Kramer and
    the State, paying particular attention to the concerns raised
    by the
    Department of Works.

    Chapter 26 assesses the Department of Transport’s reaction to
    the efforts
    by the Department of Works to delay execution of the
    contract.

    Chapter 27 documents the National Executive Council meeting
    on 23 April
    1992, at which it was decided to go ahead with execution of

  • Page 337 of 397

  • the contract.

    Chapter 24

    303

    Chapter 28 deals with developments between the National Executive
    Council meetings on 23 April and 29 April 1992 and assesses the
    action
    taken by the four key Departments during that period.

    Chapter 29 documents the National Executive Council meeting on 29
    April
    1992, as a result of which the Department of Attorney-General was
    directed to finalise the draft contract within nine days.

    Chapter 30 focuses on the legal clearance that emerged from the
    Department of Attorney-General, just prior to the National Executive
    meeting on 6 May 1992.

    Chapter 31 records the National Executive Council meeting on 6 May
    1991, as a result of which the Department of Transport and the State
    Solicitor’s Office were directed to verify certain defects in the
    draft contract
    prior to its execution by the Governor-General.

    Chapter 32 examines the events that occurred after the National
    Executive
    Council meeting on 6 May 1992, up to and including the execution of
    the
    contract on 27 May 1992.

    Chapter 33 provides an overview of the contract between the State,
    Kinhill
    Kramer Pty Ltd and Curtain Bros (Old) Pty Ltd.

    * * * * * * * * * *

    Chapter 24

    CONCERNS RAISED BY DEPARTMENT OF WORKS
    ABOUT DRAFT CONTRACT: MARCH – APRIL 1992

  • Page 338 of 397

  • [25.1] SIEEMN6GOMMITMEAT GUSHED

    Negotiations on behalf of the State were conducted by an
    interdepartmental steering committee. In accordance with the
    terms of
    National Executive Council Decision No. 36192, it comprised
    representatives
    of three Departments:

    Transport
    Attorney-General
    Finance and Planning.

    Although the Department of Works was not included in the
    National
    Executive Council decision, officers of that Department were
    nevertheless
    involved in the initial meetings of the steering committee.

    There were also occasions on which officers of other
    Departments and
    governmental bodies were involved, such as the Department of
    Lands and
    Physical Planning, the Harbours Board, the Post and
    Telecommunications
    Corporation, the National Capital District Commission and
    the Electricity
    Commission.

    A draft contract was prepared by Kinhill Kramer Pty Ltd and
    made available
    to the steering committee for perusal.

    Chapter 25

    305

    The Department of Transport assumed control of the steering
    committee,
    which met on four occasions between 13 March and 15 April
    1992.

    There were also four meetings between the steering committee
    and the
    Kinhill Kramer/Curtain Bros consortium, at which the terms of
    the draft
    agreement were negotiated. These meetings were held on 6
    March, 20
    March, 6 April and 15 April 1992.

  • Page 339 of 397

  • The Ombudsman Commission interviewed a number of members of
    the
    steering committee in the course of this investigation. After
    considering their
    evidence, and the minutes of those meetings, we are satisfied
    that there
    was a considerable difference of opinion within the committee
    as to the
    acceptability of the terms and conditions put forward by the
    Kinhill
    Kramer/Curtain Bros consortium.

    CONCERNS ABOUT THE DRAFT CONTRACT

    [252] THE VIEW THAT THE CONTRACT HEAVILY FAVOURED THE
    CONSORTIUM

    Some members of the committee thought the terms were heavily
    weighted
    in favour of the consortium. These concerns were aired quite
    early in the
    negotiations.

    One of the burning issues was the price of K65 million. On 10
    March 1992,
    the Assistant Secretary (Roads and Bridges) in the Department
    of Works,
    Mr Bolt, wrote to the Secretary for Transport in the following
    terms:

    Chapter 25

    306

    “It is difficult to avoid the conclusion that Kinhill
    Kramer have simply pulled
    their estimates out of the air and if we accept them
    without question then
    there is a real danger that the Government will be paying
    far more for this
    project than is necessary.”[Exhibit 1581

    One member of the committee testified that on a few occasions
    the

  • Page 340 of 397

  • representatives of the Department of Finance and Planning and
    the
    Department of Attorney-General deliberately failed to attend
    meetings, as
    a means of protesting against the course of the negotiations.

    As a result of these concerns the Department of Works engaged
    two
    consulting firms to separately review the terms of Kinhill
    Kramer’s draft
    contract. The consultants were:

    Beca Gure (PNG) Pty Ltd; and

    Maunsell Consultants PNG.

    [25.3] PART 1 OF THE BECA GURE REVIEW

    Beca Gure was engaged by the Department of Works on 16 April
    1992
    and presented its review in two parts.

    The first part was made available on 23 April 1992 – the day
    the Minister
    for Transport advised the National Executive Council that the
    contract
    should be signed (see Chapters 26 and 27).

    Beca Gure provided a detailed commentary on two documents:

    Chapter 25

    307

    the draft contract agreement between the State and the
    Consortium; and

  • Page 341 of 397

  • the draft “Particular Conditions of Contract for
    Payment”.
    [Exhibit 184]

    The commentary was stated to be “an aggregate of concurrent
    reviews
    carried out by Beca Gure (PNG) and Beca Worley International
    (NZ) with
    specialist legal advice from Rudd Watts and Stone in New
    Zealand”.

    [25.4] SERIOUS RESERVATIONS EXPRESSED BY BECA GURE

    Beca Gure presented a clause-by-clause analysis of the
    documents and
    expressed many serious reservations. Some of these were:

    The financing agreement between the consortium and its
    financiers was not included in the list of contract
    documents.
    If this agreement were not integrated within the
    documentation, the State would have no idea of the
    terms on
    which finance was being arranged.

    The scope of the works was not well defined.

    The contract amount was fixed in United States dollars,
    thus
    exposing the State to the risk of currency
    fluctuations.

    The contractors were entitled to import all plant and
    equipment duty free, but there were no limits on its
    use after
    completion of the project.

    Chapter 25

    308

    The State only had three months in which to transfer
    possession of the site to the consortium. This was
    insufficient,
    in view of the landowner issues that were likely to be
    encountered and the problem of relocating squatters.

    The consortium was only required to use its “best
    endeavours” to complete the project on time. There were
    no

  • Page 342 of 397

  • penalties for delayed completion or evaluation or award
    of
    extensions of time: “the State effectively has no control
    over
    progress”.

    There was inadequate provision for the State to monitor
    the
    progress of construction by a nominated representative
    and
    no provision for the State to inspect the works for
    defects
    prior to delivery.

    The terms of the contract relating to termination were
    one-
    sided: they gave the consortium innumerable grounds on
    which to cancel the contract, but made no provision for
    termination by the State.

    No provision was made for the costs and revenue that
    would
    be generated by disposal of the spoil from the cut.

    5.5] BECA GURE ADVISED THAT THE DRAFT CONTRACT WAS SERIOUSLY
    FLAWED AND SHOULD BE TOTALLY REWRITTEN

    In addition to the commentary on particular terms of the draft
    contract, Beca Gure advised as follows:
    Beca Gure advised as follows:

    Chapter 25

    309

    ‘We are of the opinion — that the
    issues identified herein are of major significance to the State and
    warrant urgent and careful consideration.

    In its present form the proposed
    Contract is very heavily weighted in favour
    of the Consortium with few, if any,
    remedies open to the State in the event of
    unsatisfactory performance. The
    financial burden placed upon the State by the
    various provisions of the Contract is
    very considerable and is not balanced by
    reciprocal obligations upon the
    consortium. The General Conditions of
    Contracts as represented by AS2124

  • Page 343 of 397

  • (1981) are largely inappropriate to lump sum
    Turnkey contracts and presuppose
    independent and impartial action by the
    Superintendent, a situation not
    inherent in the contractual arrangements
    represented by the current
    documentation.

    The requirements for exemption and/or
    reimbursement of personal and corporate
    taxation, customs duties and levies,
    both within PNG and offshore, together with
    the requirement for all payments to be
    made in foreign currency, are unusual
    and further increase the exposure of
    the State during the ten year period covered
    by the Agreement.

    It is in the opinion of ourselves and
    associated specialist advisers that the draft documents as reviewed
    are seriously flawed and should be totally rewritten.
    In their present form the documents do
    not provide the level of protection and
    recourse for the State that would
    normally be contained in contracts between
    the State and contractors providing
    goods and services.

    There are numerous and onerous
    obligations placed upon the State and any
    default exposes the State to
    substantial additional costs, over and above the
    Contract Amount of US$67.6 million.
    There is a danger that claims against the
    State for default may be translated
    into pressures to make concessions to the
    Consortium.

    We earnestly recommend that the Agreement is not signed until the
    issues we
    have identified have been resolved to
    the full satisfaction of the State.

    the State may wish to consider
    requesting competitive tenders for this project.
    It is our experience that mad
    construction costs are comparable internationally
    and in Indonesia current costs for
    dual two lane urban motorway, inclusive of
    land costs, taxes, duties and levies
    and the like are generally US$4 million/km
    or US$33.6 million for 8.4 km. While
    the Burns Peak excavation is an
    extraordinary item it is difficult to

  • Page 344 of 397

  • see why the costs for this project are some
    USS34 million (or double) the cost of
    similar projects elsewhere, and exclude
    land costs and all taxes, duties and
    the like’.

    [EXHIBIT 184, pages 2-3, emphasis added]

    [25.6] PART 2 OF THE BECA CURE REVIEW : FINANCIAL RISKS
    HIGHLIGHTED

    The second part of the review was given to the
    Department of Works on

    27 April 1992, i.e. just two days before the
    National Executive Council

    meeting on 29 April 1992 at which final approval
    of the contract was

    planned to be given (see Chapter 29).

    Chapter 25

    310

    It incorporated an analysis of financial risks, prepared by Deloitte
    Rosg
    Tohmatsu, Chartered Accountants, of Auckland New Zealand. This
    highlighted a number of additional matters of concern. For example:

    The State was not protected against the financial failure of
    members of the consortium. There were no performance
    bonds or similar guarantees and no provision for the State
    to take over the contractors’ plant and equipment in the event
    of liquidation.

    The effect of six monthly interest periods would make the real
    interest rate in the vicinity of 12%.

  • Page 345 of 397

  • Interest charges could add a further US$51 million to the cost
    of the project.

    Exchange rate fluctuations could add to the cost of the
    project. A 10% change in the value of the US dollar by June
    1995 could increase the contract price by another US$15
    million.

    There was no provision for early re-payment by the State.

    Deloitte Ross Tohmatsu concluded by stating:-

    ‘Overall, this contract is not sufficiently defined to identify
    the full costs of
    the project to the Government of Papua New Guinea — In terms of
    negotiating
    position, the State should ensure that all contingencies are
    identified, quantified
    and satisfactorily addressed prior to making any commitment to
    such a
    Contract.’ [EXHIBIT 196]

    Chapter 25

    311

    [25.71 THE MAUNSELL REVIEW : KINHILL KRAMER’S PRICE SHOULD NOT BE
    ACCEPTED

    A preliminary review of the draft contract by Maunsell
    Consultants was
    made available on 23 April 1992, the same day on which the
    first part of
    the Beca Gure review was given to the Department of Works.
    [EXHIBIT
    187]

    A more comprehensive review was delivered on 12 May 1992.
    [EXHIBIT

  • Page 346 of 397

  • 228] This indicated the value of the project was probably
    only K50 million
    and pointed to the dangers of entering into turnkey
    contracts. By the time
    it arrived, however, it was too late to have any effect,
    because the National
    Executive Council had decided on 6 May 1992 to approve the
    draft
    contract and the price of K65 million.

    The preliminary review by Maunsells emphasised that the first
    thing that
    should be done was to engage Kinhill Kramer to complete a
    conceptual
    design for the project:

    “IC.K. should be engaged as soon as possible to complete a
    conceptual design
    for the Project. This should be paid for by the
    Government, either on an agreed
    Lump Sum or on a Time basis, with a budget limit. If and
    when an agreement
    is entered into this sum is deducted from the Contract Sum
    payable.• [EXHIBIT
    187, at page 3]

    Maunsells further advised it was necessary to establish a
    reasonable
    market price for the project. It was not satisfactory to
    accept the price
    quoted by the Kinhill Kramer/Curtain Bros consortium at face
    value:

    Chapter 25

    312

    “Based on the conceptual design ._ a firm of Quantity

  • Page 347 of 397

  • Surveyors experienced
    in the field of the types of construction work
    contemplated should be engaged
    by the Government to prepare a confidential budget
    valuation of the total
    Project, including the cost of all site investigation,
    design, construction,
    supervision, and all ancillary costs such as insurances
    and sureties. This would
    form a basis for comparison with the Consortium’s Payment
    proposals.’
    [EXHIBIT 187, at page 3]

    [25.8] CREDIBILITY OF THE BECA GURE AND MAUNSELL REVIEWS
    CHALLENGED

    In the course of his response to the Ombudsman Commission’s
    preliminary report, the Executive Chairman of Kinhill Kramer
    Pty Ltd, Mr F
    M Kramer, CBE, challenged the credibility of the reviews
    undertaken by
    Beca Gure and Maunsells.

    First, Mr Kramer queried the source of some of the reviews:

    “I find, with respect, this part of the report [dealing
    with the Beca Gure and
    Maunsell reviews] to be incredible. Throughout the report
    you have constantly
    stated that the State was not properly advised or indeed
    received proper
    independent advice in relation to the documentation and
    other matters in
    respect of the project. You then deal with 2 reports
    obtained from Beca Gure
    and Maunsells Consultants together with a report put
    together by Deloitte Ross
    Tohmatsu.

    In relation to both Beca Gure and Deloitte Ross Tohmatsu
    it was interesting
    to note that both reports were carried out by experts from
    New Zealand. I fail
    to see how any New Zealander could comment upon matters
    relating to Papua
    New Guinea. I find this part of the report offensive and
    quite obviously
    irrelevant to the matters in hand. In relation to the Beca
    Gure report I would

  • Page 348 of 397

  • refer you to the report of Jackson Clark Pty Limited and
    more importantly the
    submissions by Counsel in relation to the pricing of the
    project.”

    [EXHIBIT 253, page 8, paragraph 23; note that the Jackson
    Clark document and
    counsel’s submissions to the Ellis Commission of Inquiry
    are highlighted in
    Chapter 22 of this report]

    Mr Kramer also challenged the independence of the reviews:

    ‘Quite obviously the engineering consultants are
    competitors of Kinhill Kramer
    Pty Limited and for that reason alone their independence
    has to be questioned.’
    [EXHIBIT 253, page 9, paragraph 23]

    Chapter 25

    313

    Mr Kramer then suggested that much of the advice contained
    in the
    reviews was ill-informed:

    ‘In relation to the list where Beca Cure expressed many
    serious reservations
    I make no comment other than to say such comments are
    obviously ill-
    informed. for example, in respect of point 4 if your
    investigations had made
    proper enquiry they would have ascertained that the
    Customs Department
    would not allow the use of duty free plant and equipment
    to be utilised on
    any other projects. Should this happen duty is
    immediately payable. This is
    only one example of your investigators lack of partiality
    and consideration of
    the proper facts.1133CHIBIT 253, page 9, paragraph 231

    [25.9] RESPONSE TO MATTERS RAISED BY KINHILL KRAMER

  • Page 349 of 397

  • The Ombudsman Commission makes three points about the
    matters
    raised by Mr Kramer.

    1. Source of the reviews

    As to the fact that two of the reviews emanated from New
    Zealand,
    we regard this as irrelevant to the question of their
    credibility. The
    draft contract was one that might have been executed in
    any
    country having a common law legal system similar to ours.
    As
    Papua New Guinea does not have an indigenous body of
    contract
    law, the commentaries on the draft contract did not
    require a
    detailed knowledge of Papua New Guinea.

    2. Reviews obtained

    As to the reviews being obtained from Kinhill Kramer’s
    competitors,
    this is a fact. But the specialised nature of the advice
    being sought
    meant that whoever gave it was likely to be a competitor
    of some
    sort. The important thing was the substance of the
    reviews, not their
    WINCE).

    Chapter 25

    314

    3. Use of imported plant and equipment

    We are very sceptical of the claim that the lack of restriction
    on the
    use of imported plant and equipment was not a problem because
    the Bureau of Customs would not have allowed it to be used on
    any other project.

  • Page 350 of 397

  • If the duty-free exemption was supposed to be conditional on the
    plant and equipment being used only on the Poreporena Freeway
    project, it was very important for that to be expressly stated
    in the
    contract, for a number of reasons:

    (a) It would have avoided the possibility of disputes
    arising
    in the future. If the State executes a contract which
    imposes no restrictions on the use of duty-free plant
    and equipment, the party importing . it may have a
    strong case when, say, three years later, the plant and
    equipment is used on another project and duty is
    sought to be imposed.

    (b) While the present policy of the Bureau of Customs
    might be to impose duty in these circumstances, there
    was no guarantee that that policy would have
    remained in force for the next few years.

    (c) There is no guarantee that the Bureau of Customs can
    monitor the use of all plant and equipment imported
    duty-free.

    Chapter 25

    315

    (d) The lack of any restriction on its use left
    open the
    possibility of abuse: an item might be
    imported duty
    free, used for only a very short time on
    the freeway
    project and then sold at market price.

    Our understanding is that contracts conferring duty-
    free status on
    plant and equipment almost always include a term
    imposing
    restrictions on its use.

    For all of these reasons, we consider the concern
    raised by Beca
    Gure as to the duty-free provision in the draft
    contract (and such a
    provision was contained in the final contract) to
    have been legitimate
    and certainly not ill-informed. [EXHIBIT 231A,
    Article 10.1(e)]

  • Page 351 of 397

  • [25.10] WERE THE BECA GURE AND MAUNSELL REVIEWS CREDIBLE?
    11
    Having examined each of the reviews obtained by the
    Department of ■
    Works, the Ombudsman Commission does not find in them any
    evidence
    of “bias” against Kinhill Kramer. Each of them appears to
    have been
    competently and professionally compiled. We do not
    necessarily endorse
    all of the comments and recommendations they contained.
    But there is no
    doubt, in our opinion, they raised legitimate matters of
    serious concern
    about the terms of the draft contract.

    It was imperative, if the State’s interests were to be
    adequately protected,
    for the issues raised by the various reviews to be
    comprehensively dealt
    with in the course of the negotiations with the Kinhill
    Kramer/Curtain Bros
    consortium. But this did not happen. re

    Chapter 25

    316

    THE PRICE OF THE PROJECT WAS NOT PROPERLY CHECKED

    [25.11] DEPARTMENT OF TRANSPORT MADE NO PROPER ATTEMPT TO CHECK
    THE PRICE OF THE PROJECT

    In the opinion of the Ombudsman Commission, the advice of
    Maunsells
    and Delloite Ross Tohmatsu was eminently sensible. One of
    the critical
    flaws in the National Executive Council decision to award
    the project to the
    Kinhill Kramer consortium was that there was never any
    proper attempt to
    evaluate whether the price of K65 million quoted by Kinhill
    Kramer was
    realistic. Kinhill Kramer was awarded the project without

  • Page 352 of 397

  • having to justify
    its price (see Chapter 22).

    Until the contract was signed, it was not too late to
    negotiate the price.
    However, during the course of negotiations, no attempt was
    made to get
    an objective, independent valuation of the project. This was
    just plain
    financial irresponsibility. The Ombudsman Commission is very
    concerned
    that such an abuse of public money was made possible.

    When we made these findings in our preliminary report, the
    Secretary for
    Transport responded in the following terms:

    “The project cost was K65 million, however, the
    Department negotiated the
    project cost down from K65 million to K57 million by
    changing the terms. The
    difference of ICS million was classified as contingency
    subject to the State
    approval of the need to commit such funds. It may or may
    not be used. The
    Department of Finance and Planning was aware of this and
    did not raise
    objection. This is not defective administration.’
    [EXHIBIT 254, para 191

    With due respect to Mr Amini, his assertion that the
    Department of
    Transport negotiated the price downwards by K8 million is
    not supported
    by the facts.

    Chapter 25

    317

    The “contract amount” actually contained in the contract
    executed by the
    State was US$67,619,500.00 plus interest. This was expressed
    to be
    inclusive of a general contingency sum of $5,201,500.00.
    There was no

  • Page 353 of 397

  • term in the contract which made liability to pay the
    contingency sum
    subject to “State approval”. That is, the contract amount
    was a flat sum
    and all payments due by the State to the Kinhill Kramer/
    Curtain Bros
    consortium were to be calculated in accordance with that
    amount. [See
    EXHIBIT 231A, Article 5.1 and EXHIBIT 231B, Article 2.1]

    Again, we are forced to conclude that the Department of
    Transport – being
    the Department in charge of the negotiations – was guilty of
    gross
    administrative incompetence and neglect.

    DEPARTMENT OF WORKS RAISES CONCERNS WITH DEPARTMENT OF TRANSPORT
    AND STATE SOLICITOR

    [25.12] ACTION TAKEN BY DEPARTMENT OF WORKS FOLLOWING
    CONSULTANTS’ ADVICE
    The first part of the Beca Gure review and the advice of
    Maunsells were
    made available to the Department of Works on 23 April 1992.
    On that day,
    the Acting First Assistant Secretary (Technical Services),
    Mr. D Gole, sent
    a fax to the Secretary for Transport.

    Writing on behalf of the Secretary for Works, Mr Gole
    stated:

    Chapter 25

    318

    We write to advise that at this time and date we do not believe
    that the StEt(
    should agree with the documents as they now stand.

    We have only yesterday received some of the documents to study
    (e.g. concept
    and specification and the consortium agreement and contract
    agreement) and
    note that there are a number of issues outstanding in the
    drawings. Some of

  • Page 354 of 397

  • the issues previously discussed have not yet being resolved.

    We are currently studying the documents and continue to give full
    cooperation
    to resolve the outstanding issues in the near future, providing
    full cooperation
    is given by the consortium.’ [T BIT 1851

    The next day, 24 April 1992, Mr Gale, together with Mr M Sharp, the
    First
    Assistant Secretary (Operations) in the Department of Works, sent a
    letter
    by fax to the State Solicitor. This letter summarised the main
    concerns
    raised by Beca Gure and Maunsells:

    °It is the professional opinion of the officers of this
    Department that =kw
    these and related matters are adequately addressed then the State
    will be
    seriously disadvantaged should the agreement in its current form
    be adopted.’
    [a= 192, at page 1]

    The letter to the State Solicitor also raised a number of technical
    matters:

    ‘Consideration of the technical proposals has raised concern in
    the following
    cases.

    (I)Geometric Design Standards have not been strictly adhered to
    Geometric Designs are therefore incorrect,

    Horizontal Alignments
    Vertical Alignments
    Cross-.Section
    Grades
    No spiral curves shown

    There is inadequate Definition of Accesses to and from the
    proposed
    roadwork and the existing road network and properties.

    Inter-sectional treatments are not detailed and consequently
    are not
    approved by DOW, NCD.

  • Page 355 of 397

  • Chapter 25

    319

    Plans are incorrect and incomplete and require changes
    with respect to,

    Scales
    libelling of features
    Reference of Cross-Section Types

    At the time of signing the agreement, the land required
    for the project will not
    have been acquired. This is an undesirable, and possibly
    illegal situation and
    could threaten the progress of the works and leave the
    State exposed to claims.”
    [EXHIBIT 192, at page 3]

    The covering letter to the first part of the Beca Gure
    review (which
    recommended that the contract not be signed) was faxed to
    the State

    Solicitor’s Office on 24 April 1992. [EXHIBIT 191] A copy of
    the letter
    was also made available to the Department of Transport,
    which received
    it on 28 April 1992.

    [25.13] DID THE DEPARTMENT OF WORKS ACT RESPONSIBLY?

    As we report in Chapter 26, the suggestion was made in some
    quarters
    that the Department of Works was acting irresponsibly in
    raising these
    concerns and protesting about the way in which the
    negotiations were

  • Page 356 of 397

  • proceeding.

    In the opinion of the Ombudsman Commission, the Department
    of Works
    acted properly in obtaining the reviews from private
    consultants. However,
    once the results of the reviews were available, the
    Department of Works
    could have handled the matter more effectively and
    professionally.

    The Department of Works’ letter of 24 April 1992 to the
    State Solicitor
    [EXHIBIT 192] did not indicate that “the professional
    opinion” of the officers
    of that Department was based on the reviews that had been
    obtained from
    private consultants. This letter should have clearly
    conveyed that the views

    Chapter 25

    320
    being expressed were not only those of the Department of Works’
    officers.
    Furthermore, although a copy of that letter was given to the
    Department
    of Transport, the Department of Works should have expressly stated
    to
    the Department of Transport that it had obtained the reviews from
    private
    consultants and given the Department of Transport copies of those
    reviews
    the moment they became available.

    We appreciate the difficult position that the Department of Works
    was in.
    However, if that Department had been willing to communicate more
    openly and promptly with the Department of Transport, the relations
    between those two departments may not have deteriorated to the
    extent
    that they did in this case.

    We also note that the letter of 24 April 1992 to the State Solicitor
    was
    signed by two senior officers of the Department of Works – not by

  • Page 357 of 397

  • the
    Secretary for Works. In a matter as important as this, this letter
    should
    have been signed by the Secretary for Works. Correspondence of this
    nature must be signed by, or on behalf of, the departmental head
    concerned. If it is not, the impression can easily be obtained that
    senior
    officers of a department are attempting to by-pass their
    departmental
    head.

    So, while the Department of Works acted responsibly in arranging the
    reviews of the draft contract, it did not disseminate the results of
    those
    reviews in the correct manner.

    * * * * * * * * * *

    Chapter 25

    321

    26. DEPARTMENT OF TRANSPORT RECOMMENDS SIGNING OF
    CONTRACT AGAINST ADVICE OF OTHER DEPARTMENTS:
    22 APRIL 1992

    [26.1] DEPARTMENT OF TRANSPORT STILL INTENT ON FINALISING THE
    CONTRACT

    To a large extent the efforts of the Department of Works
    to get the
    contract renegotiated were overtaken by other events.

    Though the Secretary for Transport advised against
    awarding the contract
    to Kinhill Kramer, he nevertheless saw it as his duty to

  • Page 358 of 397

  • implement the
    National Executive Council decision of 24 February 1992.
    The National
    Executive Council stipulated that the contract be signed
    within two months,
    which meant that 24 April 1992 was perceived as the
    deadline. As the
    deadline drew near, the Secretary instructed the officer
    in charge of the
    negotiations with the Kinhill Kramer/Curtain Bros
    consortium, Mr Amoako,
    to prepare a submission to the National Executive
    Council, recommending
    the action to be taken.

    [26.2] DEPARTMENT OF TRANSPORT PREPARES POUCY SUBMISSION
    RECOMMENDING THAT THE CONTRACT BE SIGNED

    Consequently, Policy Submission No. 82/92 was prepared by
    Mr Amoako,
    for the Minister’s signature. It was filed on Wednesday
    22 April 1992,
    together with five copies of a draft contract. [EXHIBIT
    181]

    Chapter 26

    322

    The Policy Submission stated that the steering committee met with
    the
    consortium on a number of occasions and that a draft agreement
    “substantially agreed to by all parties” had been prepared. The
    features of
    the contract were described in the following terms:

    The Consortium will Finance and construct a freeway from Port
    Moresby Seaport to Port Moresby Airport.

    The mad will be 4 lanes all the way through.

    The Burns Peak section will be an open cut 8% grade four lane.

    There will be a minimum of 2 ‘flyovers* (overpasses) and a

  • Page 359 of 397

  • maximum
    of t

    The mad will be the first of its kind in the city and in the
    country.

    The Consortium made up of Kinhill Kramer and Curtain Brothers
    will
    obtain loan to finance the project

    Upon satisfactory completion of the project in 36 months the
    Consortium
    will hand over the project to the State.

    The State will then begin to pay off the principal of the
    loan.

    The loan amount, drawn down will accrue an interest of 95%,
    (This is
    expected to be lower at time of signing Contract Agreement).
    Interest
    will be paid during construction.

    The total project cost is IC65 million, K5 million of which is
    earmarked
    for contingencies.

    There are other technical details of the project still to be
    completed
    but these should not stand in the way of the Contract
    Agreement being
    executed, and for works to commence. Understanding has been
    reached
    with the Consortium.”
    [EXHIBIT 183, pages 1-2, emphasis added]

    The submission concluded by recommending that the National Executive
    Council “directs Finance Minister to enter into Agreement by signing
    the
    Draft Contract with the Consortium.” [EXHIBIT 182, at page 3]

    Chapter 26

  • Page 360 of 397

  • 323

    [26.3] RESPONSE BY THE SECRETARY FOR TRANSPORT TO PRELIMINARY
    FINDINGS

    In our preliminary report, we recorded the view that it was
    wrong of the
    Department of Transport to recommend to the National
    Executive Council,
    through the Minister for Transport, that the Agreement be
    signed at that
    time. The Secretary for Transport, Mr Amini, responded as
    follows:

    ‘The submission did bring to the attention to NEC that
    there were some
    outstanding issues yet to be resolved, yet in Department’s
    view they should
    not stand in the way of the contract being executed
    because the details in
    question were to be provided during detailed design and
    that was part of the
    consortium’s work. Secondly, the Department was of the
    view that the Legal
    Correctness Certificate would be issued by the Department
    of Attorney General
    and, if they had concerns, they would be addressed at that
    stage, still not too
    late, and that is exactly what happened. We took this
    approach because it
    became clear that the attendances of the Department of
    Attorney General
    representative at the negotiating meetings were being
    interfered with by
    Department of Works officials, who wanted to delay the
    project so that other
    developer’s interests might be promoted. We raised this
    concern and it was
    repeated by Mr. Karl Stack in an NEC meeting. NEC cannot
    be deceived by
    this means. It should be remembered that the concerns were
    all technical in
    nature but the negotiation team’s commission was financial
    and legal issues.
    The technical issues were to be derived from detailed
    design. There was risk
    in this but that is a normal part of any turn-key project.
    This was not defective
    administration.’
    [EXHIBIT 254, pars 201

  • Page 361 of 397

  • The Ombudsman Commission does not regard this as a
    satisfactory
    explanation. In this chapter of the report we explain why it
    was premature
    to recommend execution of the contract in April 1992.

    [26.4] WAS THE DEPARTMENT OF TRANSPORT AWARE OF THE CONCERNS
    RAISED BY THE DEPARTMENT OF WORKS?

    Although the Policy Submission was prepared before the
    Department of
    Works officially conveyed its concerns on the draft contract,
    the
    Ombudsman Commission is satisfied that those concerns had
    been
    conveyed, unofficially, well before the submission was
    prepared.

    Chapter 26

    324

    There had been a meeting on 3 April 1992 between the steering
    committee and Kinhill Kramer. The minutes of that meeting
    show that,
    after the Kinhill Kramer representatives left, the following
    discussion took
    place:

    ‘Assistant Secretary (Roads and Bridges) [in the Dept of
    Works] expressed
    serious concern that the committee will not be able to
    adequately assess/change
    the agreement documents and drawings by the deadline for
    submission to NEC.

    First Assistant Secretary (POS) Um the Dept of Works]
    stressed the importance
    of identifying and clearly stating the shortcomings,
    dangers and extra costs of
    the final Agreement to the NEC.

  • Page 362 of 397

  • Tony James (World Bank) joined the meeting and suggested
    that the best way
    to do this project is by regular procedures. He said that
    the Government can
    arrange much better loan terms than a commercial venture,
    and the cost would
    be significantly less. He also mentioned that the
    interpretation of the word
    ‘Turnkey’ is situation dependent.

    Johnson Amoako mentioned that the DOT – DOW liaison
    meetings are off,
    and that meetings and communications will continue on a
    more informal basis.’
    [1•)011Bff 168, at page 4]

    It is clear that officers of the Department of Works were
    conveying their
    concerns to Mr Amoako informally.

    [26.5] CONCERNS ALSO RAISED BY DEPARTMENT OF ATTORNEY-GENERAL
    AND DEPARTMENT OF FINANCE AND PLANNING

    The Department of Transport was also aware the Department of
    Attorney-
    General and Department of Finance and Planning were concerned
    about
    many aspects of the contract. On 15 April 1992, for example,
    officers of
    those departments called a special meeting of the steering
    committee to
    protest against the fact they had not yet seen Kinhill
    Kramer’s financial
    proposal. They had no knowledge of the proposed financing
    agreement
    between Kinhill Kramer and the Export Finance Insurance
    Corporation.

    Chapter 26

    325

  • Page 363 of 397

  • Mr (rung, Assistant State Solicitor, informed the meeting that the
    Department of Attorney-General “required the financial proposal
    before they
    can go through the contract documents for their comments”. [EXHIBIT
    175, at page 2]

    The minutes of the meeting also record the following statements made
    by
    Department of Finance and Planning officers:

    es. The Chairman informed the meeting that although the
    financial proposal
    was not available the committee should proceed to dear other
    issues
    where we have information. The committee has a deadline to
    meet and
    it should work towards meeting the deadline.

    6. DOFF provided the following comments:-

    6.1 The financial package and scope of IC65 million to be
    negotiated.

    6.2 RMC did not support the project.

    6.3 The World Bank’s advise has changed and recommended
    Government
    financing.
    6.4 Department of Works’ cost is IC40-50 million and Kinhill
    Kramer’s cost
    is IC65 million. The final figure should be established.

    6.5 Debt servicing gap needs to be reduced over the years. The
    gap will
    be increased if this project proceeds.

    6.6 Other Transport projects and overall capital works programme
    will be
    affected if the project proceeds. DCA also have a proposal
    for a turnkey
    project on Tokua Airport.” [EXHIBIT 175, at pages 2-3]

    These were important matters which should not have been just swept
    aside by the Department of Transport and the Minister for Transport.

  • Page 364 of 397

  • Chapter 26

    326

    [26.6] DID THE DEPARTMENT OF TRANSPORT ACT RESPONSIBLY IN
    RECOMMENDING THAT THE DRAFT CONTRACT BE SIGNED?

    The meeting called by the Department of Attorney-General and
    the
    Department of Finance and Planning took place on Wednesday 15
    April
    1992 – just one week before the recommendation that the
    contract be
    signed. The concerns that had been raised were not addressed
    in the
    intervening period.

    The Department of Transport prepared the Policy Submission in
    the
    knowledge that the Department of Works, the Department of
    Attorney7
    General and the Department of Finance and Planning had
    serious
    reservations about the draft contract.

    For this reason, we find that it was irresponsible of the
    Department of
    Transport and the Minister for Transport to recommend to the
    National
    Executive Council, at that stage, that the contract be
    signed.

    It was misleading to suggest that the draft contract had been
    “substantially
    agreed to”. The fact was, there was vehement opposition to it
    by the
    Department of Attorney-General, the Department of Finance and
    Planning
    and the Department of Works.

    It made no sense to concede that there were “other technical
    details of the
    project still to b.g completed”, but then to conclude that
    “these should not

  • Page 365 of 397

  • stand in the way of the Contract Agreement being executed”.
    It was wrong
    and not in the best interests of the State.

    It was naive to believe that, because an “understanding” had
    been reached
    with the consortium, the technical details could be sorted
    out at some later
    time.

    Chapter 26

    327

    The Ombudsman Commission appreciates that the National
    Executive
    Council had set a deadline and that, at the time this Policy
    Submission
    was prepared, it was fast approaching. But what is more
    important:
    achieving a deadline or protecting the interests of the State?

    The Ombudsman Commission has formed the view that the
    Department
    of Transport had no proper appreciation of the complexity of
    the technical
    and legal issues involved in a contract of this nature.

    [26.7]WHAT MOTIVATED THE DEPARTMENT OF TRANSPORT TO IGNORE THE
    ADVICE OF THE DEPARTMENT OF WORKS?

    The Secretary for Transport believed that the Department of
    Works was
    attempting to “interfere” in what he regarded as a Department
    of Transport
    project.

    Relations between the two Departments had been frosty for some
    time.
    The situation did not improve when Mr Lohia Hitolo (until
    1992, a senior
    officer of the Department of Transport and in charge of the
    Spring Garden
    Road/Poreporena Freeway project) was appointed Secretary for
    Works.

    In Chapter 18, we noted the tension created when Mr Hitolo, as
    Secretary
    for Works, briefed the Minister for Transport on the project –
    without telling
    the Secretary for Transport – just a few weeks before the
    National

  • Page 366 of 397

  • Executive Council decided to award the project to the Kinhill
    Kramer
    consortium.

    Chapter 26

    Mr Arnini’s terse response to that incident was:

    The matter of Spring Garden Road is the responsibility of the
    Department of
    Transport until such time as the consortium is selected and all
    the detailed
    contracting arrangements are completed. At the time of design and
    construction, the Department of Works will be fully involved”.
    [FJCHIBIT 149]

    It is evident that, because of the approach taken by the Department
    of
    Works during the steering committee meeting, the Secretary for
    Transport
    formed the view that the Department of Works was opposed to the
    project. These views were expressed in an internal Department of
    Transport memo to Mr Amoako on 24 April 1992:

    ‘As discussed yesterday (23 April), it was revealed that a number
    of
    Departments is reluctant to give a full support to this
    Submission because they
    feel strongly that some important technical issues have not been
    seriously
    addressed by Kinhill Kramer Consortium and unless they are
    attended to, they
    are of the view that the submission should be deferred. In
    particular, is the
    Wog
    Department in what we have been directed to do by National
    Executive
    Council.

    The General Manager of Elcom also verbally told me yesterday that
    he is
    writing to us to express his views that we should seriously study
    the technical
    aspects of the project and seek an independent Consultant to

  • Page 367 of 397

  • assist us because
    he fears that the Kinhill Kramer Consortium has not addressed
    these thoroughly
    and there may be flaws in their submission to the Government
    through the
    Department.

    If these organizations are expressing their doubts on this
    project, we should
    at least try to listen to them and reassess our approach to it.

    It could be that these organizations may have been approached by
    Department
    of Works personnel who have been opposing this project to get off
    the ground.
    This assumption is based on what you have told me yesterday. This
    could be
    wrong but quiet investigation could reveal this one way or
    another.

    It is quite clear that a number of organizations has vested
    interest in this project
    and, unless these issues are addressed, these organizations could
    stifle the
    project thus discredit the Department and embarrass the
    Government altogether.
    This must not happen at all cost! You are, therefore, directed to
    ensure that
    everything is in order before the submission is submitted to
    National Executive
    Council on 29 April.” [EXHIBIT 190, emphasis added]

    Chapter 26

    329

    The Secretary for Transport expressed the same views when, on
    27 April
    1992, he replied to the Department of Works’ advice that the
    contract with
    Kinhill Kramer should not be signed:

    ‘Having tried to frustrate the deliberation of the
    Committee, it is not surprising

  • Page 368 of 397

  • to us to receive such a letter at the last day and put the
    blame on the
    Consortium for lack of cooperation, when the Consortium
    had given the
    Committee full cooperation by meeting demands placed on
    thene.[EXHIBIT
    194]

    On the same day, 27 April 1992, the Secretary for Transport
    directed the
    Kinhill Kramer/Curtain Bros consortium to deal only with the
    Department
    of Transport. [EXHIBIT 195]

    [26.8] NO JUSTIFICATION FOR DEPARTMENT OF TRANSPORT IGNORING THE
    CONCERNS OF OTHER DEPARTMENTS

    The Secretary for Transport thought that the Department of
    Works was
    motivated more by a desire to embarrass the Department of
    Transport,
    than genuine concern for the interests of the State.

    But even if this were, in fact, the case, the Ombudsman
    Commission can
    see no justification for the Department of Transport ignoring
    the issues that
    had been raised. Concerns were being expressed, not only by
    the
    Department of Works, but also by the Department of Attorney-
    General and
    the Department of Finance and Planning.

    These issues were fundamental to the contract and required
    urgent
    attention. They were never properly addressed during the
    negotiations with
    the Kinhill Kramer/Curtain Bros consortium.

    Chapter 26

  • Page 369 of 397

  • 330

    In an internal memo to the Secretary for Transport on 28
    April 1992, Mr
    Amoako advised he had given the comments of a consultant
    engaged by
    the Department of Works to the consortium and discussed them
    in his
    office:

    To my knowledge they did include all the outstanding
    issues at that point in
    time.”
    [EXHIBIT 201, page 2, para 4]

    This is nonsense. It is clear from reading the contract
    actually executed on
    27 May 1992, that the vast bulk of the concerns raised in the
    Beca Gure
    and the Maunsell reviews were not incorporated in the final
    contract.

    The Department of Transport had ignored the advice and the
    concerns of
    three key Departments, namely, the Department of Attorney-
    General, the
    Department of Finance and Planning and the Department of
    Works.

    [26.9] SUMMARY OF THE DEPARTMENT OF TRANSPORTS ACTIONS

    In the opinion of the Ombudsman Commission the Department of
    Transport made serious errors in the negotiations with the
    Kinhill
    Kramer/Curtain Bros consortium.

    The Department was not prepared to listen to the advice of
    other
    Departments. The pleas for caution by the Department of
    Attorney-
    General, the Department of Finance and Planning and the
    Department of

  • Page 370 of 397

  • Works were consistently brushed aside as the Department of
    Transport
    pushed ahead in its determined, but careless, pursuit of the
    National
    Executive Council’s deadline.

    Chapter 26

    [Paragraph unreadable in the original]

    An information paper could have been file for the National
    Executive
    Council’s consideration, explaining the ……… for not meeting the
    deadline and asking for an extension of time in order to
    to attend to certain important issues.

    Instead of doing this, the Department of Transport pretended that
    the

    concerns raised by the other Departments were not legitimate and
    recommended that the contract be signed.

    This was wrong and defective administration.

    * * * * * * * * * *

  • Page 371 of 397

  • Chapter 26

    NATIONAL EXECUTIVE COUNCIL DECIDES THAT CONTRACT
    MUST BE FINALISED 23 APRIL 1992

    7 I POLICY SUBMISSION TO NATIONAL EXECUTIVE COUNCIL HAD
    IGNORED CONCERNS OF KEY DEPARTMENTS

    As we reported in Chapter 26, the attempts by the
    Department of Works
    to have the terms of Kinhill Kramer’s draft contract
    renegotiated were
    thwarted by the Department of Transport.

    The Policy Submission of 22 April 1992 not only ignored
    the serious
    concerns raised by the Department of Works, it also failed
    to mention the
    concerns of the Department of Attorney-General and the
    Department of
    Finance and Planning.

    The Policy Submission recommended that the contract be
    signed and was
    considered by the National Executive Council at its
    meeting on Thursday
    23 April 1992.

    [27.2] NATIONAL EXECUTIVE COUNCIL DECIDES TO POSTPONE APPROVAL
    OF CONTRACT

    Rather than approving the draft contract, the National
    Executive Council

  • Page 372 of 397

  • decided to defer formal consideration of the matter until
    its next meeting,
    on Wednesday 29 April 1992.

    Chapter 27

    333

    However, the National Executive Council made it clear that
    negotiations
    were to be concluded by that date.

    The Departments of Transport, Attorney-General and Finance and
    Planning
    were given a formal direction in the following terms:

    “to finalise contracts on the Spring Garden Freeway with
    Kinhill Kramer and
    Curtain Bros for presentation to the NEC on 29th April 1992”.
    [EXHIBIT 186]

    As this new deadline was only six days away, the Departments which
    were
    opposing execution of the contract, as it then stood, had to act
    quickly if
    they were to achieve their objective.

    The next chapter of the report focuses on the events that occurred
    in the
    lead-up to the National Executive Council meeting of 29 April 1992.

    * * * * * * * * * *

  • Page 373 of 397

  • Chapter 27

    334

    28. ACTION TAKEN BY FOUR KEY DEPARTMENTS PRIOR TO
    THE NATIONAL EXECUTIVE COUNCIL MEETING ON
    29 APRIL 1992

    [28.1] THE POSITION OF THE FOUR KEY DEPARTMENTS: TRANSPORT.
    WORKS. ATTORNEY-GENERAL AND FINANCE AND PLANNING

    On 23 April 1992 the National Executive Council directed that
    the contract
    between the State and the Kinhill Kramer/Curtain Bros
    consortium be
    finalised by 29 April 1992. This decision put the Department
    of Works, the
    Department of Attorney-General and the Department of Finance
    and
    Planning in a difficult position.

    These Departments were opposed to the contract being signed,
    in its
    existing form. They wanted more time to negotiate. The
    Department of
    Finance and Planning also wanted to examine the financing
    agreement
    between Kinhill Kramer and the Export Finance and Insurance
    Corporation,
    which had not been made available.

    Only the Department of Transport was interested in seeing
    that the new
    deadline was met.

  • Page 374 of 397

  • This chapter of the report assesses the action taken by these
    four key
    departments in the lead-up to the meeting of the National
    Executive
    Council on Wednesday 29 April 1992.

    Chapter 28

    335

    THE DEPARTMENT OF WORKS

    [28.2] CONCERNS RAISED WITH RESOURCE MANAGEMENT COMMITTEE

    With the meeting of 29 April 1992 only a couple of days away,
    the
    Secretary for Works, Mr Hitolo, tried a different way of
    airing his
    Department’s concerns.

    On 27 April 1992, he wrote to the Chairman of the Resource
    Management
    Committee (the Secretary of the Department of Prime Minister,
    Mr Brown
    Bai CBE) in the following terms:

    I write to advise the Committee of my Department’s deep
    concern abut the
    way this project is proceeding without due consideration
    for the protection of
    the best interests of the State, and urge that the
    Committee advise the National Executive Council mg to agree
    to the signing of the proposed contracts until the
    documents have been amended accordingly and made good? [EXHIBIT 193]
    Executive Council mg to agree to the signing of the
    proposed contracts until the documents have been amended
    accordingly and made good? [EXHIBIT 193]
    documents have been amended accordingly and made good?
    [EXHIBIT 193]

  • Page 375 of 397

  • The other official action taken by the Department of Works
    during this
    period was the drafting of a letter for the Minister for
    Works, the Hon.
    Lukas Waka MP. The letter was directed to the Prime Minister.
    It stated:-

    ‘My Prime Minister, as I have stated above I would be
    failing you if I did not
    draw my serious concerns to your attention. I fully
    support the project and
    appreciate the need for rapid implementation. I would
    however strongly
    recommend that the current contract should not be signed
    until adequate time
    has been given to review and amend the documents and in
    particular the main
    agreement between the State and the Consortium- This would
    ensure that the
    State’s interests are protected and that the land related
    matters could also be addressed’. [EXHIBIT 209, at page 2]
    addressed’. [EXHIBIT 209, at page 2]

    Chapter 28

    336

    THE DEPARTMENT OF TRANSPORT

    [28.3] APPROACH REMAINED THE SAME

    During the lead-up to the meeting on 29 April 1992 the
    Department of
    Transport maintained. the approach it had taken since the
    National
    Executive Council decided in favour of Kinhill Kramer: it had
    an overriding
    duty to comply with the direction from the National Executive
    Council to
    finalise the contract.

  • Page 376 of 397

  • The officer in charge of the negotiations, Mr Amoako, advised
    the
    Secretary for Transport on 28 April 1992 that all the
    amendments
    suggested by other members of the steering committee had been
    incorporated in the draft contract. [EXHIBIT 201, at page 1]

    Mr Amoako also advised that, apart from the Department of
    Works and
    the Electricity Commission, no other Department or
    governmental body
    had expressed their objections in writing to the Department
    of Transport
    or the steering committee.

    The Ombudsman Commission accepts that the latter advice was
    correct:
    though the concerns were widespread amongst the membership of
    the
    steering committee, only the Department of Works and the
    Electricity
    Commission had formally put them in writing.

    However, Mr Amoako’s advice that all the suggested amendments
    had
    been incorporated in the draft contract was wrong and
    misleading.

    Chapter 28

    337

    [28.4] ELCOM RAISES CONCERNS WITH DEPARTMENT OF TRANSPORT

    On 28 April 1992, the General Manager of the Electricity
    Commission, Mr
    P K Amini, wrote to the Secretary for Transport, expressing
    concerns
    about the draft contract. The Electricity Commission had an
    interest in the
    project, because its transmission lines would be affected by
    the route of
    the freeway.

    These concerns mirrored those raised by the Department of
    Works;
    particularly about the conflict of interest created by having
    Kinhill Kramer
    act, on the one hand, as project manager on behalf of the

  • Page 377 of 397

  • consortium,
    and, on the other hand, as superintendent of the project on
    behalf of the
    State.

    The Electricity Commission letter was received in the
    Department of
    Transport on 29 April 1992, but there appears to have been no
    response
    to it. [EXHIBIT 202]

    [28-5] DEPARTMENT OF TRANSPORT AWARE OF WIDESPREAD CONCERN
    ABOUTRIEDRAELCONIBACI

    The Department of Attorney-General and the Department of
    Finance and
    Planning did not formalise their concerns in the same manner
    as the
    Department of Works and the Electricity Commission. However,
    the
    Department of Transport was well aware that these other
    departments
    were also very concerned about the terms of the draft
    contract.
    Unfortunately, the Department of Transport attributed this to
    the efforts of
    the Department of Works to embarrass the Department of
    Transport and
    did not take them seriously (see Chapter 26).

    Chapter 28

    Nevertheless, the Department of Transport decided to get a
    “second
    opinion”.

    [28.6] DEPARTMENT OF TRANSPORT ARRANGES OVERNIGHT REVIEW OF
    DRAFT CONTRACT

    On the afternoon of Monday 27 April 1992 – just two days
    before the
    contract was due to be approved by the National Executive
    Council – the
    Department of Transport asked the consulting firm Cardno &
    Davies (PNG)
    Pty Ltd to review some aspects of the draft contract.
    [EXHIBIT 201, at
    page 2]

  • Page 378 of 397

  • Cardno & Davies reported back to the Department of Transport
    the
    following day, 28 April 1992. Given the very short period of
    time, the
    analysis was, understandably, not as comprehensive as that
    given to the
    Department of Works by Beca Gure and Maunsells (see Chapter
    26).
    Nevertheless a number of matters of concern were raised.

    [28.7] THE CARDNO & DAVIES REVIEW

    Cardno & Davies suggested, for example:

    The scope of the project had to be defined in more
    detail.

    Specific provision had to be made for delays in land
    acquisition.

    Chapter 28

    It was necessary to identify and list all codes and
    standards
    for each item of structural work.

    The specifications for bridges did not meet the normal
    requirements of earthquake engineering for bridges in
    Papua
    New Guinea.

    The role of the superintendent had to be defined and
    clarified
    to minimize confusion. [EXHIBIT 204]

    On Wednesday 29 April 1992, the Secretary for Transport
    instructed Mr
    Amoako to incorporate the issues raised by the Cardno &
    Davies review
    and take them up with the parties concerned. This was a very
    strange
    instruction. It was given on the very day the National
    Executive Council
    was due to approve the contract. Surely it was too late for a
    major revision
    of the contract.

  • Page 379 of 397

  • [28.8] THE CARDNO & DAVIES REVIEW WAS TOO LATE TO HAVE ANY
    EFFECT

    It is not surprising that none of the concerns raised by
    Cardno & Davies
    were addressed in the final contract. In fact nothing was
    really achieved
    by this whole exercise.

    It was simply a belated and rather half-hearted attempt by
    the Department
    of Transport to get confirmation that the contract was in
    order.

    Chapter 28

    340

    But clearly the contract was not in order. This was the third
    independent
    review of the contract. In each review, there were serious
    matters of
    concern raised. They were not minor matters that could be
    negotiated
    later. They were issues which went to the heart of the
    contract, such as
    who would be the superintendent of the project and who would
    protect the
    State’s interest during the construction phase.

    [28.9] DEPARTMENT OF TRANSPORT MADE NO PROPER ATTEMPT TO HAVE
    THE CONTRACT REVIEWED

    We recorded these views in our preliminary report and
    emphasised that
    the Department of Transport had not made a proper attempt to
    have the
    contract reviewed. The Secretary for Transport responded in
    the following
    terms:

    This statement lie. that the Department of Transport made

  • Page 380 of 397

  • no proper attempt
    to have the contract reviewed] is totally incorrect. The
    negotiating team were
    doing precisely that. The consultant’s work was only a
    supplement. Remember
    the draft document had been reviewed clause-by-clause,
    paragraph-by-
    paragraph and page-by-page prior to that. This was the
    role of the Committee.
    This is not defective administration. There was no need to
    ask NEC to defer
    because the issues raised by the Consultant were adopted
    before the submission
    to NEC. The Consultant review was in contrast to that
    pursued by the
    Department of Works. Clearly, the Department of Works was
    on the wrong
    path. The person in charge was not a qualified Highway
    Engineer but an
    architect, who had recently taken the Highway Engineering
    job as Acting First
    Assistant Secretary.” [EXI-HBIT 254, pars 22]

    The Ombudsman Commission does not accept Mr Amini’s
    explanation.
    Three key departments were expressing serious concerns about
    the draft
    contract in the course of the negotiations. In these
    circumstances, it was
    incumbent on the Department of Transport to arrange its own,
    independent review before recommending the contract be
    executed.

    Chapter 28

    341

    When the Department did receive the results of the review by
    Cardno &
    Davies, it should have realised that it was dangerous to
    proceed with the
    existing draft contract

    The Ombudsman Commission reiterates the finding made in
    Chapter 26:
    it was irresponsible of the Department of Transport to pursue

  • Page 381 of 397

  • execution of
    the contract when so many doubts, from so many different
    quarters, were
    being expressed. It was irrelevant that only the Department
    of Works and
    the Electricity Commission had put their concerns in writing.
    All the
    concerns were genuine and deserved close consideration.

    Though it may have been embarrassing for the Department and
    the
    Minister for Transport to postpone execution of the contract
    on the eve of
    its approval, common sense should have prevailed: the
    National Executive
    Council should have been advised that it would be safer to
    re-negotiate
    the contract properly in the interests of the State.

    THE DEPARTMENT OF ATTORNEY-GENERAL

    pa 10] ACTION NOT TAKEN UNTIL ONE DAY BEFORE THE NATIONAL
    EXECUTIVE COUNCIL MEETING

    On Tuesday 28 April 1992 – the day before the contract was
    due to be
    approved – the Secretary of the Department of Attorney-
    General, Mr P
    Paliau ISO, sent a letter by fax to the Secretary for Works.
    He said he
    agreed the draft contract did not adequately protect the
    interests of the
    State and advised he would not be issuing a legal clearance
    for the
    contract. [EXHIBIT 205]

    Chapter 28

    342

    Mr Paliau also asked the Secretary for Works to brief the
    Minister for
    Works and get the Minister to write a letter to the Prime
    Minister,
    recommending execution of the contract be delayed.

  • Page 382 of 397

  • [28.11] SECRETARY OF THE DEPARTMENT OF ATTORNEY-GENERAL ADVISES
    PRIME MINISTER THAT LEGAL CLEARANCE WOULD NOT BE ISSUED

    On the following day, Wednesday 29 April 1992, Secretary
    Paliau wrote to
    the Chairman of the National Executive Council, Prime
    Minister Namaliu.
    He advised he had perused the contract documents and
    concluded as
    follows:

    ‘la) this project did not comply with the rules and
    procedure for Tender
    under the Public Finances (Management) Act;

    (b) the execution and performance of the Agreement
    and the Contract
    Documents in L(b) – (f) above at this stage will
    mean that the Contract
    amount of K65,000,000.00 authorized by the Loans
    Overseas (Borrowing)
    Act and also the Loans Overseas (Borrowing) (No.
    2) Act, will be
    exceeded, hence Section 209 of the Constitution
    will be breached.

    (c) the Agreement in 1 (a) above and the Contract
    Documents in 1(b) – (f)
    above do not protect or appear to protect the
    best interest of the State;

    (d) the execution of this Agreement and the Contract
    Documents therewith
    be delayed until they are adequately and
    satisfactorily finalised to
    protect the best interests of the State, the
    Consortium, the Project
    Manager and possibly the Export Finance Insurance
    Corporation of
    Australia.

    Accordingly, I decline to issue a Letter of Legal
    Clearance on the Agreement’
    [EXHIBIT 211]

    This letter was hand-delivered to the Prime Minister’s
    office on the morning
    of Wednesday 29 April 1992 by Secretary Paliau.

  • Page 383 of 397

  • Chapter 28

    343
    [28.12] DEPARTMENT OF ATTORNEY-GENERAL ACTED PROPERLY BUT ADVICE
    SHQULD HAVE BEEN GIVEN SOONER

    In view of the widespread concern expressed about the draft
    contract, the
    Ombudsman Commission considers the decision by the Secretary
    of the
    Department of Attorney-General to write the letter to the
    Prime Minister on
    29 April 1992 to have been responsible and entirely proper.

    It is unfortunate, however, that it was not written sooner,
    as this was the
    first occasion on which the Department of Attorney-General
    had formally
    put in writing the defects perceived in the draft contract.

    So, while we praise Secretary Paliau for writing the letter
    of 29 April 1992
    to the Prime Minister, we must also criticise his Department
    for not taking
    action sooner. It was not sufficient for his officers to
    simply raise their
    concerns in the steering committee. This was a case which
    called for a
    thorough briefing to the Attorney-General in writing.

    [28.13] ATTORNEY-GENERAL SHOULD HAVE BEEN ADVISED

    At the relevant time the Attorney-General was the Hon
    Bernard Narokobi,
    LLB MP. By virtue of Section 156(2) of the Constitution and
    Sections 3 and
    4 of the Attorney-General Act 1989, he was also the
    Principal Legal Adviser
    to the National Executive.

    The Department of Attorney-General should have advised him
    very early
    in the course of negotiations that there were serious

  • Page 384 of 397

  • defects in the draft
    contract provided by Kinhill Kramer.

    Chapter 28

    344

    The Attorney-General should have also been formally advised
    that the
    Public Finances (Management) Act and other legislation would
    be
    breached if the National Executive Council proceeded with
    the planned
    course of action.

    [28.14] RESPONSE OF THE DEPARTMENT OF ATTORNEY GENERAL

    We accept that the Department of Attorney-General
    representatives on the
    steering committee had raised a number of concerns during
    the
    committee’s meetings. Specifically, we accept what the
    Acting State
    Solicitor, Mr Z Gelu, said in his response to our
    preliminary findings:

    This project was arranged through the turn key concept.
    The concept by
    passes all procedures and requirements under the Public
    Finance &
    Management Act. I may say here that Messrs. hung and
    Singin raised these
    concern during their consultative meeting. The Contract
    was drafted by Kinhill
    Kramer Pty Ltd and Curtain Brothers (Qld). The Contract
    was pushed through
    NEC by the Department of Transport.” [EXHIBIT 26.2, parr
    41

    However, by raising concerns in the committee meetings, the
    Department
    of Attorney General had only gone part of the way to
    protecting the

  • Page 385 of 397

  • State’s interests.

    When this was put to Secretary Paliau in the form of a
    preliminary finding,
    he responded as follows:

    “Like any project of such nature of any matters that
    require legal assistance in
    terms of advise or drafting of agreements, I normally
    delegate such matters to
    the State Solicitor to handle consistent with his Duty
    Statements. The State
    Solicitor will only come back to me if the matters
    require my personal attention.

    Chapter 28

    345

    Furthermore, client Departments are at liberty to
    instruct the State Solicitor
    directly and I am always informed about such instructions
    by the State Solicitor.
    Again apart from such information the State Solicitor
    deals with the matter
    directly with the client Department unless the matter
    requires my personal
    attention…

    As to the findings in Chapter 28, — the matter only came
    to my personal
    attention at that particular time and I attended to it
    there and then on 29 April
    1992.

    The findings — on myself failing to advise the Attorney-
    General on serious
    defects in the draft contract and the breaching of the
    requirements of the Public

  • Page 386 of 397

  • Finances (Management) Act and other Legislation if the
    NEC proceeded with
    the course of action if proposed is ill founded.

    At that period of time when the matter was being
    entertained by the NEC, the
    Hon. Bernard Narokobi, the Attorney-General was not
    available. In fact he was
    out of speedy and effective communication and he was
    unable to fulfil the
    duties of Office of the Attorney-General.

    By virtue of Section 5 of the Attorney-Generals Act, I as
    the Departmental
    head became the Attorney-General and the Principal Legal
    Adviser to the
    National Executive Council. Therefore I see no reason why
    I should advise
    the Attorney-General or advise myself for that
    matter.” [EXHIBIT 258]

    [28.15] POOR COMMUNICATION WITHIN THE DEPARTMENT OF ATTORNEY
    GENERAL

    The Secretary’s defence is that the project had been
    delegated to the
    State Solicitor and the matter only came to the Secretary’s
    personal
    attention shortly before the meeting of the National
    Executive Council on
    29 April 1992. He also says the reason the Attorney General
    was not
    advised was that he (the Secretary) was actually the
    Attorney-General on
    29 April 1992.

    With respect to Secretary Paliau, he has not actually
    addressed our
    criticisms. If we accept that the matter was not brought to
    his attention
    until very late in the negotiations, this does not rebut our
    findings – it
    reinforces them.

  • Page 387 of 397

  • Chapter 28

    Our criticism is directed at the Department of Attorney
    General, as a
    whole, and the State Solicitor’s Office in particular, for
    not formally briefing
    Attorney-General Narokobi early in the negotiating period.
    The fact that the
    Secretary of the Department was also not fully briefed
    underscores the
    overall lack of affirmative action taken by officers of his
    Department. It also
    reflects poorly on the lines of communication within the
    Department.

    We therefore conclude that the Department of Attorney-
    General was remiss
    in its duty to promptly advise the National Executive
    Council, via the
    Attorney-General, of all of the legal problems associated
    with immediate
    execution of the contract.

    THE DEPARTMENT OF FINANCE AND PLANNING

    [28.16] CONCERNS RAISED DURING STEERING COMMITTEE MEETINGS

    The Department of Finance and Planning had little
    involvement in the
    decision to award the contract to Kinhill Kramer. The
    Department was
    concerned, as early as June 1990, about the funding of the
    project.
    [EXHIBIT 10B] However, the shortlisting and evaluation of
    proposals – even
    when it was based on financial criteria – took place without
    consulting the
    Department of Finance and Planning.

    The Department of Finance and Planning only became involved
    when the
    steering committee was established to negotiate with the
    Kinhill Kramer
    consortium.

    Chapter 28

  • Page 388 of 397

  • 347

    Like the Department of Attorney-General and the Department of Works,
    the
    Department of Finance and Planning had serious reservations about
    the
    way the negotiations were proceeding. On 15 April 1992,
    representatives
    of the Department of Finance and Planning called a special meeting
    of the 11
    steering committee to protest that they had not seen Kinhill
    Kramer’s
    financing agreement. [EXHIBIT 175]

    This, in itself, was a matter of concern: nobody knew the terms on
    which
    the consortium was obtaining finance for the project. In fact, these
    terms
    were never made available to the State. On 27 May 1992, when the
    freeway contract was signed, the agreement with the Export Finance
    Insurance Corporation was not executed. iAnd the agreement remained
    un-
    executed, even when the contract between the State, Kinhill Kramer
    Pty
    Ltd and Curtain Bros (Old) Pty Ltd was terminated on 27 August 1992
    (see Chapter 34).
    The officers of the Department of Finance and Planning suggested
    that the
    Kinhill Kramer financial package be renegotiated and that
    alternative
    sources of funding be investigated. But this was never done.

    If it had been done, implementation of the project would no doubt
    have
    been delayed. But there were obvious alternatives to Kinhill
    Kramer’s
    turnkey proposal: concessional financing from sources such as the
    World
    Bank or the Asian Development Bank, which is generally cheaper than
    finance obtained through institutions such as the Export Finance and
    Insurance Corporation of Australia.

    Unfortunately, the Department of Finance and Planning did not
    undertake
    a detailed analysis of the alternative methods of financing the
    Poreporena
    Freeway project until the eve of the National Executive Council
    meeting on
    29 April 1992.

    Chapter 28

  • Page 389 of 397

  • [28.17] FINANCIAL ANALYSIS OF ALTERNATIVE FUNDING

    The First Assistant Secretary (Loans and Revenue) in the
    Department of
    Finance and Planning, Mr Kahona, testified to the
    Ombudsman
    Commission that, on 27 or 28 April 1992, he was
    instructed by the Acting
    Secretary of the Department, Mr Mulina, to prepare a
    comparison of the
    different methods of financing.

    The EFIC interest rate was estimated to be 9.5% , which
    transpired to be
    the interest rate in the final contract. This was
    compared with the
    prevailing interest rates for World Bank (IBRD) and Asian
    Development
    Bank Loans of 7.72% and 6.58% respectively. An analysis
    of the “grant
    element’ and the “effective rate of interest’ for each
    loan regime was then
    carried out, which took account of the period of the loan
    repayments, the
    grace period and the commitment fees.

    [28.18] EFIC FINANCING SHOWN TO BE EXPENSIVE

    The Department of Finance and Planning analysis was
    summarised in the
    following terms:

    ‘Grant Element (GE) and Effective Rate of Interest
    (ERI) Comparison

    Lender Current Grant Effective
    Interest (%)Element (%) Rate of
    Interest (%)

    EFIC 9.50 13 9.7
    IBRD 7.72 13.8 7.9

  • Page 390 of 397

  • ADB 6.58 23.3 6.7

    Chapter 28

    349

    It is obvious from the above table that the grant
    element of the EFIC option
    is very low at 1.3% compared to IBRD and ADB options at
    13.8% and 23.3%
    respectively. The grant element measures the degree of
    concessionality of a
    loan in comparison to a direct grant. So, the higher the
    grant elements the
    higher the degree of concessionality.

    The effective rate of interest on the EFIC proposal is
    high at 9.7% as compared
    to either IBRD or ADB at 7.9% and 6.7% respectively.

    comparison to financing the proposed project through
    World Bank or ADB
    financing. It is also understood that the World Bank has
    indicated that they
    maybe able to fund the project at a lower total project
    estimated cost of around
    US$45 million”
    [EXHIBIT 199, at page 2, emphasis added]

    In the same report, it was estimated that, if the Kinhill
    Kramer financing

    proposal was adopted, the total cost to the State over the
    life of the loan

    would exceed K90 million.

  • Page 391 of 397

  • [28.19] REPORT GIVEN TO THE ACTING MINISTER FOR FINANCE AND
    PLANNING

    This report was presented to Acting Secretary Mulina on the
    morning of

    29 April 1992, ie the day on which the National Executive
    Council was due
    to approve the contract.

    Soon after this the report was given to the Acting Minister
    for Finance and
    Planning, Hon. Karl Stack, MP. He faxed a copy of the report
    to the

    Secretary for Transport on the following day, 30 April 1992.
    [EXHIBIT 213]

    Chapter 28

    350

    [28.20] DID THE DEPARTMENT OF FINANCE AND PLANNING ACT SOON
    ENOUGH?

    The Department of Finance and Planning report of 29 April
    1992 was
    straightforward:

    Kinhill Kramer’s turnkey financing was expensive.

    The project might be able to be implemented for K20
    million
    i than what Kinhill Kramer had quoted.

  • Page 392 of 397

  • The total project cost of the project over a
    thirteen year
    period was in excess of K90 million.

    This report was of critical importance to the whole project
    and the
    Ombudsman Commission is amazed that it was not prepared much
    sooner.

    It seems that by the time they met on the afternoon of 29
    April 1992, a
    majority of the members of the National Executive Council
    had made up
    their minds to approve the Kinhill Kramer/Curtain Bros
    contract.

    Perhaps, if the Department of Finance and Planning report
    had been
    available sooner, it may have had some impact.

    It is a matter of concern to the Ombudsman Commission that,
    though the
    Department of Finance and Planning had serious reservations
    about this
    project quite early in the contract negotiations, nothing
    tangible was done
    until the last minute. Like the Department of Attorney-
    General, the
    Department of Finance and Planning failed to give its advice
    promptly –
    when it would have had a much greater chance of being
    accepted.

    Chapter 28

    351

    [28.21] CONCERNS HAD TO BE RAISED AT A HIGH LEVEL

    We accept that the Department’s concerns were raised at the
    steering
    committee meetings. The Secretary for Finance stated to the
    Ombudsman
    Commission that, though his Department failed to follow up
    these matters
    in writing, they expected the Department of Transport and
    the Knhill
    Kramer/Curtain Bros consortium to respond to the requests at
    subsequent
    meetings. [EXHIBIT 255]

    In the opinion of the Ombudsman Commission this is simply

  • Page 393 of 397

  • not good
    enough. The Department of Finance and Planning should have
    raised its
    concerns at a much higher level: the Secretary for Finance
    should have
    thoroughly briefed the Minister for Finance in writing. And
    this should have
    been done very early in the negotiating period.
    Alternatively, the Secretary
    for Finance could have raised the matter formally in writing
    with the
    Secretary for Transport.

    [28.22] ALTERNATIVE FUNDING SOURCES SHOULD HAVE BEEN THOROUGH Y
    EXPLORED

    The Ombudsman Commission is also concerned that the
    Department of
    Finance and Planning was not more enterprising in
    investigating the
    possibility of concessional funding for the project, through
    the Office of
    International Development Assistance (01DA).

    Chapter 28

    352

    [28.23] RESPONSE BY THE DEPARTMENT OF FINANCE AND PLANNING TO
    THE OMBUDSMAN COMMISSION’S ALLEGATIONS

    The Ombudsman Commission put the above findings to the
    Secretary for
    Finance, Mr G Aopi MBE, in our preliminary report. He
    responded as
    follows:

    The report correctly states that DFP was not involved in
    the project (Le.
    contract negotiations) until after the NEC Decision in
    February 1992. Prior to
    this, all discussions were undertaken by the Department
    of Transport.

  • Page 394 of 397

  • However, our comments on the project were consistent –
    the project was
    expensive and that alternatives should be pursued. In
    addition, from a planning
    perspective, while this project was in the Transport
    development plans in terms
    of priorities, consideration should have been given to
    developing the rural
    infrastructure which is in dire need of improvement.

    In view of DOT not providing the information
    requested„ we could not provide
    a detailed brief for the Minister for Finance and
    Planning, NEC and RMC.
    Chapter 28 of the report supports this. However, it is
    unfair on the part of the
    Commission … to be critical of the Department’s action
    when other parts of the
    report state that information requested by the
    Department from DOT was never
    received.

    I would like to place once again on record that we did
    not receive any formal
    offer of financial assistance from the Consortium for
    financing of the Freeway.
    We were also not in a position to realistically and
    accurately advise the Minister
    for Finance and Planning on the implications of
    financing the project either
    through concessional sources or those proposed by the
    Consortium. The
    financial analysis _ was done just before NEC met on the
    29th April. This
    analysis was done on the basis of terms and conditions
    prevailing at that time
    and on information obtained through informal
    discussions.

    If the Department had been provided with a formal offer
    of finance for
    financing of the project, we would have provided a
    detailed analysis for the
    Minister’s consideration and other interested parties
    well in advance. The
    Minister was however, verbally briefed on several
    occasions of the Department’s
    position on the project…

    — The procurement of goods and services by Government
    agencies is dearly
    set out in the Public Finances (Management) Act, and
    senior government
    officials should be aware and understand these and other

  • Page 395 of 397

  • administrative
    procedures.

    The Department of Transport also, during various
    discussions, knew the
    Department’s position together with those of the State
    Solicitor, and these
    should have been reflected in various submissions to the
    National Executive
    Council. The Department may have been deliberately left
    out in a lot of the
    discussions because of its strong views against this
    project.

    Chapter 28

    353

    As for finding alternative sources of funds, there are
    certain laid-down
    procedures which must be followed to secure concessional
    funds. Projects
    should be submitted through the normal budgetary process
    and evaluated prior
    to negotiating the financial package. Obviously the
    process is too slow and
    cumbersome for some people, hence the turnkey
    proposal.’ [EXHIBIT 255]

    [28.24] UNSATISFACTORY EXPLANATION BY DEPARTMENT OF FINANCE AND
    PLANNING

    The reasons advanced by Mr Aopi for his Department’s failure
    to provide
    a prompt analysis of the cost of the project are not
    convincing.

    We appreciate the Department was not in a position to carry
    out a precise
    analysis, because of the unavailability of the exact terms
    of the EFIC
    financing package. But there was nothing to stop the
    Department

  • Page 396 of 397

  • estimating the cost of the EFIC finance – which is what, in
    fact, was done
    on the eve of the National Executive Council meeting of 29
    April 1992.

    The estimate could have been based on the terms of the
    financing
    package proposed by Kinhill Kramer Pty Ltd in February 1992
    and
    considered by the National Executive Council (see Chapter
    22, Exhibit
    151). And this financial analysis could, and should, have
    been done as
    soon as the National Executive Council decision was
    announced.

    It is not a good excuse for the Department of Finance and
    Planning to say
    it did nothing because it never received a formal financing
    proposal. We
    do not believe any Department of the State is entitled to
    sit back and
    make no comment on a major financial commitment by the State
    because
    it was not formally approached for advice or not given all
    the information
    it wanted.

    Chapter 28

    [28.25] CONCLUSION AS TO CONDUCT OF DEPARTMENT OF FINANC AN D
    PLANNING

    The Ombudsman Commission concludes that the Department
    of Finance
    and Planning was remiss in its duty to ensure that
    prompt advice was
    given to the National Executive Council, via the
    Minister for Finance, on the
    financial implications of the Kinhill Kramer turnkey
    proposal.

    * * * * * * * * * *

  • Page 397 of 397

  • Chapter 28